A distributed program control system for a straw fiber production unit

By leveraging the synergistic effects of material filing, load assessment, access control, and anomaly recovery modules, the problems of insufficient correlation between material segment status and workstation access capability, as well as insufficient write-back of screening return load, in the straw fiber preparation unit were solved, thus achieving stable operation of the unit and consistent management of anomaly recovery.

CN123113458APending Publication Date: 2026-11-17任丘市供销社绿丰再生物资回收有限公司
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202611288561.5
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2026-08-24
Publication Date
2026-11-17

AI Technical Summary

Technical Problem

In the existing distributed control system of straw fiber production units, there is insufficient correlation between the material section status and the station access capability, insufficient write-back of screening return load, and insufficient consistency of occupation records during abnormal recovery, which leads to the risk of overload, material blockage and load superposition.

Method used

The system employs a material filing module, a load assessment module, an access control module, a process execution module, and an anomaly recovery module. Through material filing, load assessment, access control, program consistency verification, and anomaly recovery, it generates material load tags, remaining consumption windows, and occupancy tokens, thereby achieving accurate association between material segment status and workstation and load management.

Benefits of technology

Reduce the risk of overload and material blockage at the target workstation, reduce the risk of overlapping screening return loads, ensure the consistency of occupancy records during abnormal recovery, and improve the stability of unit operation.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN123113458A_ABST
    Figure CN123113458A_ABST
Patent Text Reader

Abstract

This invention relates to the field of unit program control technology, and discloses a distributed program control system for a straw fiber production unit. The system includes a material filing module for establishing material segment and window occupancy records and generating standardized status values; a load assessment module for generating a comprehensive load index and writing it into a material load tag; an access control module for generating an access judgment value based on the remaining consumption window and the comprehensive load index to issue or reject occupancy tokens; a process execution module for performing program consistency checks and processing updated load values ​​corresponding to screening return materials; and an anomaly recovery module for generating freeze information and allocating a recovery queue based on the recovery judgment value. This invention, through the linkage of material segments, material load tags, window occupancy records, occupancy tokens, and recovery queues, ensures that material entry, return material write-back, and anomaly recovery are all executed according to the same state chain, reducing target station overload, return material load superposition, and inaccurate occupancy records.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This invention relates to the field of unit program control technology, specifically a distributed program control system for a straw fiber production unit. Background Technology

[0002] Straw fiber processing units typically include stations for feeding, cutting, kneading, moisture conditioning, fiber unwinding, drying, screening, and return. Each station can be controlled collaboratively by a PLC, fieldbus control system, and distributed controller. Existing units mostly implement interlocking control based on the single-station status such as motor load, material level, speed, and alarm signals, and handle situations such as increased station load or material level approaching the upper limit through methods such as deceleration, limited discharge, or shutdown.

[0003] The above methods can achieve basic equipment protection, but they lack continuous status recording for the material section. Before the material enters the target station, the control system usually makes control based on the current status of the target station. It is difficult to make access judgments by simultaneously combining the load of the material section, the remaining processing capacity of the target station, and the unreleased promised occupancy. The target station still has the risk of overload or material blockage.

[0004] In screening return material handling, existing controls typically treat return material as ordinary recirculated material. The correlation between the return cause, screening resistance, and return channel occupancy status and the original material section load status is insufficient. When the return material re-enters subsequent workstations, the load status is unclear. After communication interruptions, sensor malfunctions, manual intervention, or emergency shutdowns, the correspondence between material section status, occupancy records, and program status is also prone to inaccuracy. During recovery and restart, issues arise such as premature release of promised occupancy, repeated release, or unclear recovery queue division. Summary of the Invention

[0005] To address the shortcomings of existing technologies, this invention provides a distributed program control system for straw fiber production units, which solves the problems of insufficient correlation between material segment status and workstation access capability, insufficient write-back of screening return load, and insufficient consistency of occupancy records during abnormal recovery in existing distributed control systems for straw fiber production units.

[0006] To achieve the above objectives, the present invention provides the following technical solution: This invention provides a distributed program control system for a straw fiber production unit, comprising: The material filing module is used to create material segment and window occupancy records and generate standardized status values ​​from the collected initial dataset.

[0007] The load assessment module is used to obtain multiple workstation resistance status values, combine them with standardized status values, and substitute them into the load aggregation formula to calculate and generate a comprehensive load index, which is then written into the material load label.

[0008] The access control module is used to extract multiple physical reserves of core load workstations and the committed occupancy amount in the window occupancy record, substitute them into the remaining window formula to generate the remaining absorption window; and substitute the remaining absorption window and the comprehensive load index into the access judgment formula to generate the access judgment value, so as to issue or reject the occupancy token, and update the committed occupancy amount in the window occupancy record after issuance.

[0009] The process execution module is used to generate a consistency verification value by substituting a preset consistency judgment rule after the occupancy token is issued and before the material segment is handed over across workstations, and to control the material segment to enter the normal program segment or be downgraded to the transition program segment based on the consistency verification value.

[0010] The anomaly recovery module is used to extract material load tags, window occupancy records, and occupancy tokens to generate freeze information when an anomaly is triggered. Upon restart, it parses the freeze information to obtain multiple shutdown resident status values, substitutes them into the recovery judgment formula to generate a recovery judgment value, allocates the material segment to the recovery queue based on the recovery judgment value, releases the occupancy token after the corresponding recovery queue has been completed, and cancels the corresponding promised occupancy in the window occupancy record.

[0011] Furthermore, the material filing module includes an initial filing unit and a state calibration unit. The initial filing unit is used to establish material segments and empty window occupancy records according to preset filing benchmark boundaries, and to collect the original data collected during the filing stage to generate an initial dataset. The state calibration unit is used to call preset state calibration rules to perform normalization processing on the original data collected, and generate standardized state values ​​that include dry basis feed rate state values, moisture content deviation values, and continuity state values.

[0012] Furthermore, the material filing module also includes a dynamic tracking unit. The dynamic tracking unit collects real-time conveyor belt speed and conveyor belt distance, extracts the initial filing time, current workstation number, preset estimated dwell time, and dynamic correction time, substitutes these into the arrival time formula to generate the estimated arrival time, and writes the estimated arrival time into the record field corresponding to the material segment. When the real-time conveyor belt speed is zero, the dynamic tracking unit pauses the division calculation of the conveyor belt distance and real-time conveyor belt speed in the arrival time formula and adds the downtime to the dynamic correction time.

[0013] Furthermore, the load assessment module includes a resistance acquisition unit, a workstation status unit, and a load aggregation unit. The resistance acquisition unit generates a cutting resistance status value based on the acquired cutting motor current and cutting speed, and generates a material registration record in the window occupancy record when the cutting resistance status value exceeds a preset resistance threshold. The workstation status unit generates an estimated defiberization resistance status value from multiple workstation resistance status values ​​based on preset historical formula data, and generates a kneading resistance status value from multiple workstation resistance status values ​​based on the acquired kneading motor load and kneading chamber material level. The load aggregation unit substitutes the standardized status value and multiple workstation resistance status values ​​into the load aggregation formula to generate a comprehensive load index.

[0014] Furthermore, the access control module includes a window calculation unit and a token decision unit. The window calculation unit maps multiple physical margins to standard calculation margins and, in conjunction with the committed occupancy amount in the unreleased state extracted from the window occupancy record, substitutes it into the remaining window formula to generate the remaining consumption window. The token decision unit substitutes the remaining consumption window, the comprehensive load index, and the safe occupancy margin extracted from the preset process parameter table into the access judgment formula to generate an access judgment value; when the access judgment value is not less than zero, an occupancy token is issued and a new committed occupancy amount is written into the window occupancy record; when the access judgment value is less than zero, the occupancy token is rejected and a speed reduction limit instruction is generated and sent to the external actuator.

[0015] Furthermore, the access control module also includes an occupancy record unit. This unit generates a valid flag after an occupancy token is issued, assigns the token to the occupancy, and releases the token and cancels the committed occupancy amount in the window occupancy record after the material segment completes processing at the target station. The occupancy record unit also generates a short-term frozen flag or a failed flag based on the communication interruption duration, the material segment's conveying time, and a preset timeout threshold when a communication connection with the target controller is detected to be lost. After generating the failed flag, it generates an abnormal rollback procedure, causing the external actuator to perform speed-limited discharge, temporary storage, or stop feeding.

[0016] Furthermore, the process execution module includes a consistency verification unit and an execution control unit. The consistency verification unit extracts executed matching values, pending matching values, and prohibited switching matching values ​​from the material load tag, occupancy token, and target workstation, respectively, and substitutes them into the consistency judgment rules to generate a consistency verification value. The execution control unit locks the target program segment after the consistency verification value equals logical true, and generates a drying and consumption window based on the measured defiber resistance state value generated after collecting the defiber motor operating parameters through field sensors and the moisture content deviation value extracted from the standardized state value. When the drying and consumption window is less than zero, a window insufficiency command is generated and sent to the external execution mechanism to reduce the upstream feed rate.

[0017] Furthermore, the process execution module also includes a return material update unit. This unit generates a return material association tag when screening return material is generated in the material section. It extracts the return material cause status value, screening resistance status value, and channel congestion status value from the return material association tag, and generates a return material correction item based on these values. The return material update unit also accumulates the return material correction item to the comprehensive load index to obtain an updated load value, and sends the updated load value to the token decision unit to replace the original comprehensive load index in re-applying for a token.

[0018] Furthermore, the anomaly recovery module includes a state freeze unit and a recovery determination unit. The state freeze unit, upon receiving an anomaly trigger signal, extracts material load tags, window occupancy records, and occupancy tokens to generate freeze information. Upon obtaining an out-of-bounds state flag, it generates an invalid state flag and writes it into the freeze information. It also generates alternative state values ​​based on redundant variable data from the fieldbus control system and writes them into the freeze information. The recovery determination unit, when the unit resumes restarting, parses the freeze information, obtains multiple shutdown-remaining state values, and substitutes them into the recovery determination formula to generate a recovery determination value.

[0019] Furthermore, the anomaly recovery module also includes a segmented recovery unit. The segmented recovery unit is used to allocate material segments to an isolation processing queue, a return processing queue, a first-out queue, or a continue-processing queue based on the recovery judgment value, short-term frozen state flag, consistency verification value, and the token validity status value, sensor validity status value, and return-related status value parsed from multiple shutdown resident status values. After the corresponding recovery queue has been completed, the unit releases the occupancy token and cancels the corresponding committed occupancy amount in the window occupancy record.

[0020] This invention provides a distributed program control system for a straw fiber production unit. It has the following beneficial effects: 1. This invention takes the material section as the control object and links the material load label, the remaining disposal window and the occupancy token, so that the upstream material discharge can make access judgment based on the load status of the material section and the remaining processing capacity of the target station, thereby reducing the overload and blockage of the target station.

[0021] 2. After screening return material is generated, the present invention records the return material cause status value, screening resistance status value and channel congestion status value through return material association tags, and generates an updated load value accordingly, so that the screening return material re-participates in the admission judgment with the updated load status, reducing the risk of load superposition caused by the return material directly entering the subsequent work station.

[0022] 3. This invention generates freeze information when an anomaly is triggered, and allocates the resident material segments to the recovery queue according to the recovery judgment value during recovery and restart, so that the window occupancy record and occupancy token remain associated during the anomaly recovery process, reducing the risk of premature or repeated release of the committed occupancy amount. Attached Figure Description

[0023] Figure 1 This is a system architecture diagram of the present invention; Figure 2 This is a flowchart of the method of the present invention; Figure 3 This is a processing logic diagram of the material filing module of the present invention; Figure 4 This is a processing logic diagram of the load assessment module of the present invention; Figure 5 This is a processing logic diagram of the access control module of the present invention; Figure 6 This is a processing logic diagram of the process execution module of the present invention; Figure 7 This is a processing logic diagram of the anomaly recovery module of the present invention; Figure 8 This is a time-series comparison chart of the remaining absorption window and the comprehensive load index in an application embodiment of the present invention; Figure 9 This is a bar chart comparing the normalized load peak values ​​of the fiber disassembly station under three working conditions in an application embodiment of the present invention. Detailed Implementation

[0024] The technical solutions in the embodiments of the present invention will be clearly and completely described below with reference to the accompanying drawings. Obviously, the described embodiments are only some embodiments of the present invention, and not all embodiments. Based on the embodiments of the present invention, all other embodiments obtained by those skilled in the art without creative effort are within the scope of protection of the present invention.

[0025] Please see the appendix Figure 1 This invention provides a distributed program control system for a straw fiber production unit, comprising: The material filing module is used to establish material segments according to preset filing benchmark boundaries, generate material segment numbers and initial datasets, normalize the raw collected quantities in the initial datasets to generate standardized status values, and calculate the expected arrival time based on the arrival time formula.

[0026] The load assessment module is used to collect data on the cutting motor current, cutting speed, kneading motor load, kneading chamber material level, and discharge continuity. It generates multiple station resistance status values ​​(including cutting resistance status value, kneading resistance status value, and estimated fiber unwinding resistance status value), material load labels, kneading program segments, spray humidification program, and comprehensive load index.

[0027] The access control module is used to calculate the remaining consumption window based on the multiple physical margins of the core load station (including motor load, cavity material level, discharge capacity, and allowable dwell time) and window occupancy records, according to the remaining window formula, and to generate an access judgment value based on the access judgment formula, so as to issue or reject the occupancy token.

[0028] The process execution module is used to perform program consistency verification before material is handed over across workstations. After the consistency verification value equals logical true, the target program segment is locked. The module also calculates the drying and disposal window based on the measured fiber debonding resistance value and moisture content deviation value, and adjusts the hot air volume and temperature. It is also used to generate return material association tags and update the load value when screening return material is generated.

[0029] The abnormal recovery module is used to generate freeze information when it receives communication interruption signal, sensor abnormality signal, manual intervention signal or emergency shutdown signal, and calculate the recovery judgment value according to the recovery judgment formula when the unit is restarted, and allocate the stationed material segment to the isolation processing queue, return processing queue, first discharge queue or continue processing queue.

[0030] See appendix Figure 2 This invention also provides a distributed program control method for a straw fiber production unit, comprising the following steps: S1, the material filing module establishes material segments according to the preset filing benchmark boundary, generates material segment numbers and initial datasets, normalizes the original collected quantities in the initial datasets, generates standardized status values, and calculates the estimated arrival time based on the arrival time formula.

[0031] S2, the load assessment module collects the cutting motor current, cutting speed, kneading motor load, kneading chamber material level, and discharge continuity, generating cutting resistance status values, kneading resistance status values, and estimated fiber unwinding resistance status values, and writes the cutting resistance status values ​​into the material load label. Based on the standardized status values ​​and material load labels, the load assessment module generates kneading program segments and spray humidification programs, and calculates the comprehensive load index according to the load aggregation formula.

[0032] S3, the access control module calculates the remaining consumption window based on multiple physical margins of the core load station (including motor load, cavity material level, discharge capacity, and allowable dwell time) and window occupancy records, according to the remaining window formula, and calculates the access judgment value according to the access judgment formula. The access control module issues or rejects occupancy tokens based on the access judgment value and monitors the status of the occupancy tokens.

[0033] S4, the process execution module performs a program consistency check before cross-station handover in the material section, generates a consistency check value, and locks the target program segment after the consistency check value equals logical true. The process execution module calculates the drying and disposal window based on the measured fiber debonding resistance state value and moisture content deviation value, adjusts the hot air volume and hot air temperature, and generates a return material association tag and updates the load value when screening return material is generated.

[0034] S5, the anomaly recovery module generates freeze information upon receiving a communication interruption signal, sensor anomaly signal, manual intervention signal, or emergency shutdown signal, and calculates the recovery judgment value according to the recovery judgment formula when the unit resumes restart. Based on the recovery judgment value, short-term freeze state flag, token valid status value, consistency verification value, sensor valid status value, and return material associated status value, the anomaly recovery module allocates the resident material segment to the isolation processing queue, return material processing queue, first discharge queue, or continue processing queue.

[0035] To make the technical solutions in the embodiments of the present invention clearer and more complete, the technical solutions are further explained below in conjunction with each specific processing flow.

[0036] See appendix Figure 3 In this embodiment, step S1 is performed by the material filing module, which includes an initial filing unit, a status calibration unit, and a dynamic tracking unit. The material filing module forms material segment records based on the filing benchmark boundary, converts the inlet collected quantities into standardized status values, and calculates the estimated arrival time, providing the same data basis for the load assessment module and the access control module for the same material segment.

[0037] S11, the material filing module establishes material segments according to the preset filing benchmark boundaries through the initial filing unit.

[0038] The initial filing unit reads the preset filing benchmark boundary, which can be a time window, a conveying distance window, or an inlet metering window. When using a time window, the initial filing unit uses the system clock of the fieldbus control system as the trigger and establishes a material segment at the end of a time window. When using a conveying distance window, the initial filing unit obtains the cumulative conveying distance based on the conveyor belt speed and conveyor running time, and establishes a material segment when the cumulative conveying distance reaches a preset distance. When using an inlet metering window, the initial filing unit calculates the inlet metering result based on the inlet weighing signal, inlet flow signal, or feed motor load, and establishes a material segment when the inlet metering result reaches a preset metering value.

[0039] The baseline boundary for data establishment is set based on the stability of the feed at the unit inlet, the length of the conveying section, the sampling cycle of the fieldbus control system, and the control response cycle of the subsequent workstations. For example, the time window is 5s to 60s, the conveying distance window is 0.5m to 10m, and the inlet metering window is 2kg to 50kg. The specific values ​​are determined based on the conveying capacity, workstation spacing, and control cycle of the straw fiber preparation unit.

[0040] When creating a material segment, the initial filing unit creates an empty window occupancy record. The empty window occupancy record includes the material segment number field, the target workstation field, the committed occupancy quantity field, the occupancy token status field, and the release status field. When the material segment has not yet applied to enter the core load workstation, the committed occupancy quantity field is set to zero, the occupancy token status field is set to unissued, and the release status field is set to unoccupied.

[0041] The initial filing unit assigns a material segment number to each material segment and outputs this number to the fieldbus control system. The material segment number is used to transmit the status of the same material segment among the material filing module, load assessment module, access control module, process execution module, and anomaly recovery module. The material segment number includes a date code, shift code, entry sequence number, and incrementing sequence number. For the specific encoding format of the material segment number, those skilled in the art can use PLC register numbers, host computer database serial numbers, or fieldbus frame identifiers; the numbering method is well-known in the field and will not be elaborated further here.

[0042] When a material section is established, the initial data collection unit collects raw data including feeding speed, feeding motor current, initial moisture content, initial data collection time, and current station number through the fieldbus control system, and integrates these data to generate an initial dataset. The feeding speed comes from the speed feedback of the frequency converter, the speed feedback of the conveyor belt encoder, or the speed feedback of the inlet feeding mechanism; the feeding motor current comes from the current feedback of the frequency converter or the current acquisition module; the initial moisture content comes from the inlet moisture content detection device; the initial data collection time comes from the system clock of the fieldbus control system; and the current station number is the station number within the control system at the time the material section is established.

[0043] S12, the material filing module normalizes the original collected quantities in the initial dataset through the status calibration unit to generate standardized status values.

[0044] The state calibration unit acquires each raw data acquisition quantity from the initial dataset and calls the preset state calibration rules. The state calibration rules include the preset physical lower limit value, the preset physical upper limit value, the state value field, and the out-of-bounds status flag field for each raw data acquisition quantity. The state calibration rules are numerical mapping rules stored in the process parameter table.

[0045] The status calibration unit subtracts the corresponding physical lower limit from the current value of the original acquired quantity, and then divides it by the difference between the corresponding physical upper limit and physical lower limit to obtain a standardized status value within the closed interval of 0 to 1. When the physical upper limit equals the physical lower limit, the status calibration unit does not perform the division calculation, marks the corresponding acquired quantity as having an abnormal parameter configuration, and generates an out-of-bounds status flag; the out-of-bounds status flag is written to the record field corresponding to the material segment for use by the anomaly recovery module.

[0046] The standardized state values ​​include the dry basis feed rate state value, moisture content deviation value, and continuity state value. The dry basis feed rate state value is obtained from the feeding rate, the feeding motor current, and the initial moisture content. The feeding rate characterizes the feeding state per unit time at the inlet, the feeding motor current corrects the inlet load state, and the initial moisture content is used to convert the inlet material quantity into a dry basis state. The converted dry basis feed rate is then normalized.

[0047] The moisture content deviation is obtained from the difference between the initial moisture content and the preset target moisture content. The state calibration unit calculates the degree of deviation of the initial moisture content from the target moisture content, and then normalizes it according to the corresponding physical lower limit and physical upper limit values. The target moisture content is stored in the process parameter table and is set according to the processing requirements of the straw type, the rubbing station, and the defiberizing station. For example, the target moisture content is 10% to 35%.

[0048] The continuous state value is generated by the feeding speed fluctuation, the feeding motor current fluctuation, and the inlet conveying interruption state. The feeding speed fluctuation is determined according to the speed change amplitude within the current sampling period, the feeding motor current fluctuation is determined according to the current change amplitude within the current sampling period, and the inlet conveying interruption state is determined according to the duration of the feeding speed being zero or the inlet material flow detection signal being interrupted. The state calibration unit converts the above information into the original state quantity corresponding to the inlet conveying continuity, and then performs normalization processing.

[0049] The physical lower limit and physical upper limit are set according to the corresponding sensor range, the allowable operating range of the straw fiber preparation unit, and the process parameter table. For example, the physical lower limit for feeding speed is 0 m / s, and the physical upper limit is 0.1 m / s to 2.0 m / s; the physical lower limit for initial moisture content is 5%, and the physical upper limit is 45%; the physical lower limit for feeding motor current is the motor no-load current, and the physical upper limit is the motor rated current. The specific parameters are determined based on the equipment nameplate, sensor range, and process debugging results.

[0050] If the original acquired quantity does not belong to the closed interval formed by the physical lower limit and the physical upper limit, the state calibration unit will clamp the standardized state value at the boundary value of 0 or 1 and generate an out-of-bounds state flag. When the original acquired quantity is less than the physical lower limit, the standardized state value is clamped to 0; when the original acquired quantity is greater than the physical upper limit, the standardized state value is clamped to 1; when the original acquired quantity is invalid, the state calibration unit retains the invalid acquisition record and calls the redundant variable data of the same acquisition loop to generate a substitute state value; when there is no valid redundant variable data, an out-of-bounds state flag is generated, and the original acquired quantity is no longer used for this standardized state value update.

[0051] For sensor sampling, filtering, and signal de-jittering, those skilled in the art can use moving average filtering, median filtering, or PLC input filtering. The sampling processing is a well-known technique in the field and will not be elaborated upon here. The state calibration unit performs normalization processing after sampling to ensure that different physical quantities are within the same state value range before subsequent calculations.

[0052] S13, the material filing module calculates the estimated arrival time of the material segment through the dynamic tracking unit.

[0053] The dynamic tracking unit collects conveying parameters (including real-time conveyor belt speed and conveyor distance) through on-site sensors, and extracts the initial filing time and current workstation number from the initial dataset. The dynamic tracking unit also reads the preset estimated dwell time and the dynamic correction time accumulated due to anomalies, substitutes the above parameters into the arrival time formula, and calculates the estimated arrival time of the generated material segment.

[0054] The estimated dwell time is set based on the process dwell requirements of the corresponding workstation, equipment operating cycle time, and material throughput time. For example, the estimated dwell time for the cutting station is 1 to 20 seconds, for the kneading station it is 3 to 60 seconds, and for the humidification station it is 5 to 120 seconds. The dynamic correction time is used to record the accumulated time caused by machine downtime, limited material discharge, short-term frozen state marking, abnormal rollback procedures, or material return waiting. The initial value of the dynamic correction time is 0, and it is accumulated by the dynamic tracking unit according to the duration recorded by the internal timer after the above states occur. The arrival time formula is as follows: ; In the formula: For the first The estimated arrival time of each material segment; This refers to the initial file creation time; The summation symbol indicates the summation from the current workstation number. To the target workstation number The parameters of each internal interval are accumulated and calculated; The loop variable for this summation refers to the workstation or conveyor section number in the current accumulation process; For the conveying section distance; For real-time conveyor belt speed; For the estimated length of stay; The time is dynamically adjusted.

[0055] When the real-time conveyor belt speed is zero, the dynamic tracking unit pauses the division calculation between the conveyor section distance and the real-time conveyor belt speed in the arrival time formula, and extracts the downtime through an internal timer, adding the downtime to the dynamic correction time. After the conveyor belt speed recovers to a value greater than zero, the dynamic tracking unit recalculates the estimated arrival time using the arrival time formula. If the conveyor belt speed signal is invalid, the dynamic tracking unit uses a redundant speed signal from the same conveyor section. If no valid redundant speed signal exists, the estimated arrival time is stopped from being updated, and an out-of-bounds status flag is generated.

[0056] The dynamic tracking unit writes the estimated arrival time into the corresponding record field of the material segment and sends it to the load assessment module and access control module via the fieldbus control system. The estimated arrival time is used by the target controller to plan the remaining consumption window in advance, and also by the occupancy record unit to determine whether the conveying time of the material segment exceeds the preset timeout threshold. The timeout threshold is set based on the conveying distance between adjacent workstations, the minimum allowable conveying speed, the estimated dwell time, and the fieldbus communication cycle. For example, the timeout threshold is 1.2 to 3 times the estimated conveying time, or 30 to 300 seconds. The actual value is determined based on the unit's conveying path length and process cycle time.

[0057] See appendix Figure 4 In this embodiment, step S2 is performed by the load assessment module, which includes a resistance acquisition unit, a workstation status unit, and a load aggregation unit. The load assessment module writes the material status at the cutting station, the kneading station, and before fiber unwinding into the material load label, and calculates the comprehensive load index according to the load aggregation formula.

[0058] The processing principle of the load assessment module is as follows: using the material segment number as an index, the cutting resistance status value, rubbing resistance status value, estimated fiber unwinding resistance status value and the standardized status value generated by the material filing module are associated with the same material load label, so that the access control module can perform access judgment based on the comprehensive load index of the same material segment.

[0059] S21, the load assessment module generates cut-off resistance status value, material load label, local limit signal and material registration record through the resistance acquisition unit.

[0060] After the material enters the cutting station, the resistance acquisition unit collects the cutting motor current and cutting speed through field sensors. The cutting motor current comes from the corresponding inverter feedback, current transformer, or PLC analog signal acquisition module; the cutting speed comes from inverter speed feedback, encoder, or speed sensor. For the acquisition of current and speed signals, those skilled in the art can use inverter communication reading, analog signal acquisition, or pulse counting methods. These acquisition methods are well-known in the field and will not be described in detail here.

[0061] The resistance acquisition unit uses the no-load or light-load current of the cutting motor as the current reference to calculate the increase in the current of the cutting motor relative to the current reference; it uses the target speed of the cutting station as the speed reference to calculate the decrease in the current cutting speed relative to the target speed; then, according to the proportional relationship in the process parameter table, it combines the increase in current and the decrease in speed to form the original value of the cutting resistance. When the cutting motor current increases and the cutting speed decreases, the original value of the cutting resistance increases according to the proportional relationship in the process parameter table.

[0062] The current reference, target speed, and their proportional relationship are set based on the parameters on the cutting motor nameplate, the type of cutting blade, the type of straw, and the equipment debugging records. For example, the current reference is the current value between the no-load current of the cutting motor and 30% of the rated current. The target speed is set based on the rated speed of the cutting station. The corresponding proportions of the current increase and the speed decrease are set based on the process debugging results. The sum of the two is 1, and the individual proportions can be between 0.2 and 0.8.

[0063] The resistance acquisition unit calls the preset state calibration rules to convert the original value of the cutting resistance into a cutting resistance state value. The physical lower limit value corresponding to the original value of the cutting resistance is set according to the load state of the cutting station during no-load or light-load operation, and the physical upper limit value is set according to the allowable load of the cutting station, the rated current of the cutting motor, and the allowable deviation of the cutting speed. For example, the physical upper limit value is a combination of 80% to 100% of the rated current of the cutting motor and the upper limit of the target speed allowable deviation.

[0064] The resistance threshold is set based on the allowable load of the cutting station, the inlet feeding capacity, and the receiving capacity of the downstream kneading station. For example, the resistance threshold is 0.6 to 0.9. When the cutting resistance value exceeds the preset resistance threshold, the resistance acquisition unit generates a local limit signal and sends it to the external actuator. The external actuator controls the inlet feeding mechanism to reduce the feeding speed, shorten the duration of a single discharge, or extend the interval between adjacent discharges. The external actuator includes a frequency converter, a feeding motor, a conveying motor, or a discharge valve. Its execution method is well-known in the art and will not be described in detail here.

[0065] The resistance acquisition unit writes the cutting resistance status value into the material load tag. The material load tag includes the material segment number, estimated arrival time, dry basis feed rate status value, moisture content deviation value, continuity status value, and cutting resistance status value. The material segment number serves as an index field, and the cutting resistance status value serves as the load status field formed by the material segment at the cutting station; when a local limit signal is generated, the material load tag synchronously records the limit trigger status.

[0066] When the cutting resistance value exceeds the resistance threshold, the resistance acquisition unit generates a material registration record in the window occupancy record. The material registration record includes the material segment number, cutting station identifier, cutting resistance value, registration time, and release status. It is used by the window calculation unit to identify material segments that are not released and to provide a record basis for calculating the committed occupancy.

[0067] When cutting off the motor current or cutting off the speed is ineffective, the resistance acquisition unit calls the redundant variable data of the same acquisition circuit; when there is no valid redundant variable data, the resistance acquisition unit retains the previous valid cut-off resistance state value and generates an out-of-bounds state mark, the material load tag records the out-of-bounds state mark, so that the load aggregation unit continues to execute the load aggregation formula and the anomaly recovery module identifies the corresponding state anomaly.

[0068] S22, the load assessment module generates the estimated fiber unwinding resistance status value, rubbing resistance status value, rubbing program segment and spray humidification program through the workstation status unit.

[0069] The workstation status unit extracts the estimated defibering resistance status value from preset historical formula data. Historical formula data is stored in a process parameter table or a host computer formula database, including straw type, cutting length, initial moisture content range, target status of the kneading station, corresponding status of historical defibering motor operating parameters, and the estimated defibering resistance status value. The estimated defibering resistance status value is given by a calibration table, segmented intervals, or lookup table rules; it is not part of the neural network model and does not involve training samples, loss functions, or model iteration processes.

[0070] Historical formula data is set based on the commissioning records, process formulas, and operation records of similar straw fiber preparation units. For example, historical formula data establishes formula items according to rice straw, wheat straw, and corn straw. Under the same straw type, the estimated fiber unwinding resistance state value is divided according to the initial moisture content of 5% to 45%, the cutting length of 10mm to 80mm, and the load level of the kneading motor. When the historical formula data does not match the current material segment status, the workstation status unit adopts the estimated fiber unwinding resistance state value corresponding to the adjacent interval, or adopts the default estimated fiber unwinding resistance state value of the corresponding straw type in the process parameter table, and records the formula mismatch status in the material load label.

[0071] The workstation status unit collects the kneading motor load and the material level in the kneading chamber through field sensors and converts them into kneading resistance status values. The workstation status unit calculates the proportion of the kneading motor load relative to the rated load and the proportion of the material level in the kneading chamber relative to the allowable material level, and then synthesizes them into the original value of kneading resistance according to the proportional relationship in the process parameter table, and calls the status calibration rules to generate the kneading resistance status value.

[0072] The lower physical limit of the kneading motor load is set based on the no-load load of the kneading motor, and the upper physical limit is set based on the rated load of the kneading motor. The lower physical limit of the material level in the kneading chamber is set based on the cavity state, and the upper physical limit is set based on the allowable material level. For example, the upper physical limit of the material level in the kneading chamber is 70% to 95% of the effective cavity height. The ratio corresponding to the kneading motor load and the ratio corresponding to the material level in the kneading chamber are determined based on the process debugging results, and the sum of the two is 1. The ratio corresponding to the kneading motor load can be 0.4 to 0.8, and the ratio corresponding to the material level in the kneading chamber can be 0.2 to 0.6.

[0073] The workstation status unit acquires the material load label, discharge continuity, and continuity status value, and generates a kneading program segment by calling preset closed-loop control rules. Discharge continuity is determined by the material flow detection signal at the discharge port of the kneading workstation, the operating status of the discharge motor, or the load change of the discharge conveyor belt; the continuity status value comes from the material filing module. The closed-loop control rules determine the kneading speed, discharge cycle time, allowable dwell time, and abnormal retraction conditions based on the kneading resistance status value, cutting resistance status value, and continuity status value.

[0074] The closed-loop control rule employs PLC condition judgment, proportional-integral-derivative control, or segmented lookup table control. These basic control methods are well-known technologies in the field and will not be elaborated upon here. In the load assessment module, the closed-loop control rule reads the material load label and remaining consumption window, and generates a kneading program segment according to the material segment number, ensuring that the control parameters of the kneading station correspond to the load status of the material segment.

[0075] The kneading program segment includes the material segment number, kneading speed setting, discharge cycle time setting, allowable dwell time, estimated arrival time reference field, and abnormal rollback conditions. The estimated arrival time reference field records or references the estimated arrival time generated by the dynamic tracking unit. The workstation status unit extracts the estimated arrival time from the kneading program segment and sends it to the target controller, which is used by the target controller to plan the remaining consumption window in advance. The target controller is the controller corresponding to the subsequent core load workstations, including the fiber unwinding workstation controller or the drying workstation controller.

[0076] The workstation status unit obtains the remaining absorption window generated by the access control module via the internal bus and calls the closed-loop regulation rules to generate the spray humidification program. The spray humidification program includes the spray start / stop status, spray duration, spray valve opening, humidification mixing time, and discharge allowable conditions. The spray humidification program is generated based on the moisture content deviation value, the kneading resistance status value, and the remaining absorption window; when the moisture content deviation value increases, the spray humidification program increases the spray duration or the spray valve opening; when the remaining absorption window is insufficient, the spray humidification program extends the humidification mixing time or restricts the discharge to subsequent workstations.

[0077] The spray valve opening and spray duration are determined based on the spray system's calibrated flow rate, the deviation between the target moisture content and the initial moisture content, and the inlet material quantity. For spray valve opening control, those skilled in the art can use solenoid valve on / off control, proportional valve control, or variable frequency pump control; these execution methods are well-known in the field and will not be elaborated upon here. The conditioning and mixing time in the spray conditioning process is set based on the material moisture content, the material level in the kneading chamber, and the remaining disposal window. For example, the conditioning and mixing time is 5s to 120s, and the spray valve opening is 10% to 100%, with specific values ​​determined based on the spray system's calibrated flow rate and the process target moisture content.

[0078] S23, the load assessment module calculates the comprehensive load index through the load aggregation unit.

[0079] The load aggregation unit extracts the dry-basis feed rate status value, moisture content deviation value, and continuity status value from the standardized status values, and receives the cutting resistance status value, kneading resistance status value, and estimated defibering resistance status value. All of these status values ​​are within a closed interval of 0 to 1. If any status value has an out-of-bounds status marker, the load aggregation unit retains the boundary value of that status value and writes the out-of-bounds status marker along with the comprehensive load index into the material load label.

[0080] The load polymerization unit substitutes the dry-basis feed rate, moisture content deviation, cutting resistance, kneading resistance, estimated defiberization resistance, and continuity into the load polymerization formula to generate a comprehensive load index. The load polymerization formula is as follows: ; In the formula: This is a comprehensive load indicator; This is the feed rate state value for dry basis; This represents the moisture content deviation value. This is the cutoff resistance state value; This represents the kneading resistance value. To estimate the state value of fiber unwinding resistance; These are continuous state values; , , , , , All of these are preset process weighting coefficients.

[0081] The preset process weighting coefficients are set based on straw type, unit station configuration, and process debugging results, and stored in the process parameter table. Each process weighting coefficient ranges from 0 to 1; to maintain the magnitude of the comprehensive load index, to The total value is set to 1. This setting is used to unify status values ​​from different sources into a comprehensive load index, without limiting the unique impact of each status value on equipment operation.

[0082] When a certain state value is invalid and no redundant variable data is available, the load aggregation unit uses the most recent valid value of that state value or the default state value from the process parameter table for calculation, and writes an out-of-bounds status mark in the material load label. The default state value is set according to the intermediate level of the corresponding state item, for example, it can be set to 0.5, to avoid the load aggregation formula stopping execution due to the absence of a single state value.

[0083] The load aggregation unit writes the comprehensive load index into the material load tag and sends the material load tag to the access control module. The material load tag includes the material segment number, estimated arrival time, dry basis feed rate status value, moisture content deviation value, cutting resistance status value, kneading resistance status value, estimated fiber unwinding resistance status value, continuity status value, comprehensive load index, boundary crossing status flag, and limit trigger status. The access control module calculates the access judgment value based on this, and the process execution module performs program consistency verification and execution control based on this.

[0084] See appendix Figure 5 In this embodiment, step S3 is executed by the admission control module, which includes a window calculation unit, a token decision unit, and an occupancy record unit. The admission control module calculates the remaining absorption window based on the current reserve of the core load station and the window occupancy record, and controls the issuance, rejection, and status update of occupancy tokens according to the admission judgment value.

[0085] The access control module uses the unused processing capacity of the target workstation as the basis for access. The window calculation unit calculates the current reserve and deducts the committed occupancy amount that has been granted an occupancy token but has not yet been released; the token decision unit determines whether to allow the material section to enter the target workstation based on the remaining consumption window, comprehensive load index, and safe occupancy reserve; the occupancy record unit maintains the consistency between the occupancy token and the window occupancy record.

[0086] S31, the admission control module calculates the remaining absorption window through the window calculation unit.

[0087] The window calculation unit extracts the motor load, cavity material level, discharge capacity, and allowable residence time of the core load stations via the fieldbus interface. The core load stations include the fiber unwinding station, drying station, and screening station; when the unit configuration requires it, it also includes the cutting station and the kneading station. The fieldbus interface reads corresponding data from the frequency converter, material level detection device, discharge mechanism feedback signals, and station timing records, and maps it to standard calculation margins (standard calculation margins include motor load margin, cavity material level margin, discharge capacity margin, and residence time margin).

[0088] The motor load margin is obtained by normalizing the allowable motor load minus the current motor load; the cavity material level margin is obtained by normalizing the allowable material level minus the current cavity material level; the discharge capacity margin is obtained by normalizing the allowable discharge capacity minus the current discharge occupancy status; and the residence time margin is obtained by normalizing the allowable residence time minus the current material residence time. All of the above margins are state values ​​within a closed interval of 0 to 1. When the difference is less than 0, the corresponding margin is set to 0.

[0089] The permissible motor load is set based on the motor's rated current, inverter protection parameters, and process operating limits, for example, 70% to 95% of the rated current. The permissible material level is set based on the effective volume of the equipment, the discharge port height, and the blockage protection position, for example, 60% to 90% of the effective cavity height. The discharge capacity margin is set based on the discharge motor speed, discharge port opening, and downstream receiving status; the permissible residence time is set based on the material moisture content, station processing requirements, and equipment operating cycle time, for example, 10s to 300s.

[0090] The window calculation unit extracts material segment records in an unreleased state from the window occupancy record and identifies the corresponding number of unreleased materials. For each unreleased material segment, the window calculation unit reads the corresponding committed occupancy amount. The committed occupancy amount is the sum of the comprehensive load index and the safe occupancy margin written by the token decision unit when issuing the occupancy token. Unreleased states include occupancy tokens marked as valid, short-term frozen, and those being processed at the target workstation but not yet released.

[0091] The window calculation unit substitutes the motor load margin, cavity material level margin, discharge capacity margin, residence time margin, and the committed occupancy amount corresponding to the unreleased material section into the remaining window formula to calculate and generate the remaining disposal window. The remaining window formula is as follows: ; In the formula: For the remaining absorption window; This is a minimum value function, which means extracting the smallest value from multiple physical margin parameters within the parentheses; This is the motor load margin; This is the material level allowance in the cavity; This is the allowance for material discharge capacity; Allowance for remaining time; The loop variable for this summation refers to the local sequence number of the material segment that is not yet released; This represents the number of unreleased materials that are in an unreleased state. The first in the window occupancy record The committed occupancy amount corresponding to each unreleased material segment.

[0092] The remaining window formula uses the minimum value among multiple margin parameters as the base window to characterize the receiving capacity of the core load station limited by the minimum margin; it then deducts the committed occupancy from the window occupancy record, allowing material segments that have acquired occupancy tokens but have not yet been released to continue occupying the target station's processing capacity. If there are no unreleased material segments in the window occupancy record... If the value is 0, the cumulative commitment amount is treated as 0.

[0093] When the calculated remaining absorption window is less than 0, the window calculation unit clamps the remaining absorption window to 0 and generates a window insufficiency state. When the fieldbus interface cannot obtain a certain margin parameter, the window calculation unit calls the redundant variable data of the same station; when the redundant variable data is invalid, the most recent valid value of the margin parameter is used within a sampling period. If consecutive invalid values ​​exceed the timeout threshold, the margin parameter is set to 0 and a window insufficiency state is generated.

[0094] S32, the access control module calculates the access judgment value through the token decision unit and issues or rejects the use token.

[0095] When an upstream workstation submits an access application, the token decision unit obtains the remaining consumption window corresponding to the target workstation, the comprehensive load index corresponding to the material segment, and the safety margin. The access application includes the material segment number, the target workstation number, the comprehensive load index, the estimated arrival time, and the identifier of the program segment to be entered. The comprehensive load index comes from the load assessment module, the remaining consumption window comes from the window calculation unit, and the safety margin is extracted from the process parameter table.

[0096] The safety margin is set based on the target station, the program segment to be entered, the load level of the material section, and the equipment protection status. For the fiber debonding station, the safety margin is set based on the estimated fiber debonding resistance value, the allowable load of the fiber debonding motor, and the material level protection requirements of the cavity; for the drying station, the safety margin is set based on the moisture content deviation value, the maximum drying capacity, and the dehumidification status; for the screening station, the safety margin is set based on the screening load, the occupancy status of the return channel, and the oversize processing capacity. For example, the safety margin is 0.05 to 0.30, and the specific value is stored in the process parameter table and is called according to the target station and the program segment to be entered.

[0097] The token decision unit substitutes the remaining absorption window, comprehensive load index, and safe occupancy margin into the admission judgment formula to generate the admission judgment value. The admission judgment formula is as follows: ; In the formula: This is the admission criteria value; For the remaining absorption window; This is a comprehensive load indicator; To ensure safety, reserve space is used.

[0098] When the access threshold is not less than 0, the token decision unit issues an occupancy token. The occupancy token includes the material segment number, target workstation number, access threshold, allowed entry time, identifier of the program segment to be entered, occupancy token status, and release conditions. The token decision unit also writes the sum of the comprehensive load index and the safe occupancy margin as the new committed occupancy amount into the window occupancy record and marks the material segment as not released.

[0099] When the access threshold is less than 0, the token decision unit rejects the issuance of a occupancy token and generates a speed reduction limit command, which is sent to the external actuator. The speed reduction limit command is used to control the upstream station to decelerate or restrict material discharge, waiting for the target station to release the remaining processing capacity corresponding to the consumption window. The external actuator adjusts the frequency of the upstream feed motor, conveyor motor, discharge valve, or frequency converter according to the speed reduction limit command. For frequency converter speed regulation and valve opening control, those skilled in the art can use conventional analog output, fieldbus input, or digital control; the execution methods are well-known technologies in the field and will not be elaborated further here.

[0100] After rejecting an access token, the token decision unit retains an access application record. This record includes the material segment number, target workstation number, rejection time, comprehensive load index, remaining consumption window, and reason for rejection. After the window calculation unit updates the remaining consumption window, the token decision unit recalculates the access judgment value based on the new window. If the material segment generates new cutting resistance status values, kneading resistance status values, or updated load values ​​during the waiting period, the token decision unit re-executes the access judgment using the updated comprehensive load index.

[0101] S33, the access control module monitors the occupancy token through the occupancy record unit and updates the window occupancy record.

[0102] After issuing the occupancy token, the occupancy recording unit generates a valid status flag and assigns the valid status flag to the occupancy token. The valid status flag indicates that the target workstation has reserved a committed occupancy amount for this material segment, but the material segment has not yet been processed by the target workstation. The occupancy recording unit writes the valid status flag to the window occupancy record and sends the occupancy token to the target controller and the upstream workstation controller.

[0103] After the material segment arrives at the target station, the target controller verifies the material segment number, target station sequence number, and occupancy token status. If the verification matches, the occupancy record unit maintains the valid state of the occupancy token and allows the process execution module to continue executing program consistency checks. If the verification does not match, the occupancy record unit generates an exception rollback program and causes the external actuator to perform speed-limited discharge, temporary storage, or stop feeding. Speed-limited discharge, temporary storage, and stop feeding can be achieved by the inverter frequency, the discharge valve opening, or the start / stop of the conveyor motor. The execution method is well-known in the field and will not be described in detail here.

[0104] After a material segment completes processing at the target station, the occupancy record unit releases the occupancy token and simultaneously cancels the committed occupancy amount in the window occupancy record. The criteria for determining completion include the target station's outlet material flow signal, the target station's processing completion marker, the discharge motor's operating status, and the corresponding material segment's estimated arrival time. After the target controller generates the processing completion marker, the occupancy record unit sets the release status field to the released state and removes that material segment from the accumulation of committed occupancy amounts in the remaining window formula.

[0105] When the occupancy recording unit detects a communication disconnection with the target controller, it extracts the duration of the communication interruption. If the interruption duration is not greater than the timeout threshold, the occupancy recording unit generates a short-term frozen state flag and assigns an occupancy token. The short-term frozen state flag indicates that the window occupancy record will not be released temporarily, and the reserved occupancy amount at the target workstation will continue to be retained. After communication is restored, the occupancy recording unit rechecks the material section number, occupancy token status, and target workstation processing status before deciding whether to maintain the valid state flag or release the occupancy token.

[0106] The timeout threshold is set based on the communication cycle of the target workstation, the transport time of adjacent workstations, the allowable dwell time of the target workstation, and the fault response time of the fieldbus control system. For example, the timeout threshold ranges from 1 second to 60 seconds; for workstations with longer transport distances, the timeout threshold is 1.2 to 3 times the expected transport time. The specific value is determined based on the communication cycle of the fieldbus control system and the distance between the workstations.

[0107] When the material conveying time exceeds the timeout threshold, or the communication interruption duration exceeds the timeout threshold, the occupancy record unit generates a failure state flag and assigns an occupancy token. Subsequently, it generates an exception rollback procedure and sends it to the external actuator. The failure state flag is written to the window occupancy record for the exception recovery module to call when generating the recovery queue. The exception rollback procedure includes stopping the issuance of new occupancy tokens, restricting upstream material discharge, retaining the current window occupancy record, and requesting the target controller to return the workstation status. If the target controller cannot return the status, the exception recovery module performs subsequent recovery processing based on the freeze information.

[0108] The occupancy record unit performs periodic checks on the window occupancy records. These periodic checks include verifying whether the committed occupancy quantity corresponds to the occupancy token, whether the release status matches the target workstation's completion marker, and whether the number of unreleased materials matches the number of valid and short-term frozen markers. If any inconsistency is found, the occupancy record unit stops releasing the corresponding committed occupancy quantity and generates an exception rollback procedure to prevent premature or duplicate release of the window occupancy record.

[0109] See appendix Figure 6 In this embodiment, step S4 is executed by the process execution module, which includes a consistency verification unit, an execution control unit, and a return material update unit. The process execution module generates a consistency verification value when materials are transferred across workstations, generates a drying and disposal window during the processing at the target workstation, and generates an update load value when screening return material is generated.

[0110] The process execution module uses material load tags, occupancy tokens, and the program status of the target workstation as the basis for handover. Before the material segment enters the target workstation, a program consistency check is performed; if the consistency check value equals logical true, the target program segment is locked; if the consistency check value equals logical false, the transition program segment is entered. After the material segment undergoes defibering and screening, the process execution module feeds back the measured defibering resistance status value, drying and disposal window, and updated load value to the access control module for subsequent occupancy token application.

[0111] S41, the process execution module generates a consistency check value through the consistency check unit.

[0112] Before cross-workstation handover in the material segment, the consistency verification unit extracts multiple program matching values. These values ​​include executed matching values ​​extracted from the material load label, pending matching values ​​extracted from the occupancy token, and prohibited switching matching values ​​extracted from the target workstation. Executed matching values ​​indicate whether the completed program segments in the material segment meet the prerequisites for entering the target workstation; pending matching values ​​indicate whether the program segment identifier in the occupancy token matches the program segment to be executed by the target workstation; and prohibited switching matching values ​​indicate whether the target workstation is currently in the state corresponding to the prohibited switching parameters.

[0113] The executed matching value is generated by the program record in the material load label. The material load label records the completion status of the cutting station, kneading station, and spray humidification program; when a completion mark is generated for the corresponding station and no abnormal rollback program is written, the executed matching value is logically true; otherwise, it is logically false. The completion mark comes from the station outlet material flow signal, the discharge motor running status, the station processing completion mark, or the program status bit of the fieldbus control system. For the acquisition of the station completion mark, those skilled in the art can use PLC status bits, digital inputs, or fieldbus status words. The acquisition methods are well-known technologies in the field and will not be described in detail here.

[0114] The pending matching value is obtained by comparing the program segment identifier to be entered in the occupancy token with the program segment identifier currently ready to be executed at the target workstation. If they match, the pending matching value is logically true; if they do not match, the pending matching value is logically false. The program segment identifier to be entered includes the target workstation sequence number, program segment number, and allowed entry time. The program segment identifier currently ready to be executed at the target workstation is output by the target controller.

[0115] The no-switching matching value is generated by the no-switching parameters of the target workstation. The no-switching parameters include the locking status of the target program segment, the motor running status of the target workstation, the material discharge status, and the occupancy token status. When the target program segment is not locked or the locked object is consistent with the material segment number, the no-switching matching value is logically true; when the target program segment is locked to another material segment, or when the target workstation is in an invalid state, a short-term frozen state, or an abnormal rollback program execution state, the no-switching matching value is logically false.

[0116] The consistency verification unit invokes preset consistency judgment rules, simultaneously checking the executed matching value, the pending matching value, and the prohibited switching matching value. When all three values ​​are logically true, the consistency verification value is also logically true, and the process execution module allows the material segment to enter the normal program segment. When any matching value is logically false, the consistency verification value is also logically false, and the process execution module downgrades the material segment to a transitional program segment. The transitional program segment includes low-speed material discharge, limited material feeding, temporary storage and waiting, or stopping upstream material discharge; the specific execution method is completed by an external execution mechanism.

[0117] When an executed matching value, a pending matching value, or a disabled switching matching value is missing, the consistency verification unit treats the missing item as logically false and generates a record with a consistency verification value of logically false. This record is written to the corresponding fields of the material load tag and the occupancy token, for the exception recovery module to call when generating the recovery queue. The consistency judgment rule is based on the program fragment configuration of the target workstation, the occupancy token field, and the workstation protection status setting, and is stored in the process parameter table; this rule only uses logically true and logically false for judgment, does not belong to the neural network model, and does not involve training samples, loss functions, or model iteration processes.

[0118] S42, the process execution module locks the target program segment by executing the control unit and generates the measured defiber resistance state value, heat load demand and drying consumption window.

[0119] After the consistency check value equals logical true, the control unit locks the target program segment corresponding to the current workstation. The target program segment includes the material segment number, target workstation number, allowed speed range, allowed discharge status, hot air volume control range, hot air temperature control range, and release conditions. After the target program segment is locked, the target workstation processes the current material segment according to the program segment corresponding to the occupancy token; when it is necessary to adjust the speed, discharge status, hot air volume, or hot air temperature, it is executed within the allowed range of the target program segment.

[0120] The execution control unit collects the operating parameters of the debonding motor through field sensors and converts them into measured debonding resistance state values. The debonding motor operating parameters include the debonding motor current, debonding motor speed, debonding chamber material level, and debonding discharge status. The execution control unit calculates the proportion of the debonding motor current relative to the allowable current, the deviation of the debonding motor speed from the target speed, and the proportion of the debonding chamber material level relative to the allowable material level, and generates measured debonding resistance state values ​​according to the state calibration rules.

[0121] The allowable current corresponding to the operating parameters of the debonding motor is set based on the rated current of the debonding motor and the protection parameters of the frequency converter, for example, 70% to 95% of the rated current; the allowable material level in the debonding chamber is set based on the effective height of the debonding chamber and the blockage protection position, for example, 60% to 90% of the effective chamber height; the target speed is set based on the process formula of the debonding station. When the operating parameters of the debonding motor are invalid, the execution control unit calls redundant variable data from the same acquisition loop; when there is no valid redundant variable data, the previous valid measured debonding resistance state value is retained, and an out-of-bounds status flag is provided to the anomaly recovery module.

[0122] The execution control unit invokes a preset drying assessment algorithm, multiplying the measured defibering resistance value by the moisture content deviation value to obtain the heat load requirement. The measured defibering resistance value reflects the processing load of the material after defibering, while the moisture content deviation value reflects the degree of deviation of the material from the process target moisture content. Multiplying the two yields the drying requirement status of the current material section. The drying assessment algorithm is a product calculation and capacity deduction rule; it is not a neural network model and does not involve training samples, loss functions, or model iteration processes.

[0123] The control unit subtracts the heat load requirement from the preset maximum drying capacity to calculate the drying capacity absorption window. The maximum drying capacity is set based on the hot air system capacity, dehumidification capacity, allowable hot air temperature range, and allowable material residence time of the drying station. For example, the maximum drying capacity can be set according to the calibrated capacity value within the closed range of 0 to 1, or it can be given by the process parameter table according to the operating level of the drying station. The hot air temperature control range can be set from 60℃ to 160℃, and the allowable material residence time can be set from 10s to 300s. The specific values ​​are determined according to the type of straw and the configuration of the drying equipment.

[0124] When the drying and absorption window is less than zero, the control unit generates a window shortage command and sends it to the external actuator to reduce the upstream feed rate. When the drying and absorption window is not less than zero, the target program segment continues to execute according to the current hot air volume and hot air temperature control range. When the measured fiber debonding resistance state value or moisture content deviation value is invalid, the control unit calls the corresponding redundant variable data. When the redundant variable data is still invalid, the drying and absorption window is set to 0, and a window shortage command is generated.

[0125] The insufficient window instruction includes the target workstation number, material segment number, insufficient window status, and upstream limit requirement. Upon receiving the insufficient window instruction, the external actuator limits the upstream material discharge by reducing the feed motor frequency, reducing the conveyor motor frequency, shortening the discharge duration, or extending the discharge interval. For inverter frequency setting and motor start / stop control, those skilled in the art can use fieldbus setting, analog output, or digital output; the execution methods are well-known in the field and will not be elaborated further here.

[0126] The control unit uses closed-loop regulation rules to calculate and adjust the hot air volume and temperature based on the moisture content deviation. When the moisture content deviation increases, the closed-loop regulation rules increase the hot air volume or temperature within the allowable range of the target program segment; when the moisture content deviation decreases, the hot air volume or temperature decreases within the allowable range. The closed-loop regulation rules can employ proportional-integral-derivative control, segmented lookup table control, or threshold control. These basic control methods are well-known technologies in the field and will not be elaborated upon here.

[0127] S43, the process execution module generates return material association tags, return material correction items, and updated load values ​​through the return material update unit. When a material segment enters the screening station and generates screening return material, the return material update unit generates a return material association tag for the screening return material. Screening return material is determined by the oversize material flow signal at the screening station, the operating status of the return material conveyor motor, and changes in the material level or screening motor load in the return material channel. For oversize material detection and return material conveying detection, those skilled in the art can use level switches, weighing sensors, current detection, or conveyor motor status reading; these detection methods are well-known technologies in the field and will not be elaborated here.

[0128] The return material association tags include the material segment number, screening station identifier, return material cause status value, screening resistance status value, channel congestion status value, and return material generation time. The return material cause status value is determined by the proportion of oversize material, insufficient fiber debonding, moisture content deviation, or continuity of undersize discharge; the screening resistance status value is determined by the screening motor load, screen discharge status, and screening vibration status; the channel congestion status value is determined by the material level in the return material channel, the operating status of the return material conveyor motor, and the return material waiting time. These status values ​​can be converted into values ​​within a closed interval of 0 to 1 according to the status calibration rules.

[0129] The physical lower and upper limits corresponding to the return material cause status value, screening resistance status value, and channel congestion status value are set based on the equipment parameters of the screening station, the return material channel capacity, and the process debugging results. For example, the physical lower limit corresponding to the oversize ratio can be set to 0%, and the physical upper limit can be set to 20% to 60%; the physical upper limit corresponding to the material level in the return material channel can be set to 60% to 90% of the effective channel height; and the physical upper limit corresponding to the return material waiting time can be set to 10s to 180s.

[0130] The return material update unit multiplies the return material cause status value, screening resistance status value, and channel congestion status value by their respective preset correction weight coefficients to obtain three return material correction items. The correction weight coefficients are set based on the impact of the screened return material on subsequent fiber unwinding stations and the access control module, and are stored in the process parameter table. For example, the correction weight coefficients range from 0.05 to 0.40. Under the same process formula, the correction weight coefficients corresponding to each return material correction item are set separately according to the return material cause, screening load, and return material channel occupancy status.

[0131] The return material update unit adds the three return material correction items to the comprehensive load index to obtain the updated load value. The updated load value corresponds to the original material segment number or the return material association tag, indicating the load state used when the screened return material re-enters the access control module. When the updated load value exceeds the upper limit of the allowed state in the process parameter table, the return material update unit clamps the updated load value at the upper limit of the state and writes the out-of-bounds status mark to the return material association tag.

[0132] When the return material cause status value, screening resistance status value, or channel congestion status value is invalid, the return material update unit calls the corresponding redundant variable data. If no valid redundant variable data exists, the previous valid value of the corresponding status value or the default status value in the process parameter table is used to participate in the return material correction item calculation, and the out-of-bounds status mark is written to the return material association tag. The default status value is set according to the intermediate level of the corresponding status item, for example, 0.5.

[0133] The return material update unit sends the updated load value to the token decision unit for re-applying for a token. Upon receiving the updated load value, the token decision unit replaces the original comprehensive load index with the updated load value in the admission judgment formula. If the admission judgment value meets the issuance conditions, the material segment corresponding to the return material enters the token allocation process; if the admission judgment value does not meet the issuance conditions, the material segment corresponding to the return material waits for the remaining consumption window to be released. The screened return material, carrying the return material association tag and the updated load value, re-participates in the token application process.

[0134] See appendix Figure 7In this embodiment, step S5 is executed by the anomaly recovery module, which includes a state freeze unit, a recovery determination unit, and a segmented recovery unit. The anomaly recovery module generates freeze information when an anomaly is triggered and calculates a recovery determination value when the unit restarts, allocating the remaining material segments to the recovery queue. An anomaly trigger specifically refers to the triggering of an anomaly trigger signal, which can be a communication interruption signal, a sensor anomaly signal, a manual intervention signal, or an emergency shutdown signal.

[0135] The anomaly recovery module saves material load tags, window occupancy records, and occupancy tokens when an anomaly occurs, enabling the unit to identify the material segment location, occupancy token status, program lock status, window occupancy status, return material association status, and sensor validity status during recovery and restart. The segmented recovery unit first verifies the hard conditions of the anomaly, and then determines the recovery queue based on the recovery judgment value, preventing the occupancy token and window occupancy record from being released prematurely during the anomaly recovery process.

[0136] S51, the anomaly recovery module generates freeze information, invalid status flags, and alternative status values ​​through the status freeze unit. When the status freeze unit receives a communication interruption signal, sensor anomaly signal, manual intervention signal, or emergency stop signal transmitted from the fieldbus control system, it extracts the material load tag, window occupancy record, and occupancy token corresponding to the current material segment and writes them to the non-volatile storage area to generate freeze information. The freeze information includes the material segment number, current workstation number, estimated arrival time, comprehensive load index, window occupancy record, committed occupancy amount, occupancy token status, target program segment, return material association tag, and anomaly trigger type.

[0137] Communication interruption signals are generated by the fieldbus control system after communication timeout with the target controller, fieldbus interface, or internal bus; sensor anomaly signals are generated by the acquisition circuit corresponding to the field sensor when the signal exceeds the limit, the signal is lost, or the sampled value is invalid; manual intervention signals are generated by the local human-machine interface, maintenance confirmation button, or host computer operation record; emergency stop signals are generated by the emergency stop circuit or safety relay input. For writing data to non-volatile memory areas, those skilled in the art can use PLC holding registers, industrial controller non-volatile memory, or host computer databases. These storage methods are well-known technologies in the field and will not be elaborated here.

[0138] When the status freeze unit acquires an out-of-bounds status flag, it extracts the failed sensor data of the corresponding loop and generates an invalid status flag. The invalid status flag includes the sensor identifier, material section number, abnormal time, abnormal type, and corresponding status value fields. The invalid status flag is stored in the freeze information and is used to invalidate valid sensor status values ​​when the unit recovers and restarts.

[0139] When valid redundant variable data exists in the fieldbus control system, the state freeze unit generates alternative state values ​​based on the redundant variable data and writes the alternative state values ​​into the freeze information. Redundant variable data includes backup sensor data at the same workstation, inverter feedback data, valid data from adjacent sampling periods, or host computer process records. The alternative state values ​​are only used for recovery determination and temporary material handling control and do not overwrite failed sensor data; failed sensor data and invalid state markers are retained in the freeze information.

[0140] After the status freeze unit writes the freeze information, it maintains the committed occupancy amount in the window occupancy record and does not release the occupancy token that is marked as valid or short-term frozen. When the abnormal trigger type is a manual intervention signal, the status freeze unit records the manual intervention range; the material segment covered by the manual intervention range enters the abnormal hard condition judgment of the segmented recovery unit during recovery and restart. The manual intervention range can be selected by the operator through the local human-machine interface by the workstation number, material segment number, or equipment segment. The input method is well-known in the field and will not be described in detail here.

[0141] When a write operation to the non-volatile memory fails, the status freeze unit keeps the external actuator in a stopped or restricted discharge state and retains the current material segment state in the PLC holding register. After the non-volatile memory is restored, the current material segment state in the PLC holding register is written back to the freeze information. This process ensures that the occupancy token and committed occupancy amount are not released when the freeze information write fails.

[0142] S52, the anomaly recovery module calculates the recovery judgment value through the recovery judgment unit.

[0143] When the unit resumes operation, the recovery determination unit retrieves the frozen information containing alternative status values ​​from the non-volatile storage area and parses out multiple shutdown resident status values. These shutdown resident status values ​​include shutdown position status value, token validity status value, program lock status value, window occupancy status value, return material associated status value, and sensor validity status value. All of these status values ​​are converted into values ​​within a closed interval of 0 to 1 according to the status mapping rules in the process parameter table.

[0144] The shutdown position status value is generated based on the workstation where the material segment was located at the moment of the fault shutdown and its relative position to the exit. When the material segment is located on the inlet side or in front of a critical processing station, the shutdown position status value is a higher value; when the material segment is close to the exit and no longer requires critical processing, the shutdown position status value is a lower value. The token validity status value is generated based on the token holding status. The valid state flag and the short-term frozen state flag correspond to the valid state, and the invalid state flag corresponds to the invalid state.

[0145] The program lock status value is generated based on whether the target program segment is locked and whether the locked object is the current material segment; when the target program segment is locked and the locked object is the current material segment, the program lock status value is valid. The window occupancy status value is generated based on the committed occupancy amount, release status, and number of unreleased materials in the window occupancy record; when the committed occupancy amount has not been cleared and the release status is unreleased, the window occupancy status value is valid.

[0146] The return material association status value is generated based on whether the return material association tag exists and whether the return material processing is completed. When a return material association tag exists but the token allocation process for the return material has not been completed, the return material association status value is set to valid. The sensor valid status value is generated based on the invalid status flag and the alternative status value. When an invalid status flag exists but no alternative status value exists, the sensor valid status value is set to invalid. When an alternative status value exists, the sensor valid status value participates in the recovery determination as a restricted valid status.

[0147] The recovery determination unit substitutes the stop position status value, token validity status value, program lock status value, window occupancy status value, return material association status value, and sensor validity status value into the recovery determination formula to calculate and generate the recovery determination value. The recovery determination formula is as follows: ; In the formula: To restore the judgment value; This is the status value of the stopped position; This is the valid status value of the token; Set the program's lock status value; This is the window occupancy status value; This is the status value associated with the return of materials; This represents the valid state value of the sensor. , , , , , All of these are preset recovery weight coefficients.

[0148] The preset recovery weight coefficients are set based on the unit's workstation configuration, anomaly type, and recovery strategy, and are stored in the process parameter table. Each recovery weight coefficient ranges from 0 to 1; to maintain the magnitude of the recovery judgment value, to The total value can be set to 1. The continued processing threshold is set according to the continued processing conditions of the target workstation, the status of the occupancy token, and the safety material discharge requirements. For example, the continued processing threshold is 0.4 to 0.8, and the specific value is determined based on the unit commissioning results and the anomaly recovery strategy.

[0149] The recovery decision formula is a weighted state calculation, not a neural network model, and does not involve training samples, loss functions, or model iteration processes. When a state value is missing in the frozen information, the recovery decision unit first reads the alternative state value; if no alternative state value exists, the corresponding state value is set to invalid, and the material segment is handed over to the segmented recovery unit for abnormal hard condition judgment. When reading from the non-volatile memory area fails, the recovery decision unit reads the current material segment state from the PLC holding register; if it still cannot be read, the relevant material segment is placed in the isolation processing queue.

[0150] S53, the abnormal recovery module allocates material segments to the recovery queue through the segmented recovery unit, and releases the occupancy token after the recovery queue is completed.

[0151] The segmented recovery unit acquires the recovery judgment value, short-term frozen state flag, token valid state value, consistency verification value, sensor valid state value, and return-related state value, and then calls the preset recovery judgment logic. The recovery judgment logic first verifies the abnormal hard conditions, and then allocates the recovery queue based on the return-related state value, short-term frozen state flag, and recovery judgment value.

[0152] When the token's valid status value is invalid, the consistency check value is equal to a logical false value, or the sensor's valid status value is invalid, the segmented recovery unit will assign the material segment to the isolation processing queue. The isolation processing queue corresponds to temporary storage, manual confirmation, or low-speed material clearing processes; the external actuator controls the conveyor motor, discharge valve, or target station drive mechanism according to the isolation processing queue, so that the material segment does not directly enter the normal program segment.

[0153] When the return material association status value is active, the segment recovery unit will add the material segment to the return material processing queue. The return material association tag corresponding to the return material processing queue still needs to participate in the access control module's token application; when the return material processing queue is executed, the return material update unit retains the return material association tag and the updated load value, and the token decision unit recalculates the access judgment value based on the updated load value.

[0154] When the short-term freeze status flag takes effect, the segment recovery unit adds the material segment to the continue processing queue to await communication recovery. After communication is restored, the occupancy record unit rechecks the material segment number, occupancy token status, and target workstation processing status; if they match, the original target program segment continues to be used; if they do not match, the segment is transferred to the isolation processing queue.

[0155] After ruling out the above-mentioned abnormal conditions, if the recovery judgment value is less than the preset continuing processing threshold, the segmented recovery unit will add the material segment to the first discharge queue and clear it. The first discharge queue corresponds to a material segment that is close to the exit or does not require further critical processing, and the external actuator will perform low-speed discharge or limited discharge. If the recovery judgment value is not less than the continuing processing threshold and the token validity status value is valid, the segmented recovery unit will add the material segment to the continuing processing queue, and the target controller will resume processing using the original target program segment or the transition program segment.

[0156] In the recovery decision logic, the isolation processing queue has a higher priority than the return processing queue, which in turn has a higher priority than the continue processing queue. The continue processing queue corresponding to the short-term frozen state flag takes precedence over the first-exit queue formed based on the recovery decision value. This priority is used to prevent material segments with invalid sensor status values ​​or expired occupancy tokens from entering the normal program segment.

[0157] After the recovery queue is completed, the segmented recovery unit releases the corresponding occupancy token and notifies the occupancy record unit to cancel the committed occupancy amount in the occupancy record of the occupancy window. When the isolation processing queue involves manual confirmation, the occupancy token is released after the manual confirmation of material clearing is completed; the return processing queue is released after the occupancy token is re-obtained and the target station processing is completed; the first discharge queue is released after the outlet material flow signal confirms discharge; and the continue processing queue is released after the target controller generates a processing completion mark.

[0158] When the recovery queue cannot be executed, the segmented recovery unit keeps the occupancy token and window occupancy record in place and generates a new manual intervention signal. During the recovery queue execution, if the target controller generates another communication interruption signal, sensor abnormality signal, or emergency stop signal, the status freeze unit regenerates the freeze information, the segmented recovery unit stops the subsequent release actions of the current recovery queue, and retains the unreleased window occupancy record. Thus, the consistency of the material segment status and occupancy token status is maintained under continuous abnormal conditions.

[0159] To further aid in understanding the technical solutions of the embodiments of the present invention, a specific application example is given below. In this application example, the straw fiber preparation unit sequentially includes an inlet feeding station, a cutting station, a kneading station, a moisture conditioning station, a fiber unwinding station, a drying station, a screening station, and a return channel. The fieldbus control system collects data on feeding speed, feeding motor current, initial moisture content, cutting motor current, cutting speed, kneading motor load, material level in the kneading chamber, fiber unwinding motor operating parameters, drying station status, and screening return status. The material filing module establishes material segments according to time windows; in this application example, the 18th material segment is taken as the calculation object.

[0160] The material filing module records the initial filing time of the 18th material segment as 0s, the current workstation number as 1, the target workstation number as 5, and the dynamic correction time as 20s. The parameters for each internal interval from the current workstation to the target workstation are as follows: Section 1: Distance 2.4m, Belt speed 0.6m / s, Estimated dwell time 3s; Section 2: Distance 3.0m, Belt speed 0.5m / s, Estimated dwell time 8s; Section 3: Distance 2.0m, Belt speed 0.4m / s, Estimated dwell time 10s; Section 4: Distance 2.6m, Belt speed 0.52m / s, Estimated dwell time 12s. Substituting the above data into the arrival time formula, we get: ; ; Therefore, the 18th material segment is expected to arrive at the target station in 73 seconds. This expected arrival time is written into the material load tag and sent to the load assessment module and the access control module.

[0161] The load assessment module obtained the standardized state values ​​corresponding to the 18th material segment, including a dry basis feed rate of 0.62, a moisture content deviation of 0.48, a cutting resistance of 0.70, a kneading resistance of 0.64, an estimated defibering resistance of 0.58, and a continuity of 0.35. The corresponding process weight coefficients in the process parameter table are 0.18, 0.16, 0.14, 0.16, 0.22, and 0.14, respectively.

[0162] Substituting the above data into the load aggregation formula, we get: ; Therefore, the comprehensive load index for the 18th material section is 0.5654. This comprehensive load index is used by the access control module to make access decisions based on the remaining consumption window of the target workstation.

[0163] The access control module reads the motor load margin, cavity material level margin, discharge capacity margin, and residence time margin of the fiber disassembly station, which are 0.74, 0.68, 0.61, and 0.80, respectively. The window occupancy record shows two unreleased material segments, with corresponding committed occupancy amounts of 0.16 and 0.12, respectively.

[0164] Substituting the above data into the residual window formula, we get: ; In the process parameter table, the safety margin for the 18th material section entering the fiber disassembly station is 0.08. Substituting the remaining consumption window, comprehensive load index, and safety margin into the admission judgment formula, we get: ; If the admission threshold is less than 0, the token decision unit refuses to issue a holding token and generates a speed reduction and quantity limit instruction. The external actuator restricts upstream material discharge according to the speed reduction and quantity limit instruction, causing the 18th material segment to wait for the target station to release the processing capacity corresponding to the remaining consumption window.

[0165] In subsequent control cycles, the material segment that was not released in the preceding process completes the target station processing, and the committed occupancy in the window occupancy record decreases; the comprehensive load index remains at 0.5654, and the remaining consumption window of the target station is updated to 0.70. Substituting into the admission judgment formula again, we get: ; If the access threshold is not less than 0, the token decision unit issues an occupancy token to the 18th material segment and writes the total value of the comprehensive load index and the safe occupancy margin, 0.6454, as the committed occupancy amount into the window occupancy record. Thus, the target workstation's processing capacity occupancy for the 18th material segment is recorded, and this committed occupancy amount needs to be deducted when subsequent material segments apply for entry.

[0166] After the 18th material segment enters the screening station, the screening station detects backflow. The backflow update unit generates a backflow association tag and obtains a backflow cause status value of 0.42, a screening resistance status value of 0.50, and a channel congestion status value of 0.30; the corresponding correction weight coefficients are 0.20, 0.18, and 0.12, respectively. The backflow update unit multiplies the backflow cause status value by the corresponding correction weight coefficient to obtain the first backflow correction item of 0.084; multiplies the screening resistance status value by the corresponding correction weight coefficient to obtain the second backflow correction item of 0.090; and multiplies the channel congestion status value by the corresponding correction weight coefficient to obtain the third backflow correction item of 0.036. The backflow update unit adds the three backflow correction items to the original comprehensive load index of 0.5654 to obtain the updated load value of 0.7754.

[0167] The updated load value is sent to the token decision unit for re-applying for a token to return materials. Returned materials are not treated as new incoming materials and enter subsequent workstations; instead, they re-enter the admission process carrying a return material association tag and the updated load value.

[0168] In the abnormal recovery scenario, assume that when the 18th material section stops, the stop position status value is 0.70, the token validity status value is 0.80, the program lock status value is 0.70, the window occupancy status value is 0.70, the return material association status value is 0.20, and the sensor validity status value is 0.90; the recovery weight coefficients are 0.20, 0.20, 0.15, 0.15, 0.15, and 0.15, respectively. Substituting these values ​​into the recovery judgment formula, we get: ; The processing threshold is set to 0.60. Since the recovery judgment value is not less than the processing threshold and the token validity status value is valid, the segmented recovery unit adds the 18th material segment to the processing queue. If the sensor validity status value is invalid or the consistency check value is equal to logical false, the segmented recovery unit prioritizes adding the material segment to the isolation processing queue.

[0169] To verify the above control process, three sets of operating conditions were set up on the same straw fiber preparation unit.

[0170] Condition A involves relatively stable inlet feeding of wheat straw; Condition B involves corn stalks with fluctuating moisture content; and Condition C involves mixed straw materials with a high proportion of screened return material. The comparison is with a conventional distributed PLC interlocking control method, which uses upstream deceleration or shutdown based on single-station motor load, material level, and alarm status, without using material load tags, remaining consumption windows, occupancy tokens, or return material association tags. Each condition was run continuously for 30 material sections, recording the normalized peak load of the defiberization station, the number of times feeding resumed after the window was insufficient, and the number of times waiting to re-enter the access control after screened return material. Experimental data are attached. Figure 8 and attached Figure 9 As shown.

[0171] See appendix Figure 8 , Figure 8 The data from material segment numbers 13 to 24 are selected as the display objects, with the horizontal axis representing the material segment number and the vertical axis representing the normalized state value. Figure 8 The remaining consumption window is represented by a solid line with a square, the comprehensive load index is represented by a dashed line with a diamond, the occupancy token issuance point is represented by a solid line with a hollow circle, and the occupancy token rejection point is represented by a dashed line with a cross. The occupancy token issuance point and the occupancy token rejection point correspond to the access judgment results under different material segment numbers. The same material segment number corresponds to only one judgment result in the same access application. Figure 8 This is used to demonstrate the process by which the access control module issues or rejects occupancy tokens based on the remaining absorption window and comprehensive load indicators.

[0172] See appendix Figure 9 The horizontal axis represents operating conditions A, B, and C, and the vertical axis represents the normalized peak load of the fiber disassembly station; the two columns for each operating condition correspond to the conventional distributed PLC interlocking control method and the embodiment of this invention, respectively; Appendix Figure 9 This is used to demonstrate the change in the normalized load peak value of the fiber disassembly station after the access control module restricts the entry of high-load material sections into the target station under the same working conditions.

[0173] Combined with appendix Figure 8It can be seen that in the consecutive material segments numbered 13 to 24, the access control module determines the occupancy token issuance point or occupancy token rejection point based on the remaining consumption window, the comprehensive load index, and the safety occupancy margin. When the comprehensive load index is higher than the remaining consumption window, the corresponding material segment enters the waiting or limited control process; when the remaining consumption window recovers, the corresponding material segment obtains the occupancy token and enters the subsequent processing.

[0174] Combined with appendix Figure 9 It can be seen that under operating conditions A, B, and C, the normalized load peak values ​​of the fiber disassembly station corresponding to the conventional distributed PLC interlocking control method are 0.91, 0.88, and 0.94, respectively, while the normalized load peak values ​​of the fiber disassembly station corresponding to the embodiment of the present invention are 0.74, 0.70, and 0.76, respectively. The number of times the conventional distributed PLC interlocking control method continues feeding after the window is insufficient in the three operating conditions are 5, 8, and 10 times, respectively, while the corresponding number of times in the embodiment of the present invention are 1, 1, and 2 times, respectively.

[0175] The experimental results above show that the control link in this application embodiment can restrict the entry of upstream material segments when the processing capacity of the target workstation is insufficient, and maintain the processing status of the material segments through material load tags, remaining consumption windows, occupancy tokens, and return material association tags. The above experimental results correspond to the equipment configuration, process parameter table, and material conditions of this application embodiment, and are not intended to limit the scope of protection of this invention.

[0176] While specific embodiments of the present invention have been described above, those skilled in the art should understand that these specific embodiments are merely illustrative. Those skilled in the art can omit, substitute, and modify the details of the above methods and systems in various ways without departing from the principles and essence of the present invention. For example, combining the above method steps to perform substantially the same function and achieve substantially the same result using substantially the same method falls within the scope of the present invention.

Claims

1. A distributed program control system for a straw fiber production unit, characterized in that, include: The material filing module is used to create material segment and window occupancy records and generate standardized status values ​​from the collected initial dataset. The load assessment module is used to obtain multiple workstation resistance status values, combine the standardized status values, and substitute them into the load aggregation formula to calculate and generate a comprehensive load index, which is then written into the material load label. The access control module is used to extract multiple physical reserves of core load workstations and the promised occupancy in the window occupancy record, substitute them into the remaining window formula to generate the remaining absorption window, substitute the remaining absorption window and the comprehensive load index into the access judgment formula to generate the access judgment value, so as to issue or reject the occupancy token, and update the promised occupancy in the window occupancy record after issuance. The process execution module is used to generate a consistency verification value by substituting a preset consistency judgment rule after the occupancy token is issued and before the material segment is handed over across workstations, and to control the material segment to enter the normal program segment or downgrade to the transition program segment based on the consistency verification value. The abnormal recovery module is used to extract the material load tag, window occupancy record and occupancy token to generate freeze information when an abnormality is triggered, and to parse the freeze information to obtain multiple shutdown resident status values ​​when restarting, substitute them into the recovery judgment formula to generate a recovery judgment value, allocate the material segment to the recovery queue according to the recovery judgment value, release the occupancy token after execution, and cancel the promised occupancy amount.

2. The distributed program control system for the straw fiber production unit according to claim 1, characterized in that, The material filing module includes: The initial filing unit is used to establish the material segment and the empty window occupancy record according to the preset filing benchmark boundary, and to collect the original collection volume of the filing stage to generate the initial dataset. The state calibration unit is used to call preset state calibration rules to perform normalization processing on the original collected data and generate the standardized state value, which includes the feed quantity state value, moisture content deviation value and continuity state value on a dry basis.

3. The distributed program control system for the straw fiber production unit according to claim 2, characterized in that, The material filing module also includes: The dynamic tracking unit is used to collect real-time conveyor belt speed and conveyor distance, extract the initial filing time, current workstation number, preset estimated dwell time and dynamic correction time, substitute them into the arrival time formula to generate the estimated arrival time, and write the estimated arrival time into the record field corresponding to the material segment. The dynamic tracking unit is also used to pause the division calculation of the conveyor section distance and the real-time conveyor section speed in the arrival time formula when the real-time conveyor section belt speed is equal to zero, and to add the downtime to the dynamic correction time.

4. The distributed program control system for the straw fiber production unit according to claim 1, characterized in that, The load assessment module includes: The resistance acquisition unit is used to generate a cutting resistance status value based on the acquired cutting motor current and cutting speed, and generate a material registration record in the window occupancy record when the cutting resistance status value is greater than a preset resistance threshold. The workstation status unit is used to generate the estimated defiber resistance status value among the multiple workstation resistance status values ​​based on preset historical formula data, and to generate the kneading resistance status value among the multiple workstation resistance status values ​​based on the collected kneading motor load and kneading chamber material level. The load aggregation unit is used to substitute the standardized state value and the multiple workstation resistance state values ​​into the load aggregation formula to generate the comprehensive load index.

5. The distributed program control system for the straw fiber production unit according to claim 1, characterized in that, The access control module includes: A window calculation unit is used to map the multiple physical reserves to standard calculation reserves, and combine them with the committed occupancy amount in the unreleased state extracted from the window occupancy record, and substitute it into the remaining window formula to generate the remaining absorption window. The token decision unit is used to substitute the remaining consumption window, the comprehensive load index, and the safety occupancy margin extracted from the preset process parameter table into the admission judgment formula to generate the admission judgment value. When the admission judgment value is not less than zero, the occupancy token is issued and a new committed occupancy amount is written to the window occupancy record. When the admission judgment value is less than zero, the occupancy token is rejected and a speed reduction limit instruction is generated and sent to the external execution mechanism.

6. The distributed program control system for the straw fiber preparation unit according to claim 5, characterized in that, The access control module also includes: The occupancy record unit is used to generate a valid state flag after the occupancy token is issued, assign the occupancy token to the occupancy token, and release the occupancy token and cancel the promised occupancy amount in the window occupancy record after the material section completes the target workstation processing; The occupancy recording unit is also used to generate a short-term frozen state flag or a failure state flag based on the communication interruption duration, the conveying time of the material segment, and a preset timeout threshold when the communication connection with the target controller is detected to be disconnected. After generating the failure state flag, an abnormal rollback program is generated to enable the external actuator to perform speed-limited material discharge, temporary storage, or stop feeding.

7. The distributed program control system for the straw fiber production unit according to claim 6, characterized in that, The process execution module includes: A consistency verification unit is used to extract executed matching values, pending matching values, and prohibited switching matching values ​​from the material load label, the occupancy token, and the target workstation, respectively, and substitute them into the consistency determination rules to generate the consistency verification value. The execution control unit is used to lock the target program segment after the consistency check value is equal to the logical true value, and to generate a drying and absorption window based on the measured defiber resistance state value generated after the defiber motor operating parameters are collected by the field sensors and the moisture content deviation value extracted from the standardized state value. When the drying and absorption window is less than zero, a window shortage instruction is generated and sent to the external execution mechanism to reduce the upstream feed rate.

8. The distributed program control system for the straw fiber production unit according to claim 7, characterized in that, The process execution module further includes: The return material update unit is used to generate a return material association tag when screening return material is generated in the material section, extract the return material cause status value, screening resistance status value and channel congestion status value from the return material association tag, and generate a return material correction item based on the return material cause status value, the screening resistance status value and the channel congestion status value. The return material update unit is further configured to add the return material correction item to the comprehensive load index to obtain an updated load value, and send the updated load value to the token decision unit to replace the original comprehensive load index to reapply for the occupancy token.

9. The distributed program control system for the straw fiber production unit according to claim 1, characterized in that, The anomaly recovery module includes: The status freeze unit is used to extract the material load tag, the window occupancy record and the occupancy token to generate the freeze information when an abnormal trigger signal is received, and to generate an invalid status flag and write it into the freeze information when an out-of-bounds status flag is obtained. It also generates a substitute status value and writes it into the freeze information based on the redundant variable data in the fieldbus control system. The recovery determination unit is used to parse the freeze information when the unit is restarted, obtain the multiple shutdown dwell status values, and substitute them into the recovery determination formula to generate the recovery determination value.

10. The distributed program control system for the straw fiber production unit according to claim 9, characterized in that, The anomaly recovery module also includes: The segmented recovery unit is used to allocate the material segment to the isolation processing queue, the return processing queue, the first discharge queue, or the continue processing queue based on the recovery judgment value, the short-term frozen state flag, the consistency verification value, and the token valid state value, sensor valid state value, and return material associated state value parsed from the multiple shutdown resident state values. After the corresponding recovery queue has been completed, the occupancy token is released, and the corresponding committed occupancy amount in the window occupancy record is cancelled.