A device and operating method for simulating and evaluating the plugging capacity of limestone malignant leakage.
By designing a simulation and evaluation device for the ability to plug severe leakage in limestone, the problem of the lack of simulation devices in the existing technology was solved, the optimal selection of plugging materials and the optimization of construction technology were realized, and the plugging effect was improved.
Patent Information
- Application Number
- CN202611483303.2
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2026-09-22
- Publication Date
- 2026-11-17
AI Technical Summary
Existing technologies lack devices for simulating severe leakage and plugging of limestone, making it difficult to select and evaluate plugging materials and formulations, resulting in poor plugging effects and difficulty in developing effective construction plans.
A simulation and evaluation device for the plugging capacity of limestone malignant leakage was designed, including a fracture-cavity simulation system, a formation water simulation injection system, and a plugging agent simulation injection system. It can realistically simulate the plugging process and observe the plugging situation. Dynamic pressure is simulated through the observation window and the outlet constant pressure control system.
This study enabled the selection of optimal materials and optimization of construction techniques for sealing severe leakage in limestone, improving the success rate of sealing and providing a reliable evaluation method.
Smart Images

Figure CN123109641A_ABST
Abstract
Description
Technical Field
[0001] This invention belongs to the field of limestone malignant leakage plugging technology, specifically relating to a limestone malignant leakage plugging capacity simulation and evaluation device and operation method. Background Technology
[0002] Severe leakage in limestone formations is a common problem in oil and gas well drilling and production. It usually refers to the large-scale loss of drilling fluid or production fluids in limestone formations due to fractures, caves, etc. Such leakage not only affects drilling efficiency and cost, but may also endanger downhole operation safety. Therefore, it is very important to evaluate the plugging capabilities of plugging materials and technologies in limestone formations.
[0003] Plugging severe limestone leakage is a major challenge in plugging operations. The plugging slurry is easily diluted and washed away by active formation water, making it difficult to remain within the leakage channels to form an effective sealing layer. This results in poor plugging performance and a low success rate. Due to the lack of devices to simulate severe limestone leakage plugging, personnel cannot effectively select and evaluate plugging materials and formulations, nor can they simulate the plugging process or optimize the plugging techniques. Consequently, it is difficult to develop effective plugging solutions, which requires further improvement. Summary of the Invention
[0004] To address all or part of the aforementioned problems, the present invention aims to provide a simulation and evaluation device and operating method for the ability to plug severe leakage in limestone. This device can realistically simulate the situation of plugging severe leakage in limestone, enabling staff to select and evaluate the plugging materials and formulas for severe leakage in limestone, and to optimize the plugging construction process based on the simulated plugging construction process.
[0005] In a first aspect, the present invention provides a device for simulating and evaluating the plugging capacity of severe leakage in limestone, comprising: Fracture-vuggy simulation system is used to simulate formation leakage channels and observe the sealing situation; A formation water simulation injection system is used to inject formation water into the fracture-cavity simulation system; A plugging agent simulation injection system is used to inject plugging agent into the cavity simulation system; An outlet constant pressure control system is used to maintain dynamic constant pressure in the cavity simulation system.
[0006] Optionally, the suture hole simulation system includes: The simulator body has a water inlet on one side and a drainage outlet on the other side, and the formation water simulation injection system is connected to the water inlet of the simulator body. An observation window is set on the main body of the simulator; A visible well shaft is vertically connected to the simulator body and communicates with the inner cavity of the simulator body; A sealing end cap is disposed at the top of the visible well shaft, and an intermediate chamber is provided inside the sealing end cap; The drill pipe assembly is coaxially disposed inside the visible wellbore and forms a wellbore annular cavity with the visible wellbore. The drill pipe assembly is connected to the inner cavity of the simulator body. The top of the drill pipe assembly extends into the intermediate cavity and is rotatably connected to the sealing end cap. A feed hole is located at the top of the drill rod assembly; A motor assembly for controlling the rotation of the drill pipe assembly; The first feed connector has one end connected to the sealing end cap and communicating with the intermediate chamber, and the other end connected to the plugging agent simulation injection system.
[0007] Optionally, the plugging agent simulation injection system includes: There are four piston tanks, which store formation water, release agent, plugging agent, and release agent in sequence. A squeezing mechanism is used to inject water into the corresponding piston canister to squeeze the piston inside the corresponding piston canister, thereby discharging the medicine; There are four discharge pipes, each connected to the bottom of a corresponding piston tank; The main injection pipe is connected to the four discharge pipes respectively; The first injection branch pipe is connected at one end to the injection main pipe and at the other end to the first feed connector, and a first injection valve is provided on the first injection branch pipe.
[0008] Optionally, the plugging agent simulation injection system further includes: The second feed connector is connected to the visible well shaft and communicates with the well shaft annular cavity; The second injection branch pipe is connected to the injection main pipe at one end and to the second inlet connector at the other end, and a second injection valve is provided on the second injection branch pipe.
[0009] Optionally, the plugging agent simulation injection system further includes: There are four three-way valves, which are connected to the corresponding discharge pipes. Collection pool, used to collect waste; There are four collecting branch pipes, each connected to a corresponding three-way valve; The main collection pipe is connected at one end to the collection pool and at the other end to the four collection branch pipes respectively. The flushing pipe is connected at one end to the main injection pipe and at the other end to the formation water simulation injection system, and a flushing valve is provided on the flushing pipe.
[0010] Optionally, the extrusion mechanism includes: Water storage tanks are used to store clean water; There are four water inlet branch pipes, which are connected to the top of the corresponding piston tanks. The main inlet pipe is connected at one end to the water storage tank and at the other end to the four inlet branch pipes respectively. A piston pump, an inlet valve and a first flow meter are connected sequentially to each inlet branch pipe.
[0011] Optionally, the formation water simulation injection system includes: Formation water tanks are used to store formation water. The water injection pipe has one end connected to the formation water tank and the other end connected to the water inlet of the simulator body. A centrifugal pump, a second flow meter, a water injection valve and a pressure gauge are connected to the water injection pipe in sequence. The circulation pipe has one end connected to the drain end of the simulator body and the other end connected to the formation water tank, and the circulation pipe is equipped with a circulation valve. The regulating pipe is connected at one end to the water injection pipe and at the other end to the formation water tank. The regulating pipe is located between the centrifugal pump and the second flow meter, and a regulating valve is provided on the regulating pipe.
[0012] Optionally, the formation water simulation injection system further includes: The booster pipe is connected at one end to the main water inlet pipe and at the other end to the water inlet of the simulator body. The booster pipe is equipped with a booster valve and a third flow meter.
[0013] Optionally, the outlet constant pressure control system includes: Graduated cylinder; The back pressure pipe is connected at one end to the drain end of the simulator body and at the other end to the collecting cylinder. The back pressure pipe is equipped with a back pressure valve and a back pressure pump set. The discharge pipe is connected to the drainage end of the simulator body.
[0014] Secondly, the present invention provides an operation method for a limestone malignant leakage plugging capacity simulation and evaluation device, comprising the following steps: S1, injecting formation water into the fracture-vuggy simulation system through the formation water simulation injection system; S2, the release agent, the plugging agent, and the release agent are sequentially injected into the cavity simulation system through the plugging agent simulation injection system; S3, observe the sealing situation through the crack simulation system; S4, adjust the injection pressure of the formation water simulation injection system to test the pressure limit of the plugging agent.
[0015] As can be seen from the above technical solution, the device and operating method for simulating and evaluating the plugging capacity of limestone malignant leakage provided by the present invention have the following advantages: This simulation and evaluation device can realistically simulate the situation of severe leakage and plugging of limestone, so that staff can select and evaluate the best materials and formulas for plugging severe leakage of limestone, and optimize the plugging construction process based on the simulated plugging construction process.
[0016] Other features and advantages of the present invention will be set forth in the following description. Attached Figure Description
[0017] The accompanying drawings are provided to further understand the technical solutions of the present invention and constitute a part of the specification. They are used together with the embodiments of the present invention to explain the technical solutions of the present invention, and do not constitute a limitation on the technical solutions of the present invention.
[0018] Figure 1 This is a schematic diagram of the structure of the limestone malignant leakage plugging capacity simulation and evaluation device in an embodiment of the present invention; Figure 2 This is a schematic diagram of the main body of the simulator in an embodiment of the present invention; Figure 3 This is a schematic diagram of the plugging agent simulation injection system in an embodiment of the present invention; Figure 4 This is a schematic diagram of the formation water simulation injection system in an embodiment of the present invention; Figure 5 This is a schematic diagram of the outlet constant pressure control system in an embodiment of the present invention.
[0019] Explanation of reference numerals in the attached figures: 1. Fracture / Void Simulation System; 101. Simulator Main Body; 102. Observation Window; 103. Visual Wellbore; 104. Sealed End Cap; 105. Intermediate Chamber; 106. Drill Pipe Assembly; 107. Wellbore Annular Cavity; 108. Feed Inlet; 109. Motor Assembly; 110. First Feed Connector; 2. Formation Water Simulation Injection System; 201. Formation Water Tank; 202. Injection Pipe; 203. Circulation Pipe; 204. Regulating Pipe; 205. Centrifugal Pump; 206. Second Flow Meter; 207. Injection Valve; 208. Pressure Gauge; 209. Circulation Valve; 210. Regulating Valve; 211. Booster Pipe; 212. Booster Valve; 213. Third Flow Meter; 3. Plugging Agent Simulation Injection System; 301. Piston tank; 302, Extrusion mechanism; 303, Discharge pipe; 304, Main injection pipe; 305, First injection branch pipe; 306, Second injection branch pipe; 307, First injection valve; 308, Second feed connector; 309, Second injection valve; 310, Water storage tank; 311, Water inlet branch pipe; 312, Main water inlet pipe; 313, Piston pump; 314, Water inlet valve; 315, First flow meter; 316, Three-way valve; 317, Collection tank; 318, Collection branch pipe; 319, Main collection pipe; 320, Flushing pipe; 321, Flushing valve; 4. Outlet constant pressure control system; 401, Collection measuring cylinder; 404, Back pressure pipe; 403, Back pressure valve; 404, Back pressure pump set; 405, Discharge pipe. Detailed Implementation
[0020] To make the objectives, technical solutions, and advantages of the present invention clearer, the embodiments of the present invention will be described in detail below with reference to the accompanying drawings. It should be noted that, unless otherwise specified, the embodiments and features described in the embodiments of the present invention can be arbitrarily combined with each other.
[0021] like Figure 1 , Figure 2 , Figure 3 , Figure 4 , Figure 5 The illustration shows an embodiment of the present invention, which discloses a simulation and evaluation device for the plugging capacity of severe leakage in limestone. The device includes a fracture-vuggy passage simulation system 1, a formation water simulation injection system 2, a plugging agent simulation injection system 3, and an outlet constant pressure control system 4. The fracture-vuggy passage simulation system 1 is used to simulate formation leakage channels and observe the plugging situation. The formation water simulation injection system 2, the plugging agent simulation injection system 3, and the outlet constant pressure control system 4 are respectively connected to the fracture-vuggy passage simulation system 1. The formation water simulation injection system 2 is used to inject formation water into the fracture-vuggy passage simulation system 1, the plugging agent simulation injection system 3 is used to inject plugging agent into the fracture-vuggy passage simulation system 1, and the outlet constant pressure control system 4 is used to maintain a dynamic constant pressure in the fracture-vuggy passage simulation system 1.
[0022] In one embodiment, such as Figure 1 , Figure 2As shown, the fracture-cavity simulation system 1 includes a simulator body 101. The simulator body 101 has a flow channel chamber inside. A water inlet is located on one side of the simulator body 101, and a drain is located on the other side. The water inlet and drain are connected to the flow channel chamber, and the formation water simulation injection system 2 is connected to the water inlet of the simulator body 101. Simultaneously, an observation window 102 is provided on the simulator body 101 to allow personnel to observe the leak-sealing process.
[0023] In one embodiment, such as Figure 1 , Figure 2 As shown, a visible well shaft 103 is vertically fixedly connected to the simulator body 101, and the visible well shaft 103 communicates with the inner cavity of the simulator body 101. A sealing end cap 104 is fixedly connected to the top of the visible well shaft 103, and an intermediate chamber 105 is provided inside the sealing end cap 104.
[0024] In one embodiment, such as Figure 1 , Figure 2 As shown, a drill pipe assembly 106 is coaxially disposed inside the visible wellbore 103, forming a wellbore annular cavity 107 between the drill pipe assembly 106 and the visible wellbore 103, and the drill pipe assembly 106 communicates with the inner cavity of the simulator body 101. The top of the drill pipe assembly 106 extends into the intermediate chamber 105 and is rotatably connected to the sealing end cap 104, and a feed hole 108 is provided on the top of the drill pipe assembly 106.
[0025] In one embodiment, such as Figure 1 , Figure 2 As shown, a motor assembly 109 is provided on the sealing end cap 104, which is used to control the rotation of the drill rod assembly 106. The upper end of the sealing end cap 104 is connected to a first feed connector 110, which communicates with the intermediate chamber 105, and the plugging agent simulation injection system 3 is connected to the first feed connector 110.
[0026] In one embodiment, such as Figure 1 , Figure 3 As shown, the plugging agent simulation injection system 3 includes four piston tanks 301 and a squeezing mechanism 302. The four piston tanks 301 sequentially store formation water, release agent, plugging agent, and release agent again. The squeezing mechanism 302 is used to inject water into the corresponding piston tank 301 to squeeze the piston inside the corresponding piston tank 301, thereby discharging the agent. Each piston tank 301 has a discharge pipe 303 connected to its bottom. The bottom of the piston tank 301 has a stirrer to agitate the agent and prevent it from settling.
[0027] In one embodiment, such as Figure 2 , Figure 3As shown, the plugging agent simulation injection system 3 also includes an injection main pipe 304, a first injection branch pipe 305, and a second injection branch pipe 306. The injection main pipe 304 is connected to four discharge pipes 303 respectively. One end of the first injection branch pipe 305 is connected to the injection main pipe 304, and the other end is connected to the first inlet connector 110. A first injection valve 307 is provided on the first injection branch pipe 305. A second inlet connector 308 is connected to the upper end of the visible well shaft 103. The second inlet connector 308 is in communication with the well shaft annulus. One end of the second injection branch pipe 306 is connected to the injection main pipe 304, and the other end is connected to the second inlet connector 308. A second injection valve 309 is provided on the second injection branch pipe 306.
[0028] The plugging agent simulation injection system 3 in this embodiment has three modes, as follows: Mode 1: Rinse Mode Open the second injection valve 309 and close the first injection valve 307. The extrusion mechanism 302 injects water into the piston tank 301 that stores formation water, so that the formation water enters the flow channel cavity of the wellbore annular cavity 107 and the simulator body 101 to achieve flushing of the visible wellbore 103 and the simulator body 101.
[0029] Mode 2: Grouting Mode The first injection valve 307 is opened and the second injection valve 309 is closed. The extrusion mechanism 302 first injects water into one of the piston tanks 301 storing release agent so that the release agent enters the drill pipe assembly 106. Then, the extrusion mechanism 302 injects water into the piston tank 301 storing plugging agent so that the plugging agent enters the drill pipe assembly 106. Immediately afterwards, the extrusion mechanism 302 injects water into the other piston tank 301 storing release agent so that the release agent enters the drill pipe assembly 106.
[0030] Mode 3: Plaster Replacement Mode Water is injected into the piston tank 301 storing formation water by the squeezing mechanism 302, so that the formation water enters the drill pipe assembly 106. Driven by the formation water, the plugging agent and the release agent move downward until the plugging agent enters the simulator body 101.
[0031] In one embodiment, such as Figure 3As shown, the plugging agent simulation injection system 3 also includes three-way valves 316, a collection pool 317, collection branch pipes 318, a collection main pipe 319, and a flushing pipe 320. Four three-way valves 316 are provided, and each of the four three-way valves 316 is connected to a corresponding discharge pipe 303. Four collection branch pipes 318 are provided, and each of the four collection branch pipes 318 is connected to a corresponding three-way valve 316. One end of the collection main pipe 319 is connected to the collection pool 317, and the other end is connected to each of the four collection branch pipes 318, to achieve unified recycling of waste materials. One end of the flushing pipe 320 is connected to the injection main pipe 304, and the other end is connected to the formation water simulation injection system 2. A flushing valve 321 is provided on the flushing pipe 320 to achieve flushing of the drill pipe assembly 106, the visible wellbore 103, and the simulator body 101.
[0032] In one embodiment, such as Figure 3 As shown, the extrusion mechanism 302 includes a water storage tank 310, inlet branch pipes 311, and a main inlet pipe 312. The water storage tank 310 stores clean water. Four inlet branch pipes 311 are provided, and each of the four inlet branch pipes 311 is connected to the top of a corresponding piston tank 301. One end of the main inlet pipe 312 is connected to the water storage tank 310, and the other end is connected to each of the four inlet branch pipes 311. A piston pump 313, an inlet valve 314, and a first flow meter 315 are connected sequentially to each inlet branch pipe 311. The piston pump 313 injects clean water from the water storage tank 310 into the piston tank 301. The piston in the piston tank 301 moves downward under pressure, thereby extruding the medicine from the piston tank 301.
[0033] In one embodiment, such as Figure 4 As shown, the formation water simulation injection system 2 includes a formation water tank 201, an injection pipe 202, a circulation pipe 203, and a regulating pipe 204. The formation water tank 201 is used to store formation water. One end of the injection pipe 202 is connected to the formation water tank 201, and the other end is connected to the water inlet of the simulator body 101. A centrifugal pump 205, a second flow meter 206, an injection valve 207, and a pressure gauge 208 are connected sequentially to the injection pipe 202.
[0034] In one embodiment, such as Figure 4 As shown, one end of the circulation pipe 203 is connected to the drain end of the simulator body 101, and the other end is connected to the formation water tank 201. A circulation valve 209 is installed on the circulation pipe 203. One end of the regulating pipe 204 is connected to the water injection pipe 202, and the other end is connected to the formation water tank 201. The regulating pipe 204 is located between the centrifugal pump 205 and the second flow meter 206, and a regulating valve 210 is installed on the regulating pipe 204.
[0035] In one embodiment, such as Figure 4As shown, the formation water simulation injection system 2 also includes a booster pipe 211. One end of the booster pipe 211 is connected to the main water inlet pipe 312, and the other end is connected to the water inlet of the simulator body 101. At the same time, a booster valve 212 and a third flow meter 213 are installed on the booster pipe 211.
[0036] Formation water is drawn from the formation water tank 201 by a centrifugal pump 205 and then enters the simulator body 101 through the injection pipe 202. During this process, the flow rate and velocity of the formation water are regulated by controlling the opening of the regulating valve 210 and the injection valve 207. Excess formation water flows back to the formation water tank 201 through the regulating pipe 204. Simultaneously, the formation water discharged from the simulator body 101 can flow back to the formation water tank 201 through the circulation pipe 203, thus achieving the recycling of formation water. Furthermore, during the leak-sealing simulation, the pressure-boosting valve 212 can be opened to allow clean water from the storage tank 310 to enter the simulator body 101, thereby controlling the flow rate and velocity of the formation water to simulate a high-pressure state and test the ultimate pressure-bearing capacity of the plugging agent.
[0037] In one embodiment, such as Figure 1 , Figure 5 As shown, the outlet constant pressure control system 4 includes a collecting cylinder 401. A back pressure pipe 404 is connected to the drain end of the simulator body 101. The back pressure pipe 404 is connected to the collecting cylinder 401, and a back pressure valve 403 and a back pressure pump assembly 404 are installed on the back pressure pipe 404. A discharge pipe 405 is connected to the drain end of the simulator body 101, and the discharge pipe 405 is connected to the collection tank 317 for unified wastewater recycling.
[0038] The back pressure pump set 404 controls the pressure at the discharge end of the simulator body 101. The discharged formation water flows into the collection cylinder 401 through the back pressure pipe 404. After the internal pressure of the simulator body 101 increases, the excess formation water is discharged through the discharge pipe 405, thereby keeping the pressure of the simulator body 101 in dynamic balance. This is existing technology and will not be elaborated on here.
[0039] The limestone malignant leakage plugging capacity simulation and evaluation device in this embodiment simulates the injection and replacement process of plugging slurry, the formation leakage channels, and the sealing situation based on the simulated fracture-vuggy leakage layer environment. This simulates the real field environment, realistically reflects the injection, retention, and sealing process of plugging slurry, and directly observes the entire sealing process. It aims to evaluate the sealing effect of plugging slurry and guide on-site leakage plugging construction, providing a reliable evaluation method for the limestone malignant leakage plugging capacity and playing a guiding role in evaluating the limestone malignant leakage plugging capacity.
[0040] This embodiment also discloses the operation method of the limestone malignant leakage plugging capacity simulation evaluation device, including the following steps: S1, injecting formation water into fracture-cavity simulation system 1 through formation water simulation injection system 2; S2, through the plugging agent simulation injection system 3, release agent, plugging agent, and release agent are sequentially injected into the cavity simulation system 1; S3, observe the sealing situation through the crack simulation system 1; S4, adjust the injection pressure of the formation water simulation injection system 2 to test the pressure limit of the plugging agent.
[0041] Specifically: First, open the water injection valve 207, regulating valve 210, and circulation valve 209, and start the centrifugal pump 205. This allows the formation water in the formation water tank 201 to enter the simulator body 101 and return to the formation water tank 201 through the circulation pipe 203. Simultaneously, control the opening of the water injection valve 207 and regulating valve 210 to adjust the flow rate and volume of the formation water. Then, open the first injection valve 307 and the inlet valve 314, and start the plunger pump. The clean water in the storage tank 310 first enters one of the piston tanks 301 storing the release agent, allowing the release agent to enter the intermediate chamber 105 through the main injection pipe and the first injection branch pipe 305, and then enter the drill pipe assembly 106 through the feed hole 108.
[0042] Subsequently, the clean water in the water storage tank 310 enters the piston tank 301 storing the plugging agent, which then enters the drill pipe assembly 106. Next, the clean water in the water storage tank 310 enters another piston tank 301 storing a release agent, allowing the release agent to enter the drill pipe assembly 106. Then, the clean water in the water storage tank 310 enters the piston tank 301 storing formation water, which then enters the drill pipe assembly 106 and pushes the plugging agent downwards until it enters the simulator body 101.
[0043] Next, observe the drain end of the simulator body 101. If the water flow decreases significantly, close the circulation valve 209 and open the valve on the discharge pipe 405. Use the back pressure pump group 404 to maintain dynamic pressure balance in the simulator body 101. Then, open the pressure boosting valve 212, and clean water from the water storage tank 310 enters the simulator body 101. Observe whether water flows out from the drain end of the simulator body 101 to test the pressure limit value of the plugging agent.
[0044] It should be noted that, unless otherwise stated, the technical or scientific terms used in this invention should have the ordinary meaning as understood by one of ordinary skill in the art.
[0045] Furthermore, the terms "first," "second," etc., are used for descriptive purposes only and should not be construed as indicating or implying relative importance or implicitly specifying the number of technical features indicated. In the description of this invention, "a plurality of" means two or more, unless otherwise explicitly defined.
[0046] Finally, it should be noted that the above embodiments are only used to illustrate the technical solutions of the present invention, and not to limit them. Although the present invention has been described in detail with reference to the foregoing embodiments, those skilled in the art should understand that modifications can still be made to the technical solutions described in the foregoing embodiments, or equivalent substitutions can be made to some or all of the technical features therein. These modifications or substitutions do not cause the essence of the corresponding technical solutions to deviate from the scope of the technical solutions of the embodiments of the present invention, and they should all be covered within the scope of the claims and specification of the present invention. In particular, as long as there is no structural conflict, the various technical features mentioned in the embodiments can be combined in any way. The present invention is not limited to the specific embodiments disclosed herein, but includes all technical solutions falling within the scope of the claims.
Claims
1. A device for simulating and evaluating the ability of a plug to stop a malignant loss of drilling fluid in a limestone formation, characterized in that, include: A fracture-cavity simulation system (1) is used to simulate formation leakage channels and observe the sealing situation; Formation water simulation injection system (2) is used to inject formation water into the fracture-cavity simulation system (1); A plugging agent simulation injection system (3) is used to inject plugging agent into the cavity simulation system (1); The outlet constant pressure control system (4) is used to keep the hole simulation system (1) dynamically constant pressure.
2. The simulation evaluation device according to claim 1, characterized by The hole simulation system (1) includes: The simulator body (101) has a water inlet on one side and a drain on the other side, and the formation water simulation injection system (2) is connected to the water inlet of the simulator body (101). An observation window (102) is set on the simulator body (101); A visible well shaft (103) is vertically connected to the simulator body (101) and communicates with the inner cavity of the simulator body (101); A sealing end cap (104) is disposed on the top of the visible well shaft (103), and an intermediate chamber (105) is provided inside the sealing end cap (104); The drill pipe assembly (106) is coaxially disposed inside the visible wellbore (103) and forms a wellbore annular cavity (107) with the visible wellbore (103). The drill pipe assembly (106) communicates with the inner cavity of the simulator body (101). The top of the drill pipe assembly (106) extends into the intermediate chamber (105) and is rotatably connected to the sealing end cap (104). A feed hole (108) is provided at the top of the drill rod assembly (106); A motor assembly (109) is used to control the rotation of the drill rod assembly (106); The first feed connector (110) is connected at one end to the sealing end cap (104) and communicates with the intermediate chamber (105), and at the other end to the plugging agent simulation injection system (3).
3. The simulation evaluation device according to claim 2, characterized by The plugging agent simulation injection system (3) includes: Piston tanks (301), four in number, which store formation water, release agent, plugging agent, and release agent in sequence; The squeezing mechanism (302) is used to inject water into the corresponding piston can (301) to squeeze the piston inside the corresponding piston can (301), thereby discharging the medicine; There are four discharge pipes (303), which are connected to the bottom of the corresponding piston tanks (301); The main injection pipe (304) is connected to the four discharge pipes (303) respectively; The first injection branch pipe (305) is connected at one end to the injection main pipe (304) and at the other end to the first feed connector (110), and a first injection valve (307) is provided on the first injection branch pipe (305).
4. The simulation evaluation device according to claim 3, characterized by The plugging agent simulation injection system (3) also includes: The second feed connector (308) is connected to the visible well shaft (103) and communicates with the well shaft annular cavity (107); The second injection branch pipe (306) is connected at one end to the injection main pipe (304) and at the other end to the second feed connector (308), and a second injection valve (309) is provided on the second injection branch pipe (306).
5. The simulation evaluation device according to claim 3, characterized by The plugging agent simulation injection system (3) also includes: Four three-way valves (316) are connected to the corresponding discharge pipes (303); Collection pool (317) for collecting waste; Four collection branch pipes (318) are provided, each connected to a corresponding three-way valve (316). The main collection pipe (319) is connected at one end to the collection pool (317) and at the other end to the four collection branch pipes (318) respectively; The flushing pipe (320) is connected at one end to the main injection pipe (304) and at the other end to the formation water simulation injection system (2), and a flushing valve (321) is provided on the flushing pipe (320).
6. The simulation evaluation device according to claim 3, characterized by The extrusion mechanism (302) includes: Water storage tank (310) for storing clean water; There are four water inlet branch pipes (311), which are connected to the top of the corresponding piston tank (301); The main water inlet pipe (312) is connected at one end to the water storage tank (310) and at the other end to the four water inlet branch pipes (311) respectively. A piston pump (313), a water inlet valve (314) and a first flow meter (315) are connected sequentially on the water inlet branch pipes (311).
7. The simulation evaluation device according to claim 6, characterized by The formation water simulation injection system (2) includes: Formation water tank (201), used for storing formation water; The water injection pipe (202) is connected at one end to the formation water tank (201) and at the other end to the water inlet of the simulator body (101). A centrifugal pump (205), a second flow meter (206), a water injection valve (207) and a pressure gauge (208) are connected in sequence on the water injection pipe (202). The circulation pipe (203) is connected at one end to the drain end of the simulator body (101) and at the other end to the formation water tank (201), and a circulation valve (209) is provided on the circulation pipe (203); The regulating pipe (204) is connected at one end to the water injection pipe (202) and at the other end to the formation water tank (201). The regulating pipe (204) is located between the centrifugal pump (205) and the second flow meter (206), and a regulating valve (210) is provided on the regulating pipe (204).
8. The simulation evaluation device according to claim 7, characterized by The formation water simulation injection system (2) also includes: The booster pipe (211) is connected at one end to the main water inlet pipe (312) and at the other end to the water inlet of the simulator body (101). The booster pipe (211) is equipped with a booster valve (212) and a third flow meter (213).
9. The simulation evaluation device according to claim 2, characterized by The outlet constant pressure control system (4) includes: Collect graduated cylinder (401); The back pressure pipe (404) is connected at one end to the drain end of the simulator body (101) and at the other end to the collecting cylinder (401). The back pressure pipe (404) is equipped with a back pressure valve (403) and a back pressure pump group (404). The discharge pipe (405) is connected to the drain end of the simulator body (101).
10. A method of operating the device for simulating and evaluating the lost circulation plugging capacity of limestones according to any one of claims 1 to 9, characterized in that, Includes the following steps: S1, Formation water is injected into the fracture-cavity simulation system (1) through the formation water simulation injection system (2); S2, through the plugging agent simulation injection system (3), release agent, plugging agent, and release agent are sequentially injected into the cavity simulation system (1); S3, observe the sealing situation through the crack simulation system (1); S4, adjust the injection pressure of the formation water simulation injection system (2) to test the pressure limit of the plugging agent.