Offshore wind turbine large component disassembly and assembly space cooperative operation method
By using a self-elevating platform vessel for refined collaborative planning and dynamic intelligent decision-making, the technical bottleneck of disassembling and assembling large components in the operation and maintenance of deep-sea wind power has been solved, enabling efficient and safe replacement of large components of offshore wind turbines, improving operational safety and hoisting efficiency, and reducing unit downtime and power generation loss.
Patent Information
- Application Number
- CN202611295568.X
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2026-08-25
- Publication Date
- 2026-11-17
AI Technical Summary
Existing technologies lack systematic solutions for the operation and maintenance of deep-sea wind power, making it impossible to efficiently and safely replace large components such as main engines and rotors in situ. Especially when resources are limited, there are key technical bottlenecks in how to rationally plan the dismantling of old components, storage and hoisting and transportation of new components on a platform deck with limited space, avoid interference, and perform dynamic stability checks.
Using a jack-up platform vessel as the working platform, and integrating the operational advantages of the jack-up platform vessel through refined collaborative planning technology, including dynamic intelligent decision-making on the depth of the pile legs, digital collaborative planning and multi-objective optimization of the deck component layout, the platform stability and lifting safety are ensured. The main crane and auxiliary crane work together to achieve efficient disassembly and installation of the impeller and main engine.
It significantly shortens the operation cycle, reduces unit downtime and power generation loss, improves the economy and risk resistance of offshore wind power operation and maintenance, ensures the safety and efficiency of operations, prevents accidental rotor rotation or structural damage, optimizes the hoisting path, and reduces operational risks.
Smart Images

Figure CN123109983A_ABST
Abstract
Description
Technical Field
[0001] This invention relates to the field of marine engineering technology, specifically to a construction method for disassembling and installing offshore wind turbines using a self-elevating platform vessel. Background Technology
[0002] Offshore wind power operation and maintenance, especially the on-site replacement of core components such as generators and gearboxes of large-megawatt units, is one of the major challenges facing the industry. To optimize offshore wind turbine installation operations, the industry has conducted extensive technological exploration. On the one hand, for self-elevating platform vessels, the mainstream construction equipment, related technologies focus on improving their structural performance and pile foundation construction accuracy. For example, patent document CN111441354A discloses "An underwater pile stabilization system and pile driving method based on a self-elevating platform vessel," which aims to improve the verticality control and positioning accuracy of the pile during the pile driving process by setting an adjustable guide frame. On the other hand, some innovative methods have also emerged to improve the efficiency of specific lifting stages. For example, patent document CN113915073A discloses "A rapid impeller lifting method for offshore wind turbine self-elevating platform vessels," which utilizes auxiliary lifting devices and specific tooling on the platform to adjust and grasp the impeller's attitude, aiming to achieve rapid lifting.
[0003] However, existing technologies mostly focus on foundation construction or overall hoisting during the wind farm construction phase. For deep-sea wind power operation and maintenance scenarios, a systematic solution is still lacking for efficiently and safely replacing large components such as main engines and rotors in situ when resources are limited (e.g., no large main crane vessel is available). The aforementioned CN113915073A focuses on improving the speed of rotor installation but does not address the dismantling process or the coordinated planning and safe arrangement of large components (old and new main engines, rotors) on the entire deck. CN111441354A primarily addresses pile driving in the initial construction phase and cannot address the challenges of complex spatial interference, ship stability, and multi-component coordinated operations during operation and maintenance hoisting. In replacement operations, how to rationally plan the dismantling of old components, storage and hoisting and transportation paths of new components on the limited space of the platform deck, avoiding interference, and conducting dynamic stability checks are key technical bottlenecks for ensuring operational safety and improving overall efficiency. Therefore, an integrated construction method covering the entire process of self-elevating platform vessels, from precise positioning and pile fixing to fine deck planning and safe component hoisting, is urgently needed. Summary of the Invention
[0004] This invention aims to provide a spatial collaborative operation method for the disassembly and assembly of large components of offshore wind turbines, overcoming the shortcomings of existing technologies. This method integrates the operational advantages of self-elevating platform vessels with refined collaborative planning technology, aiming to achieve efficient, safe, and low-cost replacement of large components of offshore wind turbines.
[0005] To achieve the above technical solution, this invention provides a spatial collaborative operation method for disassembling and assembling large components of offshore wind turbines, using a self-elevating platform vessel as the operation platform, specifically including the following steps: S1. The self-elevating platform vessel sails to the target wind turbine position and positions itself, then lowers the pile legs, performs pre-loading of the piles, and raises the platform to the predetermined working height to form a stable offshore operation platform. S2. Collaborative planning for the hoisting of large components on the platform ship deck: First, collect operational and environmental data and establish a constraint system for hoisting procedures. Then, build a deck layout template. Through model simulation, complete interference verification and ship stability check. Finally, rely on the improved MOPSO algorithm for multi-objective optimization to select the optimal deck hoisting layout scheme. S3: Disassemble the impeller: Adjust the impeller to the predetermined posture and lock it, install the guy rope assembly at the predetermined position of the blade, install the impeller lifting tool on the hub, then disconnect the connection between the impeller and the main gearbox, and use the main crane of the work platform to lift the impeller as a whole and safely place it in the designated area of the deck. S4: Dismantle the main unit: Disconnect the cable connection between the main unit and the tower, install the main unit lifting device on the main unit, then disconnect the connection between the main unit and the tower, and use the main crane to lift the main unit as a whole and place it in the designated area on the deck; S5: Install the new main unit: hoist the new main unit to the working platform deck, repeat the reverse process of step S4, and use the main crane to hoist the new main unit to the top of the tower and complete the docking and fixing with the tower; S6: Install the impeller: Repeat the reverse process of step S3, using the main crane and auxiliary crane of the work platform to lift the impeller placed on the deck as a whole, turn it over and raise it to the height of the main engine, and complete the alignment, connection and fixation of the impeller and the main engine gearbox.
[0006] Preferably, in step S1, when lowering the pile leg, it is necessary to first calculate and dynamically decide on the pile leg insertion depth. The specific process includes: S11. Input the geological survey data of the target location, determine the key bearing layer, and record the top depth of the key bearing layer. D kp , bottom depth D bot and soil layer parameters; S12. Calculate the recommended insertion depth range for each pile leg. D min ,D max ] Optimal insertion depth D opt Generate insertion depth-bearing capacity curve; S13. After the platform is towed to the target position, the lifting system is activated to lower the three pile legs to the mud surface at a rate of ≤1.0m / min. After the pile legs contact the mud surface, the penetration continues at a rate of ≤0.5m / min. S14. Immediately after the pile leg contacts the mud surface, the real-time monitoring module is activated to collect data from each sensor at a sampling frequency of 1Hz and calculate the mud penetration depth of each pile leg in real time. D leg Terminal resistance R tip insertion depth change rate v t ; S15. During the entire process of pile driving and preloading, at fixed time intervals Δ t Execute the following decision cycle: S151. Read the real-time status parameters of each pile leg; S152. Calculate the penetration status of each pile leg. T i Insertion depth deviation Ei puncture risk level R ; S153, Constructing the State Vector S= ( T m ,T m' ,E avg ,R ); S154. Input the state vector into the hierarchical decision rule base and match the corresponding decision rule; S155, Output operation instruction combination; S156. Display decision suggestions through a human-machine interface, and execute them after the operator confirms or corrects them. S157. If the decision instruction is "re-evaluate the decision", proceed to step S2 to recalculate. S16, when the insertion depth deviation of all pile legs is E i When all conditions are within the normal range and the puncture risk level R=0, pre-ballasting operations shall commence. S17. After the platform reaches a stable standing state, record the monitoring data, decision records and final insertion depth parameters of the entire pile driving process and store them in the historical database for reference in subsequent machine operation.
[0007] Preferably, in step S2, the specific steps for collaborative planning of the hoisting of large components on the platform vessel deck include: S21. Basic data collection and parametric modeling: Collect parameters of the work platform hull, crane, and pile legs, build a parameter library for wind power carrier components, and collect environmental operation parameters of the work area, ship motion characteristics, and work window. S22. Modeling and Sequence Constraints of Lifting Process: Build a standard lifting process for wind turbine replacement, establish the mapping relationship between processes and components, and define the sequential logic of processes by dividing them into hard and soft constraints. S23. Construct a deck layout template library and classify multiple applicable templates: plan the deck zones, accurately define the component placement parameters, and bind the layout templates with the hoisting process to avoid spatial interference and optimize the hoisting path; S24. Feasibility verification of layout based on interferometry: Build a three-dimensional model of the ship and components (OBB) and a kinematic model of the crane, use the GJK-EPA algorithm to simulate the collision detection of the lifting path, and construct an interference evaluation index to determine whether the deck layout template is feasible. S25. Ship stability coupling verification: For each deck layout template, divide into multiple operating conditions, calculate the weight and center of gravity of each condition, and carry out stability verification according to the classification society specifications. If unstable, optimize the ballast water adjustment to meet the stability requirements. S26. Template selection based on multi-objective optimization: Construct an objective function that takes into account working distance, turning angle, timeliness and safety, use the improved MOPSO algorithm to obtain the Pareto optimal solution set, and determine the final deck layout scheme in combination with on-site requirements.
[0008] Preferably, in step S3, the specific process of adjusting the impeller to the predetermined attitude and locking it is as follows: operate the wind turbine yaw and reverse drag system to make one of the blades vertically downward, while the impeller hanger mounting boss faces upward, and then lock the impeller by the wind turbine hydraulic locking pin and the high-speed shaft brake.
[0009] Preferably, in step S3, the specific process of installing the guy rope assembly at the predetermined position of the blade includes: using a manned cage to send the operator and guy rope into the air, installing the tail guy rope at a predetermined distance from the blade root in the vertical direction, and installing the tip guy rope at the tips of the two blades in the horizontal position.
[0010] Preferably, in step S3, before disconnecting the impeller from the main gearbox, the step further includes: temporarily fixing the hub disc to the hub using at least three tooling bolts inside the hub.
[0011] Preferably, in step S4, after the main unit is lifted off the top of the tower and lowered to a preset height from the deck, the double-headed studs used to connect the main unit and the tower are removed inside the main unit.
[0012] Preferably, between steps S5 and S6, when the main unit is installed but the impeller has not yet been installed, if the tower is in an impeller-less state, a baffle assembly is wrapped around the outer wall of the tower to suppress vortex-induced vibration.
[0013] Preferably, in step S6, the specific process of the main crane and the auxiliary crane working together is as follows: the hook of the main crane is connected to the impeller lifting device, and the hook of the auxiliary crane is connected to the tail cable wind rope. The two cranes work together to turn the impeller from a horizontal position to a vertical position.
[0014] The beneficial effects of the spatial collaborative operation method for disassembling and assembling large components of offshore wind turbines provided by this invention are as follows: 1) This invention adopts a self-elevating platform vessel as an independent and stable offshore operation platform, integrating the entire process of planning, dismantling, and installation, forming a complete integrated solution from precise positioning and safe pile insertion to efficient component replacement. This significantly shortens the operation cycle, reduces unit downtime and power generation loss, and improves the economy and risk resistance of offshore wind power operation and maintenance.
[0015] 2) By introducing a dynamic intelligent decision-making mechanism for the insertion depth of the pile legs, this invention can adaptively adjust the pile-down strategy based on real-time geological data and platform status, effectively preventing puncture risks, ensuring the stability of the platform under complex seabed geological conditions, providing a solid foundation for subsequent high-altitude precision operations, and improving operational safety.
[0016] 3) This invention avoids spatial interference and ship stability issues in advance by digitally and collaboratively planning and optimizing the layout of deck components and the hoisting process, and optimizes the hoisting path, thereby improving hoisting efficiency, reducing operational risks, and ensuring the smoothness and safety of the operation process in actual operation.
[0017] 4) This invention ensures that the impeller, which weighs over 100 tons, is controllable and balanced in force during disassembly through detailed steps such as impeller attitude locking, guy rope arrangement, and temporary hub fixing. This effectively prevents accidental rotation or structural damage to the impeller and greatly improves the safety of impeller hoisting operations. Attached Figure Description Figure 1 This is a flowchart of the steps of the present invention. Detailed Implementation
[0018] The technical solutions of the embodiments of the present invention will be clearly and completely described below with reference to the accompanying drawings. Obviously, the described embodiments are only some embodiments of the present invention, and not all embodiments. All other embodiments obtained by those skilled in the art without creative effort are within the protection scope of the present invention.
[0019] Example 1: A method for collaborative spatial operation of disassembly and assembly of large components of offshore wind turbines.
[0020] Reference Figure 1As shown, a method for collaborative spatial operation of disassembling and assembling large components of offshore wind turbines uses a self-elevating platform vessel as the operating platform, and specifically includes the following steps: Step 1: Navigate the self-elevating platform vessel to the target wind turbine location and position it. Then, lower the pile legs, perform pile preloading, and raise the platform to the predetermined working height to form a stable offshore operation platform.
[0021] When lowering the pile legs, it is necessary to first calculate and dynamically decide on the insertion depth of the pile legs. The specific process includes: 1. Input the geological survey data of the target site, determine the key bearing layer, and record the top depth of the key bearing layer. D kp , bottom depth D bot And soil layer parameters. In practice, based on the site geotechnical investigation data, the bearing strata capable of supporting the platform load are identified, and the upper and lower boundaries of the strata and soil strength parameters are clearly defined as the bottom-level input conditions for the insertion depth theoretical calculation, distinguishing high-risk puncture strata such as hard upper and soft lower. By establishing a geological foundation model, blind pile driving can be avoided, and strata with potential puncture risks can be identified in advance, providing a geological basis for the delineation of insertion depth intervals and risk prediction.
[0022] 2. Calculate the recommended insertion depth range for each pile leg. D min ,D max ] Optimal insertion depth D opt This process generates an insertion depth-bearing capacity curve. In practical work, by combining pile shoe dimensions and stratum parameters to calculate the foundation bearing capacity, the minimum insertion depth to meet bearing requirements and the maximum insertion depth to avoid difficulties in pile extraction are determined, thus obtaining the theoretically optimal insertion depth. A characteristic curve showing the change in bearing capacity with insertion depth is then constructed. By providing the theoretical target range for pile insertion as a benchmark for on-site operations, and by visually judging the bearing capacity growth trend through the curve, the locations of puncture and sudden changes in bearing capacity can be predicted, thereby guiding dynamic adjustments on-site and ensuring operational safety.
[0023] 3. After the platform is towed to the target location, the lifting system is activated to simultaneously lower the three pile legs to the mud surface at a rate of ≤1.0m / min. After the pile legs contact the mud surface, the penetration speed is reduced to ≤0.5m / min. In actual operation, graded speed limits ensure smooth lowering. The pile legs approach the mud surface quickly during the suspended stage to improve efficiency. After the pile shoe contacts the seabed, the penetration speed is reduced to mitigate soil disturbance and prevent sudden punctures induced by high-speed penetration.
[0024] 4. Immediately after the pile leg contacts the mud surface, the real-time monitoring module is activated to collect data from each sensor at a sampling frequency of 1Hz and calculate the mud penetration depth of each pile leg in real time. D leg Terminal resistanceR tip insertion depth change rate v t By establishing a high-frequency closed-loop monitoring system, real-time physical quantities such as pile leg displacement, load, and penetration rate can be continuously acquired, and the stress state of the foundation can be dynamically inverted. This enables digital perception of the entire pile insertion process, timely capture of early signs of puncture such as sudden increases in penetration rate and sharp drops in end resistance, and provides continuous measured data for real-time decision-making.
[0025] 5. Throughout the entire process of pile driving and preloading, at fixed time intervals Δ t Execute the following decision cycle: (51) Read the real-time status parameters of each pile leg, collect the latest monitoring data such as depth, load, and settlement rate, refresh the system status, ensure that the decision-making basis is the current real working conditions, and avoid misjudgment caused by using lagging data.
[0026] (52) Calculate the penetration status of each pile leg. T i Insertion depth deviation Ei puncture risk level R This will transform raw monitoring data into standardized risk indicators, enabling quantitative risk assessment and eliminating the subjectivity of human experience-based judgment.
[0027] (53) Constructing the state vector S= ( T m ,T m' ,E avg ,R This involves integrating multiple indicators such as penetration trend, settlement rate, uneven penetration depth, and puncture risk to form a unified working condition representation vector. This enables the fusion of multi-source parameters, facilitates rule base matching, and prevents one-sided judgments based on a single indicator.
[0028] (54) Input the state vector into the hierarchical decision rule library, match the corresponding decision rules, and realize the automatic identification of working conditions by pre-setting the standard handling logic corresponding to various working conditions in the decision rule library, thereby forming a standardized intelligent decision logic, reducing human judgment errors, and supporting automated piling control.
[0029] (55) Output operation command combination, automatically output lifting start and stop, speed adjustment, pause pile insertion, start preload and other complete operation suggestions, provide clear handling solutions for operators and shorten emergency response time.
[0030] (56) Decision suggestions are displayed through the human-machine interface, and the operator confirms or corrects them before execution. The human intervention authority is retained to realize intelligent algorithm and human-machine collaborative control, improve the fault tolerance of the operation, and meet the safety operation specifications of the maritime and platform.
[0031] (57) If the geological measured characteristics deviate significantly from the previous exploration data, the decision instruction outputs "re-evaluate decision", jumps to step S2 to recalculate, and starts the theoretical model iterative update.
[0032] 6. When the insertion depth deviation E of all pile legs i Preloading operations should begin when all conditions are within the normal range and the puncture risk level R=0; preloading should not be carried out under unstable foundation or uneven stress conditions; and preloading loads should be used to prevent uneven settlement of pile legs or puncture overturning.
[0033] 7. Once the platform reaches a stable standing position, record the monitoring data, decision-making records, and final insertion depth parameters for the entire pile driving process, and store them in the historical database for reference in subsequent turbine placement operations. This will provide reference data for subsequent turbine placement operations at this wind farm; continuously optimize the insertion depth calculation model and improve decision-making rules; and achieve digital accumulation of operational experience, thereby improving the accuracy and safety of subsequent placement plans. In this embodiment, by introducing a dynamic intelligent decision-making mechanism for the depth of the pile legs, the pile-down strategy can be adaptively adjusted according to real-time geological data and platform status, effectively preventing puncture risks, ensuring the stability of the platform under complex seabed geological conditions, providing a solid foundation for subsequent high-altitude precision operations, and improving operational safety.
[0034] Step 2: Coordinate the hoisting of large components on the platform vessel deck. Specific steps include: 1. Basic Data Acquisition and Parametric Modeling: Collect parameters of the operating platform hull, crane, and legs to build a parameter library for wind power transport components, and collect environmental operating parameters such as sea conditions, vessel motion characteristics, and operating window conditions. Specific data collected includes: (11) Ship parameters, including but not limited to: Main deck dimensions (length × width × usable area), deck load-bearing capacity (surface load and point load limits); Crane type (full slewing crane / main crane / crawler crane), crane location coordinates, crane working radius range, maximum lifting height, boom length and slewing angle limit; Ship depth, draft range, ballast tank distribution and adjustment capabilities; Number and location of pile legs, distribution of pile fixing chambers.
[0035] (12) Component parameters: Establish a parameterized database for the list of components carried on this voyage. The parameter vector for each component i is: P i = ( ID i , Type i, L i , W i , H i , M i , CG i , Shape i , Fix i ); in: Type i ∈{impeller, main unit (new), main unit (old), tower, lifting tool, auxiliary tooling}; L i , W i , H i The dimensions are length, width, and height. M i For quality; CG i These are the coordinates of the center of gravity (relative to the component's own coordinate system). Shape i This refers to the three-dimensional shape contour data; Fix i For fixing methods (such as binding, brackets, tooling, etc.).
[0036] (13) Environmental and operational parameters: Obtain sea state parameters (significant wave height, period, wind speed, etc.), ship rolling characteristics (roll / pitch / heave amplitude and period), and operational time window of the operational sea area.
[0037] 2. Lifting Process Modeling and Sequence Constraints: A standard lifting process for wind turbine replacement is established, defining the mapping relationship between processes and components, and classifying the process sequence into hard and soft constraints. The specific process is as follows: (21) Standard process flow modeling: Establish a standard hoisting process flow for replacing major components of offshore wind turbines, with "removing impeller → removing old main unit → installing new main unit → installing impeller" as the basic sequence, and define the logical dependencies between each process.
[0038] (22) Sequence-Component Mapping: Establish a mapping relationship between each hoisting operation and its corresponding component. Let the set of operations be T={t1, t2, ..., t...} n}, each process t j The corresponding operation is O p (t j ) ∈{receiving, hoisting, installing, dismantling, returning}, with associated component C(t) j ).
[0039] (23) Define timing constraints, define the timing constraints between processes: Hard constraints (unbreakable): such as the old main unit must be removed before the new main unit can be installed, or the impeller must be removed before the main unit can be removed; Soft constraints (optimizable): such as minimizing the slewing angle of the crane when moving from one working position to another.
[0040] Define process t a With t b The precondition is t a <t b , indicating t a Must be t b Completed previously.
[0041] 3. Construct a deck layout template library and categorize applicable templates into multiple types: Plan deck zones, accurately define component placement parameters, and link template layout with the hoisting process to avoid spatial interference and optimize hoisting paths. Specific processes include: (31) Template Classification: Based on the number of main engines carried on this voyage, establish standardized deck layout templates, including at least: Type-A template (single new host): suitable for scenarios involving one new host and one old host (to be disassembled); Type-B template (dual new hosts): suitable for scenarios involving two new hosts and multiple old hosts; Type-C Template (Single New Main Unit + Spare Parts): Suitable for scenarios involving one new main unit and additional spare parts / tooling.
[0042] (32) Template space division: Each template divides the main deck into several functional areas: Impeller storage area: Used to store new impellers to be installed and old impellers after disassembly. The impellers are usually placed in a horizontal or near-horizontal position. Host storage area: divided into "new host area" and "old host recycling area", new and old hosts are stored separately to avoid confusion; Lifting Gear / Tooling Area: Storage of lifting slings, elephant leg tooling, assembly brackets and other auxiliary equipment; Operating passageway: Space is reserved for crane rotation and component movement; Buffer zone: An area where transitional components are temporarily placed.
[0043] (33) Detailed template definition: Each template specifies the placement, orientation, and fixing method of each component precisely: Layout k = {( P i , Pos i, θ i , Fix i ) | i=1,2,...,m}, in Pos i = ( x i , y i () represents the placement position of the component in the deck coordinate system. θ i The orientation angle (relative to the bow and stern lines of the ship). Fix i This is a fixed scheme number.
[0044] (34) Template and process binding: Each deck layout template is strictly bound to a specific hoisting process to ensure that the crane picks up and puts down the parts at each hoisting operation, and that there is no spatial interference with other stored parts.
[0045] 4. Feasibility Verification of Layout Based on Interference Analysis: A 3D OBB model of the ship and components, and a kinematic model of the crane are constructed. The GJK-EPA algorithm is used to simulate collision detection along the lifting path, and an interference evaluation index is built to determine the feasibility of the deck layout template. The specific process includes: (41) Three-dimensional spatial modeling: Based on the acquired parameters, a three-dimensional digital model of the ship deck and all components is established. The Oriented Bounding Box Tree (OBB Tree) technology is used to construct the collision body hierarchy for each component.
[0046] The OBB tree construction method is as follows: For the 3D shape of part i, recursively construct an oriented bounding box hierarchy tree, where each node stores the bounding box parameters (center) of that node. i axis i extent i ), where axis i For three principal axis directions, extent i It is the half-side length along the three axes.
[0047] (42) Kinematic modeling of the crane: Establish the kinematic model of the crane, including: Rotation angle range [ θ min , θ max ]; Amplitude range min , max ]; boom length L boom ; Lifting height range [ H min , H max ].
[0048] The position of the crane hook at any given time can be determined by the rotation angle. θ Amplitude and lifting height h The only certainty: Pos hook (θ, ,h) = (R base +L boom cos cosθ,R base + L boom cos sinθ, h) in R base These are the coordinates of the crane's rotation center.
[0049] (43) Hoisting path interference detection: For template layout k Each process in t j The complete motion path of the crane from the starting position to the target position is simulated, and real-time collision detection is performed using the GJK-EPA algorithm (Gilbert-Johnson-Keerthi and ExpandingPolytope Algorithm).
[0050] The specific steps of interference detection are as follows: a. Represent cranes, suspended loads, and all components on the deck using an OBB Tree structure; b. Discretize the hoisting path and generate a path point sequence { Path 1 , Path 2 , ..., Path q}; c. For each path point, perform hierarchical collision detection of the OBB Tree: starting from the root node, if the bounding boxes of the root nodes of the two trees do not intersect, skip the branch; if they intersect, recursively check the child nodes downwards until the leaf node. d. If any collision is detected, mark the path point as an "interference point" and record the interfering component and its location.
[0051] (44) Interference evaluation index: Define template Layout k Interference evaluation value:
[0052] in = 1 indicates that path point p of process j is interfered with. w j This is the weighting coefficient for process j (critical processes have higher weights). I(Layout k ) =0 indicates that the template is feasible as there is no interference during the entire hoisting process.
[0053] 5. Ship Stability Coupling Verification: Multiple operating conditions are defined for each deck layout template. The weight and center of gravity of each condition are calculated, and stability verification is conducted according to classification society specifications. If instability is detected, ballast water adjustments are made to meet stability requirements. The process specifically includes: (51) Loading condition definition: Templates are arranged for each deck. Layout k Define its loading conditions at each stage of operation: Navigation conditions: All components are fixed in place according to the template, and the ship is in a navigation state; Pre-operation conditions: The vessel is in place (e.g., piles have been driven in), and all components are still in place; Operating conditions: Some components have been lifted away or have not yet been put in place, and the deck load distribution is dynamically changing; Post-operation status: old parts have been removed, new parts have been installed, and deck load has been redistributed.
[0054] (52) Weight and center of gravity calculation: For each working condition s, calculate the total weight and center of gravity of the ship:
[0055] in M ship and CG ship This refers to the empty ship's weight and center of gravity.
[0056] (53) Stability verification: In accordance with the relevant requirements of CCS (China Classification Society) and other relevant standards, a complete stability calculation was performed for each operating condition: initial stability GM Verification: GM≥GMmin (Standard requirement value); Large tilt angle stability check: The area under the static stability lever arm curve meets the specification requirements; Wind tilt moment check: M wind ≤M right(Wind tilting moment ≤ Restoring moment); Allowable center of gravity height check: Actual center of gravity height ≤ Allowable center of gravity height.
[0057] (54) Ballast Optimization: If the stability of a certain working condition does not meet the requirements, optimization is achieved by adjusting the ballast water distribution in the ballast tank. Let the change in ballast water volume in ballast tank b be... Ballast b The optimization problem then becomes:
[0058] s.t.GM s ( Ballast)≥GM min Other stability constraints The optimal ballast adjustment scheme is solved using linear programming or gradient descent method.
[0059] 6. Template Optimization Based on Multi-Objectives: An objective function is constructed that considers working distance, turning angle, timeliness, and safety. An improved MOPSO algorithm is used to obtain the Pareto optimal solution set, and the final deck layout scheme is determined based on site requirements. Specifically, this includes: (61) Optimize the objective definition and define a multi-objective function for template evaluation:
[0060] in: f move Total distance the component moves (including crane travel and component translation); f rotate Total slewing angle of the crane; f time Total operation time estimate (including hoisting time and auxiliary time); f safety Safety margin indicators (based on interference detection results and stability margin); a 1 , a 2 , a 3 ,a 4 is the weighting coefficient, which can be dynamically adjusted according to the needs of the task.
[0061] (62) Optimization algorithm: Template optimization is performed using an improved multi-objective particle swarm optimization algorithm (MOPSO).
[0062] Each particle represents a deck layout scheme, encoded as the position coordinates of each component. x i , y i ) and orientation angleθ i The vector. The specific algorithm flow includes: a. Initialization: Using the standard template from step three as the initial population, randomly generate mutation schemes; b. Fitness evaluation: For each particle, call the interferometry analysis in step four and the stability check in step five to calculate the multi-objective function value; c. Non-dominated sorting: The fast non-dominated sorting method is used to divide the particles into different Pareto fronts; d. Speed and position updates:
[0063]
[0064] in w Here, c1 and c2 are inertial weights, c1 and c2 are learning factors, and r1 and r2 are random numbers; e. Constraint handling: For schemes that exceed deck boundaries or cause interference, apply a penalty function: Penalty(Layout)=λ•max(0, I(Layout))+μ•max(0, GMmin-GM(Layout)) f. Iteration Termination: Termination occurs when the maximum number of iterations is reached or the population converges, and the Pareto optimal solution set is output.
[0065] (63) Optimal solution selection: Select the final implementation scheme from the Pareto optimal solution set according to the actual operation requirements (such as prioritizing safety or prioritizing efficiency).
[0066] In this embodiment, by digitally and collaboratively planning and optimizing the layout of deck components and the hoisting process, spatial interference and ship stability issues are avoided in advance, and the hoisting path is optimized. This improves hoisting efficiency, reduces operational risks, and ensures the smoothness and safety of the operation process in actual operation.
[0067] Step 3: Disassemble the impeller: On the work platform, adjust the impeller to the predetermined posture and lock it. Install the guy rope assembly at the predetermined position of the blade and install the impeller lifting tool on the hub. Then disconnect the impeller from the main gearbox and use the main crane of the work platform to lift the impeller as a whole and place it safely in the designated area of the deck.
[0068] The specific process of adjusting and locking the impeller to the predetermined attitude is as follows: Operate the wind turbine yaw and anti-drag system to make one blade vertically downwards, with the impeller lifting bracket mounting boss facing upwards. Then, lock the impeller using the wind turbine hydraulic locking pin and the high-speed shaft brake. The specific process of installing the guy rope assembly at the predetermined position on the blade includes: using a personnel cage to send the workers and guy ropes into the air; installing the tail guy rope at a predetermined distance from the root of the vertically downward-facing blade; and installing tip guy ropes at the tips of the two horizontally positioned blades. Before disconnecting the impeller from the main gearbox, the process also includes: temporarily fixing the hub disc to the hub using at least three tooling bolts inside the hub.
[0069] In this embodiment, by locking the impeller attitude, arranging the guy ropes, and temporarily fixing the hub in step three, the attitude of the impeller, which weighs over 100 tons, is controllable and the force is balanced during the disassembly process. This effectively prevents the impeller from rotating accidentally or being damaged, and greatly improves the safety of the impeller hoisting operation.
[0070] Step 4: Dismantle the main unit: On the work platform, disconnect the cable connection between the main unit and the tower, install the main unit lifting tool onto the main unit, then disconnect the connection between the main unit and the tower, and use the main crane to lift the main unit as a whole and place it in the designated area on the deck; after lifting the main unit off the top of the tower, when it is lowered to a preset height from the deck, remove the double-headed studs used to connect the main unit and the tower inside the main unit, avoiding the risks of high-altitude bolt removal operations on the deck, simplifying deck operations, and improving work efficiency.
[0071] Step 5: Install the new main unit: Hoist the new main unit to the working platform deck, and repeat the reverse process of Step 4. Use the main crane to hoist the new main unit to the top of the tower and connect and secure it to the tower. When the main unit is installed but the impeller has not yet been installed, if the tower is in an impeller-less state, wrap a baffle assembly around the outer wall of the tower. This can effectively suppress vortex-induced vibration of the tower, prevent structural fatigue damage, and provide a safe buffer for possible operation interruptions due to weather or other reasons.
[0072] Step Six: Install the Impeller: Repeat the reverse process of Step Three, using the main and auxiliary cranes of the work platform to lift, turn over, and raise the impeller, which is placed on the deck, to the height of the main engine, completing the alignment, connection, and fixation of the impeller and the main engine gearbox. Specifically, the main and auxiliary cranes work together as follows: the hook of the main crane is connected to the impeller lifting device, and the hook of the auxiliary crane is connected to the tail cable and guy ropes. The two cranes work together to turn the impeller from a horizontal to a vertical position. Using the main and auxiliary cranes in tandem to achieve the "turning over" action of the impeller from a horizontal to a vertical position ensures smooth and controllable operation, reduces reliance on the capacity of large single lifting equipment, and fully utilizes the existing equipment capabilities of the platform vessel.
[0073] The present invention will now be described in detail with reference to specific embodiments. This embodiment takes the replacement of the main unit and rotor of an 8MW offshore wind turbine in the South China Sea as an example.
[0074] First, a self-elevating platform vessel equipped with a main crane (e.g., 800T) and an auxiliary crane (e.g., 200T), carrying a brand-new main engine and necessary tools and equipment, is towed by a tugboat or propelled to the target location. Once the platform is in place, the dynamic pile leg insertion depth decision-making process described in step one is executed: the system retrieves the geological survey report for the location, identifies the sandy soil layer as the key bearing layer, and calculates the recommended insertion depth range as 38-42 meters, with the optimal insertion depth D... opt The depth was 40 meters. Operators lowered the pile legs at a rate of 0.8 m / min to contact the mud, then continued penetration at 0.3 m / min. The real-time monitoring system continuously collected data. When an abnormally rapid penetration rate was detected in a particular pile leg, the state vector triggered the rule "Penetration Risk R=2 (Medium)". The decision system immediately output the instruction to "Pause the current pile leg and increase the preload of the remaining pile legs by 5%". After operator confirmation, the instruction was executed, successfully mitigating the risk of localized weak interlayers. Ultimately, all three pile legs stood stably at an insertion depth of approximately 40.5 meters, and the platform was raised to a working height of 20 meters above sea level.
[0075] Next, the deck collaborative planning described in step two is executed. The engineer inputs the platform vessel parameters, the dimensions and weights of the old and new main engines and impellers, and the current sea state. The system retrieves a layout template from the template library with "one old and one new main engine near the ship's side, impeller in the center," and automatically performs 3D collision detection (using the GJK-EPA algorithm to simulate the crane's rotation path during impeller lifting), confirming no interference. Stability checks show that the center of gravity is slightly high when lifting the old main engine from the tower; the system recommends injecting 200 tons of ballast water into a specific ballast tank to meet specifications. The optimization algorithm ultimately generates the Pareto optimal solution with the shortest operating path and smoothest crane movement.
[0076] After the operation begins, the impeller is disassembled first (corresponding to step three). The operator remotely controls the turbine's yaw system, making one blade of the impeller point vertically downwards, and activates the impeller locking pin and high-speed shaft brake to lock it in place. Workers ride in a hoist cage to a point approximately 10 meters from the blade root and install the tail cable. Subsequently, tip cable wind ropes are also installed at the tips of the two horizontal blades. Next, inside the hub, the hub disc is temporarily secured with four high-strength tooling bolts. After installing the specialized impeller lifting tool, the connecting bolts are removed, and the main crane slowly lifts the 120-ton impeller from the nacelle, using the auxiliary crane and cable wind ropes to control its swing, and smoothly places it in the designated area on the deck.
[0077] The main unit is then disassembled (corresponding to step four). All cables are disconnected, the main unit lifting equipment is installed, and the tower flange connection bolts are removed. The main crane then lifts the main unit away. When the main unit is lowered to a height of approximately 10 meters above the deck, workers on the tower use a safety basket to approach and quickly remove any remaining double-ended studs from the main unit flange. The old main unit is then placed in the designated location on the deck.
[0078] The installation of the new main unit is the reverse process of disassembly (corresponding to step five). After hoisting into place, if the weather forecast indicates that there may be continuous strong winds that delay the installation of the impeller by more than 48 hours, a spiral-shaped baffle assembly should be immediately wrapped around the outer wall of the tower to suppress vortex-induced vibration.
[0079] Finally, the new impeller is installed (corresponding to step six). The main crane hook is connected to the impeller lifting tool, and the auxiliary crane hook is connected to the tailing cable. The two cranes work together to slowly lift the impeller, which is lying flat on the deck, and "flip" it to a vertical position. Afterward, the main crane lifts it alone and precisely aligns it with the main engine gearbox input flange to complete the connection and fixation. After removing all tooling and guy ropes, the wind turbine cable connection is restored, and preliminary commissioning is performed. The platform vessel lowers its legs and moves out of the turbine position, completing the entire replacement operation.
[0080] This invention constructs a self-elevating platform vessel as a stable offshore "operation base" unaffected by wave fluctuations. Its legs are inserted into the seabed, lifting the hull above the water surface, fundamentally eliminating wave-induced heave, roll, and pitch, creating near-land-like stability conditions for high-precision, high-risk aerial hoisting operations. On this stable platform, an advanced dynamic leg decision-making system ensures a solid foundation, digital collaborative planning optimizes logistics and processes, and a series of specialized process steps designed for the characteristics of wind turbine components (such as rotor asymmetry and precise main unit connections) (such as attitude locking, guy rope control, and coordinated turning) enable the safe, efficient, and orderly disassembly and installation of core components of large offshore wind turbines.
[0081] The above description is only a preferred embodiment of the present invention, but the present invention should not be limited to the content disclosed in the embodiments and drawings. Therefore, any equivalent or modified embodiments made without departing from the spirit of the present invention shall fall within the protection scope of the present invention.
Claims
1. A method for coordinated work in a disassembly space of large components of an offshore wind turbine, characterized in that, The use of a self-elevating platform vessel as the working platform includes the following steps: S1. The self-elevating platform vessel sails to the target wind turbine position and positions itself, then lowers the pile legs, performs pre-loading of the piles, and raises the platform to the predetermined working height to form a stable offshore operation platform. S2. Collaborative planning for the hoisting of large components on the platform ship deck: First, collect operational and environmental data and establish a constraint system for hoisting procedures. Then, build a deck layout template. Through model simulation, complete interference verification and ship stability check. Finally, rely on the improved MOPSO algorithm for multi-objective optimization to select the optimal deck hoisting layout scheme. S3: Disassemble the impeller: Adjust the impeller to the predetermined posture and lock it, install the guy rope assembly at the predetermined position of the blade, install the impeller lifting tool on the hub, then disconnect the connection between the impeller and the main gearbox, and use the main crane of the work platform to lift the impeller as a whole and safely place it in the designated area of the deck. S4: Dismantle the main unit: Disconnect the cable connection between the main unit and the tower, install the main unit lifting device on the main unit, then disconnect the connection between the main unit and the tower, and use the main crane to lift the main unit as a whole and place it in the designated area on the deck; S5: Install the new main unit: hoist the new main unit to the working platform deck, repeat the reverse process of step S4, and use the main crane to hoist the new main unit to the top of the tower and complete the docking and fixing with the tower; S6: Install the impeller: Repeat the reverse process of step S3, using the main crane and auxiliary crane of the work platform to lift the impeller placed on the deck as a whole, turn it over and raise it to the height of the main engine, and complete the alignment, connection and fixation of the impeller and the main engine gearbox.
2. The method according to claim 1, wherein, In step S1, when lowering the pile legs, it is necessary to first calculate and dynamically decide on the insertion depth of the pile legs. The specific process includes: S11, input the geological survey data of the target site, determine the key bearing layer, record the depth of the top of the key bearing layer D kp , the depth of the bottom of the layer D bot and the soil layer parameters; S12. Calculate the recommended insertion depth range for each pile leg. D min ,D max ] Optimal insertion depth D opt Generate insertion depth-bearing capacity curve; S13. After the platform is towed to the target position, the lifting system is activated to lower the three pile legs to the mud surface at a rate of ≤1.0m / min. After the pile legs contact the mud surface, the penetration continues at a rate of ≤0.5m / min. S14. Immediately after the pile leg contacts the mud surface, the real-time monitoring module is activated to collect data from each sensor at a sampling frequency of 1Hz and calculate the mud penetration depth of each pile leg in real time. D leg Terminal resistance R tip insertion depth change rate v t ; S15. During the entire process of pile driving and preloading, at fixed time intervals Δ t Execute the following decision cycle: S151. Read the real-time status parameters of each pile leg; S152. Calculate the penetration status of each pile leg. T i Insertion depth deviation Ei puncture risk level R ; S153, Constructing the State Vector S= ( T m ,T m' ,E avg ,R ); S154. Input the state vector into the hierarchical decision rule base and match the corresponding decision rule; S155, Output operation instruction combination; S156. Display decision suggestions through a human-machine interface, and execute them after the operator confirms or corrects them. S157. If the decision instruction is "re-evaluate the decision", proceed to step S2 to recalculate. S16, when the insertion depth deviation of all pile legs is E i When all conditions are within the normal range and the puncture risk level R=0, pre-ballasting operations shall commence. S17. After the platform reaches a stable standing state, record the monitoring data, decision records and final insertion depth parameters of the entire pile driving process and store them in the historical database for reference in subsequent machine operation.
3. The method for collaborative spatial operation of disassembly and assembly of large components of offshore wind turbines according to claim 1, characterized in that, In step S2, the specific steps for collaborative planning of the hoisting of large components on the platform ship deck include: S21. Basic data collection and parametric modeling: Collect parameters of the work platform hull, crane, and pile legs, build a parameter library for wind power carrier components, and collect environmental operation parameters of the work area, ship motion characteristics, and work window. S22. Modeling and Sequence Constraints of Lifting Process: Build a standard lifting process for wind turbine replacement, establish the mapping relationship between processes and components, and define the sequential logic of processes by dividing them into hard and soft constraints. S23. Construct a deck layout template library and classify multiple applicable templates: plan the deck zones, accurately define the component placement parameters, and bind the layout templates with the hoisting process to avoid spatial interference and optimize the hoisting path; S24. Feasibility verification of layout based on interferometry: Build a three-dimensional model of the ship and components (OBB) and a kinematic model of the crane, use the GJK-EPA algorithm to simulate the collision detection of the lifting path, and construct an interference evaluation index to determine whether the deck layout template is feasible. S25. Ship stability coupling verification: For each deck layout template, divide into multiple operating conditions, calculate the weight and center of gravity of each condition, and carry out stability verification according to the classification society specifications. If unstable, optimize the ballast water adjustment to meet the stability requirements. S26. Template selection based on multi-objective optimization: Construct an objective function that takes into account working distance, turning angle, timeliness and safety, use the improved MOPSO algorithm to obtain the Pareto optimal solution set, and determine the final deck layout scheme in combination with on-site requirements.
4. The method for collaborative spatial operation of disassembly and assembly of large components of offshore wind turbines according to claim 1, characterized in that, In step S3, the specific process of adjusting the impeller to the predetermined attitude and locking it is as follows: operate the wind turbine yaw and reverse drag system to make one of the blades vertically downward, while the impeller hanger mounting boss faces upward, and then lock the impeller through the wind turbine hydraulic locking pin and the high-speed shaft brake.
5. The method for collaborative spatial operation of disassembly and assembly of large components of offshore wind turbines according to claim 1, characterized in that, In step S3, the specific process of installing the guy rope assembly at the predetermined position of the blade includes: using a manned cage to send the operator and guy rope into the air, installing the tail guy rope at a predetermined distance from the blade root that is vertically downward, and installing the tip guy rope at the tips of the two blades in the horizontal state respectively.
6. The method for collaborative spatial operation of disassembly and assembly of large components of offshore wind turbines according to claim 1, characterized in that, In step S3, before disconnecting the impeller from the main gearbox, the step of temporarily fixing the hub disc to the hub is included using at least three tooling bolts inside the hub.
7. The method for collaborative spatial operation of disassembly and assembly of large components of offshore wind turbines according to claim 1, characterized in that, In step S4, after the main unit is lifted off the top of the tower and lowered to a preset height from the deck, the double-headed studs used to connect the main unit and the tower are removed inside the main unit.
8. The method for collaborative spatial operation of disassembly and assembly of large components of offshore wind turbines according to claim 1, characterized in that, Between steps S5 and S6, when the main unit is installed but the impeller has not yet been installed, if the tower is in an impeller-less state, a baffle assembly is wrapped around the outer wall of the tower to suppress vortex-induced vibration.
9. The method for collaborative spatial operation of disassembly and assembly of large components of offshore wind turbines according to claim 1, characterized in that, In step S6, the specific process of the main crane and the auxiliary crane working together is as follows: the hook of the main crane is connected to the impeller lifting device, and the hook of the auxiliary crane is connected to the tail cable wind rope. The two cranes work together to turn the impeller from a horizontal position to a vertical position.
Citation Information
Patent Citations
Underwater pile stabilizing system and pile sinking method based on self-elevating type platform ship
CN111441354A
Rapid impeller hoisting method for offshore wind power self-elevating platform ship
CN113915073A