A method for collaborative control of graded anomalies in stabilized soil mixing plants

By constructing a backup circuit within the target logical material group under redundant operating conditions of multi-physical batching circuits to redistribute flow and switch global follow-up control modes, the problem of low utilization rate of redundant hardware resources in existing technologies is solved, thereby improving production efficiency and the stability of finished product mixture ratio.

CN123113570APending Publication Date: 2026-11-17XUZHOU XCMG MAINTENANCE MACHINERY CO LTD
View PDF 1 Cites 0 Cited by

Patent Information

Application Number
CN202611440279.4
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2026-09-16
Publication Date
2026-11-17

AI Technical Summary

Technical Problem

Existing technologies cannot effectively utilize redundant hardware resources in the case of multiple redundant physical batching loops, resulting in reduced production efficiency and low equipment utilization. They also cannot identify and utilize the surplus conveying capacity of multiple physical batching loops, causing unnecessary capacity losses.

Method used

By constructing a backup loop within the target logical material group, priority compensation is given to the redistribution of flow within the group, and when necessary, the system switches to a global follow-up control mode. By utilizing the surplus conveying capacity of the redundant loop, combined with a dual closed-loop verification mechanism, the stability of the finished product mixture ratio and production efficiency are ensured.

Benefits of technology

In the case of redundant operation of multi-physical batching loops, redundant hardware resources are used first to compensate for flow gaps, reduce unnecessary production capacity losses, improve equipment utilization, and switch to global follow-up control mode in special circumstances to ensure the reliability and stability of finished product mixture ratio.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN123113570A_ABST
    Figure CN123113570A_ABST
Patent Text Reader

Abstract

This invention provides a method for graded abnormal collaborative control of stabilized soil batching, relating to the field of stabilized soil batching technology. The method includes the following steps: Step S1: Divide multiple physical batching loops into corresponding logical material groups according to the type of material being transported, and determine the initial set flow rate of each physical batching loop; Step S2: Real-time acquisition of the instantaneous actual flow rate of each physical batching loop and the current operating frequency of the frequency converter, and obtain the theoretical supply flow rate of each physical batching loop; Step S3: Calculate the relative flow rate deviation between the instantaneous actual flow rate of each physical batching loop and its initial set flow rate; Step S4: Based on the theoretical supply flow rate of the backup loop after excluding abnormal loops in the target logical material group and the initial set flow rate, calculate the total compensation margin of the backup loops and the flow gap caused by abnormal loops. This invention has a reasonable structure and can maintain production efficiency as much as possible under redundant operating conditions of multiple physical batching loops, improving the utilization rate of redundant equipment hardware.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of batching for stabilized soil mixing plants, and specifically relates to a hierarchical anomaly cooperative control method for batching in a stabilized soil mixing plant. Background Art

[0002] The number of batching hoppers equipped in stabilized soil mixing plant equipment is often larger than the type of materials, and hardware redundancy where multiple physical batching circuits convey the same aggregate is common. During the production process, fluctuations in material feeding by loaders and arching in hoppers will cause the actual flow rate of the batching circuit to deviate from the set flow rate of the formula, resulting in unqualified gradation of the finished mixed material. The weighing scales for on-site stabilized soil mixing plants generally select a certain reference operating frequency (typically 20Hz) for flow calibration, and this calibration frequency is a common operating point for formula production; however, the maximum output frequency of the frequency converter hardware matched with the weighing scale can reach 50Hz, and the hardware conveying mechanism of the frequency converter itself has redundant conveying capacity greater than the nominal calibrated flow rate, which provides a physical implementation basis for flow complementation between circuits of the same material.

[0003] In the prior art, the patent with publication number CN104552609A proposes a system and method for dynamically adjusting the set amount of a formula. The dynamic adjustment scheme adopts a single-mode anomaly handling solution, and the control logic is solidified as: when the relative flow deviation of any physical batching circuit exceeds a preset threshold, all physical batching circuits are controlled to perform global equal-ratio adjustment according to the original formula proportion, so as to ensure the qualified ratio of the finished mixed material by reducing the overall production capacity. This scheme has inherent technical defects: regardless of whether the equipment has the hardware redundancy condition of multiple physical batching circuits for the same material, as long as a single-circuit flow anomaly is triggered, the total production flow of the whole machine will inevitably decrease synchronously; the system cannot identify and utilize the surplus conveying capacity of the existing redundant batching circuits to offset the single-circuit feeding gap, resulting in unnecessary production capacity loss and extremely low utilization rate of equipment redundant hardware. There is an urgent need for a hierarchical anomaly cooperative control method for batching in stabilized soil mixing plants to solve the above-mentioned problems. Contents of the Invention

[0004] In view of the deficiencies existing in the prior art, the purpose of the present invention is to provide a hierarchical anomaly cooperative control method for batching in a stabilized soil mixing plant, so as to solve the problems raised in the above-mentioned background art. The present invention has a reasonable structure, can preserve the production efficiency as much as possible under the redundant working condition of multiple physical batching circuits, reduce unnecessary production capacity loss, and improve the utilization rate of equipment redundant hardware.

[0005] In order to achieve the above purpose, the present invention is realized through the following technical solution: a hierarchical anomaly cooperative control method for batching in a stabilized soil mixing plant, comprising the following steps:

[0006] Step S1, parameter configuration and initialization: Divide multiple physical batching loops into corresponding logical material groups according to the type of material being conveyed, set the abnormal control threshold and secondary verification delay time, and determine the initial set flow rate of each physical batching loop based on the total production of the equipment and the mixing ratio of each batching loop;

[0007] Step S2: Real-time acquisition of the instantaneous actual flow rate of each physical batching circuit and the current operating frequency of the frequency converter, and acquisition of the theoretical supply flow rate of each physical batching circuit;

[0008] Step S3: Calculate the relative flow deviation between the instantaneous actual flow rate of each physical batching loop and its initial set flow rate; when the relative flow deviation of a physical batching loop exceeds the abnormal control threshold, the loop is identified as an abnormal loop and its target logical material group is located; otherwise, each physical batching loop maintains the original formula's initial set flow rate and returns to step S2.

[0009] Step S4: Based on the theoretical supply flow rate and initial set flow rate of the backup circuit after excluding the abnormal circuit in the target logical material group, calculate the total compensation margin of the backup circuit and calculate the flow gap caused by the abnormal circuit.

[0010] Step S5: If the total compensation margin is greater than or equal to the flow gap, the flow in the backup loops within the target logical material group is redistributed, the flow increment to be added to each backup loop and the updated target set flow are calculated and determined, and the original formula initial set flow of other physical batching loops except the target logical material group remains unchanged, and a secondary verification delay is started; otherwise, switch to global follow-up control mode.

[0011] Step S6: After the second verification delay ends, determine whether the actual total instantaneous flow rate of the target logical material group has reached the initial set total flow rate of its formula; if it has, maintain the flow redistribution within the group; if it has not, turn off the redistribution mode within the group and switch to the global follow-up control mode.

[0012] Step S7: Determine whether the relative deviation of the flow rate of the abnormal loop has returned to the qualified range. If it has, return to step S2; otherwise, maintain the current control mode.

[0013] Furthermore, in step S1, the initial set flow rate record for each physical batching loop is determined as follows: .

[0014] Furthermore, the step S2 of obtaining the supply flow rate of each physical batching loop specifically includes the following steps:

[0015] Step S21: Based on the linear calibration relationship of frequency and flow rate of the weighing scale, the formula for calculating the theoretical flow rate that the inverter matched with the weighing scale for each physical batching circuit can supply under 50Hz operating conditions is as follows: ,in, This represents the instantaneous actual flow rate of each physical batching loop. This refers to the current operating frequency of the frequency converter in each physical batching circuit.

[0016] Furthermore, the formula for calculating the relative deviation of the flow rate in step S3 is as follows: ,in, The initial flow rate setting for each physical batching loop. This represents the instantaneous actual flow rate of each physical batching loop;

[0017] when Each physical ingredient loop maintains the initial set flow rate of the original formula and returns to step S2; when The loop was identified as an abnormal loop, and its target logical material group was located. This is the threshold for abnormal control.

[0018] Further, the formula for calculating the total compensation margin of the backup circuit in step S4 is as follows: ,in, The theoretical supply flow rate for the backup circuit in the target logic material group after excluding abnormal circuits. The initial set flow rate for the backup loop after excluding abnormal loops in the target logic material group;

[0019] The formula for calculating the flow gap caused by the abnormal loop in step S4 is as follows: Where x is the number of the abnormal loop, The initial flow rate for the abnormal loop. This represents the instantaneous actual flow rate of the abnormal loop.

[0020] Furthermore, the formula for calculating the required additional flow rate for each backup circuit in step S5 is as follows: ,in, The flow gap caused by the abnormal loop The theoretical supply flow rate for the backup circuit in the target logic material group after excluding abnormal circuits. The initial set flow rate for the backup loop after excluding abnormal loops in the target logic material group. This represents the total compensation margin for the backup circuit;

[0021] The formula for the updated target flow rate of each backup circuit is as follows: ,in, The additional flow rate required for each backup circuit. The initial set flow rate for the backup loop after excluding abnormal loops in the target logic material group;

[0022] Computational constraints Complete the assigned traffic values ​​and redistribute traffic within the group. Set the target flow rate for each backup circuit after the update. The theoretical supply flow rate of the backup circuit after excluding abnormal circuits in the target logic material group;

[0023] In step S5, after switching to the global follow-up control mode, if the relative deviation of the flow rate of the abnormal loop returns to the qualified level (i.e., the relative deviation of the flow rate of the abnormal loop is less than or equal to the abnormal control threshold), then exit the abnormal control mode, and all loops return to the initial set flow rate of the formula, and return to step S2 loop; otherwise, directly return to step S2 loop.

[0024] Furthermore, after disabling the intra-group redistribution mode and switching to the global follow-up control mode in step S6, an audible and visual alarm is triggered, and the abnormal event, timestamp, and flow parameters are written into the device operation log, and step S7 is executed.

[0025] Furthermore, the start of the secondary verification delay in step S5 is determined according to the set secondary verification delay time, and during the delay time, the actual total instantaneous flow of the target logic material group is not judged in step S6 to determine whether it meets the standard, and the actual total instantaneous flow of the target logic material group is continuously collected.

[0026] Furthermore, the step S7 of determining whether the relative deviation of the flow rate of the abnormal loop has returned to the acceptable range specifically includes the following steps:

[0027] Step S71: Determine that the relative deviation of the flow rate of the abnormal loop has returned to the qualified level, that is, the relative deviation of the flow rate of the abnormal loop is less than or equal to the abnormal control threshold: Exit the abnormal control mode, return all loops to the initial set flow rate of the recipe, and return to step S2 to cycle. The abnormal control mode is either intra-group flow redistribution or global follow-up control mode.

[0028] If the relative flow deviation of the abnormal loop fails to return to the qualified level (i.e., the relative flow deviation of the abnormal loop is greater than the abnormal control threshold), return to step S6, maintain the current control mode, until the relative flow deviation of the abnormal loop returns to the qualified level, then return to step S2 to continue the cyclical acquisition and monitoring. The current control mode is either intra-group flow redistribution or global follow-up control mode.

[0029] Furthermore, the global follow-up control mode allows the formula of each physical batching loop to be synchronously adjusted according to the ratio of the initially set flow rate.

[0030] Beneficial effects:

[0031] This invention constructs a two-level anomaly handling mode: "prioritizing compensation for intra-group flow redistribution using a backup loop within the target logical material group + switching to a global follow-up control mode for fallback." Under conditions of redundant multi-physical batching loops and sufficient incoming materials, it prioritizes utilizing the surplus capacity within the target logical material group to compensate for flow gaps, avoiding the unnecessary production reduction defects of traditional follow-up control. In scenarios such as single-physical batching loop operation, insufficient compensation margin, or deterioration of incoming materials after compensation, it automatically downgrades to the global follow-up control fallback mode. This addresses industry pain points such as redundant hardware waste in traditional solutions and lack of fallback in simple complementary solutions, reducing unnecessary capacity losses and improving the utilization rate of redundant equipment hardware. Through two-level closed-loop verification, the control reliability is extremely high.

[0032] By setting up a dual closed-loop mechanism of pre-judgment of total compensation margin before compensation and secondary verification after compensation with delay, the feasibility of the compensation plan is guaranteed, and abnormal working conditions of incoming materials can be accurately identified. This solves the problem of discrepancies between theoretical calculations and actual working conditions, effectively avoids loss of control of the mixture ratio, and achieves reliable control of the finished mixture ratio under all working conditions.

[0033] It can prioritize maintaining production efficiency under redundant operating conditions of multiple physical batching loops and control the proportion of finished product mixture. It is adaptable to all operating conditions and has a wide range of applications. It can fully adapt to single-loop, dual-loop, and three or more loop operating conditions of logic material groups. It adopts the method of allocating the flow gap according to the proportion of the remaining output capacity of the spare loop, which is conducive to the reasonable allocation of compensation flow among redundant loops, reducing the flow fluctuation of non-target logic material groups and improving the stability of finished product mixture proportion control. Attached Figure Description

[0034] Other features, objects, and advantages of the present invention will become more apparent from the following detailed description of non-limiting embodiments with reference to the accompanying drawings:

[0035] Figure 1 A flowchart of a method for coordinated control of graded anomalies in stabilized soil batching plant according to an embodiment of the present invention;

[0036] Figure 2 This is a flow timing diagram of a graded abnormality collaborative control method for stabilized soil batching plant according to Embodiment 2 of the present invention.

[0037] The accompanying drawings are provided to further understand the embodiments and form part of the specification. They are used together with the embodiments for explanation and do not constitute a limitation on the embodiments. Detailed Implementation

[0038] The technical solutions in the embodiments of the present invention will be clearly and completely described below with reference to the accompanying drawings. Obviously, the described embodiments are only some embodiments of the present invention, and not all embodiments. Based on the embodiments, all other embodiments obtained by those skilled in the art without creative effort are within the scope of protection.

[0039] In the description of the embodiments, it should be understood that the terms "upper", "lower", "front", "rear", "left", "right", "top", "bottom", "inner", "outer", etc., indicate the orientation or positional relationship based on the orientation or positional relationship shown in the drawings. They are only for the convenience of describing the embodiments and simplifying the description, and do not indicate or imply that the device or element referred to must have a specific orientation, or be constructed and operated in a specific orientation. Therefore, they should not be construed as limitations on the embodiments.

[0040] like Figure 1 As shown in the figure, this invention provides a method for coordinated control of grading anomalies in stabilized soil mixing plants, comprising the following steps:

[0041] Step S1, parameter configuration and initialization: Divide multiple physical batching loops into corresponding logical material groups according to the type of material being conveyed, set the abnormal control threshold and secondary verification delay time, and determine the initial set flow rate of each physical batching loop based on the total production of the equipment and the mixing ratio of each batching loop;

[0042] Step S2: Real-time acquisition of the instantaneous actual flow rate of each physical batching circuit and the current operating frequency of the frequency converter, and acquisition of the theoretical supply flow rate of each physical batching circuit;

[0043] Step S3: Calculate the relative deviation between the instantaneous actual flow rate of each physical batching loop and its initial set flow rate; when the relative deviation of the flow rate of a physical batching loop exceeds the abnormal control threshold, the loop is identified as an abnormal loop and its target logical material group is located; otherwise, when it is less than or equal to the abnormal control threshold, each physical batching loop maintains the original initial set flow rate of the formula and returns to step S2.

[0044] Step S4: Based on the theoretical supply flow rate and initial set flow rate of the backup circuit after excluding the abnormal circuit in the target logical material group, calculate the total compensation margin of the backup circuit and calculate the flow gap caused by the abnormal circuit.

[0045] Step S5: If the total compensation margin is greater than or equal to the flow gap, the flow in the backup loops within the target logical material group is redistributed, the flow increment to be added to each backup loop and the updated target set flow are calculated and determined, and the original formula initial set flow of other physical batching loops except the target logical material group remains unchanged, and a secondary verification delay is started; otherwise, switch to global follow-up control mode.

[0046] Step S6: After the second verification delay ends, determine whether the actual total instantaneous flow rate of the target logical material group has reached the initial set total flow rate of its formula; if it has, maintain the flow redistribution within the group; if it has not, turn off the redistribution mode within the group and switch to the global follow-up control mode.

[0047] Step S7: Determine whether the relative deviation of the flow rate in the abnormal loop has returned to the acceptable range. If it has, return to step S2; otherwise, maintain the current control mode. This design constructs a two-level abnormal handling mode: "prioritizing compensation for flow redistribution within the target logic material group using a backup loop + switching to a global follow-up control mode for global follow-up backup." Under conditions of redundant multi-physical batching loops and sufficient incoming materials, it prioritizes using the surplus capacity within the target logic material group to compensate for flow gaps, avoiding the unnecessary production reduction defects of traditional follow-up control. Under conditions of single-physical batching loop operation, insufficient compensation margin, and deterioration of incoming materials after compensation, it automatically downgrades to the global follow-up control backup mode, solving the industry pain points of redundant hardware waste in traditional solutions and lack of backup in simple complementary solutions, reducing unnecessary capacity losses, and improving the utilization rate of redundant hardware. Through two-level closed-loop verification, the control reliability is extremely high. The invention employs a dual closed-loop mechanism: pre-judgment of total compensation margin before compensation and secondary verification after compensation with a delay. This mechanism ensures the feasibility of the compensation scheme and accurately identifies abnormal on-site material conditions, resolving discrepancies between theoretical calculations and actual working conditions. It effectively prevents runaway mixing ratios and ensures reliable control of the finished mixture ratio under all working conditions. The invention fully reuses the original weighing flow rate and frequency converter signals of the equipment, eliminating the need for additional material level sensors.

[0048] In step S1, the initial set flow rate of each physical batching loop is recorded as follows: .

[0049] Step S2, obtaining the available flow rate of each physical batching loop, specifically includes the following steps:

[0050] Step S21: Based on the linear calibration relationship of frequency and flow rate of the weighing scale, the formula for calculating the theoretical flow rate that the inverter matched with the weighing scale for each physical batching circuit can supply under 50Hz operating conditions is as follows: ,in, This represents the instantaneous actual flow rate of each physical batching loop. This refers to the current operating frequency of the frequency converter in each physical batching loop. The design continuously collects the instantaneous actual flow rate of each physical batching loop and the current operating frequency of the frequency converter. Based on the linear calibration relationship between the frequency and flow rate of the metering scale, it calculates the theoretically available flow rate under the 50Hz extreme operating condition, iteratively updates the dynamic theoretically available flow rate of each loop, and achieves adaptive self-learning of the equipment's operating capacity. The metering scale is either an electronic belt scale or an electronic screw scale.

[0051] The formula for calculating the relative deviation of flow rate in step S3 is as follows: ,in, The initial flow rate setting for each physical batching loop. This represents the instantaneous actual flow rate of each physical batching loop;

[0052] when Each physical ingredient loop maintains the initial set flow rate of the original formula and returns to step S2; when The loop was identified as an abnormal loop, and its target logical material group was located. The design uses an abnormal control threshold. It calculates the relative deviation of the loop flow in real time. When the deviation does not exceed the abnormal control threshold, each loop maintains stable operation at the initial formula setting. When the relative deviation of the flow of any loop exceeds the preset abnormal control threshold, it is marked as an abnormal loop and its target logical material group is located. This allows for precise screening of all backup physical batching loops within the material group, excluding abnormal loops.

[0053] The formula for calculating the total compensation margin of the standby circuit in step S4 is as follows: ,in, The theoretical supply flow rate for the backup circuit in the target logic material group after excluding abnormal circuits. The initial set flow rate for the backup loop after excluding abnormal loops in the target logic material group;

[0054] The formula for calculating the flow gap caused by the abnormal loop in step S4 is as follows: Where x is the number of the abnormal loop, The initial flow rate for the abnormal loop. This represents the instantaneous actual flow rate of the abnormal loop. The design calculates the total compensation margin of the backup loop and the flow gap generated by the abnormal loop to complete the pre-calculation of compensation parameters and feasibility prediction. If the total compensation margin of the backup loop is insufficient to cover the flow gap, the compensation logic within the group is directly exited, and the global follow-up control processing mode is switched.

[0055] The formula for calculating the required additional flow rate for each backup circuit in step S5 is as follows: ,in, The flow gap caused by the abnormal loop The theoretical supply flow rate for the backup circuit in the target logic material group after excluding abnormal circuits. The initial set flow rate for the backup loop after excluding abnormal loops in the target logic material group. This represents the total compensation margin for the backup circuit;

[0056] The formula for the updated target set flow rate of each backup circuit is as follows: ,in, The additional flow rate required for each backup circuit. The theoretical flow rate is set for the backup loop in the target logic material group after excluding abnormal loops;

[0057] Computational constraints Complete the assigned traffic values ​​and redistribute traffic within the group. Set the target flow rate for each backup circuit after the update. The theoretical supply flow rate of the backup circuit after excluding abnormal circuits in the target logic material group;

[0058] In step S5, after switching to the global follow-up control mode, if the relative flow deviation of the abnormal loop returns to the qualified level (i.e., the relative flow deviation of the abnormal loop is less than or equal to the abnormal control threshold), then the abnormal control mode is exited, all loops return to the initial set flow of the formula, and the cycle returns to step S2; otherwise, the cycle directly returns to step S2. This design, by performing flow redistribution within the group on the standby loops if the total compensation margin of the standby loops meets the compensation requirements, allocates the flow gap according to the proportion of the additional margin available in each standby loop to the total compensation margin, accurately calculates the additional flow required for each standby loop and the updated target set flow, and directly completes the set flow assignment update within the constraint of not exceeding the upper limit of the dynamically supplyable flow of the loops. The initial set flow of the formula for the batching loops of non-target logic material groups remains unchanged.

[0059] After disabling the intra-group redistribution mode and switching to the global follow-up control mode in step S6, an audible and visual alarm is triggered, and the abnormal event, timestamp, and flow parameters are written to the device operation log. Then, step S7 is executed.

[0060] In step S5, the secondary verification delay is determined based on the set delay time. During the delay period, the actual total instantaneous flow rate of the target logic material group is not evaluated in step S6, but the actual total instantaneous flow rate of the target logic material group is continuously collected. This design, after flow redistribution, initiates the secondary verification delay. During the delay, only the actual total flow rate of the material group is collected, and false judgment logic is masked, avoiding detection deviations caused by mechanical conveying response lag. After the delay, the system checks whether the total flow rate of the material group meets the standard: if the actual total flow rate meets the standard, the current compensation state within the group is maintained; if the actual total flow rate does not meet the standard, it is determined that the on-site material supply capacity is insufficient and the compensation has failed, terminating the flow redistribution process within the group and switching to global follow-up control mode.

[0061] Step S7, determining whether the relative flow deviation of the abnormal loop has returned to the acceptable range, specifically includes the following steps:

[0062] Step S71: Determine that the relative deviation of the flow rate of the abnormal loop has returned to the qualified level, that is, the relative deviation of the flow rate of the abnormal loop is less than or equal to the abnormal control threshold: Exit the abnormal control mode, return all loops to the initial set flow rate of the recipe, and return to step S2 to cycle. The abnormal control mode is either intra-group flow redistribution or global follow-up control mode.

[0063] If the relative flow deviation of an abnormal loop fails to return to acceptable levels (i.e., the relative flow deviation exceeds the abnormal control threshold), the system returns to step S6, maintaining the current control mode until the relative flow deviation of the abnormal loop returns to acceptable levels. Then, it returns to step S2 to continue cyclical monitoring. The current control mode is either intra-group flow redistribution or global follow-up control. This design continuously monitors the operating status of abnormal loops. Once the relative flow deviation returns to the acceptable range, all abnormal control modes are exited, and all loops resume operation at their initial formula settings. If the abnormality persists, the current control mode is maintained for continuous monitoring, forming a complete closed-loop hierarchical control process.

[0064] The global follow-up control mode allows the formula of each physical batching loop to be adjusted synchronously according to the ratio of the initially set flow rate.

[0065] As an embodiment of the present invention:

[0066] Step S1: Power on the equipment to complete initialization, parameter configuration and initialization. According to the on-site batching process, divide multiple physical batching loops into corresponding logical material groups according to the type of conveyed material. Configure and set the abnormal control threshold and secondary verification delay time in a unified manner. Calculate, determine and record the initial set flow rate of each physical batching loop based on the total production of the equipment and the mixing ratio of each batching loop.

[0067] Step S2: Real-time acquisition of the instantaneous actual flow rate of each physical batching circuit and the current operating frequency of the frequency converter. Based on the linear relationship between the frequency and flow rate of the metering scale calibrated at the factory, and combined with the current effective operating point, extrapolation calculation of the theoretical supply flow rate of each physical batching circuit under the rated frequency of 50Hz is performed. The dynamic supply flow rate of each circuit is continuously iterated, updated and corrected to achieve adaptive self-learning update of the equipment's conveying capacity and obtain the supply flow rate of each physical batching circuit.

[0068] Step S3: Calculate the relative deviation between the instantaneous actual flow rate of each physical batching loop and its initial set flow rate; when the relative deviation of the flow rate of a physical batching loop exceeds the abnormal control threshold, the loop is identified as an abnormal loop, the loop number is marked as x, and its target logical material group is located; otherwise, each physical batching loop maintains the original initial set flow rate of the formula and returns to step S2.

[0069] Step S4: Based on the theoretical supply flow and initial set flow of all backup circuits in the target logical material group after excluding abnormal circuit x, calculate the total compensation margin of the backup circuits and calculate the flow gap caused by the abnormal circuits, so as to provide accurate data basis for subsequent compensation feasibility judgment.

[0070] Step S5: If the total compensation margin is greater than or equal to the flow gap, the flow of the backup loops in the target logical material group is redistributed within the group. The required additional flow of each backup loop and the updated target set flow are calculated. Based on the proportion of the additional margin of each backup physical batching loop to the total compensation margin, the flow gap is proportionally allocated. The flow increment corresponding to each backup loop is calculated and added to the original set flow to obtain the new target set flow. The updated flow is strictly constrained not to exceed the upper limit of the loop's dynamic supply flow. The parameter assignment update is completed directly. The original formula initial set flow of other physical batching loops, except for the target logical material group, remains unchanged. A secondary verification delay is started. During the delay, only the actual total instantaneous flow data of the target material group is continuously collected to shield instantaneous misjudgments and avoid sampling deviations caused by mechanical conveying response lag. Otherwise, if the total compensation margin cannot cover the flow gap, it is determined that the compensation conditions in the target logical material group are insufficient, and the execution is directly switched to the global follow-up control mode.

[0071] Step S6: After the secondary verification delay ends, determine whether the actual total instantaneous flow rate of the target logic material group has reached the initial set flow rate of its formula. If it has, maintain the flow redistribution within the group. If it has not, it indicates that the on-site material supply capacity is insufficient and the theoretical compensation has failed. Close the flow redistribution mode within the group and switch to the global follow-up control mode. Under the condition that the total compensation margin is insufficient or the secondary verification fails, the flow redistribution logic within the group is automatically closed. All physical batching loops uniformly execute global follow-up scaling control according to the original formula ratio to ensure that the finished product mixture ratio is constant. At the same time, trigger the equipment's audible and visual alarms, record the abnormal time, abnormal type and flow parameters to achieve traceability of abnormal events.

[0072] Step S7: Determine whether the relative deviation of the flow rate of the abnormal loop has returned to the qualified range. If it has, return to step S2; otherwise, maintain the current control mode.

[0073] To further clarify and fully illustrate the actual execution logic of the hierarchical collaborative control method of this application, strictly corresponding to the decision branches of steps S1-S7 above, and simultaneously covering full hardware adaptation scenarios of dual-loop, three or more multi-loop systems, this method's hierarchical handling logic and stability under different boundary conditions are verified. The following is a concrete implementation example based on three sets of progressive typical operating conditions. The overall control flow is as follows: Figure 1 The timing of dynamic changes in flow rate under normal compensation conditions is referenced. Figure 2 Timing diagram.

[0074] Example 1: The total compensation margin of the backup circuit is insufficient, triggering the global follow-up fallback condition (corresponding to the branch where the judgment in step S5 is not valid).

[0075] This embodiment refers to Figure 1 The branch indicating that step S5 is invalid applies to situations where a material group has multiple redundant physical batching loops, but the overall compensation capacity of the backup loops is insufficient. This covers scenarios with dual loops, three or more loops, and weak redundancy. For example, in a dual-loop material group, loop #1 abnormally generates a flow gap of 40t / h, while backup loop #2 has an additional margin of only 20t / h, meaning the total compensation margin of the material group cannot cover the flow gap; or the total additional margin of each backup loop in a multi-loop material group is less than the flow gap. If the compensation condition within the target logic material group is not met (total compensation margin greater than or equal to the flow gap), the system directly jumps to the global follow-up control mode. This mode ensures the accuracy of the mixture ratio through global ratio scaling, avoiding the problem of uncontrolled ratio distribution.

[0076] Example 2: The total compensation margin of the backup circuit is sufficient, and the flow redistribution within the target logic material group is in normal compensation condition (corresponding to the normal execution branch of step S5).

[0077] This embodiment simultaneously covers two core effective compensation scenarios: dual-loop full complementarity and multi-loop proportional allocation. For the dual physical batching loop operation: Loop #4 is abnormal, loop #3 is on standby, the abnormal loop has a flow gap of 22t / h, the standby loop has an original set flow of 60t / h and an additional 60t / h margin, the total compensation margin is sufficient, the flow gap is fully added to the standby loop, the target set flow is updated to complete the compensation, a second verification confirms the flow meets the standard, and no production capacity is lost. For the three or more multi-loop operation: If one loop is abnormal, the remaining standby loops allocate the flow gap according to the proportion of their respective additional margins to the total compensation margin, automatically matching the multi-loop collaborative compensation logic to achieve optimal flow redistribution within the target logic material group, and stable operation after successful verification. The overall control logic, parameter calculation, and step-by-step execution process of this embodiment are described in reference [reference needed]. Figure 1 The illustrated hierarchical anomaly collaborative control flowchart is executed; the flow dynamic adjustment timing and flow change process in this embodiment are referenced. Figure 2 The flow timing diagram shown is for Figure 2 The corresponding core optimal implementation conditions.

[0078] Example 3: The theoretical total compensation margin of the backup circuit is sufficient, but the on-site material supply is insufficient, and the secondary verification fails, resulting in a fallback and degradation (corresponding to the failure branch of step S6).

[0079] A single loop within a certain logical material group malfunctioned. The calculated total compensation margin exceeded the flow deficit. Step S5, the flow redistribution logic within the target logical material group, was executed normally. The backup loop's set flow was updated, and a secondary verification delay was initiated. However, due to actual operating conditions such as material agglomeration, moisture content fluctuations, material bridging, and supply disruptions, although the theoretical compensation capacity was sufficient, the actual total flow of the material group after the delay failed to reach the formula's set total flow. The system determined that the on-site material supply capacity was insufficient and the group's compensation had failed. It automatically exited the flow redistribution mode and executed a global follow-up control mode to ensure the finished product proportions were qualified, achieving a secondary fault tolerance degradation when the pre-judgment did not match the actual operating conditions.

[0080] The above embodiments 1-3 fully cover all hardware redundancy configuration scenarios applicable to dual-loop, three or more multi-loop systems in this application. The hierarchical abnormal collaborative control method of this application includes the following determination branches: when the compensation condition within the target logical material group does not meet the requirement that the total compensation margin is greater than or equal to the flow gap, the total compensation margin is insufficient, so the system is downgraded and switched to the global follow-up control mode; when the compensation condition within the target logical material group meets the requirement that the total compensation margin is greater than or equal to the flow gap, the system performs flow sharing compensation for the spare loop within the target logical material group and keeps the current formula setting flow of other logical material groups or non-target physical batching loops unchanged; after the secondary verification delay ends, if the actual total flow of the target logical material group reaches its formula setting total flow, the flow redistribution within the group is maintained; if it does not reach the target, the system performs a secondary downgrade, closes the intra-group redistribution, and switches to the global follow-up control mode; at the same time, it is determined whether the relative deviation of the abnormal loop flow returns to the qualified range. If it returns, the system exits the abnormal control mode and returns to step S2; otherwise, the current control mode is maintained.

[0081] Through the above-mentioned graded judgment and fault-tolerant processing, production efficiency can be maintained first under the redundant operating conditions of multiple physical batching loops, and the finished product mixture ratio can be controlled. It is adaptable to all operating conditions and has a wide range of application scenarios. It can fully adapt to the single-loop, dual-loop and three or more loop operating conditions of logic material groups. By adopting the method of allocating the flow gap according to the proportion of the remaining output capacity of the spare loop, it is beneficial to reasonably allocate the compensation flow among the redundant loops, reduce the flow fluctuation of non-target logic material groups, and improve the stability of finished product mixture ratio control.

[0082] It should be noted that, in this document, relational terms such as "first" and "second" are used only to distinguish one entity or operation from another, and do not necessarily require or imply any such actual relationship or order between these entities or operations. Furthermore, the terms "comprising," "including," or any other variations thereof are intended to cover non-exclusive inclusion, such that a process, method, article, or apparatus that comprises a list of elements includes not only those elements but also other elements not expressly listed, or elements inherent to such process, method, article, or apparatus.

[0083] The embodiments have been described above, and such description is not restrictive. The figures shown are only one embodiment, and the actual structure is not limited to this. In short, if a person skilled in the art is inspired by this description and designs a similar structure and embodiment without departing from the inventive spirit, such design should fall within the scope of protection.

Claims

1. A method for stable soil plant grading abnormality cooperative control, characterized by, Includes the following steps: Step S1, parameter configuration and initialization: Divide multiple physical batching loops into corresponding logical material groups according to the type of material being conveyed, set the abnormal control threshold and secondary verification delay time, and determine the initial set flow rate of each physical batching loop based on the total production of the equipment and the mixing ratio of each batching loop; Step S2: Real-time acquisition of the instantaneous actual flow rate of each physical batching circuit and the current operating frequency of the frequency converter, and acquisition of the theoretical supply flow rate of each physical batching circuit; Step S3: Calculate the relative flow deviation between the instantaneous actual flow rate of each physical batching loop and its initial set flow rate; when the relative flow deviation of a physical batching loop exceeds the abnormal control threshold, the loop is identified as an abnormal loop and its target logical material group is located; otherwise, each physical batching loop maintains the original formula's initial set flow rate and returns to step S2. Step S4: Based on the theoretical supply flow rate and initial set flow rate of the backup circuit after excluding the abnormal circuit in the target logical material group, calculate the total compensation margin of the backup circuit and calculate the flow gap caused by the abnormal circuit. Step S5: If the total compensation margin is greater than or equal to the flow gap, the flow in the backup loops within the target logical material group is redistributed. The flow increment to be added to each backup loop and the updated target set flow are calculated and determined. The original formula initial set flow remains unchanged for other physical batching loops except the target logical material group, and a secondary verification delay is started. Otherwise, switch to global follow-up control mode; Step S6: After the second verification delay ends, determine whether the actual total instantaneous flow rate of the target logical material group has reached the initial set total flow rate of its formula; if it has, maintain the flow redistribution within the group; if it has not, turn off the redistribution mode within the group and switch to the global follow-up control mode. Step S7: Determine whether the relative deviation of the flow rate of the abnormal loop has returned to the qualified range. If it has, return to step S2; otherwise, maintain the current control mode.

2. The method for coordinated control of graded anomalies in stabilized soil batching plants according to claim 1, characterized in that, In step S1, the initial set flow rate record for each physical batching loop is determined as follows: .

3. The method for coordinated control of graded anomalies in stabilized soil batching plants according to claim 1, characterized in that, Step S2, which involves obtaining the available flow rate of each physical batching loop, specifically includes the following steps: Step S21: Based on the linear calibration relationship of frequency and flow rate of the weighing scale, the formula for calculating the theoretical flow rate that the inverter matched with the weighing scale for each physical batching circuit can supply under 50Hz operating conditions is as follows: ,in, This represents the instantaneous actual flow rate of each physical batching loop. This refers to the current operating frequency of the frequency converter in each physical batching circuit.

4. The method for coordinated control of graded anomalies in stabilized soil batching plants according to claim 1, characterized in that, The formula for calculating the relative deviation of the flow rate in step S3 is as follows: ,in, The initial flow rate setting for each physical batching loop. This represents the instantaneous actual flow rate of each physical batching loop; when Each physical ingredient loop maintains the initial set flow rate of the original formula and returns to step S2; when The loop was identified as an abnormal loop, and its target logical material group was located. This is the threshold for abnormal control.

5. The method for coordinated control of graded anomalies in stabilized soil batching plants according to claim 1, characterized in that, The formula for calculating the total compensation margin of the backup circuit in step S4 is as follows: ,in, The theoretical supply flow rate for the backup circuit in the target logic material group after excluding abnormal circuits. The initial set flow rate for the backup loop after excluding abnormal loops in the target logic material group; The formula for calculating the flow gap caused by the abnormal loop in step S4 is as follows: Where x is the number of the abnormal loop, The initial flow rate for the abnormal loop. This represents the instantaneous actual flow rate of the abnormal loop.

6. The method for coordinated control of graded anomalies in stabilized soil batching plants according to claim 5, characterized in that, The formula for calculating the required additional flow rate for each backup circuit in step S5 is as follows: ,in, The flow gap caused by the abnormal loop The theoretical supply flow rate for the backup circuit in the target logic material group after excluding abnormal circuits. The initial set flow rate for the backup loop after excluding abnormal loops in the target logic material group. This represents the total compensation margin for the backup circuit; The formula for the updated target flow rate of each backup circuit is as follows: ,in, The additional flow rate required for each backup circuit. The initial set flow rate for the backup loop after excluding abnormal loops in the target logic material group; Computational constraints Complete the assigned traffic values ​​and redistribute traffic within the group. Set the target flow rate for each backup circuit after the update. The theoretical supply flow rate of the backup circuit after excluding abnormal circuits in the target logic material group; In step S5, after switching to the global follow-up control mode, if the relative deviation of the flow rate of the abnormal loop returns to the qualified level (i.e., the relative deviation of the flow rate of the abnormal loop is less than or equal to the abnormal control threshold), then exit the abnormal control mode, and all loops return to the initial set flow rate of the formula, and return to step S2 loop; otherwise, directly return to step S2 loop.

7. The method for coordinated control of graded anomalies in stabilized soil batching plants according to claim 1, characterized in that, In step S6, after disabling the intra-group redistribution mode and switching to the global follow-up control mode, an audible and visual alarm is triggered, and the abnormal event, timestamp, and flow parameters are written into the device operation log. Then, step S7 is executed.

8. The method for coordinated control of graded anomalies in stabilized soil batching plants according to claim 1, characterized in that, In step S5, the start of the secondary verification delay is determined according to the set secondary verification delay time. During the delay time, the actual total instantaneous flow of the target logic material group is not judged in step S6 to determine whether it meets the standard, and the actual total instantaneous flow of the target logic material group is continuously collected.

9. The method for coordinated control of graded anomalies in stabilized soil batching plants according to claim 1, characterized in that, The step S7, determining whether the relative deviation of the flow rate of the abnormal loop has returned to the acceptable range, specifically includes the following steps: Step S71: Determine that the relative deviation of the flow rate of the abnormal loop has returned to the qualified level, that is, the relative deviation of the flow rate of the abnormal loop is less than or equal to the abnormal control threshold: Exit the abnormal control mode, return all loops to the initial set flow rate of the recipe, and return to step S2 to cycle. The abnormal control mode is either intra-group flow redistribution or global follow-up control mode. If the relative flow deviation of the abnormal loop fails to return to the qualified level (i.e., the relative flow deviation of the abnormal loop is greater than the abnormal control threshold), return to step S6, maintain the current control mode, until the relative flow deviation of the abnormal loop returns to the qualified level, then return to step S2 to continue the cyclical acquisition and monitoring. The current control mode is either intra-group flow redistribution or global follow-up control mode.

10. The method for coordinated control of graded anomalies in stabilized soil batching plants according to claim 1, characterized in that, The global follow-up control mode adjusts the formula of each physical batching loop synchronously according to the ratio of the initially set flow rate.

Citation Information

Patent Citations

  • Formula setting quantity follow-up adjustment system and formula setting quantity follow-up adjustment method

    CN104552609A