A tower foundation settlement monitoring device

The design, which combines threaded rods and trapezoidal blocks, simplifies the height adjustment of the tower foundation settlement monitoring device, solves the problem of cumbersome operation in the existing technology, realizes convenient assembly and maintenance, reduces the risk of cable damage, and improves the stability of the equipment and the service life of the sensor.

CN123111196APending Publication Date: 2026-11-17STATE GRID SHANDONG ELECTRIC POWER CO GAOQING COUNTY POWER SUPPLY CO
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202611437422.4
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2026-09-16
Publication Date
2026-11-17

AI Technical Summary

Technical Problem

The existing tower foundation settlement monitoring device is cumbersome to operate when adjusting the height, requiring the disassembly of multiple bolts and fasteners, which makes assembly and maintenance inconvenient.

Method used

The design employs a combination of threaded rod, trapezoidal block, ball bearing, U-shaped rod, limit block, and spring. The locking or releasing of the placement plate is achieved by rotating the threaded rod, simplifying the height adjustment process. Furthermore, the transmission plate and constraint mechanism prevent cable damage from pulling.

Benefits of technology

It simplifies the operation steps for adjusting the height of electrical equipment, improves the convenience of assembly and maintenance, reduces the risk of cable damage, and ensures the stability of electrical connections and the service life of sensors.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN123111196A_ABST
    Figure CN123111196A_ABST
Patent Text Reader

Abstract

This invention relates to the field of foundation settlement monitoring technology and discloses a tower foundation settlement monitoring device, including a tower body, a monitoring mechanism, and a data processing mechanism. The tower body is equipped with mounting boxes on all four sides. An L-shaped plate is installed inside each mounting box. The data processing mechanism includes a data box and a placement plate. A slide rail is slidably connected to the outer wall of the placement plate, and a threaded rod is rotatably connected to the inside of the placement plate. A trapezoidal block is threadedly connected to the outer wall of the threaded rod. A ball bearing is installed on the outer wall of the trapezoidal block, and a U-shaped rod is installed on the outer wall of the ball bearing. A limit block is installed on the outer wall of the U-shaped rod. Through the arrangement of the threaded rod, trapezoidal block, ball bearing, U-shaped rod, limit block, and spring two, simply rotating the threaded rod releases the limit of the placement plate, or moving the trapezoidal block away from the ball bearing, and the spring two drives the limit block into the slide rail to lock the placement plate. This eliminates the need to disassemble and assemble multiple sets of bolts and fasteners, simplifying the operation steps for adjusting the height of the electrical equipment inside the box.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This invention relates to the field of foundation settlement monitoring technology, specifically to a tower foundation settlement monitoring device. Background Technology

[0002] With the continuous advancement of national infrastructure construction, the number of iron towers used in fields such as communications and power is constantly increasing. As an important supporting structure for communication signal transmission and power facilities, the stability of the tower foundation directly affects the normal operation of communication systems and power facilities. Therefore, continuous monitoring of the settlement status of iron tower foundations and timely early warning when abnormal settlement trends occur are of great significance for ensuring the safe operation of iron towers.

[0003] Existing tower foundation settlement monitoring devices typically include settlement detection components set at different points on the tower foundation, data acquisition equipment, and acquisition boxes installed near the tower. The settlement detection components detect the height changes at each monitoring point and transmit the detection data to the acquisition equipment, which then feeds it back to the operator or monitoring system via a communication module, thereby achieving continuous monitoring of the tower foundation settlement status.

[0004] The inventors of this application discovered in their research that the core deficiency of the aforementioned prior art lies in the fact that the data acquisition box typically integrates various electrical components such as data acquisition equipment, DTU communication modules, and power supplies, and the placement plate is fixed to the slide rail or mounting bracket inside the box using fasteners such as bolts and nuts. However, when adjusting the height of the existing placement plate, it is usually necessary to disassemble multiple bolts and fasteners sequentially, adjust to the required height, and then reinstall and tighten them one by one. The operation process is relatively cumbersome, and corresponding disassembly and assembly tools are also required during on-site assembly or maintenance. Summary of the Invention

[0005] This invention provides a tower foundation settlement monitoring device, which solves the problem of cumbersome operation when adjusting the height of the placement plate, and simplifies the operation steps for adjusting the height of electrical equipment inside the box.

[0006] To achieve the above objectives, the present invention provides the following technical solution: a tower foundation settlement monitoring device, comprising a tower body, a monitoring mechanism, and a data processing mechanism. The tower body is equipped with mounting boxes on all four sides. An L-shaped plate is installed inside each mounting box. The monitoring mechanism is located on the upper surface of the L-shaped plate. The data processing mechanism includes a data box and a placement plate. A slide rail is slidably connected to the outer wall of the placement plate. A threaded rod is rotatably connected to the inside of the placement plate. A trapezoidal block is threadedly connected to the outer wall of the threaded rod. A ball bearing is provided on the outer wall of the trapezoidal block. A U-shaped rod is installed on the outer wall of the ball bearing. A limit block is installed on the outer wall of the U-shaped rod. A spring is installed between the limit block and the placement plate.

[0007] By utilizing monitoring mechanisms arranged around the tower body, a multi-point settlement monitoring array is formed to automatically monitor the settlement at each point on the tower body. At the same time, the data processing mechanism collects the monitoring data and feeds it back to the operator. The placement plate is locked or released through the threaded rod and its connecting parts, thereby facilitating the position adjustment of the placement plate and the equipment on the upper side.

[0008] By adopting the above technical solution, a multi-point settlement monitoring array is formed by setting up monitoring institutions around the tower body. The monitoring institutions are set on L-shaped plates and installed in the mounting box to settle synchronously with the tower body, so as to automatically collect the foundation settlement at multiple locations of the tower body. The data processing institution receives the settlement detection data output by the monitoring institutions, completes the data processing, and feeds back the monitoring results to the operation and maintenance personnel, realizing the collection and remote output of settlement data.

[0009] Preferably, the outer wall of the limiting block is inserted into the inside of the slide rail, the outer wall of the slide rail is installed inside the data box, the outer wall of the placement plate is set on the inner wall of the data box, and the outer walls of the trapezoidal block, the U-shaped rod and the limiting block are all slidably connected to the inside of the placement plate.

[0010] Preferably, multiple placement plates are provided, and a data acquisition instrument and a DTU device are respectively mounted on the upper surface of the placement plate. The DTU device is electrically connected to an antenna via a cable. The data acquisition instrument and the DTU device are electrically connected. The data acquisition instrument and the monitoring mechanism are electrically connected. A fixing bracket is mounted on the lower surface of the antenna. The lower surface of the fixing bracket is mounted on the upper surface of the data box.

[0011] Preferably, the monitoring mechanism includes a magnetostrictive hydrostatic level, the lower surface of which is mounted on the upper surface of the L-shaped plate. The magnetostrictive hydrostatic level is arranged around the tower body. A liquid-passing pipe and a gas-passing pipe are connected between the multiple magnetostrictive hydrostatic level instruments respectively. A data line is electrically connected between the multiple magnetostrictive hydrostatic level instruments, and the data line is electrically connected to the data acquisition instrument.

[0012] Preferably, a transmission plate is installed on the outer wall of the trapezoidal block, and a constraint mechanism is provided on the outer wall of the transmission plate. The constraint mechanism includes a hollow block, the outer wall of which is installed inside the placement plate. A moving block is slidably connected inside the hollow block, and the outer wall of the moving block is installed on the outer wall of the transmission plate. The outer wall of the transmission plate is slidably connected to the placement plate and the interior of the hollow block.

[0013] Preferably, the movable block is rotatably connected to a connecting plate inside, and the outer wall of the connecting plate is rotatably connected to a T-shaped frame, the outer wall of the T-shaped frame being rotatably connected to the interior of the hollow block.

[0014] Preferably, a moving rod is installed on the outer wall of the moving block, and the outer wall of the moving rod is slidably connected to the interior of the hollow block and the placement plate. An arc-shaped block is installed on the outer wall of the moving rod.

[0015] Preferably, one end of a spring is connected inside the mounting box, the other end of the spring is mounted on an L-shaped plate, and a fixing rod is slidably connected inside the L-shaped plate, with both ends of the fixing rod mounted inside the mounting box.

[0016] Preferably, a buffer pad is provided on the side of the L-shaped plate away from the spring, the outer wall of the buffer pad is located inside the mounting box, and a disc spring is installed on the side of the buffer pad away from the L-shaped plate, the outer wall of the disc spring is located inside the mounting box.

[0017] Preferably, the outer wall of the fixed frame is provided with a photovoltaic mechanism, the photovoltaic mechanism includes a photovoltaic panel, the outer wall of the photovoltaic panel is installed on the outer wall of the fixed frame, the photovoltaic panel is electrically connected to a battery, the battery is electrically connected to a controller, the controller is electrically connected to the data acquisition instrument and the DTU device respectively, and the outer walls of the battery and the controller are both installed inside the data box.

[0018] By adopting the above technical solution, the transmission plate moves horizontally in sync with the trapezoidal block, and the adjustment driving force of the threaded rod and trapezoidal block is reused to output the power of locking or releasing the placement plate to the constraint mechanism in a synchronized manner. No additional drive source is required to achieve mechanical linkage. While adjusting the height of the placement plate, the cable constraint component is driven simultaneously to prevent the cable from being rigidly clamped and pulled, thus preventing the cable from being stretched and damaged.

[0019] This invention provides a device for monitoring the settlement of iron tower foundations. It has the following beneficial effects:

[0020] 1. This invention, through the arrangement of a threaded rod, trapezoidal block, ball bearings, U-shaped rod, limiting block, and spring two, allows the placement plate to be moved outwards by simply rotating the threaded rod, which in turn drives the ball bearings, U-shaped rod, and limiting block on both sides through the trapezoidal block, allowing them to slide out of the slide rail and release the limiting position of the placement plate. Alternatively, the trapezoidal block can move away from the ball bearings, and the limiting block can be driven by spring two to insert into the slide rail and lock the placement plate. This eliminates the need to disassemble and assemble multiple sets of bolts and fasteners, simplifying the operation steps for adjusting the height of electrical equipment inside the box and facilitating on-site assembly, maintenance, and replacement of components.

[0021] 2. When the trapezoidal block moves, it can push the moving block, the moving rod, and the arc-shaped block to move. At the same time, through the connecting plate and the T-shaped frame, the arc-shaped blocks on both sides can move relative to each other or away from each other. When the placement plate moves up and down, the arc-shaped blocks on both sides can be released from their restriction on the cable, avoiding damage to the cable due to pulling during the adjustment process. When the placement plate is fixed in position, it can also limit the cable, constrain and position the wiring inside the box, reduce cable shaking caused by vibration in the field environment, reduce the risk of loose joints, and ensure stable and reliable electrical connection.

[0022] 3. This invention, through the installation of a mounting box, spring 1, a fixing rod, a disc spring, and a buffer pad, mounts the magnetostrictive static level on an L-shaped plate. When the tower is blown by wind, the tower sways laterally, and the L-shaped plate can slide laterally along the fixing rod. The double elastic buffering of spring 1 and disc spring, combined with the buffer pad, reduces vibration impact, reduces device wear caused by alternating vibration of the magnetostrictive static level, and extends the sensor's service life in the field. In the vertical direction, the L-shaped plate and the magnetostrictive static level settle synchronously with the tower foundation, and the vertical displacement is not constrained by the buffer structure, ensuring that the settlement displacement can be completely transmitted to the magnetostrictive static level. Attached Figure Description

[0023] Figure 1 This is a perspective view of the present invention;

[0024] Figure 2 This is a partial structural schematic diagram of the magnetostrictive hydrostatic level of the present invention;

[0025] Figure 3 This is a partial structural diagram of the placement plate of the present invention;

[0026] Figure 4 This is a partial structural diagram of the fixing frame of the present invention;

[0027] Figure 5 This is a schematic diagram of a partial structure of the slide rail of the present invention;

[0028] Figure 6 This is a cross-sectional view of the internal structure of the placement plate of the present invention;

[0029] Figure 7 This is a cross-sectional view of the internal structure of the trapezoidal block of the present invention;

[0030] Figure 8 This is a cross-sectional schematic diagram of the internal structure of the hollow block of the present invention;

[0031] Figure 9 This is a partial structural diagram of the L-shaped plate of the present invention;

[0032] Figure 10 This is a cross-sectional view of the internal structure of the mounting box of the present invention.

[0033] The components include: 1. Tower body; 2. Mounting box; 3. L-shaped plate; 4. Monitoring mechanism; 5. Data processing mechanism; 6. Fixing frame; 7. Photovoltaic mechanism; 8. Constraint mechanism.

[0034] 21. Spring 1; 22. Fixing rod; 23. Disc spring; 24. Buffer pad;

[0035] 41. Magnetostrictive hydrostatic level; 42. Liquid inlet tube; 43. Air inlet tube; 44. Data cable;

[0036] 51. Data box; 52. Placement board; 53. Data acquisition unit; 54. DTU equipment; 55. Antenna; 56. Slide rail;

[0037] 521. Threaded rod; 522. Trapezoidal block; 523. Ball bearing; 524. U-shaped rod; 525. Limiting block; 526. Spring II; 527. Transmission plate;

[0038] 71. Photovoltaic panel; 72. Battery; 73. Controller;

[0039] 81. Hollow block; 82. Moving block; 83. Connecting plate; 84. T-shaped frame; 85. Moving rod; 86. Arc-shaped block. Detailed Implementation

[0040] The technical solution of the present invention will now be clearly and completely described with reference to the accompanying drawings. Obviously, the described embodiments are only a part of the embodiments of the present invention, and not all of them. Based on the embodiments of the present invention, all other embodiments obtained by those skilled in the art without creative effort are within the scope of protection of the present invention.

[0041] Please see the appendix Figure 1 -Appendix Figure 7 This invention provides a tower foundation settlement monitoring device, including a tower body 1, a monitoring mechanism 4, and a data processing mechanism 5. Installation boxes 2 are installed around the tower body 1. An L-shaped plate 3 is installed inside the installation box 2. The monitoring mechanism 4 is located on the upper surface of the L-shaped plate 3. The data processing mechanism 5 includes a data box 51 and a placement plate 52. A slide rail 56 is slidably connected to the outer wall of the placement plate 52. A threaded rod 521 is rotatably connected inside the placement plate 52. A trapezoidal block 522 is threadedly connected to the outer wall of the threaded rod 521. A ball bearing 523 is provided on the outer wall of the trapezoidal block 522. A U-shaped rod 524 is installed on the outer wall of the ball bearing 523. A limit block 525 is installed on the outer wall of the U-shaped rod 524. A spring 526 is installed between the limit block 525 and the placement plate 52.

[0042] By using the monitoring mechanisms 4 arranged around the tower body 1, a multi-point settlement monitoring array for the tower body 1 is formed, which automatically monitors the settlement at each point of the tower body 1. At the same time, the data processing mechanism 5 collects the monitoring data and feeds it back to the operator. The placement plate 52 is locked or released through the threaded rod 521 and its connecting parts, thereby facilitating the position adjustment of the placement plate 52 and the equipment on the upper side.

[0043] Specifically, the mounting box 2 provides an installation reference for the L-shaped plate 3, allowing the monitoring equipment of the monitoring mechanism 4 to be vertically mounted on the L-shaped plate 3. The electrical equipment inside the data box 51 collects and processes the monitoring data of the monitoring mechanism 4. The placement plate 52 provides an installation reference for the electrical equipment, preventing accidental movement. The interior of the placement plate 52 supports and limits the rotation of the threaded rod 521, while also restricting the trapezoidal block 522 to only move horizontally. This facilitates movement of the trapezoidal block 522 as the threaded rod 521 rotates. Ball bearings 523 are installed on the U-shaped rod 524, positioned between the U-shaped rod 524 and the trapezoidal block 522, to reduce... The light trapezoidal block 522 provides transmission resistance to the U-shaped rod 524, which in turn drives the limiting block 525 to move, thereby inserting into or pulling out of the slide rail 56. This achieves the limiting or release of the placement plate 52 itself, allowing for height adjustment of the placement plate 52 and the electrical equipment installed thereon, facilitating on-site assembly, maintenance, and equipment replacement. By using appropriate elastic force through the second spring 526, when the trapezoidal block 522 no longer pushes the U-shaped rod 524 and the limiting block 525 to the sides of the placement plate 52, it can push the limiting blocks 525 on both sides towards the slide rail 56, placing the limiting blocks 525 inside the slide rail 56, thus preventing them from being affected by external forces and allowing the limiting blocks 525 to slide out of the slide rail 56.

[0044] Please see the appendix Figure 4 -Appendix Figure 7 The outer wall of the limiting block 525 is inserted into the inside of the slide rail 56. The outer wall of the slide rail 56 is installed inside the data box 51. The outer wall of the placement plate 52 is set on the inner wall of the data box 51. The outer walls of the trapezoidal block 522, the U-shaped rod 524 and the limiting block 525 are all slidably connected to the inside of the placement plate 52.

[0045] Specifically, the limiting block 525 slides in and out inside the slide rail 56 to limit or release itself, while the outer wall of the placement plate 52 contacts the inner wall of the data box 51, so that the inner wall of the data box 51 also bears the weight of the placement plate 52 and the equipment on its upper side, reducing the mechanical stress between the limiting block 525 and the slide rail 56. The movement of the trapezoidal block 522, the U-shaped rod 524 and the limiting block 525 are all offset and limited by the inside of the placement plate 52.

[0046] Please see the appendix Figure 3 and attached Figure 4 Multiple placement plates 52 are provided. A data acquisition unit 53 and a DTU device 54 are respectively installed on the upper surface of the placement plate 52. The DTU device 54 is electrically connected to an antenna 55 via a wire. The data acquisition unit 53 and the DTU device 54 are electrically connected. The data acquisition unit 53 is electrically connected to the monitoring mechanism 4. A mounting bracket 6 is installed on the lower surface of the antenna 55. The lower surface of the mounting bracket 6 is installed on the upper surface of the data box 51.

[0047] Specifically, the data acquisition unit 53 can be a dedicated displacement acquisition component for monitoring equipment, or a PLC can be used to directly read level instrument data. The DTU device 54 serves as a communication unit, transmitting the data from the data acquisition unit 53 to the maintenance terminal remotely via the antenna 55. The antenna 55 acts as a signal transmitting and receiving component, working with the DTU device 54 to achieve wireless data transmission.

[0048] Please see the appendix Figure 2 and attached Figure 3 The monitoring device 4 includes a magnetostrictive hydrostatic level 41. The lower surface of the magnetostrictive hydrostatic level 41 is mounted on the upper surface of the L-shaped plate 3. The magnetostrictive hydrostatic level 41 is arranged around the tower body 1. Multiple magnetostrictive hydrostatic level 41 are connected by liquid pipes 42 and air pipes 43 respectively. Multiple magnetostrictive hydrostatic level 41 are electrically connected by data lines 44, and the data lines 44 are electrically connected to the data acquisition device 53.

[0049] Specifically, multiple magnetostrictive static levels 41 are set up and interconnected via liquid-conducting pipes 42. One reference point is set, and the rest are measuring points. All are filled with conductive liquid, and the vent pipes 43 at the top of all tanks are connected to ensure consistent atmospheric pressure. After all magnetostrictive static levels 41 are leveled, the liquid in the connecting pipes is stationary, and the liquid levels in all tanks are at the same absolute horizontal plane. When a monitoring point experiences settlement or elevation, the instrument tank moves downward or upward along with the structure, but the connected liquid levels remain at their original horizontal plane. Therefore, the float moves up and down relative to the tank and probe. The position of the float is detected by the magnetostrictive effect, and the liquid level change is converted into an electrical signal to obtain the sedimentation value of each measuring point. The data line 44 collects the monitored data through the vent pipe 43. Through the above, one of the magnetostrictive static level 41s around the tower body 1 can be selected as the base point and the rest as measuring points. Alternatively, an additional magnetostrictive static level 41 can be set as the base point, and all the magnetostrictive static level 41s around the tower body 1 can be used as measuring points.

[0050] Please see the appendix Figure 6 -Appendix Figure 8A transmission plate 527 is installed on the outer wall of the trapezoidal block 522. A constraint mechanism 8 is provided on the outer wall of the transmission plate 527. The constraint mechanism 8 includes a hollow block 81. The outer wall of the hollow block 81 is installed inside the placement plate 52. A moving block 82 is slidably connected inside the hollow block 81. The outer wall of the moving block 82 is installed on the outer wall of the transmission plate 527. The outer wall of the transmission plate 527 is slidably connected to the placement plate 52 and the hollow block 81. A connecting plate 83 is rotatably connected inside the moving block 82. A T-shaped frame 84 is rotatably connected to the outer wall of the connecting plate 83. The outer wall of the T-shaped frame 84 is rotatably connected to the inside of the hollow block 81. A moving rod 85 is installed on the outer wall of the moving block 82. The outer wall of the moving rod 85 is slidably connected to the hollow block 81 and the placement plate 52. An arc-shaped block 86 is installed on the outer wall of the moving rod 85.

[0051] Specifically, hollow blocks 81 are installed inside the placement plate 52 and correspond to the interfaces of electrical components on the upper side of the placement plate 52. This allows the cables connected to the interfaces of the upper and lower electrical components to be clamped and limited when the arc-shaped blocks 86 on both sides move relative to each other, reducing excessive cable swaying rather than clamping and fixing the cable position. Through the cooperation of the transmission plate 527 and the moving block 82, the number of hollow blocks 81 inside the placement plate 52 can be changed according to actual needs. The movement of the moving block 82 and the moving rod 85 is offset and limited by the interior of the hollow blocks 81. Both ends of the connecting plate 83 are set on short rods. The movable blocks 82 and T-shaped frame 84 are rotated. The two ends of the T-shaped frame 84 are connected to the movable blocks 82 on both sides through the connecting plate 83. The movable blocks 82 are arranged in a circle on both sides with the T-shaped frame 84 as the center. As the T-shaped frame 84 rotates, it drives the movable blocks 82 on both sides to move relative to or away from each other. The transmission plate 527 actively drives the movable block 82 on one side to move. Through the T-shaped frame 84, the movable blocks 82 on both sides move synchronously, so as to drive the arc-shaped blocks 86 on both sides to limit or release the cable at its center. This prevents the cable from being limited and affecting the movement of the placement plate 52 when the height of the placement plate 52 is adjusted.

[0052] Please see the appendix Figure 9 and attached Figure 10 One end of spring 21 is connected to the inside of the mounting box 2. The other end of spring 21 is installed on L-shaped plate 3. A fixing rod 22 is slidably connected inside L-shaped plate 3. Both ends of fixing rod 22 are installed inside the mounting box 2. A buffer pad 24 is provided on the side of L-shaped plate 3 away from spring 21. The outer wall of buffer pad 24 is installed inside the mounting box 2. A disc spring 23 is installed on the side of buffer pad 24 away from L-shaped plate 3. The outer wall of disc spring 23 is installed inside the mounting box 2.

[0053] Specifically, the spring 21 is used for lateral buffering to absorb the impact of lateral swaying caused by the wind from the tower, while the fixed rod 22 allows the L-shaped plate 3 to slide through, limiting the L-shaped plate 3 to only slide laterally and ensuring the normal transmission of vertical settlement displacement. The disc spring 23, in conjunction with the buffer pad 24, further consumes the lateral vibration energy, and the disc spring 23 itself has a certain rigidity, thereby reducing the swaying of the L-shaped plate 3 when it moves laterally.

[0054] Please see the appendix Figure 3 and attached Figure 4 A photovoltaic mechanism 7 is provided on the outer wall of the fixed frame 6. The photovoltaic mechanism 7 includes a photovoltaic panel 71. The outer wall of the photovoltaic panel 71 is installed on the outer wall of the fixed frame 6. The photovoltaic panel 71 is electrically connected to a battery 72. The battery 72 is electrically connected to a controller 73. The controller 73 is electrically connected to the data acquisition instrument 53 and the DTU device 54 respectively. The outer walls of the battery 72 and the controller 73 are both installed inside the data box 51.

[0055] Specifically, the photovoltaic panel 71 can be installed along both sides of the sun's rising and setting trajectory according to the actual installation location, thereby improving the solar utilization rate after the photovoltaic panel 71 is installed and fixed. The photovoltaic panel 71, as a solar power generation panel, converts light energy into electrical energy, and the battery 72, as an energy storage component, stores the electrical energy generated by the photovoltaic panel 71. The controller 73 controls the charging and discharging of the battery 72 to provide a stable power supply for the data acquisition instrument 53 and the DTU device 54.

[0056] Work process: The installation box 2 around the tower body 1 carries the magnetostrictive static level 41 through the L-shaped plate 3. Multiple magnetostrictive static level 41 are connected to liquid through the liquid pipe 42 and connected to air pressure through the air pipe 43, forming a multi-point settlement monitoring array around the tower body 1.

[0057] When the foundation of tower 1 settles, the magnetostrictive hydrostatic level 41 moves vertically along with the foundation, causing a relative change in the liquid level inside each instrument. The position of the float is detected by the magnetostrictive effect, and the liquid level change is converted into an electrical signal, thereby obtaining the settlement value of each measuring point. The data is transmitted to the acquisition instrument 53 inside the data box 51 via the data cable 44. The acquisition instrument 53 transmits the received settlement data to the DTU device 54. The DTU device 54 transmits the monitoring data remotely to the operator's terminal via the antenna 55 installed on the mounting bracket 6. At the same time, the photovoltaic panel 71 in the photovoltaic mechanism 7 collects solar energy, the battery 72 stores electrical energy, and the controller 73 completes the charging and discharging control, providing field power for the entire monitoring electrical components of the acquisition instrument 53 and the DTU device 54.

[0058] When the tower sways laterally due to wind, the spring 21, fixing rod 22, disc spring 23, and buffer pad 24 inside the mounting box 2 work together to buffer the L-shaped plate 3 laterally, isolate the lateral wind vibration interference, and only transmit the vertical foundation settlement displacement, so as to avoid the lateral swaying from interfering with the measurement accuracy of the magnetostrictive static level 41.

[0059] By rotating the threaded rod 521, the trapezoidal block 522 is driven to move horizontally. Through the ball bearing 523 and the U-shaped rod 524, the elastic force of the second spring 526 is overcome, and the limit block 525 is driven to slide out of the interior of the slide rail 56. At this time, the placement plate 52 is unlocked and can slide vertically along the slide rail 56, thereby adjusting the vertical installation height of the placement plate 52 and the acquisition instrument 53, DTU equipment 54 or other electrical components on the plate.

[0060] While the trapezoidal block 522 moves horizontally, it drives the transmission plate 527 to move synchronously, driving the constraint mechanism 8. The transmission plate 527 drives the moving block 82 to slide inside the hollow block 81. Through the reversing transmission of the connecting plates 83 on both sides and the T-shaped frame 84, the moving rods 85 on both sides are pushed to move in opposite directions, so that the arc blocks 86 on both sides release the cable in the center. During the up and down adjustment of the placement plate 52, the cable is not clamped, preventing the cable from being pulled and damaged. Conversely, after the position of the placement plate 52 is locked, the arc blocks 86 on both sides limit the cable to avoid accidental shaking.

[0061] Although embodiments of the invention have been shown and described, it will be understood by those skilled in the art that various changes, modifications, substitutions and alterations can be made to these embodiments without departing from the principles and spirit of the invention, the scope of which is defined by the appended claims and their equivalents.

Claims

1. A tower foundation settlement monitoring device, comprising a tower body (1), a monitoring mechanism (4), and a data processing mechanism (5), characterized in that, The tower body (1) is equipped with mounting boxes (2) on all four sides. An L-shaped plate (3) is set inside the mounting box (2). The monitoring mechanism (4) is set on the upper surface of the L-shaped plate (3). The data processing mechanism (5) includes a data box (51) and a placement plate (52). A slide rail (56) is slidably connected to the outer wall of the placement plate (52). A threaded rod (521) is rotatably connected inside the placement plate (52). A trapezoidal block (522) is threadedly connected to the outer wall of the threaded rod (521). A ball bearing (523) is set on the outer wall of the trapezoidal block (522). A U-shaped rod (524) is installed on the outer wall of the ball bearing (523). A limit block (525) is installed on the outer wall of the U-shaped rod (524). A spring (526) is installed between the limit block (525) and the placement plate (52). By using the monitoring mechanism (4) arranged around the tower body (1), a multi-point settlement monitoring array of the tower body (1) is formed to automatically monitor the settlement of each point of the tower body (1). At the same time, the data processing mechanism (5) collects the monitoring data and feeds it back to the operator. The placement plate (52) is locked or released by the threaded rod (521) and its connecting parts, so as to facilitate the position adjustment of the placement plate (52) and the equipment on the upper side.

2. The tower foundation settlement monitoring device according to claim 1, characterized in that, The outer wall of the limiting block (525) is inserted into the inside of the slide rail (56), the outer wall of the slide rail (56) is installed inside the data box (51), the outer wall of the placement plate (52) is set on the inner wall of the data box (51), and the outer walls of the trapezoidal block (522), the U-shaped rod (524) and the limiting block (525) are all slidably connected to the inside of the placement plate (52).

3. The tower foundation settlement monitoring device according to claim 1, characterized in that, Multiple placement plates (52) are provided. A data acquisition device (53) and a DTU device (54) are respectively installed on the upper surface of the placement plate (52). The DTU device (54) is electrically connected to an antenna (55) via a wire. The data acquisition device (53) and the DTU device (54) are electrically connected. The data acquisition device (53) and the monitoring mechanism (4) are electrically connected. A mounting bracket (6) is installed on the lower surface of the antenna (55). The lower surface of the mounting bracket (6) is installed on the upper surface of the data box (51).

4. The tower foundation settlement monitoring device according to claim 1, characterized in that, The monitoring mechanism (4) includes a magnetostrictive hydrostatic level (41), the lower surface of which is mounted on the upper surface of the L-shaped plate (3). The magnetostrictive hydrostatic level (41) is arranged around the tower body (1). A liquid pipe (42) and a gas pipe (43) are connected between multiple magnetostrictive hydrostatic levels (41). A data line (44) is electrically connected between multiple magnetostrictive hydrostatic levels (41), and the data line (44) is electrically connected to the data acquisition instrument (53).

5. The tower foundation settlement monitoring device according to claim 1, characterized in that, A transmission plate (527) is installed on the outer wall of the trapezoidal block (522). A constraint mechanism (8) is provided on the outer wall of the transmission plate (527). The constraint mechanism (8) includes a hollow block (81). The outer wall of the hollow block (81) is installed inside the placement plate (52). A moving block (82) is slidably connected inside the hollow block (81). The outer wall of the moving block (82) is installed on the outer wall of the transmission plate (527). The outer wall of the transmission plate (527) is slidably connected inside the placement plate (52) and the hollow block (81).

6. The tower foundation settlement monitoring device according to claim 5, characterized in that, The movable block (82) is rotatably connected to a connecting plate (83), and the outer wall of the connecting plate (83) is rotatably connected to a T-shaped frame (84). The outer wall of the T-shaped frame (84) is rotatably connected to the interior of the hollow block (81).

7. The tower foundation settlement monitoring device according to claim 5, characterized in that, The outer wall of the movable block (82) is equipped with a movable rod (85), the outer wall of the movable rod (85) is slidably connected to the interior of the hollow block (81) and the placement plate (52), and the outer wall of the movable rod (85) is equipped with an arc-shaped block (86).

8. The tower foundation settlement monitoring device according to claim 1, characterized in that, The mounting box (2) is connected to one end of a spring (21), and the other end of the spring (21) is mounted on an L-shaped plate (3). A fixing rod (22) is slidably connected inside the L-shaped plate (3), and both ends of the fixing rod (22) are mounted inside the mounting box (2).

9. A tower foundation settlement monitoring device according to claim 1, characterized in that, A buffer pad (24) is provided on the side of the L-shaped plate (3) away from the spring (21). The outer wall of the buffer pad (24) is located inside the mounting box (2). A disc spring (23) is installed on the side of the buffer pad (24) away from the L-shaped plate (3). The outer wall of the disc spring (23) is located inside the mounting box (2).

10. A tower foundation settlement monitoring device according to claim 3, characterized in that, The outer wall of the fixed frame (6) is provided with a photovoltaic mechanism (7), which includes a photovoltaic panel (71). The outer wall of the photovoltaic panel (71) is installed on the outer wall of the fixed frame (6). The photovoltaic panel (71) is electrically connected to a battery (72). The battery (72) is electrically connected to a controller (73). The controller (73) is electrically connected to the data acquisition instrument (53) and the DTU device (54) respectively. The outer walls of the battery (72) and the controller (73) are both installed inside the data box (51).