A Method for Distributed Small-Section Tunneling Disturbance Identification and Co-optimization of Jacking Timing
By establishing a three-dimensional spatial model of the tunnel complex and a dynamic disturbance influence domain, and optimizing the jacking sequence and construction parameters, the problem of accurately reflecting the disturbance influence range in the construction of dispersed small-section tunnel complexes was solved, and dynamic control of construction risks and resource optimization were achieved.
Patent Information
- Application Number
- CN202611262877.7
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2026-08-19
- Publication Date
- 2026-11-17
AI Technical Summary
Existing technologies are unable to accurately reflect the changing characteristics of the disturbance range of decentralized small-section tunnel jacking construction with the tunneling location and time. They lack a unified evaluation of the degree of overlap and recovery status of different jacking disturbances, and the optimization of the construction sequence is difficult to meet the constraints of on-site resources, resulting in the difficulty in controlling construction risks.
By establishing a three-dimensional spatial model of the tunnel complex, dividing the construction sections, identifying the dynamic three-dimensional disturbance influence domain, determining the degree of disturbance superposition, optimizing the jacking sequence and construction parameters, and making rolling adjustments based on on-site monitoring data, the construction plan can be dynamically optimized.
This improved the feasibility of the construction plan and the efficiency of resource utilization, reduced the risk of overlapping construction disturbances, and ensured construction safety and efficiency.
Smart Images

Figure CN123117431A_ABST
Abstract
Description
Technical Field
[0001] This invention relates to the field of underground engineering construction technology, specifically to a method for identifying disturbances and coordinating the timing of jacking in decentralized small-section tunnel groups. Background Technology
[0002] In municipal integrated pipe gallery, water supply and drainage, power and communication, and underground space engineering projects, multiple small-section pipe jacking lines are often scattered and densely arranged within a limited area. These pipes may be parallel, oblique, or stacked vertically. During pipe jacking construction, excavation, jacking, correction, and grouting operations will cause changes in the stress, pore pressure, and deformation state of the surrounding strata. This disturbance will move with the position of the tunneling machine and gradually recover after the machine head passes. When adjacent pipe jacking lines enter the adjacent area before the previous disturbance has been fully recovered, the construction disturbance is likely to be superimposed.
[0003] Current methods for constructing multi-tunnel pipe jacking projects typically determine the impact range based on pipe diameter multiples, jacking clearance, or static numerical analysis, and assess construction risks through pre-set construction sequences or final settlement results. These methods fail to reflect the changing characteristics of the disturbance impact range with tunneling location and time, and lack a unified means to evaluate the overlap and recovery status of different jacking disturbances. Furthermore, current construction sequence optimization often focuses on the overall sequence of jacking operations, making it difficult to further determine the required construction intervals, face offsets, and control ranges of construction parameters for specific construction sections. Simultaneously, constraints on construction resources such as working shafts, hoisting equipment, mud circulation systems, and jacking equipment are usually considered separately from ground disturbance analysis, making some optimization results difficult to implement directly. On the other hand, when measured settlement, displacement, and other responses deviate from predicted results, existing construction sequences and parameters typically lack a mechanism for dynamic adjustment based on monitoring results. Summary of the Invention
[0004] The purpose of this invention is to provide a method for identifying disturbances and co-optimizing the jacking timing of distributed small-section tunnel jacking systems, thereby solving the problems existing in the prior art.
[0005] To achieve the above objectives, the present invention provides the following technical solution: a method for identifying disturbances and co-optimizing the jacking sequence of distributed small-section tunnel groups, comprising: S1, acquiring the spatial location, geological conditions, environmentally sensitive targets, and construction conditions of each jacking pipe in the tunnel group to be constructed, establishing a three-dimensional spatial model of the tunnel group, and dividing each jacking pipe into multiple construction sections; S2, determining the dynamic three-dimensional disturbance influence domain of a single tunnel, which changes with the tunneling location and decays over time as the tunnel head passes, based on the tunneling location, geological conditions, and construction status of each jacking pipe; S3, spatiotemporally superimposing the dynamic three-dimensional disturbance influence domains of different jacking pipes, determining the disturbance superposition degree characterizing the disturbance intensity, influence domain overlap, and time recovery state, and identifying different construction sections based on the disturbance superposition degree. S4. Determine the minimum construction interval and / or minimum face offset between corresponding construction sections of different pipe jacking, with the disturbance superposition degree not exceeding the corresponding allowable disturbance threshold as a constraint; S5. Combining the minimum construction interval and / or minimum face offset with the constraints of construction resource occupation, determine the jacking sequence of each construction section and the construction parameter window corresponding to the disturbance control level, using the construction section as the scheduling unit, to obtain an executable jacking control scheme; S6. Acquire on-site monitoring data during construction, correct the dynamic three-dimensional disturbance influence domain and disturbance superposition degree according to the deviation between the measured response and the predicted response, and continuously update the jacking sequence and construction parameter window of the sections that have not yet been constructed.
[0006] Preferably, step S1 includes obtaining the design axis, pipe diameter, burial depth, coordinates of the launching shaft and the receiving shaft of each jacking pipe, and obtaining one or more of the longitudinal slope, horizontal curve parameters and vertical curve parameters to establish the spatial position relationship of each jacking pipe; obtaining one or more of the soil type, unit weight, cohesion, internal friction angle, compression modulus, permeability coefficient and groundwater level of the corresponding strata along each jacking pipe to establish the geological conditions corresponding to each construction section; obtaining one or more of the surface buildings, roads, existing pipelines and rail transit structures located within the influence range of the jacking pipe construction to determine the environmentally sensitive targets and their spatial relationship with each jacking pipe; obtaining the spatial relationship between working shafts and one or more of the hoisting equipment, soil removal equipment, mud circulation system, jacking pump station, construction team equipment and construction parameters to determine the construction conditions corresponding to each jacking pipe; and dividing each jacking pipe into multiple construction sections along the axial direction based on one or more of the following: the location where geological conditions change, the influence section corresponding to the environmentally sensitive target along the jacking pipe axis, the location where the spatial distance between adjacent jacking pipes changes, the potential disturbance overlap area determined based on the spatial proximity relationship of the jacking pipes, and the section where the allocation of construction resources changes.
[0007] Preferably, step S2 includes using the current center position of the tunneling machine or the working face position of any jacking pipe as a moving reference position; determining the radial distance from the spatial position to be evaluated to the axis of the jacking pipe, and the longitudinal distance of the spatial position to be evaluated relative to the current center position of the tunneling machine or the working face position; determining the radial disturbance attenuation degree based on the radial distance, so that the intensity of construction disturbance decreases as the spatial position to be evaluated moves away from the axis of the jacking pipe; determining the longitudinal disturbance attenuation degree based on the longitudinal distance, so that the intensity of construction disturbance decreases as the spatial position to be evaluated moves away from the current center position of the tunneling machine or the working face position; and determining the longitudinal disturbance attenuation degree based on the geological conditions, pipe diameter, burial depth, and overburden strips. The construction disturbance intensity is corrected based on the conditions and current construction parameters, including at least one of jacking speed, excavation face pressure, grouting volume, grouting pressure, and correction amount. After the tunneling machine passes the axial position corresponding to the spatial location to be evaluated, the degree of disturbance recovery is determined based on the duration after the machine head passes, so that the residual disturbance generated by the previous construction decreases as the duration increases. The construction disturbance intensity at the current moment of the spatial location to be evaluated is determined by comprehensively considering the radial disturbance attenuation degree, the longitudinal disturbance attenuation degree, the formation condition correction result, the pipe diameter and burial depth correction result, the construction parameter correction result, and the disturbance recovery degree.
[0008] Preferably, S2 further includes determining the radial disturbance attenuation degree using an exponential attenuation method, a Gaussian attenuation method, or an attenuation method fitted based on experimental data and historical engineering data that monotonically decreases with increasing radial distance; determining the longitudinal disturbance attenuation degree using an exponential attenuation method, a Gaussian attenuation method, or an attenuation method fitted based on experimental data and historical engineering data that monotonically decreases with increasing longitudinal distance; determining the disturbance recovery degree using a single-stage exponential attenuation method, a multi-stage exponential attenuation method, a segmented attenuation method, or a non-parametric attenuation method fitted based on field monitoring data that monotonically decreases with increasing duration after the random head passes through; determining the radial disturbance influence scale, longitudinal disturbance influence scale, and disturbance recovery rate under different geological conditions and construction states based on at least one of indoor tests, test sections, historical engineering data, and field monitoring data; setting at least one disturbance intensity threshold; determining the set of spatial locations where the construction disturbance intensity reaches or exceeds the corresponding disturbance intensity threshold as a dynamic three-dimensional disturbance influence domain; and forming dynamic three-dimensional disturbance influence domains corresponding to different disturbance intensity levels by setting multiple different disturbance intensity thresholds.
[0009] Preferably, step S3 includes: determining the dynamic three-dimensional disturbance influence domain corresponding to at least two jacking pipes at the same construction moment; determining the overlapping area between different dynamic three-dimensional disturbance influence domains, and obtaining at least one of the overlapping volume and overlapping projected area of the overlapping area; obtaining the construction disturbance intensity corresponding to each jacking pipe in the overlapping area and the residual degree of disturbance of the preceding jacking pipe; determining the geometric coupling degree between different jacking pipes based on at least one of the net distance, intersection angle, relative position between upper and lower sections, and formation anisotropy between the corresponding jacking pipes; and determining the corresponding spatial relationship between the overlapping area and environmentally sensitive targets. Environmental sensitivity weight; the degree of superposition of inter-tunnel disturbance between two jacking pipes is determined by comprehensively considering at least one of the overlapping volume and overlapping projected area, the construction disturbance intensity corresponding to each jacking pipe in the overlapping area, the residual degree of disturbance of the preceding jacking pipe, the degree of geometric coupling, and the environmental sensitivity weight; when there are no less than three jacking pipes involved in the construction, the degree of superposition of inter-tunnel disturbance between each pair of jacking pipes and the degree of common overlap of the dynamic three-dimensional disturbance influence domains of more than three jacking pipes are used to determine the degree of multi-tunnel comprehensive disturbance superposition by weighted combination, nonlinear amplification, selection of maximum disturbance, or combination method calibrated according to test data and historical engineering data.
[0010] Preferably, step S3 further includes dividing the disturbance control level of each construction section into independent disturbance zone, weak coupling zone, strong coupling zone, and prohibited synchronous construction zone according to the disturbance superposition degree from low to high; for independent disturbance zone, the corresponding pipe jacking is allowed to be jacked synchronously or freely staggered; for weak coupling zone, the corresponding pipe jacking must meet at least one of the control requirements of minimum construction interval time and minimum face offset, and the upper limit of jacking speed is reduced and the pressure stability of the excavation face is improved; for strong coupling zone, at least one of the control methods of staggered jacking, waiting, or stopping jacking is implemented for the corresponding pipe jacking, and the jacking speed and single correction amount are reduced, while the grouting guarantee level is improved; for prohibited synchronous construction zone, two or more corresponding faces are prohibited from entering at the same time, and the subsequent pipe jacking is allowed to enter only after the preceding pipe jacking has completed the corresponding construction section and its construction disturbance has recovered to the allowable state; so that different disturbance control levels correspond to different synchronous construction permission conditions, construction interval requirements, face offset requirements, and construction parameter control requirements.
[0011] Preferably, step S4 includes: for corresponding construction sections requiring staggered construction, sequentially changing the entry time of the later-performing jacking pipe into the construction section, and calculating the maximum disturbance superposition degree generated during construction under different entry time conditions; determining the minimum construction interval time as the shortest construction time difference when the maximum disturbance superposition degree does not exceed the allowable disturbance threshold and at least one of the predicted settlement and predicted displacement does not exceed the corresponding allowable value; for corresponding construction sections allowing at least two jacking pipes to be constructed simultaneously, sequentially changing the relative positions between the faces of different jacking pipes, and calculating the maximum disturbance superposition degree generated during construction under different face stagger distances; determining the minimum axial distance that needs to be maintained when the maximum disturbance superposition degree does not exceed the allowable disturbance threshold, or the minimum equivalent stagger distance calculated along the respective axes of different jacking pipes, as the minimum face stagger distance; and determining at least one of the corresponding minimum construction interval time and minimum face stagger distance according to the disturbance control level, geological conditions, and allowable deformation requirements of environmentally sensitive targets in different construction sections.
[0012] Preferably, step S5 includes at least one of the construction resources involved in the construction resource occupancy constraint, including shared working shafts, hoisting channels, excavation equipment, mud circulation systems, jacking pump stations, and construction team equipment. Based on the number of operations allowed for each construction resource within the same time period, corresponding mutual exclusion constraints or capacity constraints are determined. When at least two jacking pipes share the same hoisting channel or hoisting equipment, and the hoisting channel or hoisting equipment is only allowed to perform one hoisting operation within the same time period, the hoisting operations of the corresponding jacking pipe sections are staggered in time. When at least two jacking pipes share the mud circulation system, the total mud treatment demand corresponding to each jacking pipe at the same time does not exceed the mud circulation system's capacity. The allowable processing capacity of the ring system; when at least two jacking pipes share a jacking pump station, and the jacking pump station is only allowed to provide power to the jacking equipment corresponding to one jacking pipe in the same time period, the jacking operations of the corresponding jacking pipes are staggered in time; the construction sequence constraints are determined according to the construction sequence relationship between each construction section, and the construction section is used as the timing adjustment unit. Under the constraints of minimum construction interval time, minimum face offset, construction resource occupation, and construction sequence, multiple candidate jacking sequences are generated, so that different jacking pipe construction sections without disturbance conflicts and construction resource conflicts can be constructed in cross or parallel, and construction sections with disturbance coupling can be controlled by offset, waiting, or jacking stop.
[0013] Preferably, step S5 further includes determining a construction parameter window for the corresponding construction section based on the disturbance control level. The construction parameter window includes the allowable ranges for at least two of the following construction parameters: jacking speed, excavation face control pressure, synchronous grouting volume, compensating grouting volume, grouting pressure, and single-time correction amount. Parameter adjustment thresholds are set for each disturbance control level. When the disturbance superposition degree corresponding to the construction section reaches the parameter adjustment threshold, at least one of the upper limit of jacking speed and the upper limit of single-time correction amount is reduced, and at least one of the excavation face pressure control accuracy and grouting guarantee amount is increased. For construction sections where the disturbance superposition degree reaches the parameter adjustment threshold, the jacking speed is controlled to 60%–80% of the jacking speed when there is no overlap of different dynamic three-dimensional disturbance influence domains in the construction section, and the synchronous grouting volume is controlled to 110%–125% of the synchronous grouting volume when there is no overlap of different dynamic three-dimensional disturbance influence domains in the construction section. The excavation face pressure deviation and single-time correction amount are also limited. Within the corresponding preset allowable range; under the conditions that the disturbance superposition degree corresponding to each construction section does not exceed the preset control upper limit corresponding to the disturbance control level, and meets the constraints of minimum construction interval time, minimum face offset, and construction resource occupation, the candidate jacking sequence is evaluated and screened based on at least two of the following: disturbance superposition degree during construction, predicted maximum settlement or displacement, total construction period, degree of construction resource conflict, and number of shutdowns or equipment switching; the candidate jacking sequence is solved using at least one of the following methods: enumeration search, dynamic programming, mixed integer programming, heuristic search, genetic algorithm, particle swarm optimization, reinforcement learning, or rule-based rolling scheduling; an executable jacking control scheme is determined based on the screened candidate jacking sequence, and the executable jacking control scheme includes at least the allowable start-up conditions, shutdown conditions, minimum construction interval time and / or minimum face offset, allowable synchronous construction state, and allowable range of corresponding construction parameters for each jacking pipe or construction section.
[0014] Preferably, step S6 includes acquiring at least one of the following as field monitoring data during construction: surface settlement, deep stratum displacement, existing pipeline displacement, building and structure settlement, jacking force, mud pressure, excavation face pressure, and tunneling machine posture; determining the corresponding measured response based on the field monitoring data, and acquiring the predicted response corresponding to the measured response; determining the response deviation based on the ratio, difference, or statistical residual between the measured response and the predicted response; correcting at least one of the following based on the response deviation: the spatial influence range of the dynamic three-dimensional disturbance influence domain, the time decay state after the tunnel head passes, and the degree of influence of the construction state on the disturbance intensity; redetermining the disturbance superposition degree based on the corrected dynamic three-dimensional disturbance influence domain; redetermining at least one of the following based on the redetermined disturbance superposition degree: the minimum construction interval time and the minimum face offset corresponding to the unconstructed section; when the measured response meets the preset unfavorable deviation condition relative to the predicted response, the delay... At least one of the following is adopted: extending the minimum construction interval time of the unconstructed section and increasing the minimum face offset, and narrowing the allowable range of the corresponding construction parameter window; when the measured response meets the preset favorable deviation condition relative to the predicted response, and the re-determined disturbance superposition degree does not exceed the corresponding allowable disturbance threshold, at least one of the following is adopted: shortening the minimum construction interval time of the unconstructed section and reducing the minimum face offset; a first monitoring threshold and a second monitoring threshold higher than the first monitoring threshold are preset for the field monitoring data. When the field monitoring data reaches the first monitoring threshold, at least one of the following is adopted: extending the minimum construction interval time, increasing the minimum face offset, and narrowing the construction parameter window according to the disturbance control level of the corresponding construction section; when the field monitoring data reaches the second monitoring threshold, the jacking of at least one pipe jacking in the corresponding construction section is suspended, and the jacking sequence and construction parameter window of the unconstructed section are re-determined to continuously update the executable jacking control scheme.
[0015] As can be seen from the above technical solution, the present invention has the following beneficial effects: This method for identifying disturbances and co-optimizing the jacking sequence in a distributed, small-section tunnel group can more accurately reflect the dynamic characteristics of tunnel construction disturbances as they gradually attenuate with tunneling progress and after the tunnel boring machine passes. By establishing a three-dimensional spatial model of the tunnel group and dividing each jacking section into segments, and combining the tunneling location, geological conditions, and construction status, a dynamic three-dimensional disturbance influence domain that varies with spatial location and time can be constructed. Furthermore, by spatiotemporally superimposing the disturbance influence domains of different jacking sections and determining the degree of superposition, the disturbance severity in different construction sections can be classified and identified, providing a unified basis for risk assessment in tunnel group construction. By determining the minimum construction interval and / or minimum face offset based on the degree of disturbance superposition, and combining this with the constraints of construction resource occupation and construction parameter windows to perform segment-level jacking sequence collaborative optimization, the construction sequence can be transformed into control requirements that can be directly executed on site, improving the feasibility of the construction plan and the efficiency of resource utilization. At the same time, by using on-site monitoring data to make rolling corrections to the dynamic three-dimensional disturbance influence domain, disturbance superposition degree, and subsequent jacking sequence, the construction control plan can be adjusted in a timely manner according to the actual construction response, thereby reducing the risk of disturbance superposition in multi-tunnel pipe jacking construction while taking into account both construction safety and construction efficiency. Attached Figure Description
[0016] Figure 1 This is a flowchart of the method of the present invention; Figure 2 This is a schematic diagram illustrating the spatial relationship of the distributed small-section group of tunnels and the constraints of the shared working well in this invention. Figure 3 This is a two-dimensional projection schematic diagram of the dynamic three-dimensional disturbance influence domain of a single tunnel moving with the position of the tunneling machine according to the present invention; Figure 4 This is a schematic diagram illustrating the decay of disturbance over time after construction and the determination of minimum intermittent time in this invention. Figure 5 This is a schematic diagram illustrating the calculation of the intersection of the influence domains of dynamic disturbances between the two holes and the degree of disturbance superposition according to the present invention. Figure 6 This is a schematic diagram of the hierarchical control zone based on the degree of disturbance superposition and the corresponding construction state of the present invention. Figure 7 This is a schematic diagram illustrating the minimum spatial misalignment control of the two-hole working faces according to the present invention; Figure 8 This is a schematic diagram illustrating the minimum construction interval time for the front and rear tunnels to enter the same coupling zone according to the present invention; Figure 9 This is a schematic diagram illustrating the resource conflict constraints of the shared working well and construction equipment in this invention. Figure 10 This is a schematic diagram of the rolling correction closed loop based on on-site monitoring feedback of the present invention. Detailed Implementation
[0017] The technical solutions of the embodiments of the present invention will be clearly and completely described below with reference to the accompanying drawings. Obviously, the described embodiments are only some embodiments of the present invention, and not all embodiments. Based on the embodiments of the present invention, all other embodiments obtained by those skilled in the art without creative effort are within the scope of protection of the present invention.
[0018] Example 1: As Figure 1 and Figure 10 As shown, this invention provides a technical solution: a method for identifying disturbances and co-optimizing the jacking sequence of distributed small-section tunnel groups, characterized by comprising: S1, acquiring the spatial location, geological conditions, environmentally sensitive targets, and construction conditions of each jacking pipe in the tunnel group to be constructed, establishing a three-dimensional spatial model of the tunnel group, and dividing each jacking pipe into multiple construction sections; S2, determining the dynamic three-dimensional disturbance influence domain of a single tunnel, which changes with the tunneling location and decays over time as the tunnel head passes, based on the tunneling location, geological conditions, and construction status of each jacking pipe; S3, spatiotemporally superimposing the dynamic three-dimensional disturbance influence domains of different jacking pipes, determining the disturbance superposition degree characterizing the disturbance intensity, influence domain overlap, and time recovery state, and identifying different construction sections based on the disturbance superposition degree. S4. Determine the minimum construction interval and / or minimum face offset between corresponding construction sections of different pipe jacking, with the disturbance superposition degree not exceeding the corresponding allowable disturbance threshold as a constraint; S5. Combining the minimum construction interval and / or minimum face offset with the constraints of construction resource occupation, determine the jacking sequence of each construction section and the construction parameter window corresponding to the disturbance control level, using the construction section as the scheduling unit, to obtain an executable jacking control scheme; S6. Acquire on-site monitoring data during construction, correct the dynamic three-dimensional disturbance influence domain and disturbance superposition degree according to the deviation between the measured response and the predicted response, and continuously update the jacking sequence and construction parameter window of the sections that have not yet been constructed.
[0019] In this embodiment, the design axis, starting position, receiving position, jacking direction, overburden thickness and spatial position of each pipe are first obtained, and the geological distribution, groundwater conditions, location of environmentally sensitive targets, and construction conditions such as construction equipment, working wells and construction teams are also obtained. The above information is uniformly entered into a three-dimensional spatial model so that each pipe, various geological formations, environmentally sensitive targets and construction resources correspond in the same spatial coordinate system.
[0020] Construction sections are set up along the jacking direction of each pipe. The boundary of the construction section is determined based on the geological boundary, the boundary of the control range of environmentally sensitive targets, the location of changes in the spatial relationship between adjacent pipes, and the location of changes in construction conditions. The start and end positions, geological type, relationship between adjacent pipes, environmental control requirements, and construction resource occupation of each construction section are recorded. Subsequent disturbance identification and jacking scheduling are all based on the construction section as the processing unit.
[0021] The current working face position is determined based on the real-time position of the pipe jacking machine head, and the disturbance influence range of a single tunnel is determined based on the longitudinal, lateral, and vertical distances between the working face and the surrounding space. The three dimensions of the disturbance influence range are predetermined based on the pipe jacking cross-section size, overburden thickness, stratum parameters, and current construction status. As the machine head advances forward, the disturbance influence range moves synchronously with the working face. After the machine head passes a certain position, the recovery time is recorded from the moment the machine head passes, and the disturbance effect at that position is continuously attenuated according to the predetermined stratum recovery time parameters, thus forming a dynamic three-dimensional disturbance influence domain that moves with the tunneling position and attenuates with the time the machine head passes.
[0022] The dynamic three-dimensional disturbance influence domains of different jacking pipes are spatially superimposed at a unified time. For the same spatial location, the disturbance intensity generated by each jacking pipe, the number of disturbance influence domains covering the location at the same time, and the recovery status of the jacking pipes at the location are statistically analyzed. Then, the disturbance superposition degree is formed according to the calculation rules determined before construction. The disturbance superposition degree corresponds to a unique value, which is used to reflect the degree of disturbance of the joint construction of multiple tunnels at the current time.
[0023] For each construction section, the maximum disturbance superposition degree during construction is calculated, and this value is compared with the pre-set primary and secondary control thresholds. When the maximum disturbance superposition degree does not exceed the primary control threshold, the construction section is identified as a primary disturbance control section; when it exceeds the primary control threshold but does not exceed the secondary control threshold, it is identified as a secondary disturbance control section; when it exceeds the secondary control threshold, it is identified as a tertiary disturbance control section. Each level corresponds to a fixed allowable disturbance threshold and construction parameter window.
[0024] For two construction sections with mutual disturbance relationship, first change the construction start time interval of the two sections and calculate the disturbance superposition degree under each time interval; when the construction time interval reaches the first time value that makes the disturbance superposition degree not exceed the corresponding allowable disturbance threshold, the time value is determined as the minimum construction interval time; for two construction sections that allow synchronous jacking, change the spatial offset distance between the two working faces; when the spatial offset reaches the first distance value that makes the disturbance superposition degree not exceed the allowable disturbance threshold, the distance is determined as the minimum working face offset.
[0025] Using construction sections as scheduling nodes, the scheduling constraints are combined with the sequential order between different construction sections of the same pipe jacking, the minimum construction interval time between different pipe jacking construction sections, the minimum face offset, and the resource occupancy relationship of equipment, working shafts, and construction teams. This determines the start time, end time, construction sequence, and allowed synchronous construction relationship of each construction section, thus forming the jacking sequence.
[0026] The corresponding construction parameter window is invoked according to the disturbance control level of the construction section; the construction parameter window includes one or more of the following: jacking speed range, face pressure range, cutterhead speed range, and grouting pressure range; the construction parameters are read in real time during construction and compared with the parameter window corresponding to the current construction section; when the construction parameters exceed the corresponding range, the operating parameters of the construction equipment are adjusted to make it re-enter the corresponding parameter window.
[0027] During construction, monitoring data on surface settlement, stratum displacement, displacement of environmentally sensitive targets, displacement of underground pipelines, pore water pressure, and operating parameters of construction equipment are acquired according to a fixed collection cycle. The measured response is compared with the predicted response at the same location and time. When the deviation between the two exceeds the model correction threshold set before construction, the disturbance influence range, disturbance intensity, and stratum recovery time parameters are corrected according to the deviation direction and deviation value. Then, the disturbance superposition degree, disturbance control level, minimum construction interval time, and minimum face misalignment of the unconstructed section are recalculated.
[0028] For sections that have been completed, the actual construction records are retained. For sections under construction, the construction status is updated based on the real-time position of the working face. For sections that have not yet been constructed, the jacking sequence and construction parameter windows are re-determined based on the corrected disturbance results.
[0029] Example 2: S1 includes obtaining the design axis, pipe diameter, burial depth, coordinates of the launching shaft and receiving shaft of each jacking pipe, and obtaining one or more of the longitudinal slope, horizontal curve parameters and vertical curve parameters to establish the spatial position relationship of each jacking pipe; obtaining one or more of the soil type, unit weight, cohesion, internal friction angle, compression modulus, permeability coefficient and groundwater level of the corresponding strata along each jacking pipe to establish the geological conditions corresponding to each construction section; obtaining one or more of the surface buildings, roads, existing pipelines and rail transit structures within the influence range of the jacking pipe construction to determine the environmentally sensitive targets and their spatial relationship with each jacking pipe; obtaining the spatial relationship between working shafts and one or more of the hoisting equipment, soil removal equipment, mud circulation system, jacking pump station, construction team equipment and construction parameters to determine the construction conditions corresponding to each jacking pipe; and dividing each jacking pipe into multiple construction sections along the axial direction based on one or more of the following: the location where geological conditions change, the influence section corresponding to the environmentally sensitive target along the jacking pipe axis, the location where the spatial distance between adjacent jacking pipes changes, the potential disturbance overlap area determined based on the spatial proximity relationship of the jacking pipes, and the section where the allocation of construction resources changes.
[0030] In this embodiment, the spatial relationship of each jacking pipe is first established. The starting and ending positions of the jacking pipe axis are determined using the coordinates of the launching shaft and the receiving shaft. The planar coordinates of the straight segments are determined point by point according to the design orientation and axial length. The planar coordinates of each mileage position are determined according to the curve radius, turning angle, and curve length of the horizontal curve segments. The elevation change of the longitudinal slope segments is obtained by multiplying the horizontal distance between adjacent mileage points by the longitudinal slope. The slope and elevation of each mileage position are determined according to the vertical curve parameters. Half of the pipe diameter is extended outward from the axis to form the outer contour of the jacking pipe, thereby obtaining the three-dimensional position of each jacking pipe in a unified coordinate system. The three-dimensional coordinates of the corresponding positions of adjacent jacking pipes are obtained, the spatial distance between the two axes is calculated, and then the radii of the two jacking pipes are subtracted to obtain the net distance between the pipe bodies at the corresponding positions, thereby determining the spatial proximity relationship between each jacking pipe.
[0031] When configuring geological conditions along the pipe jacking axis, the top and bottom surfaces of soil layers and groundwater levels in the exploration data are converted to the corresponding mileage of the pipe jacking axis. When the pipe jacking axis or the outer contour of the pipe body is located between the top and bottom surfaces of a certain soil layer, the soil type, unit weight, cohesion, internal friction angle, compression modulus, and permeability coefficient are assigned to the corresponding mileage position. The groundwater level is determined according to the distance ratio between adjacent exploration points to the corresponding mileage elevation. The location where the outer contour of the pipe jacking intersects with the geological interface is determined as the location of geological condition change and serves as the boundary of the construction section.
[0032] For surface structures, roads, existing pipelines, and rail transit structures, a spatial outline is established based on their actual planar boundaries, structural elevations, foundation areas, or pipeline outlines. The shortest distance between this spatial outline and the outer outline of the pipe jacking is calculated. When the shortest distance is within the construction influence range defined for the project, the corresponding object is identified as an environmentally sensitive target for the pipe jacking. The boundary of the environmentally sensitive target is projected along the pipe jacking axis to obtain the starting and ending mileages within the projection range. Combined with the construction influence range, the corresponding influence segment along the pipe jacking axis is determined. The starting and ending points of the influence segment are used as the segment boundaries.
[0033] Construction conditions are determined based on the actual working shafts and the allocation of construction resources. The service targets and time periods of the pipe jacking, hoisting equipment, excavation equipment, mud circulation system, jacking pump station, and construction team equipment connected to each working shaft are recorded, and the corresponding resources are associated with specific construction sections. The same equipment or construction team can only correspond to one construction section at a time; therefore, when two construction sections call for the same resource, a priority relationship for resource usage is established between them. Jacking speed, face pressure, cutterhead speed, and grouting parameters are recorded according to the corresponding pipe jacking and construction section to determine the construction conditions for each section.
[0034] The potential disturbance overlap zone is determined based on the net distance between adjacent jacking pipes. The net distance between two jacking pipes is calculated continuously along the jacking direction and compared with the sum of the construction influence distances corresponding to the two jacking pipes. When the net distance between the pipes is not greater than the sum of the construction influence distances, the location is determined as the potential disturbance overlap location. The first mileage location and the last mileage location that continuously meet this condition are respectively taken as the start and end points of the potential disturbance overlap zone.
[0035] Finally, the locations of changes in geological conditions, the start and end points of the affected sections of environmentally sensitive targets, the locations of changes in the spatial distance between adjacent pipe jacking sections, the start and end points of the potential disturbance overlap areas, and the locations of changes in construction resource allocation are uniformly converted into the mileage of the pipe jacking axis and arranged sequentially according to the jacking direction. The area between two adjacent boundary positions is determined as one construction section. For each construction section, the corresponding geological conditions, environmentally sensitive targets, net distance between adjacent pipe jacking sections, potential disturbance overlap objects, construction resources, and construction parameters are recorded, thereby completing the division of construction sections along the axial direction for each pipe jacking.
[0036] Example 3: S2 includes using the current center position of the tunneling machine or the working face position of any jacking pipe as the moving reference position; determining the radial distance from the spatial position to be evaluated to the axis of the jacking pipe, and the longitudinal distance of the spatial position to be evaluated relative to the current center position of the tunneling machine or the working face position; determining the radial disturbance attenuation degree based on the radial distance, so that the intensity of construction disturbance decreases as the spatial position to be evaluated moves away from the axis of the jacking pipe; determining the longitudinal disturbance attenuation degree based on the longitudinal distance, so that the intensity of construction disturbance decreases as the spatial position to be evaluated moves away from the current center position of the tunneling machine or the working face position; and considering geological conditions, pipe diameter, burial depth, and overburden conditions. The current construction parameters are used to correct the intensity of construction disturbance. These current construction parameters include at least one of the following: jacking speed, excavation face pressure, grouting volume, grouting pressure, and correction amount. After the tunneling machine passes the axial position corresponding to the spatial location to be evaluated, the degree of disturbance recovery is determined based on the duration after the machine head passes, so that the residual disturbance generated by the previous construction decreases as the duration increases. The intensity of construction disturbance at the spatial location to be evaluated at the current moment is determined by comprehensively considering the degree of radial disturbance attenuation, the degree of longitudinal disturbance attenuation, the result of geological condition correction, the result of pipe diameter and burial depth correction, the result of construction parameter correction, and the degree of disturbance recovery.
[0037] In this embodiment, the center position of the tunnel boring machine is used as the moving reference position; based on the jacking mileage recorded in real time by the construction equipment, the three-dimensional coordinates corresponding to the mileage are determined on the design axis of the tunnel boring machine, and the coordinates are used as the current disturbance calculation benchmark point; the benchmark point position is updated once after each construction data acquisition, so that the disturbance influence position changes synchronously with the advancement of the tunnel boring machine.
[0038] For any spatial location to be evaluated, determine the projection point on the design axis of the tunnel jacking machine that is closest to that location. Calculate the differences between the spatial location to be evaluated and each adjacent node on the axis in three coordinate directions. Square each of the three differences, sum them, and take the square root to obtain the corresponding distances. Use the minimum distance as the radial distance from the spatial location to be evaluated to the tunnel jacking machine axis. Then, calculate the axial length between the projection point and the current center position of the tunneling machine along the design axis, as the longitudinal distance. Record the longitudinal direction based on whether the projection point is located in front of or behind the tunneling machine.
[0039] The degree of radial disturbance attenuation is predetermined based on the monitoring results of the test section. Monitoring points are arranged along the direction perpendicular to the jacking pipe axis. The response value of the monitoring point closest to the jacking pipe axis is used as the benchmark. The response values of the remaining monitoring points are divided by the benchmark response value to obtain the radial attenuation coefficient corresponding to each radial distance. When the actual radial distance is between two calibrated distances, the two corresponding attenuation coefficients are linearly interpolated according to the proportion of the distance between the two distances. Therefore, as the radial distance increases, a correspondingly smaller radial attenuation coefficient is used.
[0040] The degree of longitudinal disturbance attenuation is calibrated based on the measured response at different axial positions in front of and behind the tunnel face. Taking the response value corresponding to the center position of the tunneling machine as the benchmark, the response values of each monitoring position in front of and behind the tunnel face are divided by the benchmark response value to obtain the correspondence between the longitudinal distance and the longitudinal attenuation coefficient. During actual construction, the corresponding coefficient is read according to the current longitudinal distance. When it is between two adjacent calibration distances, linear interpolation is performed according to the distance ratio to determine the current degree of longitudinal disturbance attenuation.
[0041] The geological conditions, pipe diameter, burial depth, and overburden conditions were corrected using a benchmark comparison method. Before construction, a benchmark condition was selected, and the disturbance response under different soil types and corresponding unit weight, cohesion, internal friction angle, compression modulus, and permeability coefficient conditions was compared with the benchmark condition response to obtain the geological correction coefficient. The same method was used to establish the correspondence between pipe diameter, burial depth, and overburden thickness and the correction coefficient. During construction, the corresponding correction coefficient was read according to the actual parameters of the current section. When the parameter was between two adjacent calibration values, linear interpolation was used to determine the value.
[0042] The construction parameter correction is determined based on the real-time values of jacking speed, excavation face pressure, grouting volume, grouting pressure, and correction amount. During the test construction, one construction parameter is changed each time while keeping the other parameters unchanged. The changed monitoring response is divided by the monitoring response under the benchmark construction parameters to obtain the correction coefficient corresponding to that parameter. During the actual construction, the current values of each construction parameter are obtained, and the correction coefficients are determined according to the pre-established correspondence. These correction coefficients are then used sequentially to correct the current disturbance intensity.
[0043] When the center of the tunneling machine passes through the axial projection position corresponding to the spatial position to be evaluated, the passing time is recorded; the duration after the machine head passes is obtained by subtracting the passing time from the current time; before construction, the remaining disturbance response at each time node after the machine head passes is recorded and divided by the disturbance response at the passing time to obtain the correspondence between the duration and the recovery coefficient; during construction, the recovery coefficient is obtained according to the actual duration so that the remaining disturbance generated by the previous construction decreases as the duration increases.
[0044] Finally, based on the baseline disturbance intensity determined by the test section, the results were corrected sequentially using radial attenuation, longitudinal attenuation, stratum correction, pipe diameter correction, burial depth and overburden correction, construction parameter correction, and recovery results after the tunnel boring machine passed through. The obtained values were used as the construction disturbance intensity of the spatial location to be evaluated at the current moment. The above calculations were repeated for each spatial location around the pipe jacking, and the continuous spatial range in which the construction disturbance intensity reached the preset disturbance judgment value was determined as the single-tunnel dynamic three-dimensional disturbance influence domain at the current moment.
[0045] Example 4: S2 further includes determining the radial disturbance attenuation level using an exponential attenuation method, a Gaussian attenuation method, or an attenuation method fitted based on experimental data and historical engineering data, which monotonically decreases with increasing radial distance; determining the longitudinal disturbance attenuation level using an exponential attenuation method, a Gaussian attenuation method, or an attenuation method fitted based on experimental data and historical engineering data, which monotonically decreases with increasing longitudinal distance; determining the disturbance recovery level using a single-stage exponential attenuation method, a multi-stage exponential attenuation method, a segmented attenuation method, or a non-parametric attenuation method fitted based on field monitoring data, which monotonically decreases with increasing duration after the random head passes through; determining the radial disturbance influence scale, longitudinal disturbance influence scale, and disturbance recovery rate under different geological conditions and construction states based on at least one of indoor tests, test sections, historical engineering data, and field monitoring data; setting at least one disturbance intensity threshold, defining the set of spatial locations where the construction disturbance intensity reaches or exceeds the corresponding disturbance intensity threshold as a dynamic three-dimensional disturbance influence domain, and forming dynamic three-dimensional disturbance influence domains corresponding to different disturbance intensity levels by setting multiple different disturbance intensity thresholds.
[0046] In this embodiment, radial disturbance attenuation is determined based on the radial distance from the location to be evaluated to the jacking pipe axis. When using exponential attenuation, the baseline disturbance intensity near the jacking pipe axis is used as the starting value. Based on different radial distances and corresponding disturbance responses obtained from the test section monitoring, the attenuation rate corresponding to a unit radial distance is determined, and then the attenuated disturbance intensity is calculated segment by segment according to the actual radial distance. When using Gaussian attenuation, a correspondence is established between the square of the radial distance and the measured disturbance response. The radial influence scale is obtained by fitting data from each monitoring point, and the corresponding attenuation degree is obtained according to the radial distance of the location to be evaluated during actual calculation. When fitting experimental data or historical engineering data, the radial distance and the measured disturbance response are paired point by point. The minimum sum of the squares of the differences between the fitted result and the measured result is used as the fitting condition to obtain a definite relationship between the radial distance and the degree of disturbance attenuation.
[0047] Longitudinal disturbance attenuation is based on the current center position of the tunnel boring machine or the working face position. The axial distances of the location to be evaluated in front of or behind the working face are calculated respectively. During the construction of the test section, the axial distances and disturbance responses of each monitoring position in front of and behind the working face are recorded, and the disturbance response corresponding to the working face position is used as the benchmark. When using exponential or Gaussian attenuation methods, the longitudinal attenuation relationships in front of and behind the working face are fitted according to the monitoring data respectively. During actual construction, the longitudinal disturbance attenuation degree is obtained by substituting the corresponding attenuation relationship according to the direction and longitudinal distance of the location to be evaluated.
[0048] After the tunneling machine passes the axial position corresponding to the location to be evaluated, the time of passage of the machine head is recorded, and the duration is obtained by subtracting the passage time from the current time. When using single-stage exponential decay, a uniform recovery rate is determined based on the remaining disturbance response at each monitoring time after the machine head passes. When using multi-stage exponential decay, monitoring times are selected sequentially as stage boundary points, and the fitting error of each stage before and after the boundary point is calculated. The time corresponding to the minimum total fitting error is determined as the stage boundary time, and each stage uses a corresponding recovery rate. When using piecewise decay or non-parametric decay, a time series is established according to the field monitoring time and the remaining disturbance response. When the current duration is between two adjacent monitoring times, interpolation is performed according to the time ratio to determine the current disturbance recovery degree.
[0049] The radial disturbance impact scale, longitudinal disturbance impact scale, and disturbance recovery rate were determined separately according to the geological conditions and construction status. Radial distance, longitudinal distance, tunnel boring machine passage time, and corresponding disturbance responses obtained from indoor tests, test sections, historical projects, or field monitoring were categorized, with data from the same soil layer category and the same construction status grouped together. The radial distance corresponding to the disturbance attenuating to the boundary value was determined based on the radial monitoring data, serving as the radial disturbance impact scale. The longitudinal disturbance impact scale was determined using the same method based on the longitudinal monitoring data. The disturbance recovery rate for the geological layer and construction status was determined based on the remaining disturbance change at adjacent monitoring times after the tunnel boring machine's passage and the corresponding time interval.
[0050] The disturbance intensity threshold is determined based on the response control value of the environmentally sensitive target. The construction disturbance intensity at each monitoring location in the test section or the constructed section is matched with the measured settlement, displacement or deformation response at the same location and time to establish a monotonic correspondence between the construction disturbance intensity and the measured response. The early warning value, alarm value or control value determined by the engineering monitoring plan is substituted into this correspondence to obtain the corresponding construction disturbance intensity, which is used as the disturbance intensity threshold of the corresponding level.
[0051] During construction, the current construction disturbance intensity is calculated for each spatial location around the pipe jacking, and compared point by point with the set disturbance intensity threshold. Locations where the construction disturbance intensity reaches or exceeds the corresponding threshold are retained, and the spatially continuous retained locations are connected to form a dynamic three-dimensional disturbance influence domain. When three disturbance intensity thresholds are set, three comparisons are performed respectively to form dynamic three-dimensional disturbance influence domains corresponding to the three disturbance intensity levels.
[0052] Example 5: S3 includes determining the dynamic three-dimensional disturbance influence domain corresponding to at least two jacking pipes at the same construction moment; determining the overlapping area between different dynamic three-dimensional disturbance influence domains, and obtaining at least one of the overlapping volume and overlapping projected area of the overlapping area; obtaining the construction disturbance intensity corresponding to each jacking pipe in the overlapping area and the residual degree of disturbance of the preceding jacking pipe; determining the geometric coupling degree between different jacking pipes based on at least one of the net distance, intersection angle, relative position between upper and lower sections, and formation anisotropy between the corresponding jacking pipes; and determining the corresponding spatial relationship between the overlapping area and environmentally sensitive targets. Environmental sensitivity weight; the degree of superposition of inter-tunnel disturbance between two jacking pipes is determined by comprehensively considering at least one of the overlapping volume and overlapping projected area, the construction disturbance intensity corresponding to each jacking pipe in the overlapping area, the residual degree of disturbance of the preceding jacking pipe, the degree of geometric coupling, and the environmental sensitivity weight; when there are no less than three jacking pipes involved in the construction, the degree of superposition of inter-tunnel disturbance between each pair of jacking pipes and the degree of common overlap of the dynamic three-dimensional disturbance influence domains of more than three jacking pipes are used to determine the degree of multi-tunnel comprehensive disturbance superposition by weighted combination, nonlinear amplification, selection of maximum disturbance, or combination method calibrated according to test data and historical engineering data.
[0053] In this embodiment, the dynamic three-dimensional disturbance influence domains corresponding to each pipe jacking are obtained at the same construction time and unified into the same three-dimensional coordinate system. For any two pipe jackings, the two disturbance influence domains are spatially intersected, and the spatial units located within the two disturbance influence domains are determined as overlapping units. The overlapping volume is determined by multiplying the number of overlapping units by the volume of a single spatial unit. The overlapping projection area is determined by multiplying the number of projection units occupied by the overlapping area after projection onto the horizontal plane by the area of a single projection unit. Repeated projection units are calculated only once.
[0054] For each spatial unit within the overlapping area, the construction disturbance intensity generated by the two jacking pipes at the current moment is calculated according to the method determined in Example 3. When the preceding jacking machine head has passed the corresponding axial position, the construction disturbance intensity when the machine head passes is used as the benchmark. Based on the duration after the machine head passes, the corresponding remaining proportion is obtained from the disturbance recovery relationship established in Example 4. Then, the construction disturbance intensity when passing is multiplied by the remaining proportion to obtain the remaining disturbance intensity of the preceding jacking pipe at the current moment.
[0055] The geometric coupling degree is determined based on the spatial relationship between the two jacking pipes. The shortest distance between the outer contours of the two jacking pipes is calculated along the overlapping section to obtain the net jacking distance. The intersection angle is calculated based on the orientation of the two jacking pipe axes within the overlapping section. The relative vertical positions are determined based on the elevation difference between corresponding positions of the two axes. The anisotropy of the formation is determined by the ratio of the disturbance propagation distance along the bedding plane to the disturbance propagation distance perpendicular to the bedding plane. Before construction, the above parameters are compared item by item with the measured disturbance responses of the test section or historical projects. By adjusting the weights of each parameter, the sum of squares of the differences between the calculated results and the measured responses is minimized. Based on this, the geometric coupling degree calculation parameters used in this project are determined.
[0056] The environmental sensitivity weight is determined based on the spatial relationship between the overlapping area and the environmentally sensitive target. First, the shortest distance from the boundary of the overlapping area to the outer contour of the environmentally sensitive target is calculated. Then, it is calibrated by combining the allowable settlement value, allowable displacement value, or allowable deformation value corresponding to that environmentally sensitive target. The measured response and allowable response values under the same distance conditions in the test section or constructed section are correlated, and the weight corresponding to the smallest sum of squared differences between the calculated response and the measured response is used as the environmental sensitivity weight for that type of environmentally sensitive target.
[0057] When calculating the superposition degree of disturbance between two jacking pipes, the overlapping volume is divided by the smaller of the two disturbance influence domains to obtain the volume overlap ratio. When using the overlapping projected area, the projected area overlap ratio is calculated in the same way. Then, the overlap ratio, the construction disturbance intensity of the two jacking pipes in the overlapping area, the residual disturbance degree of the preceding jacking pipe, the geometric coupling degree, and the environmental sensitivity weights are combined according to the weights determined in the test section. The result is used as the superposition degree of disturbance between the pipes at the current construction moment. Each weight is calculated group by group using test section data, and the weighted group with the smallest sum of squared differences between the calculated result and the measured response is adopted as the value.
[0058] When three or more pipe jacking operations are involved in the construction, the degree of overlap of disturbances between any two pipe jacking operations is first calculated. Then, the spatial area covered by the common influence domains of the three or more pipe jacking operations is determined, and the degree of overlap is obtained by dividing the common overlap volume by the smallest volume among the overlapping disturbance influence domains. When using a weighted combination, the degree of overlap of disturbances between each pair of pipes is combined with the degree of overlap according to the calibration weight. When using nonlinear amplification, the overlap result between the two pipes is corrected according to the calibration relationship between the degree of overlap and the measured disturbance increment. When using the maximum disturbance selection, the maximum value among the degree of overlap of disturbances between each pair of pipes and the corrected degree of overlap is taken. Before construction, the results of each combination method are calculated using experimental data or historical engineering data. The combination method with the smallest sum of squared differences between the calculated results and the measured response is used to determine the comprehensive degree of overlap of disturbances between the multiple pipes.
[0059] Example 6: S3 further includes dividing the disturbance control level of each construction section into independent disturbance zone, weak coupling zone, strong coupling zone, and prohibited synchronous construction zone according to the disturbance superposition degree from low to high; for independent disturbance zone, the corresponding pipe jacking is allowed to be jacked synchronously or freely staggered; for weak coupling zone, the corresponding pipe jacking must meet at least one of the control requirements of minimum construction interval time and minimum face offset, and the upper limit of jacking speed is reduced and the pressure stability of the excavation face is improved; for strong coupling zone, at least one of the control methods of staggered jacking, waiting, or stopping jacking is implemented for the corresponding pipe jacking, and the jacking speed and single correction amount are reduced, while the grouting guarantee level is improved; for prohibited synchronous construction zone, two or more corresponding faces are prohibited from entering at the same time, and the subsequent pipe jacking is allowed to enter only after the preceding pipe jacking has completed the corresponding construction section and its construction disturbance has recovered to the allowable state; so that different disturbance control levels correspond to different synchronous construction permission conditions, construction interval requirements, face offset requirements, and construction parameter control requirements.
[0060] In this embodiment, the disturbance superposition degree of each construction section during the planned construction period is calculated according to Embodiment 5, and four disturbance control levels are divided using three grade boundaries. The first grade boundary is determined based on the disturbance superposition degree corresponding to the point where the double-tunnel construction response in the test section begins to exceed the envelope value of the corresponding single-tunnel construction response and exceeds the allowable error of the monitoring instrument. The second grade boundary is determined based on the disturbance superposition degree corresponding to the point where the engineering monitoring early warning value is reached, derived from the correspondence between the disturbance superposition degree and the measured response on site. The third grade boundary is determined based on the disturbance superposition degree corresponding to the point where the engineering monitoring control value is reached. Construction sections with disturbance superposition degrees not exceeding the first grade boundary are classified as independent disturbance zones, while sections exceeding the first, second, and third grade boundaries are classified as weakly coupled zones, strongly coupled zones, and prohibited synchronous construction zones, respectively.
[0061] Within the independent disturbance zone, no additional construction breaks or face offset constraints caused by tunnel disturbances are set; during scheduling, only the resource occupancy relationship of the working shaft, jacking equipment, soil removal equipment, and construction team is checked. When there is no resource conflict, corresponding pipe jacking is allowed to proceed synchronously; when there is a resource conflict, staggered jacking is arranged according to the resource release time.
[0062] The weak coupling zone is controlled according to the minimum construction interval and minimum face offset determined in Example 1. When time constraints are used, the time when the subsequent pipe jacking enters this section must not be earlier than the time when the previous pipe jacking has completed this section and the minimum construction interval has elapsed. When spatial constraints are used, the spatial distance between the two faces along the corresponding axes is calculated in real time and is not less than the minimum face offset. The upper limit of the jacking speed is determined by adjusting the jacking speed step by step through the test section and selecting the maximum jacking speed corresponding to the measured response not exceeding the warning value. The excavation face pressure is controlled by the target pressure calculated from the current soil layer. The upper and lower limits are determined according to the allowable pressure deviation when the measured response in the test section does not exceed the warning value. During construction, the excavation face pressure is kept within this range.
[0063] In the strongly coupled zone, corresponding tunnel faces are prohibited from being in the same jacking state within the same section according to the construction sequence. After the preceding jacking pipe enters the section, the subsequent jacking pipe waits. If the subsequent jacking pipe has already entered the associated section, the jacking of one of the pipes is stopped until the predetermined construction interval or staggered distance conditions are met. The jacking speed and single correction amount in this section are adjusted in stages through test sections, with the measured response not exceeding the engineering monitoring control value as the selection criterion. The corresponding upper limit is determined from the test parameters that meet this condition. Grouting control is implemented according to the minimum grouting volume, grouting pressure range, and grouting trigger value determined in the test section. Grouting is immediately implemented when the actual grouting volume is lower than the specified value or the monitored settlement reaches the grouting trigger value.
[0064] Within the prohibited synchronous construction zone, the corresponding pipe jacking is set to an exclusive construction relationship, allowing only one working face to enter the zone. After the preceding pipe jacking completes the construction zone, the remaining disturbance is calculated according to the disturbance recovery relationship of claim 4. When the disturbance superposition degree corresponding to the remaining disturbance drops below the third-level limit and the measured response of the environmentally sensitive target does not reach the engineering monitoring control value, the construction mutual exclusion state of the zone is lifted, allowing the subsequent pipe jacking to enter.
[0065] Therefore, each construction section has corresponding synchronous construction permit status, construction interval time, face offset, jacking speed, excavation face pressure, single correction amount and grouting parameter control conditions based on its disturbance control level, which serve as direct constraints for determining the subsequent jacking sequence and construction parameter window.
[0066] Example 7: S4 includes, for corresponding construction sections requiring staggered construction, sequentially changing the entry time of the subsequent jacking pipe into the construction section, and calculating the maximum disturbance superposition degree generated during construction under different entry time conditions; determining the minimum construction interval time as the shortest construction time difference when the maximum disturbance superposition degree does not exceed the allowable disturbance threshold, and at least one of the predicted settlement and predicted displacement does not exceed the corresponding allowable value; for corresponding construction sections allowing at least two jacking pipes to be constructed simultaneously, sequentially changing the relative positions between the faces of different jacking pipes, and calculating the maximum disturbance superposition degree generated during construction under different face staggering distances; determining the minimum axial distance that needs to be maintained when the maximum disturbance superposition degree does not exceed the allowable disturbance threshold, or the minimum equivalent staggering distance calculated along the respective axes of different jacking pipes, as the minimum face stagger; and determining at least one of the corresponding minimum construction interval time and minimum face stagger based on the disturbance control level, geological conditions, and allowable deformation requirements of environmentally sensitive targets in different construction sections.
[0067] In this embodiment, for two construction sections that need to be constructed in a staggered manner, the planned construction time of the preceding pipe jacking is first fixed, and then the time when the subsequent pipe jacking enters the corresponding construction section is postponed in turn by a preset time step. Each time the entry time is changed, the disturbance superposition degree of the two pipe jackings at each calculation time during the entire associated construction period is recalculated according to the method in Embodiment 5, and the maximum value is selected from all calculation results as the maximum disturbance superposition degree corresponding to the construction time difference.
[0068] The permissible disturbance threshold is obtained based on the disturbance control level determined in Example 6. The disturbance superposition degree of the test section or the constructed section is matched with the measured settlement and displacement of the environmentally sensitive target at the same time. The permissible settlement value or permissible displacement value specified in the engineering monitoring plan is used as the control boundary. The disturbance superposition degree corresponding to reaching the control boundary is determined in reverse, and this value is used as the permissible disturbance threshold of the corresponding construction section.
[0069] Predicted settlement or displacement under different construction time differences is determined based on the corresponding data of disturbance superposition degree and measured settlement and displacement in the test section. The measured data are arranged in ascending order of disturbance superposition degree to establish a correspondence between disturbance superposition degree and settlement / displacement. The currently calculated maximum disturbance superposition degree is then substituted into this correspondence to obtain the predicted settlement or displacement. Construction intervals are gradually increased starting from the shortest time difference. When the maximum disturbance superposition degree does not exceed the allowable disturbance threshold, and the predicted settlement or displacement does not exceed the allowable value specified in the project, the construction time difference that first simultaneously meets the above conditions is determined as the minimum construction interval.
[0070] For construction sections where simultaneous construction is permitted, the position of one jacking face is used as a reference, and the position of the other jacking face is adjusted sequentially according to a preset distance step. Each time a set of relative positions of the faces is formed, the disturbance superposition degree during the associated construction period is recalculated, and the maximum value during that period is taken. For parallel or nearly parallel jacking, the axial position difference between the two faces along the jacking direction is directly calculated, and the axial position difference corresponding to the first instance where the maximum disturbance superposition degree does not exceed the allowable disturbance threshold is determined as the minimum axial distance.
[0071] For pipe jacking systems with overlapping or different axial directions, determine the reference mileage point closest to the center of the overlapping area on both pipe jacking axes. Then calculate the axial length from each working face to this reference mileage point. Calculate the difference between the two axial lengths in their respective jacking directions, taking the positive and negative values respectively, and use the absolute value as the equivalent offset distance between the two working faces. Change the working face positions sequentially and recalculate the maximum disturbance superposition. The equivalent offset distance that first ensures the maximum disturbance superposition does not exceed the allowable disturbance threshold is determined as the minimum working face offset.
[0072] Each construction section calls upon the corresponding permissible disturbance threshold according to the disturbance control level. Based on the geological parameters of the section, the disturbance propagation and recovery parameters determined in Examples 3 and 4 are re-adopted, and the permissible settlement or permissible displacement values corresponding to environmentally sensitive targets are used for verification. For sections that require staggered construction, the minimum construction interval time is obtained. For sections that allow synchronous construction but need to maintain spatial separation, the minimum face offset is obtained. For sections that have both time recovery constraints and spatial overlap constraints, two control values are determined simultaneously and used as direct constraints for subsequent jacking sequence determination.
[0073] Example 8: S5 includes at least one of the construction resources involved in the construction resource occupancy constraints, namely, shared working shafts, hoisting channels, excavation equipment, mud circulation systems, jacking pump stations, and construction team equipment. Based on the number of operations allowed for each construction resource within the same time period, corresponding mutual exclusion constraints or capacity constraints are determined. When at least two jacking pipes share the same hoisting channel or hoisting equipment, and the hoisting channel or hoisting equipment is only allowed to perform one hoisting operation within the same time period, the hoisting operations of the corresponding jacking pipe sections are staggered in time. When at least two jacking pipes share the mud circulation system, the total mud treatment demand corresponding to each jacking pipe at the same time is ensured not to exceed the mud circulation system's capacity. The allowable processing capacity of the ring system; when at least two jacking pipes share a jacking pump station, and the jacking pump station is only allowed to provide power to the jacking equipment corresponding to one jacking pipe in the same time period, the jacking operations of the corresponding jacking pipes are staggered in time; the construction sequence constraints are determined according to the construction sequence relationship between each construction section, and the construction section is used as the timing adjustment unit. Under the constraints of minimum construction interval time, minimum face offset, construction resource occupation, and construction sequence, multiple candidate jacking sequences are generated, so that different jacking pipe construction sections without disturbance conflicts and construction resource conflicts can be constructed in cross or parallel, and construction sections with disturbance coupling can be controlled by offset, waiting, or jacking stop.
[0074] In this embodiment, resource occupancy records are first established for the shared working well, hoisting channel, soil removal equipment, mud circulation system, jacking pump station, and construction team equipment, recording the number of operations that each resource is allowed to perform simultaneously within a unit construction period. When the allowed number of operations is 1, the construction section that calls the resource is set to a mutual exclusion relationship, and other construction sections cannot occupy the resource at the same time while any construction section occupies the resource. When the allowed number of operations reaches 2 or more, the resource requirements of each construction section are added together, and the total requirement does not exceed the available capacity of the resource as a capacity constraint.
[0075] For pipe jacking that shares a hoisting channel or hoisting equipment, the hoisting occupancy period is determined based on the planned start time, duration, and end time of hoisting for each pipe section. When the hoisting equipment performs only one hoisting operation in the same time period, the hoisting occupancy periods of different pipe jackings are compared item by item. When time overlap occurs, the later hoisting operation is postponed until after the previous hoisting operation ends, so that the occupancy periods of the two hoisting operations do not overlap.
[0076] When sharing a mud circulation system, the mud treatment requirements for each jacking section in the corresponding time period are determined based on the jacking speed, the amount of mud generated per unit jacking length, and the mud return flow rate of each construction section. The mud treatment requirements of all jacking sections in the jacking state at the same time are added together and compared with the rated treatment capacity of the mud circulation system. When the total demand exceeds the rated treatment capacity, the start time of one construction section is adjusted or its jacking is suspended until the total mud treatment demand at the same time does not exceed the rated treatment capacity.
[0077] When sharing a jacking pump station, the pump station occupancy period shall be established according to the start and end time of each jacking operation; when the jacking pump station can only provide power to one jacking pipe, the occupancy periods of the pump station for each jacking operation shall not overlap; after the previous jacking pipe finishes jacking in its construction section and releases the pump station, the next jacking pipe shall enter the jacking state.
[0078] The sequence of construction sections is determined according to the jacking direction; in the same pipe jacking, the next construction section can only begin after the previous construction section is completed; for sections with the minimum construction interval time described in Example 7, the start time of the subsequent section must also meet the specified construction interval; for construction sections with the minimum face offset requirement, the positions of the two faces are calculated hourly during synchronous jacking, and synchronous construction is maintained only after the actual offset reaches the specified value.
[0079] Based on the above constraints, each construction section is used as the unit for timing adjustment. The start time of each construction section is changed sequentially to form different jacking sequences. For each candidate sequence, the construction intervals, face offsets, resource occupancy, and construction procedure conditions are checked sequentially. If any condition is not met, the candidate sequence is deleted. The completion time of all construction sections is calculated for the retained candidate sequences, and the sequence that satisfies all constraints and has the shortest overall completion time is selected as the jacking execution sequence.
[0080] For construction sections without disturbance conflicts and not occupying the same restrictive construction resources, cross-construction or parallel construction will be arranged after the procedural relationships are satisfied. For construction sections with disturbance coupling, staggered jacking will be arranged based on the minimum face offset and minimum construction interval. Sections that have not yet met the allowable construction conditions will be put on hold. Sections that have entered the associated construction range and whose continued jacking will cause the disturbance constraints to exceed the limits will be stopped until the corresponding control conditions are met again.
[0081] Example 9: S5 further includes determining a construction parameter window for the corresponding construction section based on the disturbance control level. The construction parameter window includes the allowable range of at least two of the following construction parameters: jacking speed, excavation face control pressure, synchronous grouting volume, compensation grouting volume, grouting pressure, and single correction amount. Parameter adjustment thresholds are set for each disturbance control level. When the disturbance superposition degree corresponding to the construction section reaches the parameter adjustment threshold, at least one of the upper limit of jacking speed and the upper limit of single correction amount is reduced, and at least one of the excavation face pressure control accuracy and grouting guarantee amount is increased. For construction sections where the disturbance superposition degree reaches the parameter adjustment threshold, the jacking speed is controlled to 60%–80% of the jacking speed when there is no overlap of different dynamic three-dimensional disturbance influence domains in the construction section, the synchronous grouting volume is controlled to 110%–125% of the synchronous grouting volume when there is no overlap of different dynamic three-dimensional disturbance influence domains in the construction section, and the excavation face pressure deviation and single correction amount are respectively limited. Within the corresponding preset allowable range; under the conditions that the disturbance superposition degree corresponding to each construction section does not exceed the preset control upper limit corresponding to the disturbance control level, and meets the constraints of minimum construction interval time, minimum face offset, and construction resource occupation, the candidate jacking sequence is evaluated and screened based on at least two of the following: disturbance superposition degree during construction, predicted maximum settlement or displacement, total construction period, degree of construction resource conflict, and number of shutdowns or equipment switching; the candidate jacking sequence is solved using at least one of the following methods: enumeration search, dynamic programming, mixed integer programming, heuristic search, genetic algorithm, particle swarm optimization, reinforcement learning, or rule-based rolling scheduling; an executable jacking control scheme is determined based on the screened candidate jacking sequence, and the executable jacking control scheme includes at least the allowable start-up conditions, shutdown conditions, minimum construction interval time and / or minimum face offset, allowable synchronous construction state, and allowable range of corresponding construction parameters for each jacking pipe or construction section. In this embodiment, stable construction data for each construction section without overlapping dynamic three-dimensional disturbance influence domains of different pipe jacking are first used as a benchmark. The jacking speed, excavation face control pressure, synchronous grouting volume, compensation grouting volume, grouting pressure, and single correction amount are recorded. Then, based on the test section data, each construction parameter is adjusted in stages, and the disturbance superposition degree, settlement, and displacement corresponding to each level of parameter are recorded. The parameter value range where the disturbance superposition degree does not exceed the upper limit of the corresponding control level, and the settlement and displacement do not exceed the corresponding allowable values, is determined as the construction parameter window for the corresponding disturbance control level of that construction section.
[0082] The parameter adjustment threshold is determined based on the correspondence between the disturbance superposition degree and the on-site monitoring response. The disturbance superposition degree of each monitoring time in the constructed section is correlated with the settlement or displacement at the same time, and arranged in ascending order of disturbance superposition degree. The disturbance superposition degree corresponding to the first time the monitoring response reaches the engineering monitoring early warning value is determined, and this value is used as the parameter adjustment threshold. Using the same method, the disturbance superposition degree corresponding to the monitoring response reaching the engineering monitoring control value is determined, and this value is used as the upper limit of the control for that disturbance control level. When multiple environmentally sensitive targets exist, the parameter adjustment threshold and upper limit for each target are calculated separately, and the smallest value is used.
[0083] When the disturbance superposition degree of the construction section reaches the parameter adjustment threshold, the jacking speed when there is no overlap of disturbance influence domains in the construction section is used as the benchmark. Candidate values are formed by taking 60%, 65%, 70%, 75%, and 80% of the benchmark jacking speed, respectively. The disturbance superposition degree and predicted settlement or displacement corresponding to each candidate value are calculated. The jacking speed with the largest value among the candidate values that meet the upper limit of disturbance control and allowable deformation requirements is selected as the upper limit of jacking speed for the construction section. Simultaneous grouting volume is formed as candidate values according to 110%, 115%, 120%, and 125% of the benchmark simultaneous grouting volume, respectively. The predicted settlement or displacement corresponding to each candidate value is calculated. The smallest value among the candidate values that meet the control requirements is selected as the control value for simultaneous grouting volume.
[0084] The allowable deviation of excavation face pressure and the upper limit of single correction amount are determined based on test section data. During the test, the excavation face pressure deviation and single correction amount are changed respectively, while keeping other construction parameters constant, and the corresponding disturbance superposition degree and monitoring response are recorded. The maximum pressure deviation corresponding to the disturbance superposition degree not exceeding the parameter adjustment threshold and the monitoring response not exceeding the warning value is determined as the allowable deviation of excavation face pressure; the maximum single correction amount corresponding to the same conditions is determined as the upper limit of single correction amount. The compensation grouting volume and grouting pressure are determined using the same method, based on the correspondence between grouting parameters and settlement control results in the test section, to determine the allowable range.
[0085] The candidate jacking sequence is generated based on the construction section sequence determined in Example 8. For each candidate sequence, the maximum disturbance superposition degree, the predicted maximum settlement or displacement, the total construction period, the number of resource conflicts, and the number of jacking stops, starts, or equipment switching are calculated. First, candidate sequences that exceed the corresponding control limit or do not meet the requirements for minimum construction interval, minimum face offset, and construction resource occupation are deleted. The remaining candidate sequences are sorted in ascending order of maximum disturbance superposition degree. When the maximum disturbance superposition degree is the same, they are then sorted in ascending order of predicted maximum settlement or displacement, total construction period, and number of jacking stops and equipment switching. The candidate sequence ranked first is determined as the execution sequence.
[0086] When using enumeration to search for candidate jacking time sequences, the start time of each construction section is adjusted sequentially with a preset time step, and different construction combinations are formed by combining the sequential relationship of each pipe jacking operation. For each combination formed, the disturbance control conditions, construction interval conditions, face offset conditions, and construction resource conditions are checked, and combinations that do not satisfy any of the constraints are deleted. When using dynamic programming, mixed-integer programming, heuristic search, genetic algorithm, particle swarm optimization, reinforcement learning, or rule-based rolling scheduling, the same construction section constraints and evaluation indicators are used, and the candidate time sequence that satisfies all constraints and has the best evaluation result is taken as the solution.
[0087] Based on the selected jacking sequence, the permissible start-up conditions, stop-up conditions, minimum construction interval, minimum face offset, permissible synchronous construction status, and permissible range of construction parameters are determined for each pipe jacking or construction section. Specifically, jacking can be started when the preceding construction section is completed, construction resources are available, the disturbance superposition degree is below the corresponding control upper limit, and the face offset meets the requirements; jacking is stopped when the disturbance superposition degree reaches the control upper limit, on-site settlement or displacement reaches the engineering monitoring control value, or the actual construction parameters exceed the corresponding parameter window. This forms a construction plan that can be directly used for on-site jacking control.
[0088] Example 10: S6 includes acquiring at least one of the following as field monitoring data during construction: surface settlement, deep stratum displacement, existing pipeline displacement, building and structure settlement, jacking force, mud pressure, excavation face pressure, and tunneling machine attitude; determining the corresponding measured response based on the field monitoring data, and acquiring the predicted response corresponding to the measured response; determining the response deviation based on the ratio, difference, or statistical residual between the measured response and the predicted response; correcting at least one of the following based on the response deviation: spatial influence range of the dynamic three-dimensional disturbance influence domain, time decay state after the tunnel head passes, and degree of influence of construction state on disturbance intensity; redetermining the disturbance superposition degree based on the corrected dynamic three-dimensional disturbance influence domain; redetermining at least one of the following based on the redetermined disturbance superposition degree: minimum construction interval time and minimum face offset corresponding to the unconstructed section; extending the time interval when the measured response meets the preset unfavorable deviation condition relative to the predicted response. At least one of the following is adopted for the unconstructed section: minimum construction interval time and increasing minimum face offset, and narrowing the allowable range of the corresponding construction parameter window; when the measured response meets the preset favorable deviation condition relative to the predicted response, and the re-determined disturbance superposition degree does not exceed the corresponding allowable disturbance threshold, at least one of the following is adopted for the unconstructed section: minimum construction interval time and decreasing minimum face offset; a first monitoring threshold and a second monitoring threshold higher than the first monitoring threshold are preset for the field monitoring data. When the field monitoring data reaches the first monitoring threshold, at least one of the following is adopted for the disturbance control level of the corresponding construction section: minimum construction interval time, increasing minimum face offset, and narrowing the construction parameter window; when the field monitoring data reaches the second monitoring threshold, at least one pipe jacking in the corresponding construction section is suspended, and the jacking sequence and construction parameter window of the unconstructed section are re-determined to continuously update the executable jacking control scheme.
[0089] In this embodiment, during the pipe jacking construction process, data on surface settlement, deep stratum displacement, existing pipeline displacement, building settlement, as well as jacking force, mud pressure, excavation face pressure, and tunneling machine attitude are acquired according to the acquisition cycle of the monitoring scheme. Each monitoring data is then correlated according to the monitoring point coordinates, acquisition time, and corresponding pipe jacking construction mileage to determine the measured response of each monitoring location at the corresponding construction time.
[0090] The predicted response is determined by the calculation results of the current dynamic three-dimensional disturbance influence domain and disturbance superposition degree, and the predicted value at the same location and the same acquisition time as the measured data is selected for comparison. When using the difference judgment, the response deviation is obtained by subtracting the predicted response from the measured response. When using the ratio judgment, the deviation ratio is obtained by dividing the measured response by the predicted response. When using the statistical residual, the average residual and the residual fluctuation range are first calculated using the predicted value and the measured value of the construction stage, and then the degree to which the current response deviates from the existing residual range is determined.
[0091] When the response deviation exceeds the model correction conditions, the dynamic three-dimensional disturbance influence domain is corrected; the spatial influence range is redefined based on the actual distance from the jacking axis and the tunnel face when the measured responses at each monitoring point reach the disturbance boundary value at the same time; the time decay state is redefined based on the ratio of the remaining response at continuous monitoring times after the jacking head passes to the response when the jacking head passes; the degree of construction state correction is recalibrated based on the ratio of the measured responses before and after changes in jacking speed, excavation face pressure, grouting parameters, and correction amount. After the correction is completed, the disturbance superposition degree of each associated construction section is recalculated according to the method of claim 5.
[0092] When redetermining the minimum construction interval and minimum face offset, the calculation process described in Example 7 is adopted; after fixing the actual construction state of the preceding pipe jacking, the entry time of the subsequent section is changed step by step, and the shortest time difference when the disturbance superposition degree does not exceed the allowable disturbance threshold and the predicted settlement or displacement does not exceed the allowable value is taken as the new minimum construction interval; when synchronous construction is allowed, the relative position of the face is changed step by step, and the minimum offset distance corresponding to the first time the disturbance superposition degree meets the allowable condition is taken as the new minimum face offset.
[0093] The adverse deviation conditions are determined based on the predicted and measured responses of the constructed sections. The response deviations of the continuous monitoring data in the early stage of construction are arranged from smallest to largest absolute value, and the minimum deviation corresponding to the measured response reaching the engineering monitoring early warning value is taken as the adverse deviation limit. When the measured response exceeds the predicted response and the response deviation reaches the limit, it is judged as an adverse deviation. At this time, the minimum construction interval time is extended step by step according to the preset adjustment step size or the minimum face offset is increased, and the construction parameter window is re-checked according to Example 9 until the recalculated disturbance superposition degree and predicted response meet the control requirements.
[0094] Favorable deviation conditions are determined based on the same monitoring data. When the measured response is continuously lower than the predicted response, and the absolute value of the deviation reaches the favorable deviation limit calibrated at the beginning of construction, it is judged as a favorable deviation. Under the condition that the recalculated disturbance superposition degree still does not exceed the allowable disturbance threshold, the minimum construction interval time or the minimum face offset is reduced step by step. The disturbance superposition degree and predicted settlement or displacement are recalculated for each adjustment until the boundary conditions corresponding to the allowable disturbance threshold are reached.
[0095] The first and second monitoring thresholds are determined based on the permissible response values of environmentally sensitive targets. The second monitoring threshold uses engineering monitoring control values, while the first monitoring threshold uses engineering monitoring early warning values. For jacking force, mud pressure, excavation face pressure, and tunneling machine attitude, the permissible operating range of the equipment and the early warning and stop-work values in the construction control documents are used, respectively. When the on-site monitoring data reaches the first monitoring threshold, the construction interval, face offset, and construction parameter window are re-checked according to the corresponding disturbance control level, and adjustments are made by extending the interval, increasing the offset, or narrowing the parameter range.
[0096] When the on-site monitoring data reaches the second monitoring threshold, the pipe jacking construction section with the highest correlation to the disturbance at that monitoring location is immediately suspended. The dynamic three-dimensional disturbance influence domain, disturbance superposition degree, minimum construction interval time and minimum working face misalignment are recalculated based on the actual working face position after the suspension and the monitoring data. Then, the jacking sequence and construction parameter window of the unconstructed section are regenerated according to Examples 8 and 9. The actual records of the completed construction section remain unchanged, thereby completing the rolling update of the executable jacking control scheme.
[0097] Although embodiments of the invention have been shown and described, it will be understood by those skilled in the art that various changes, modifications, substitutions and alterations can be made to these embodiments without departing from the principles and spirit of the invention, the scope of which is defined by the appended claims and their equivalents.
Claims
1. A method for collaborative optimization of disturbance identification and jacking timing in distributed small-section tunnel jacking systems, characterized in that: include: S1. Obtain the spatial location, geological conditions, environmentally sensitive targets and construction conditions of each jacking pipe in the tunnel group to be constructed, establish a three-dimensional spatial model of the tunnel group, and divide each jacking pipe into multiple construction sections; S2. Based on the tunneling location, geological conditions, and construction status of each jacking pipe, determine the dynamic three-dimensional disturbance influence domain of a single tunnel that changes with the tunneling location and decays over time as the tunnel head passes through. S3. Spatiotemporally superimpose the dynamic three-dimensional disturbance influence domains of different pipe jacking systems to determine the disturbance superposition degree, which characterizes the disturbance intensity, influence domain overlap, and time recovery state, and identify the disturbance control level of different construction sections based on the disturbance superposition degree. S4. With the disturbance superposition degree not exceeding the corresponding allowable disturbance threshold as a constraint, determine the minimum construction interval time and / or minimum face misalignment between the corresponding construction sections of different pipe jacking. S5. Combining the minimum construction interval time and / or the minimum face offset and construction resource occupation constraints, take the construction section as the scheduling unit, determine the jacking sequence of each construction section and the construction parameter window corresponding to the disturbance control level, and obtain an executable jacking control scheme. S6. During construction, acquire on-site monitoring data, correct the dynamic three-dimensional disturbance influence domain and disturbance superposition degree based on the deviation between the measured response and the predicted response, and continuously update the jacking sequence and construction parameter window for the unconstructed section.
2. The method for identifying disturbances and co-optimizing jacking timing in a distributed small-section tunnel group as described in claim 1, characterized in that: S1 includes: Take the design axis, pipe diameter, burial depth, coordinates of the launching well and the receiving well for each jacking pipe, and obtain one or more of the longitudinal slope, horizontal curve parameters and vertical curve parameters to establish the spatial position relationship of each jacking pipe; Obtain one or more of the following: soil type, unit weight, cohesion, internal friction angle, compression modulus, permeability coefficient and groundwater level along each stratum of the pipe jacking route, and establish the stratum conditions corresponding to each construction section. Acquire one or more of the surface buildings, roads, existing pipelines and rail transit structures located within the influence range of pipe jacking construction, and determine the environmentally sensitive targets and their spatial relationship with each pipe jacking; Obtain the spatial relationship between working shafts, as well as one or more of the following: hoisting equipment, soil removal equipment, mud circulation system, jacking pump station, construction team equipment, and construction parameters, and determine the construction conditions corresponding to each pipe jacking. Based on one or more of the following: the location of changes in geological conditions, the affected section corresponding to environmentally sensitive targets along the pipe jacking axis, the location of changes in the spatial distance between adjacent pipe jacking sections, the potential disturbance overlap area determined based on the spatial proximity of pipe jacking sections, and the section where the allocation of construction resources changes, each pipe jacking section is divided into multiple construction sections along the axial direction.
3. The method for identifying disturbances and co-optimizing jacking timing in a distributed small-section tunnel group as described in claim 1, characterized in that: S2 includes: The current center position of the tunneling machine or the working face position of any pipe jacking machine is used as the reference position for movement; Determine the radial distance from the spatial location to be evaluated to the axis of the jacking pipe, and the longitudinal distance of the spatial location to be evaluated relative to the current center position of the tunneling machine or the working face position; The radial disturbance attenuation degree is determined based on the radial distance, so that the intensity of construction disturbance decreases as the spatial location to be evaluated moves away from the axis of the pipe jacking. The degree of longitudinal disturbance attenuation is determined based on the longitudinal distance, so that the intensity of construction disturbance decreases as the spatial location to be evaluated moves away from the current center position of the tunneling machine or the working face position; The intensity of construction disturbance is corrected based on the geological conditions, pipe diameter, burial depth, overburden conditions, and current construction parameters. The current construction parameters include at least one of the following: jacking speed, excavation face pressure, grouting volume, grouting pressure, and correction amount. After the tunneling machine passes through the axial position corresponding to the spatial position to be evaluated, the degree of disturbance recovery is determined based on the duration after the machine head passes through, so that the residual disturbance generated by the previous construction decreases as the duration increases; By comprehensively considering the radial disturbance attenuation degree, the longitudinal disturbance attenuation degree, the formation condition correction results, the pipe diameter and burial depth correction results, the construction parameter correction results, and the disturbance recovery degree, the construction disturbance intensity at the current moment of the spatial location to be evaluated is determined.
4. The method for identifying disturbances and co-optimizing jacking timing in a distributed small-section tunnel group as described in claim 3, characterized in that: S2 further includes: The degree of radial disturbance attenuation is determined by adopting an exponential attenuation method that monotonically decreases with increasing radial distance, a Gaussian attenuation method, or an attenuation method obtained by fitting experimental data and historical engineering data; The degree of longitudinal disturbance attenuation is determined by adopting an exponential attenuation method that monotonically decreases with increasing longitudinal distance, a Gaussian attenuation method, or an attenuation method obtained by fitting experimental data and historical engineering data; The degree of disturbance recovery is determined by using a single-stage exponential decay method that monotonically decreases as the duration of the random head passes through, a multi-stage exponential decay method, a segmented decay method, or a non-parametric decay method obtained by fitting field monitoring data. Based on at least one of indoor tests, test sections, historical engineering data, and field monitoring data, determine the radial disturbance impact scale, longitudinal disturbance impact scale, and disturbance recovery rate under different geological conditions and construction states. Set at least one disturbance intensity threshold, and determine the set of spatial locations where the construction disturbance intensity reaches or exceeds the corresponding disturbance intensity threshold as a dynamic three-dimensional disturbance influence domain. By setting multiple different disturbance intensity thresholds, dynamic three-dimensional disturbance influence domains corresponding to different disturbance intensity levels are formed.
5. The method for identifying disturbances and co-optimizing jacking timing in a distributed small-section tunnel group as described in claim 1, characterized in that: S3 includes: Determine the dynamic three-dimensional disturbance influence domain corresponding to at least two pipe jacking operations at the same construction moment; Determine the overlapping regions between different dynamic three-dimensional disturbance influence domains, and obtain at least one of the overlapping volume and overlapping projected area of the overlapping regions; Obtain the construction disturbance intensity corresponding to each pipe jacking in the overlapping area and the remaining degree of disturbance from the preceding pipe jacking; The degree of geometric coupling between different jacking pipes is determined based on at least one of the following: net distance between corresponding jacking pipes, cross angle, relative vertical position, and formation anisotropy. Based on the spatial relationship between the overlapping areas and environmentally sensitive targets, the environmental sensitivity weights corresponding to the overlapping areas are determined. The degree of overlap of the tunnel disturbance between the two tunnel jacking pipes is determined by taking into account at least one of the overlapping volume and overlapping projected area, the construction disturbance intensity corresponding to each jacking pipe in the overlapping area, the residual degree of disturbance of the preceding jacking pipe, the degree of geometric coupling, and the environmental sensitivity weight. When there are no fewer than three pipe jackings involved in the construction, the degree of superposition of multi-hole comprehensive disturbance is determined by weighted combination, nonlinear amplification, selection of maximum disturbance, or combination method based on test data and historical engineering data, according to the degree of superposition of disturbance between the two pipe jackings and the degree of overlap of the dynamic three-dimensional disturbance influence domains of the three or more pipe jackings.
6. The method for identifying disturbances and co-optimizing jacking timing in a distributed small-section tunnel group as described in claim 5, characterized in that: S3 further includes: Based on the degree of disturbance superposition from low to high, the disturbance control level corresponding to each construction section is divided into independent disturbance zone, weak coupling zone, strong coupling zone and prohibited synchronous construction zone. For independent disturbance zones, synchronous or staggered pipe jacking is permitted. For weakly coupled zones, the corresponding jacking pipe should meet at least one of the control requirements of minimum construction interval time and minimum face misalignment, and the upper limit of jacking speed should be reduced and the pressure stability of the excavation face should be improved. For the strong coupling zone, implement at least one of the following control measures for the corresponding pipe jacking: staggered jacking, waiting, or stopping jacking, and reduce the jacking speed and the amount of correction per time, while improving the grouting guarantee level. For areas where synchronous construction is prohibited, two or more corresponding tunnel faces are prohibited from entering at the same time. Subsequent tunnel jacking is only allowed to enter after the preceding tunnel jacking has completed its corresponding construction section and its construction disturbance has been restored to an acceptable state. Different disturbance control levels correspond to different synchronous construction permit conditions, construction interval requirements, face offset requirements, and construction parameter control requirements.
7. The method for identifying disturbances and co-optimizing jacking timing in a distributed small-section tunnel group as described in claim 1, characterized in that: S4 includes: For corresponding construction sections that need to be staggered, the time when the later construction pipe jacking enters the construction section is changed in turn, and the maximum degree of disturbance superposition during construction under different entry time conditions is calculated. The shortest construction time difference when the maximum disturbance superposition degree does not exceed the allowable disturbance threshold and at least one of the predicted settlement and predicted displacement does not exceed the corresponding allowable value is determined as the minimum construction interval time. For the corresponding construction section where at least two pipe jackings are allowed to be constructed simultaneously, the relative positions between the different pipe jacking faces are changed sequentially, and the maximum degree of disturbance superposition during construction is calculated under the different staggered distances of the pipe faces. The minimum axial distance that needs to be maintained when the maximum disturbance superposition does not exceed the allowable disturbance threshold, or the minimum equivalent offset distance calculated along the respective axes of different jacking pipes, is determined as the minimum face offset. Based on the disturbance control level, geological conditions, and allowable deformation requirements of environmentally sensitive targets in different construction sections, at least one of the following is determined: minimum construction interval time and minimum face misalignment.
8. The method for identifying disturbances and co-optimizing jacking timing in a distributed small-section tunnel group as described in claim 1, characterized in that: S5 includes: The construction resources involved in the construction resource occupancy constraints include at least one of the following: shared working well, hoisting channel, soil removal equipment, mud circulation system, jacking pump station, and construction team equipment. Based on the number of operations that each construction resource is allowed to perform in the same time period, the corresponding mutual exclusion constraints or capacity constraints are determined. When at least two jacking pipes share the same hoisting channel or hoisting equipment, and the hoisting channel or hoisting equipment is only allowed to perform one hoisting operation at the same time, the hoisting operations of the corresponding jacking pipe sections shall be staggered in time. When at least two pipe jackings share a mud circulation system, the total mud treatment demand of each pipe jacking at any given time shall not exceed the allowable processing capacity of the mud circulation system. When at least two pipe jacking operations share a jacking pump station, and the jacking pump station is only allowed to provide power to the jacking equipment corresponding to one pipe jacking operation at the same time, the jacking operations of the corresponding pipe jacking operations are staggered in time. Based on the construction sequence relationship between each construction section, the construction procedure constraints are determined, and the construction section is used as the timing adjustment unit. Multiple candidate jacking sequences are generated under the constraints of minimum construction interval time, minimum face offset, construction resource occupation, and construction procedure. This allows different pipe jacking construction sections without disturbance conflicts or construction resource conflicts to carry out cross-construction or parallel construction, and allows construction sections with disturbance coupling to implement offset, waiting, or jacking stop control.
9. The method for identifying disturbances and co-optimizing jacking timing in a distributed small-section tunnel jacking system according to claim 8, characterized in that: The S5 also includes: Based on the disturbance control level, a construction parameter window is determined for the corresponding construction section. The construction parameter window includes the allowable range of at least two of the following construction parameters: jacking speed, excavation face control pressure, synchronous grouting volume, compensation grouting volume, grouting pressure, and single correction volume. For each disturbance control level, parameter adjustment thresholds are set. When the disturbance superposition degree corresponding to the construction section reaches the parameter adjustment threshold, at least one of the upper limit of jacking speed and the upper limit of single correction amount is reduced, and at least one of the excavation face pressure control accuracy and grouting guarantee amount is increased. For construction sections where the degree of disturbance superposition reaches the parameter adjustment threshold, the jacking speed is controlled to 60% to 80% of the jacking speed when there is no overlap of different dynamic three-dimensional disturbance influence domains of pipe jacking in the construction section, the synchronous grouting volume is controlled to 110% to 125% of the synchronous grouting volume when there is no overlap of different dynamic three-dimensional disturbance influence domains of pipe jacking in the construction section, and the excavation face pressure deviation and single correction amount are limited to the corresponding preset allowable ranges. Under the conditions that the degree of disturbance superposition in each construction section does not exceed the preset control limit corresponding to the disturbance control level, and meets the constraints of minimum construction interval time, minimum face offset and construction resource occupation, the candidate jacking sequence is evaluated and screened based on at least two of the following: degree of disturbance superposition during construction, predicted maximum settlement or displacement, total construction period, degree of construction resource conflict and number of shutdowns or equipment switching. The candidate top-up time series is solved by using at least one of the following methods: enumeration search, dynamic programming, mixed integer programming, heuristic search, genetic algorithm, particle swarm optimization, reinforcement learning, or rule-based rolling scheduling. Based on the candidate jacking sequence obtained through screening, an executable jacking control scheme is determined. The executable jacking control scheme includes at least the allowable start-up conditions, stop-jacking conditions, minimum construction interval time and / or minimum face misalignment, allowable synchronous construction status, and allowable range of corresponding construction parameters for each jacking pipe or construction section.
10. The method for identifying disturbances and co-optimizing jacking timing in a distributed small-section tunnel jacking system according to claim 1, characterized in that: S6 includes: During construction, at least one of the following data should be collected as on-site monitoring data: surface settlement, deep stratum displacement, existing pipeline displacement, building and structure settlement, jacking force, mud pressure, excavation face pressure, and tunneling machine posture. The corresponding measured response is determined based on the on-site monitoring data, and the predicted response corresponding to the measured response is obtained. The response deviation is determined based on the ratio, difference, or statistical residual between the measured response and the predicted response. Based on the response deviation, at least one of the following is corrected: the spatial influence range of the dynamic three-dimensional disturbance influence domain, the time decay state after the machine head passes, and the degree of influence of the construction state on the disturbance intensity. The disturbance superposition degree is then redetermined based on the corrected dynamic three-dimensional disturbance influence domain. Based on the redefined disturbance superposition degree, at least one of the minimum construction interval time and minimum face offset corresponding to the unconstructed section is redefined; When the measured response meets the preset unfavorable deviation condition relative to the predicted response, at least one of the following is adopted: extending the minimum construction interval time of the unconstructed section and increasing the minimum face offset, and narrowing the allowable range of the corresponding construction parameter window; when the measured response meets the preset favorable deviation condition relative to the predicted response, and the re-determined disturbance superposition degree does not exceed the corresponding allowable disturbance threshold, at least one of the following is adopted: shortening the minimum construction interval time of the unconstructed section and decreasing the minimum face offset. For on-site monitoring data, a first monitoring threshold and a second monitoring threshold higher than the first monitoring threshold are preset. When the on-site monitoring data reaches the first monitoring threshold, at least one of the following is adjusted according to the disturbance control level of the corresponding construction section: extending the minimum construction interval time, increasing the minimum face offset, and narrowing the construction parameter window. When the on-site monitoring data reaches the second monitoring threshold, the jacking of at least one pipe jacking in the corresponding construction section is suspended, and the jacking sequence and construction parameter window of the unconstructed sections are re-determined to continuously update the executable jacking control scheme.