A downhole directional hydraulic fracturing roof depressurization system and method

By using a mechanical locking structure with a rotating sleeve and a limiting pawl, along with a stress monitoring device, and combining a multi-stage fracturing sandblasting device and a packer, the problems of disordered fracture propagation and cumbersome segmented operations in downhole directional hydraulic fracturing devices have been solved, achieving precise directional fracture propagation and improved construction efficiency.

CN123109655APending Publication Date: 2026-11-17NORTH CHINA INSTITUTE OF SCIENCE & TECHNOLOGY (NATIONAL SAFETY TRAINING CENTER OF COAL MINES)
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202611428299.X
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2026-09-15
Publication Date
2026-11-17

AI Technical Summary

Technical Problem

Existing downhole directional hydraulic fracturing roof fracturing and pressure relief devices have shortcomings in terms of fracture controllability and construction efficiency. They cannot accurately control the fracture initiation direction and extension trajectory, and the segmented fracturing operation is cumbersome, prolonging downhole operation time and increasing safety risks.

Method used

The mechanical locking structure of rotating sleeve and limiting pawl, combined with stress monitoring device and multi-stage fracturing sandblasting and packer, realizes directional injection and closed-loop control, ensuring stable propagation of fractures along the direction of maximum horizontal principal stress, and achieves continuous segmented fracturing through step-by-step ball dropping design.

Benefits of technology

It achieves precise directional propagation and uniform weakening of fractures, reducing downhole operation time and safety risks, and improving construction efficiency and cost control.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN123109655A_ABST
    Figure CN123109655A_ABST
Patent Text Reader

Abstract

This invention discloses a directional hydraulic fracturing roof fracturing and pressure relief system and method for underground coal mines, belonging to the field of underground hydraulic fracturing technology. It includes a high-pressure fracturing pump unit installed in the roadway, and a long directional borehole drilled into the roof strata and extending horizontally along the roof strata. A high-pressure hose is inserted into the long directional borehole, with one end connected to the high-pressure fracturing pump unit and the other end fixedly connected to a tool string arranged axially along the long directional borehole. This invention employs a rotating sleeve and a limiting pawl to ensure that the fracture always expands stably along the direction of the maximum horizontal principal stress, accurately cutting off the roof stress transmission arch and completely solving the defects of disordered, bifurcated, and uneven pressure relief in traditional fracturing. This invention also employs a multi-stage fracturing sandblaster and packer, enabling the tool string to irreversibly open the fracturing sandblaster and packer in a bottom-to-top sequence, completing all segmented fracturing operations and significantly reducing the total underground operation time and auxiliary process time.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This invention belongs to the field of underground hydraulic fracturing technology in coal mines, specifically a system and method for directional hydraulic fracturing of the roof to induce fracturing and relieve pressure. Background Technology

[0002] Directional hydraulic fracturing of the roof in underground mines is an advanced technology used to actively control hard roofs in coal mines and prevent dynamic disasters such as rockbursts. Its core lies in injecting high-pressure water into directional boreholes in the target rock formation underground via a surface high-pressure pump station. This forces the rock mass to generate and expand fractures, thereby systematically weakening the roof and releasing accumulated energy.

[0003] Existing downhole directional hydraulic fracturing roof depressurization devices have serious defects in both fracture controllability and construction efficiency. On the one hand, the fracturing blaster uses radial uniform sandblasting and lacks a mechanical guiding structure. After high-pressure water is injected, it spreads randomly along the fracture due to the lack of directional constraint, making it impossible to effectively control the fracture initiation direction and extension trajectory. This results in random fracture extension and frequent bifurcation and deviation, making it difficult to stably extend along the direction of the maximum horizontal principal stress and to accurately cut off the stress transmission arch of the roof, ultimately leading to a non-uniform weakening of the roof. On the other hand, the segmented fracturing operation adopts a serial process of "single-segment fracturing - complete depressurization - drainage - tubing removal - repositioning and resealing". Each additional segment of fracturing requires repeating the entire set of cumbersome operations. When operating multiple segments, repeated disassembly and adjustment not only drastically extends the total downhole operation time and adds unnecessary auxiliary procedures, but also forces operators to be exposed to extreme high-risk environments such as high gas and high stress for a long time, significantly increasing safety risks. Moreover, the entire process cannot achieve continuous cyclic fracturing. The combination of these two shortcomings weakens the accuracy and stability of the pressure relief effect and severely restricts construction efficiency and large-scale application.

[0004] Therefore, it is necessary to provide a downhole directional hydraulic fracturing roof fracturing and depressurization system and method to solve the problems mentioned in the background art. Summary of the Invention

[0005] To achieve the above objectives, the present invention provides the following technical solution: a downhole directional hydraulic fracturing roof fracturing and pressure relief system, comprising:

[0006] A high-pressure fracturing pump unit is installed in the roadway;

[0007] A directional long borehole, wherein the directional long borehole is drilled in the top rock stratum and extends horizontally along the top rock stratum;

[0008] A high-pressure hose is inserted into the directional long borehole; one end of the high-pressure hose is connected to the high-pressure fracturing pump unit, and the other end of the high-pressure hose is fixedly connected to a tool string;

[0009] A tool string located inside the directional long borehole and arranged along the axial direction of the directional long borehole; the tool string includes a dropper, a fracturing sandblasting device and a packer arranged in an alternating manner, a check valve and a guide shoe connected in sequence from the borehole opening to the bottom of the borehole.

[0010] The fracturing sandblasting device includes an outer cylinder, on which a set of fracturing ports are evenly opened on the outer circumferential side wall; a rotating sleeve is coaxially rotatably installed inside the outer cylinder, and a jet groove corresponding to the position of each fracturing port is opened on the cylinder wall of the rotating sleeve.

[0011] The ball is thrown in conjunction with each of the fracturing blasting machines and the corresponding packers to seal the directional long borehole step by step.

[0012] Furthermore, as a preferred embodiment, the guide shoe is a conical guide structure and is located at the bottom of the tool string; the guide shoe guides the tool string into the directional long borehole.

[0013] Furthermore, as a preferred embodiment, the one-way valve is disposed between the third packer and the guide shoe. The one-way valve allows high-pressure fracturing fluid to flow unidirectionally into the bottom of the directional long borehole, preventing the fluid in the directional long borehole from flowing back during fracturing operations.

[0014] Furthermore, as a preferred embodiment, the fracturing blasting device includes a first fracturing blasting device, a second fracturing blasting device, and a third fracturing blasting device; the packer includes a first packer, a second packer, and a third packer.

[0015] Furthermore, as a preferred embodiment, the fracturing blasting device further includes an inner cylinder, a sliding sleeve, and a pin; a set of limiting pawls are evenly arranged circumferentially between the rotating sleeve and the outer cylinder, each limiting pawl is rotatably connected to the outer cylinder, and a limiting spring ring is commonly fitted on the outer side of each limiting pawl; a limiting toothed ring is machined at the end of the rotating sleeve near the limiting spring ring, and the limiting toothed ring forms a one-way meshing engagement with each limiting pawl; a rotating toothed ring is machined at the end of the rotating sleeve away from the limiting spring ring;

[0016] The inner cylinder is coaxially fitted inside the outer cylinder. A fixing groove is provided at one end of the inner cylinder near the rotating sleeve. A motor is fixedly installed in the fixing groove. A gear is fixedly connected to the output shaft end of the motor. The gear meshes with the rotating gear ring on the rotating sleeve.

[0017] The sliding sleeve is slidably assembled in the internal channel formed by the outer cylinder, the rotating sleeve and the inner cylinder, and its initial position is fixed by the pin. After the ball is thrown into the internal channel of the outer cylinder from the tunnel, the ball pushes the sliding sleeve to move axially, shearing the pin, thereby opening the jet channel and allowing the fracturing fluid to be ejected through the jet channel and the corresponding fracturing port.

[0018] Furthermore, as a preferred embodiment, the first fracturing sandblaster, the second fracturing sandblaster, and the third fracturing sandblaster have the same structure, but the inner diameter of the sliding sleeves provided inside the three are progressively smaller.

[0019] Furthermore, as a preferred embodiment, a set of stress monitoring devices is fixedly installed on the outer circumferential sidewall of the outer cylinder, and the installation position of each stress monitoring device is circumferentially offset from each fracturing port.

[0020] A method for depressurizing the roof of a well using downhole directional hydraulic fracturing includes the following steps:

[0021] S1. Tool insertion and positioning: The guide shoe guides the tool string to be smoothly lowered into the directional long borehole; the sliding sleeve is locked by the pin, and the jet groove is sealed with the fracturing port;

[0022] S2. Perforation: Insert a ball that matches the inner diameter of the sliding sleeve of the first fracturing sandblaster, set the sliding sleeve, pump in high-pressure fluid, cut the pin, and after the sliding sleeve is removed, the flow channel is open, and the jet penetrates the hole wall to form a fracturing channel.

[0023] S3. Directional fracturing: High-pressure fracturing fluid is injected into the top rock layer through the fracturing port. After exceeding the fracturing pressure, artificial fractures are formed, and proppant enters with the fluid to prevent closure. Simultaneously, closed-loop control is implemented. The stress monitoring device collects stress signals from all directions, and the control system inverts and calibrates the optimal fracturing orientation. The control system controls the motor to drive the rotating sleeve to align the jet channel with the target, and the fracturing port switches directions. Dynamic corrections are made when encountering fracture deviation or stress transfer, realizing single-stage multi-angle directional fracturing.

[0024] S4. Inter-segment switching and multi-segment cycle: The inner diameter of the sliding sleeves of the three fracturing blasting machines decreases step by step to match the ball with different diameters; a larger diameter ball is inserted, which passes through the unopened large inner diameter sliding sleeve and sets the next smaller inner diameter sliding sleeve, repeating the "setting-perforation-fracturing" process; one pass of the tool string irreversibly opens each of the fracturing blasting machines from bottom to top, completing continuous segmented fracturing.

[0025] Compared with the prior art, the beneficial effects of the present invention are:

[0026] This invention employs a rotating sleeve and a limiting pawl, abandoning the traditional radial uniform sandblasting structure. Through the mechanical locking of the rotating sleeve and the limiting pawl, directional spraying is achieved: rotating to the target position locks the angle, preventing high-pressure water flow impact deviation and concentrating hydraulic energy in a single direction to form directional cutting capability, precisely initiating cracks and expanding them along a preset surface. Simultaneously, stress monitoring devices are circumferentially misaligned on the outer wall of the outer cylinder to collect stress signals from all directions in real time. The control system inverts the stress field and instructs the motor to switch the jet direction. During fracturing, the stress redistribution caused by crack expansion is continuously monitored. If deviation is detected, the orientation is recalculated and corrected, forming a closed loop of "monitoring-decision-switching-correction". This ensures that the crack always expands stably along the direction of the maximum horizontal principal stress, precisely cutting off the stress transmission arch of the top plate, weakening uniformity and controllability, and completely solving the defects of disordered, bifurcation, and uneven pressure relief in traditional fracturing.

[0027] This invention employs a multi-stage fracturing jetting device and packer, wherein the sliding sleeve in the fracturing jetting device and the central tube in the packer adopt a "smaller at the bottom and larger at the top" diameter design. By matching balls of different diameters with the sliding sleeve and central tube one by one, the fracturing jetting device and packer can be irreversibly opened in a single tool string from bottom to top, completing all stages of fracturing construction. This significantly reduces the total downhole operation time and auxiliary process time, minimizes the number of times the tubing string is pulled out and back in, thereby significantly reducing the risk of downhole accidents such as stuck pipe and eccentric wear. At the same time, it reduces the waste of multiple pumping injections of fracturing fluid and proppant, effectively controlling the construction cost of a single well. Attached Figure Description

[0028] Figure 1 This is a schematic diagram of the overall structure of the present invention;

[0029] Figure 2 This is a schematic diagram of the toolchain structure in this invention;

[0030] Figure 3 This is a schematic diagram of the fracturing sandblasting device in this invention;

[0031] Figure 4 This is a schematic diagram of the internal structure of the fracturing sandblasting device in this invention;

[0032] Figure 5 This is a schematic diagram of the packer structure in this invention;

[0033] Figure 6 This is a schematic diagram of the internal structure of the packer in this invention;

[0034] In the diagram: 1. High-pressure fracturing pump unit; 2. Tunnel; 3. Directional long borehole; 4. Roof strata; 5. High-pressure hose; 6. Tool string; 7. Fracturing blasting machine; 71. First fracturing blasting machine; 72. Second fracturing blasting machine; 73. Third fracturing blasting machine; 74. Outer cylinder; 741. Fracturing port; 75. Inner cylinder; 751. Fixing groove; 76. Sliding sleeve; 77. Pin; 78. Rotating sleeve; 781. Limiting gear ring; 782. Rotating gear ring; 783. Jet channel; 79. Gear; 710. Motor; 71 1. Limiting pawl; 712. Limiting spring ring; 8. Packer; 81. First packer; 82. Second packer; 83. Third packer; 84. Upper connector; 85. Centralizing body; 851. Centralizing block; 86. Middle ring; 87. Vase spring; 88. Vase tooth; 89. Central tube; 810. Cone; 811. One-way locking ring; 812. Shear pin; 813. Rubber sleeve; 814. Load-bearing ring; 815. Lower connector; 9. Release handle; 10. One-way valve; 11. Guide shoe; 12. Throwing ball; 13. Coal seam. Detailed Implementation

[0035] Please see Figures 1-6 In this embodiment of the invention, a downhole directional hydraulic fracturing roof fracturing and depressurization system includes:

[0036] High-pressure fracturing pump unit 1 is installed in roadway 2;

[0037] Directional long borehole 3 is drilled in the top rock layer 4 and extends horizontally along the top rock layer 4;

[0038] High-pressure hose 5 is inserted into the directional long borehole 3; one end of high-pressure hose 5 is connected to high-pressure fracturing pump group 1, and the other end of high-pressure hose 5 is fixedly connected to tool string 6.

[0039] Tool string 6 is located inside the directional long borehole 3 and arranged along the axial direction of the directional long borehole 3; the tool string 6 includes a dropper 9 connected in series from the borehole opening to the bottom of the borehole, a fracturing sandblasting gun 7 and a packer 8 arranged in an alternating manner, a check valve 10 and a guide shoe 11.

[0040] The fracturing blasting machine 7 includes an outer cylinder 74, on which a set of fracturing ports 741 are evenly opened; a rotating sleeve 78 is coaxially mounted inside the outer cylinder 74, and a jet groove 783 corresponding to the position of each fracturing port 741 is opened on the cylinder wall of the rotating sleeve 78. When the rotating sleeve 78 rotates, the jet groove 783 can be aligned with each fracturing port 741 in sequence to realize the switching of the spraying direction.

[0041] Ball 12 is used in conjunction with each fracturing blasting machine 7 and the corresponding packer 8 to seal the directional long borehole 3 step by step.

[0042] The high-pressure fracturing pump unit 1 delivers high-pressure fracturing fluid to the tool string 6 through the high-pressure hose 5. The tool string 6, through the cooperation of each fracturing sandblaster 7 and the corresponding packer 8, performs multi-stage continuous hydraulic fracturing operations on the top rock layer 4.

[0043] In this embodiment, the guide shoe 11 is a conical guide structure and is located at the bottom of the tool string 6; the guide shoe 11 guides the tool string 6 into the directional long borehole 3. While preventing the tool string 6 from scraping the borehole wall of the directional long borehole 3, the guide shoe 11 grinds the protruding coal and rock on the borehole wall, clears the passage, and ensures smooth delivery to the predetermined section.

[0044] In a preferred embodiment, the one-way valve 10 is disposed between the third packer 83 and the guide shoe 11. The one-way valve 10 allows high-pressure fracturing fluid to flow unidirectionally into the bottom of the directional long borehole 3, preventing the fluid in the directional long borehole 3 from flowing back during fracturing operations.

[0045] On the one hand, it effectively prevents the high-pressure fracturing fluid at the bottom of the hole from flowing backward during fracturing operations, avoiding premature unsealing of the packer 8 due to reverse pressure differential caused by pressure backflow; on the other hand, by cutting off the return path, it ensures that the pressure inside the packer 8's sealing cavity is stable and does not leak, thereby maintaining its continuous and reliable expansion and sealing state, and ensuring the isolation effectiveness of each packer section during the segmented fracturing process.

[0046] In this embodiment, the fracturing blasting device 7 includes a first fracturing blasting device 71, a second fracturing blasting device 72, and a third fracturing blasting device 73; the packer 8 includes a first packer 81, a second packer 82, and a third packer 83.

[0047] In this embodiment, the fracturing blasting machine 7 also includes an inner cylinder 75, a sliding sleeve 76, and a pin 77; a set of limiting pawls 711 are evenly arranged circumferentially between the rotating sleeve 78 and the outer cylinder 74, each limiting pawl 711 is rotatably connected to the outer cylinder 74, and a limiting spring ring 712 is sleeved on the outer side of each limiting pawl 711, the limiting spring ring 712 is used to provide circumferential locking force; a limiting toothed ring 781 is machined at the end of the rotating sleeve 78 near the limiting spring ring 712, the limiting toothed ring 781 and each limiting pawl 711 form a one-way meshing engagement; a rotating toothed ring 782 is machined at the end of the rotating sleeve 78 away from the limiting spring ring 712.

[0048] The inner cylinder 75 is coaxially fitted inside the outer cylinder 74. A fixing groove 751 is provided at one end of the inner cylinder 75 near the rotating sleeve 78. A motor 710 is fixedly installed in the fixing groove 751. A gear 79 is fixedly connected to the output shaft end of the motor 710. The gear 79 meshes with the rotating gear ring 782 on the rotating sleeve 78 to drive the rotating sleeve 78 to rotate.

[0049] The sliding sleeve 76 is slidably assembled in the internal channel formed by the outer cylinder 74, the rotating sleeve 78 and the inner cylinder 75, and its initial position is limited and fixed by the pin 77. After the ball 12 is inserted into the internal channel of the outer cylinder 74 from the roadway 2, the ball 12 pushes the sliding sleeve 76 to move axially, shears the pin 77, thereby opening the jet channel 783, so that the fracturing fluid can be ejected through the jet channel 783 and the corresponding fracturing port 741.

[0050] 1. Unlocked at pitching level 12, opening the jet channel.

[0051] Before fracturing, the ball 12 is inserted into the internal channel of the outer cylinder 74 from the roadway 2. The ball 12 moves down the channel to the sliding sleeve 76. Under hydraulic propulsion, the sliding sleeve 76 is pushed to move axially and shear the initial limiting pin 77. After the sliding sleeve 76 is removed from its original position, the internal flow channel between the jet groove 783 and the fracturing port 741 is completely opened, and the fracturing fluid can flow from the inner cylinder 75 through the jet groove 783 to the fracturing port 741 of the outer cylinder 74, providing a passage for subsequent directional injection.

[0052] 2. Motor 710 starts, driving the rotating sleeve 78 to rotate.

[0053] When it is necessary to switch the injection direction, the control system issues a command to start the motor 710. The output shaft of the motor 710 drives the fixed gear 79 to rotate synchronously. The gear 79 meshes with the rotating gear ring 782 on the rotating sleeve 78, transmitting the driving force to the rotating sleeve 78, forcing the rotating sleeve 78 to rotate relative to the outer cylinder 74 around its own axis.

[0054] 3. The 711 limit pawl, in conjunction with the 711, enables directional switching.

[0055] During the rotation of the rotating sleeve 78, the limiting toothed ring 781 at its end rotates synchronously. The limiting toothed ring 781 and the circumferentially arranged limiting pawls 711 move relative to each other. Under the elastic constraint of the limiting spring ring 712, each limiting pawl 711 always fits against the limiting toothed ring 781, forming a one-way step-by-step meshing. Every time the rotating sleeve 78 rotates through one tooth pitch, the limiting pawl 711 engages with the next tooth groove, which not only ensures the continuity of rotation but also prevents the rotating sleeve 78 from reversing under the action of the fracturing fluid backlash. As the rotating sleeve 78 rotates gradually, the unique jet groove 783 on its cylinder wall is aligned sequentially with each fracturing port 741 that is evenly distributed circumferentially on the outer cylinder 74, thereby realizing the control of the injection direction from discrete positioning to precise switching.

[0056] 4. The fracturing fluid is injected in a directional manner to carry out selective fracturing.

[0057] Once the jet channel 783 is aligned with the target fracturing port 741, the high-pressure fracturing fluid is ejected outward through the fracturing port 741 and acts on the top rock layer 4. By repeatedly controlling the rotation angle and number of steps of the motor 710, fracturing can be performed sequentially or selectively in multiple preset radial directions, realizing the artificial control of the fracture initiation direction and avoiding the blind diffusion of fracturing fluid along disordered fractures.

[0058] In this embodiment, the first fracturing sandblaster 71, the second fracturing sandblaster 72, and the third fracturing sandblaster 73 have the same structure, but the inner diameter of the sliding sleeve 76 inside each of them decreases in turn. The sliding sleeve 76 in the first fracturing sandblaster 71, the second fracturing sandblaster 72, and the third fracturing sandblaster 73 adopts a different diameter design. By matching the ball 12 of different diameters with the sliding sleeve 76 one by one, the fracturing sandblaster 7 can be irreversibly opened in a bottom-to-top sequence in one pass of the tool string 6 to complete the layered fracturing operation.

[0059] In this embodiment, a set of stress monitoring devices (not shown in the figure) are fixedly installed on the outer circumferential sidewall of the outer cylinder 74, and the installation position of each stress monitoring device is circumferentially offset from each fracturing port 741.

[0060] The stress monitoring device and the fracturing blasting machine 7 work together to form a complete closed-loop directional fracturing system: The stress monitoring devices, circumferentially staggered on the outer wall of the outer cylinder 74, begin to collect stress response signals of the roof rock strata 4 in all directions around the directional long borehole 3 in real time after the packer 8 is set, and transmit the data back to the control system. After the stress field distribution is inverted by the algorithm, the optimal fracturing orientation (i.e., the orientation consistent with the direction of the maximum horizontal principal stress and capable of effectively cutting off the stress transmission arch of the roof) is accurately determined; subsequently, the control system sends a command to the motor 710, driving the gear 79 to rotate the rotating sleeve 78. The unidirectional stepping action of the limiting pawl 711 and the limiting spring ring 712 enables the jet channel 783 to be precisely aligned with the target fracturing opening 741, completing a rapid switch in the injection direction. During fracturing, the stress monitoring device continuously monitors the redistribution of surrounding rock stress caused by crack propagation. Once crack deviation or stress concentration zone shift is detected, the control system recalculates and corrects the orientation and readjusts the rotating sleeve 78, switching the jet to the new target fracturing opening 741 for dynamic correction. In this way, multi-angle and multi-round directional control is achieved within a single fracturing stage, ensuring accurate and reliable fracturing effect.

[0061] In a preferred embodiment, the packer 8 includes an upper connector 84, a central tube 89, a cone 810, a shear pin 812, a rubber sleeve 813, and a lower connector 815; the upper connector 84 is slidably connected to the upper end of the central tube 89, and a straightener 85 is slidably fitted on the outside of the central tube 89 below the upper connector 84, and a straightener block 851 is embedded in the circumferential groove of the straightener 85;

[0062] A middle ring 86 is provided below the straightening body 85. A slip tooth 88 that is slidably connected to the central tube 89 is installed on the inner side of the middle ring 86. A slip spring 87 is provided between the slip tooth 88 and the middle ring 86.

[0063] A cone 810 is fitted onto the outside of the central tube 89 and located below the slip tooth 88. The conical surface of the cone 810 mates with the inner conical surface of the slip tooth 88. The cone 810 provides a radially expanding ramp for the slip tooth 88, pushing it outward during setting and anchoring it to the inner wall of the directional long borehole 3. Below the cone 810, a one-way locking ring 811 is fitted onto the outside of the central tube 89. A shear pin 812 passes radially through the one-way locking ring 811 and connects to the central tube 89 to limit the initial position of the one-way locking ring 811. The one-way locking ring 811 engages with a one-way tooth groove (not shown in the figure) on the outer wall of the central tube 89 to achieve one-way locking.

[0064] The rubber sleeve 813 is fitted onto the outside of the central tube 89, and the upper end of the rubber sleeve 813 abuts against the one-way locking ring 811; a load-bearing ring 814 is fitted onto the outside of the rubber sleeve 813; the lower connector 815 is fixedly connected to the lower end of the central tube 89, and the upper end of the lower connector 815 abuts against the lower end of the rubber sleeve 813; the rubber sleeve 813 expands radially under pressure and fits tightly against the inner wall of the directional long drill hole 3; the load-bearing ring 814 transmits axial compressive force, evenly squeezing the rubber sleeve 813 to ensure that the sealing surface is subjected to uniform force.

[0065] The central tube 89 is the main channel for fracturing fluid, responsible for delivering high-pressure fracturing fluid. When the centralizer 85 is lowered, it ensures that the tool string 6 is centered to prevent uneven wear on the packer 8. During setting, the auxiliary slip teeth 88 open evenly to avoid unilateral stress and bear part of the radial load, protecting the slip teeth 88 and the rubber sleeve 813. The central ring 86, as the core support component of the centralizer 85, cooperates with the centralizer block 851 of the centralizer 85 to form a stable radial support structure. During the lowering process, the central ring 86 can keep the entire packer 8 at the center of the directional long borehole 3, preventing the rubber sleeve 813 and slip teeth 88 from unevenly wearing the inner wall of the directional long borehole 3, reducing lowering resistance and wear.

[0066] The sliding sleeve 76 moves, driving the upper connector 84 to push the centering body 85 to move axially, opening the slip teeth 88. The slip teeth 88 are embedded in the inner wall of the directional long borehole 3, completing the anchoring. At the same time, the axial force is transmitted to the cone 810 and the one-way locking ring 811. When the pressure reaches the set value, the shear pin 812 is sheared, and the rubber sleeve 813 is compressed and expanded, radially pressing against the inner wall of the long borehole 4, completing the seal. After the setting is in place, the one-way locking ring 811 automatically locks the rubber sleeve 813 to prevent pressure fluctuations from causing the rubber sleeve 813 to rebound. After the construction is completed, the locking of the one-way locking ring 811 is released by lifting the pipe column. The rubber sleeve 813 and the slip teeth 88 retract respectively, releasing the anchoring and sealing state. The tool returns to its original outer diameter and is smoothly pulled out along the directional long borehole 3, completing the entire operation process.

[0067] In a preferred embodiment, the first packer 81, the second packer 82, and the third packer 83 have the same structure and are all expandable packers, but the inner diameter of the central tube 89 inside each packer decreases in turn. After the packer 8 expands under the influence of high-pressure fracturing fluid, it seals against the borehole wall of the directional long borehole 3.

[0068] A method for depressurizing the roof of a well using downhole directional hydraulic fracturing includes the following steps:

[0069] S1. Tool Insertion and Positioning: The tool string 6 is lowered from the roadway 2 through the directional long borehole 3. The conical guide shoe 11 at its bottom guides the tool string 6 smoothly along the trajectory of the directional long borehole 3, simultaneously grinding away any protruding coal and rock from the borehole wall and clearing the passageway to prevent the tool string 6 from scraping against the borehole wall. At this time, the sliding sleeves 76 inside each fracturing and sandblasting nozzle 7 are locked in their initial positions by pins 77, and the flow channel between the jet channel 783 and the fracturing port 741 is in a closed state. The slip teeth 88 of each packer 8 are retracted, and the rubber sleeve 813 is in a contracted state. The overall outer diameter is smaller than the inner diameter of the directional long borehole 3, allowing for smooth insertion into the target layer. During insertion, the centralizing body 85 and centralizing block 851 of the packer 8 cooperate with the central ring 86 to keep the tool string 6 always centered in the directional long borehole 3, preventing the rubber sleeve 813 and slip teeth 88 from excessively abrading the borehole wall.

[0070] S2. Initial Setting and Perforation: After the tool string 6 is in place, a ball 12, matching the inner diameter of the sliding sleeve 76 of the first fracturing blower 71, is inserted from the tunnel 2 into the high-pressure hose 5. The ball 12 descends along the internal channels of the high-pressure hose 5 and the central tube 89, settling on the sliding sleeve 76 of the first fracturing blower 71 and sealing its internal channels. High-pressure fracturing fluid continues to be pumped in, hydraulically pushing the sliding sleeve 76 to move axially, shearing the pin 77, thus completing two actions simultaneously:

[0071] (1) Packer 8 sets: The sliding sleeve 76 moves and drives the upper connector 84 to push the centering body 85 to move axially, opening the slip teeth 88 so that they are embedded in the inner wall of the directional long drill hole 3 to complete the anchoring; the axial force continues to be transmitted to the cone 810 and the one-way locking ring 811. When the pressure reaches the set value, the shear pin 812 is sheared, the rubber sleeve 813 is compressed and expanded, and it radially adheres to the inner wall of the directional long drill hole 3 to complete the seal; after the setting is in place, the one-way locking ring 811 automatically locks the rubber sleeve 813 to prevent pressure fluctuations from causing rebound.

[0072] (2) Fracturing channel establishment: After the sliding sleeve 76 is removed from its original position, the internal flow channel between the jet groove 783 and the fracturing port 741 is opened, and the high-pressure fracturing fluid is sprayed outward through the jet groove 783 and the fracturing port 741, penetrating the borehole wall to form a fracturing channel in the top rock layer 4.

[0073] S3. Directional fracturing operation: High-pressure fracturing pump unit 1 continues to pressurize and inject fracturing fluid. The fluid enters the top rock layer 4 through the opened fracturing port 741 and fracturing channel. When the injection pressure exceeds the rock layer fracturing pressure, the top rock layer 4 is forced open to form an artificial fracture. The proppant in the fracturing fluid enters the fracture with the fluid to prevent the fracture from closing.

[0074] During fracturing, directional control and dynamic correction are carried out simultaneously:

[0075] Stress sensing: The stress monitoring device, which is circumferentially misaligned on the outer wall of the outer cylinder 74, collects stress response signals of the top rock layer 4 in all directions around the directional long borehole 3 in real time and transmits the data back to the control system.

[0076] Orientation decision: The control system uses an algorithm to invert the stress field distribution and accurately calibrate the optimal crack-inducing orientation, which is the orientation that is consistent with the direction of the maximum horizontal principal stress and can effectively cut off the stress transmission arch of the top plate.

[0077] Direction switching: The control system sends a command to the motor 710, which drives the gear 79 to rotate, and drives the rotating sleeve 78 to rotate via the rotating gear ring 782; Under the one-way stepping engagement of the limiting pawl 711 and the limiting spring ring 712, the rotating sleeve 78 rotates precisely to the preset angle, so that the jet groove 783 is aligned with the target fracturing opening 741, and the injection direction switching is completed.

[0078] Dynamic correction: During the fracturing process, the stress monitoring device continuously provides feedback on the redistribution of stress in the surrounding rock. Once the fracturing deviation or the shift of the stress concentration zone is detected, the control system recalculates the correction orientation and readjusts the rotating sleeve 78, switching the jet to the new target fracturing opening 741 to implement dynamic correction, thereby achieving multi-angle and multi-round directional control within a single fracturing stage.

[0079] S4. Inter-segment switching and multi-segment cycle: After the current segment fracturing is completed, an inter-segment switching operation is performed. The core mechanism is that the diameter of the ball 12 is matched with the inner diameter of the sliding sleeve 76 in stages: the first fracturing blasting machine 71, the second fracturing blasting machine 72 and the third fracturing blasting machine 73 have the same structure, but the inner diameter of the sliding sleeve 76 inside the three machines decreases in stages, matching different diameter balls 12. When it is necessary to open the next segment, a larger diameter ball 12 is put into the tunnel 2. The ball 12 passes through the unopened fracturing blasting machine 7 (because the large ball cannot sit in the unopened large inner diameter sliding sleeve 76, it will continue to descend) until it lands on the sliding sleeve 76 of the next stage fracturing blasting machine 7 (with a smaller inner diameter), repeating the above "setting-perforation-fracturing" process.

[0080] By using this step-by-step ball-throwing method 12, the fracturing sandblasting guns 7 can be irreversibly activated in a single pass of tool string 6 in a bottom-to-top sequence, thus completing segmented continuous fracturing construction.

[0081] S5. Unsealing and Retrieval: After all fracturing operations in all sections are completed, a circulating well flush is performed to remove residual sand particles from the tool string 6. The tubing string is then pulled up, releasing the locking state of the one-way locking ring 811. The rubber sleeve 813 retracts under elastic restoring force, the slip teeth 88 close, and the packer 8 is released from its anchoring and sealing state, restoring the overall outer diameter to its initial size. The tool string 6 is then successfully retrieved along the directional long borehole 3, completing the entire fracturing operation.

[0082] The above description is merely a preferred embodiment of the present invention, but the scope of protection of the present invention is not limited thereto. Any equivalent substitutions or modifications made by those skilled in the art within the scope of the technology disclosed in the present invention, based on the technical solution and inventive concept of the present invention, should be covered within the scope of protection of the present invention.

Claims

1. A downhole directional hydraulic fracturing roof cracking pressure relief system characterized by, It includes: High-pressure fracturing pump unit (1), wherein the high-pressure fracturing pump unit (1) is installed in the roadway (2); Directional long borehole (3), the directional long borehole (3) is opened in the top rock layer (4) and extends horizontally along the top rock layer (4); High-pressure hose (5) is inserted into the directional long borehole (3); one end of the high-pressure hose (5) is connected to the high-pressure fracturing pump group (1), and the other end of the high-pressure hose (5) is fixedly connected to a tool string (6). The tool string (6) is located inside the directional long borehole (3) and arranged along the axial direction of the directional long borehole (3); the tool string (6) includes a dropper (9) connected in sequence from the borehole opening to the bottom of the borehole, a fracturing sandblasting gun (7) and a packer (8) arranged in an alternating manner, a flow valve (10) and a guide shoe (11). The fracturing sandblasting device (7) includes an outer cylinder (74), and a set of fracturing ports (741) are evenly provided on the outer circumferential side wall of the outer cylinder (74); a rotating sleeve (78) is coaxially rotatably installed inside the outer cylinder (74), and a jet groove (783) is provided on the cylinder wall of the rotating sleeve (78) corresponding to the position of each fracturing port (741). The ball (12) is used in conjunction with each of the fracturing sandblasting machines (7) and the corresponding packer (8) to seal the directional long borehole (3) step by step.

2. The downhole directional hydraulic fracturing roof cracking pressure relief system according to claim 1, characterized in that: The guide shoe (11) is a tapered guide structure and is located at the bottom of the tool string (6); the guide shoe (11) guides the tool string (6) into the directional long drill hole (3).

3. The downhole directional hydraulic fracturing roof cracking pressure relief system according to claim 2, characterized in that: The one-way valve (10) is located between the third packer (83) and the guide shoe (11). The one-way valve (10) allows high-pressure fracturing fluid to flow unidirectionally into the bottom of the directional long borehole (3) to prevent the fluid in the directional long borehole (3) from flowing back in reverse during fracturing operations.

4. The downhole directional hydraulic fracturing roof cracking pressure relief system of claim 1, wherein: The fracturing blasting device (7) includes a first fracturing blasting device (71), a second fracturing blasting device (72), and a third fracturing blasting device (73); the packer (8) includes a first packer (81), a second packer (82), and a third packer (83).

5. A downhole directional hydraulic fracturing roof fracturing and pressure relief system according to claim 4, characterized in that: The fracturing blasting machine (7) also includes an inner cylinder (75), a sliding sleeve (76), and a pin (77); a set of limiting pawls (711) are evenly arranged circumferentially between the rotating sleeve (78) and the outer cylinder (74), each of the limiting pawls (711) is rotatably connected to the outer cylinder (74), and a limiting spring ring (712) is sleeved on the outer side of each of the limiting pawls (711); a limiting tooth ring (781) is machined at the end of the rotating sleeve (78) near the limiting spring ring (712), and the limiting tooth ring (781) and each of the limiting pawls (711) form a one-way meshing engagement; a rotating tooth ring (782) is machined at the end of the rotating sleeve (78) away from the limiting spring ring (712). The inner cylinder (75) is coaxially fitted inside the outer cylinder (74). A fixing groove (751) is provided at one end of the inner cylinder (75) near the rotating sleeve (78). A motor (710) is fixedly installed in the fixing groove (751). A gear (79) is fixedly connected to the output shaft end of the motor (710). The gear (79) meshes with the rotating gear ring (782) on the rotating sleeve (78). The sliding sleeve (76) is slidably assembled in the internal channel formed by the outer cylinder (74), the rotating sleeve (78) and the inner cylinder (75), and its initial position is limited and fixed by the pin (77). After the ball (12) is inserted into the internal channel of the outer cylinder (74) from the tunnel (2), the ball (12) pushes the sliding sleeve (76) to move axially, shearing the pin (77), thereby opening the jet channel (783) so that the fracturing fluid can be ejected through the jet channel (783) and the corresponding fracturing port (741).

6. A downhole directional hydraulic fracturing roof fracturing and depressurization system according to claim 5, characterized in that: The first fracturing sandblaster (71), the second fracturing sandblaster (72) and the third fracturing sandblaster (73) have the same structure, but the inner diameter of the sliding sleeve (76) inside the three decreases step by step.

7. A downhole directional hydraulic fracturing roof fracturing and depressurization system according to claim 5, characterized in that: A set of stress monitoring devices is fixedly installed on the outer circumferential sidewall of the outer cylinder (74), and the installation position of each stress monitoring device is circumferentially offset from each fracturing port (741).

8. A method for depressurizing the roof of a downhole directional hydraulic fracturing system, comprising the use of a downhole directional hydraulic fracturing roof depressurization system as described in any one of claims 1-7, characterized in that, It includes the following steps: S1. Tool entry and positioning: The guide shoe (11) guides the tool string (6) to be smoothly lowered into the directional long borehole (3); the sliding sleeve (76) is locked by the pin (77), and the jet groove (783) is closed with the fracturing port (741); S2. Perforation: Insert a ball (12) that matches the inner diameter of the sliding sleeve (76) of the first fracturing sandblaster (71), set the sliding sleeve (76), pump in high-pressure fluid, cut the pin (77), and after the sliding sleeve (76) is removed, the flow channel is connected, and the jet penetrates the hole wall to form a fracturing channel. S3. Directional fracturing construction: High-pressure fracturing fluid is injected into the top rock layer (4) through the fracturing port (741). After exceeding the fracturing pressure, artificial fractures are formed, and proppant enters with the fluid to prevent closure. At the same time, closed-loop control is implemented. The stress monitoring device collects stress signals from all directions, and the control system inverts and calibrates the optimal fracturing orientation. The control system controls the motor (710) to drive the rotating sleeve (78) so that the jet channel (783) is aligned with the target fracturing port (741) and the direction is switched. Dynamic correction is made when encountering fracture deviation or stress transfer to achieve single-stage multi-angle directional fracturing. S4. Inter-segment switching and multi-segment cycle: The inner diameter of the sliding sleeve (76) of the three fracturing sandblasters (7) decreases step by step to match the ball (12) of different diameters; the ball (12) of a larger diameter is inserted, which passes through the unopened sliding sleeve (76) of the large inner diameter, and sets the next level of the sliding sleeve (76) of the small inner diameter, repeating the "setting-perforation-fracturing" process; the tool string (6) irreversibly opens each of the fracturing sandblasters (7) from bottom to top in one pass, completing continuous segmented fracturing.