Construction engineering pile

By adopting the design of annular structures, ground nails and plug-in components in construction engineering piles, the horizontal reinforcement of the pile body and the improvement of concrete strength are achieved, which solves the problems of pile body shaking and concrete cracking in the existing technology, and improves the quality of engineering piles. stability and safety performance.

CN221798411UActive Publication Date: 2024-10-01PANJIN HUANBANG CONSTR ENG CO LTD
View PDF 0 Cites 1 Cited by

Patent Information

Application Number
CN202420356726.8
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-02-27
Publication Date
2024-10-01
Estimated Expiration
2034-02-27

AI Technical Summary

Technical Problem

Existing construction piles are prone to shaking during construction, and concrete is prone to cracking during use, resulting in insufficient stability and safety performance.

Method used

Design a construction engineering pile with an annular structure and a ground nail fixed at the bottom. The pile body is provided with through holes and side plug-in components. The plug-in component includes a moving rod and a ball. Through the cooperation of the plug-in component and the pouring component, the pile is realized. Horizontal reinforcement of the body and improvement of the strength of the concrete.

Benefits of technology

It improves the stability of the pile body in the pile hole, avoids concrete cracking, enhances the overall strength and safety performance of the engineering pile, and reduces safety hazards.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN221798411U_ABST
    Figure CN221798411U_ABST
Patent Text Reader

Abstract

The utility model discloses a constructional engineering pile which comprises a pile body, a plurality of ground nails are evenly and fixedly connected to the bottom end of the pile body, a plurality of through holes are evenly formed in the pile body, a side inserting assembly is arranged in each through hole, and four inserting assemblies are evenly arranged on the inner wall of the pile body. And a plurality of pouring assemblies are uniformly arranged between the inserting assemblies. Compared with the prior art, the stability of the pile body in a pile hole can be improved through the side inserting assembly, the situation that the structural strength of the engineering pile is affected by shaking of the pile body block in the concrete pouring process is avoided, the poured concrete is reinforced through the pouring assembly, stress concentration is avoided, and the construction quality is improved. Therefore, the phenomenon that concrete in the pile body cracks in the using process of the engineering pile is reduced, the strength of the whole engineering pile is improved, the quality and safety performance of the engineering pile are improved, and potential safety hazards are reduced.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of engineering piles, in particular to a building engineering pile. Background Art

[0002] Engineering piles are piles used in engineering projects, and they are ultimately used in buildings and structures to bear forces. Engineering piles are piles used on engineering entities and must bear certain loads. Engineering piles can be divided into two categories according to the construction method: prefabricated piles and cast-in-place piles. Cast-in-place piles are holes directly drilled at the designed pile positions. They have a circular cross-section. After the holes are formed, steel cages are placed in the holes and concrete is poured. They are used in urban buildings. During the construction process, the pre-buried holes must first be drilled. When the pre-buried holes are drilled to a sufficient depth, the engineering piles are then buried in the pre-buried holes. Finally, the interior of the engineering piles is filled with irrigated concrete.

[0003] A Chinese patent with publication number CN220394513U discloses a construction engineering pile; it includes a pile body, a pile tip and a connecting piece, the pile tip is arranged at the bottom of the pile body, the pile body includes a plurality of overlapping pile rings, a connecting piece is respectively arranged between every two adjacent pile rings, and the pile ring at the bottom layer is connected to the pile tip; the connecting piece includes a connecting rod, a rotating shaft, a triangular fixing block and an elastic piece, the top of the pile ring has a first fixing groove, the connecting rod is fixedly connected to the pile ring and is located at the bottom of the pile ring, the rotating shaft is rotatably connected to the connecting rod, the triangular fixing block is fixedly connected to the rotating shaft, the two ends of the elastic piece are respectively connected to the connecting rod and the triangular fixing block, and the triangular fixing block is adapted to the first fixing groove. Through the above structure, the effect of adjusting the length of the construction engineering pile according to the actual construction situation is obtained.

[0004] However, when the construction pile is used, it is fixed by the pressure of the soil in the pile hole, just like the existing technology. It does not have a good lateral reinforcement function. The pile is easy to shake in the pile hole, which reduces the stability. Secondly, after the construction pile is installed and concrete is poured into the pile ring, the concrete is easy to crack over time, which directly affects the quality and safety performance of the pile and poses certain safety hazards. Therefore, we propose a new construction pile. Utility Model Content

[0005] The main purpose of the utility model is to provide a construction engineering pile, which can effectively solve the problems in the background technology.

[0006] To achieve the above-mentioned purpose, the technical solution adopted by the utility model is: a construction engineering pile, including a pile body, a plurality of ground nails are evenly fixedly connected to the bottom end of the pile body, a plurality of through holes are evenly opened on the pile body, a side plug-in component is arranged in each through hole, four plug-in components are evenly arranged on the inner wall of the pile body, and a plurality of casting components are evenly arranged between the plug-in components.

[0007] As a further description of the above technical solution, the pile body is an annular structure, and a plurality of through holes are evenly distributed in four rows on the pile body, and the four plug-in components correspond one by one to the four rows of through holes respectively.

[0008] As a further description of the above technical solution, the side insertion assembly includes a moving rod, one end of which is evenly and fixedly connected to a plurality of pins, the other end of which is rollingly connected to a ball, a limiting ring and a fixing ring are sleeved on the moving rod, and a spring is fixedly connected between the limiting ring and the fixing ring.

[0009] As a further description of the above technical solution, the moving rod is slidably connected to the limiting ring, the diameter of the ball is smaller than the aperture of the through hole, the limiting ring is fixedly connected to the end of the through hole away from the ball, and the fixing ring is fixedly sleeved on the moving rod.

[0010] As a further description of the above technical solution, the plug-in assembly includes a fixing bar and a plug-in bar, a sliding groove is provided on one side of the fixing bar, and a plurality of slope grooves are evenly provided on one side of the plug-in bar.

[0011] As a further description of the above technical solution, the side of the slide groove on the fixed bar is fixedly connected to the inner wall of the pile body, and is adapted to the plug-in bar and the slide groove, and is slidably connected. The slide groove is connected to the through hole, and the number of the slope grooves is the same as the number of through holes in each column.

[0012] As a further description of the above technical solution, the casting assembly includes two first hanging rings and two second hanging rings, a first connecting rod is arranged between the two first hanging rings, a second connecting rod is arranged between the two second hanging rings, and both ends of the first connecting rod and the second connecting rod are fixedly connected with L-shaped hooks.

[0013] As a further description of the above technical solution, the two first hanging rings are respectively fixedly connected to two opposite fixing bars, and the two second hanging rings are respectively fixedly connected to another two opposite fixing bars. The L-shaped hook matches the first hanging ring and the second hanging ring. The L-shaped hooks at both ends of the first connecting rod are respectively hooked in the circular holes of the two first hanging rings, and the L-shaped hooks at both ends of the second connecting rod are respectively hooked in the circular holes of the two second hanging rings, and the first connecting rod and the second connecting rod are staggered downward.

[0014] Compared with the prior art, the utility model has the following beneficial effects:

[0015] 1. By arranging the pile body, ground nails, through holes, side plug-in components and plug-in components in coordination, the mobile rod on the side plug-in component can be moved in the through hole through the plug-in component, so that the plug-in nails on the mobile rod can be inserted into the soil of the pile hole, so that the entire pile body itself has the function of horizontal reinforcement in the pile hole, which can improve the stability of the pile body in the pile hole and avoid the shaking of the pile body block during the concrete pouring process to affect the structural strength of the engineering pile.

[0016] 2. By arranging the pile body, the plug-in assembly and the pouring assembly in coordination, a number of pouring assemblies are longitudinally distributed in the internal space of the pile body, and the pouring assembly is fixedly connected with the fixing strips on the plug-in assembly. After pouring the concrete, stress concentration can be effectively prevented and the strength of the concrete can be improved, thereby reducing the cracking of the concrete in the pile body during the use of the engineering pile, increasing the strength of the entire engineering pile, improving the quality and safety performance of the engineering pile, and reducing safety hazards. BRIEF DESCRIPTION OF THE DRAWINGS

[0017] Figure 1 This is a schematic diagram of the overall structure of a construction engineering pile of the utility model;

[0018] Figure 2 This is a cross-sectional view of the overall structure of a construction engineering pile of the utility model;

[0019] Figure 3 It is a partial structural cross-sectional view of a plug-in strip of a construction engineering pile in an inserted state according to the utility model;

[0020] Figure 4 This is a schematic diagram of the structure of a side-insertion component of a construction engineering pile according to the utility model;

[0021] Figure 5 The utility model is a schematic diagram of a casting assembly structure of a construction engineering pile.

[0022] In the figure: 1. pile body; 2. ground nail; 3. through hole; 4. side plug assembly; 5. plug assembly; 6. casting assembly; 41. moving rod; 42. plug nail; 43. ball; 44. limit ring; 45. fixing ring; 46. spring; 51. fixing strip; 52. plug strip; 53. slide groove; 54. slope groove; 61. first hanging ring; 62. second hanging ring; 63. first connecting rod; 64. second connecting rod; 65. L-shaped hook. DETAILED DESCRIPTION

[0023] In order to make the technical means, creative features and purpose effects achieved by the present invention easy to understand, the present invention is further described below in conjunction with specific implementation methods.

[0024] In the description of the present invention, it should be noted that the terms "upper", "lower", "inner", "outer", "front end", "rear end", "two ends", "one end", "the other end" and the like indicate positions or positional relationships based on the positions or positional relationships shown in the drawings, and are only for the convenience of describing the present invention and simplifying the description, and do not indicate or imply that the device or element referred to must have a specific orientation, be constructed and operate in a specific orientation, and therefore cannot be understood as a limitation on the present invention. In addition, the terms "first" and "second" are used for descriptive purposes only and cannot be understood as indicating or implying relative importance.

[0025] In the description of the present invention, it should be noted that, unless otherwise clearly specified and limited, the terms "installed", "provided with", "connected", etc. should be understood in a broad sense. For example, "connected" can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection, or it can be an indirect connection through an intermediate medium, or it can be the internal communication of two components. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.

[0026] See also Figure 1-5 The utility model provides a technical solution: a construction engineering pile includes a pile body 1, the pile body 1 is an annular structure, a plurality of ground nails 2 are evenly fixedly connected to the bottom end of the pile body 1, a plurality of through holes 3 are evenly opened on the pile body 1, and the plurality of through holes 3 are evenly distributed on the pile body 1 in four rows, and a side plug assembly 4 is arranged in each through hole 3, and the side plug assembly 4 includes a moving rod 41, and the end of the moving rod 41 away from the inside of the pile body 1 is evenly fixedly connected with a plurality of plug nails 42, and the end of the moving rod 41 close to the inside of the pile body 1 is rollingly connected with a ball 43, and the diameter of the ball 43 is smaller than the aperture of the through hole 3, and a limiting ring 44 and a fixing ring 45 are sleeved on the moving rod 41, and the moving rod 41 is slidably connected with the limiting ring 44, and the limiting ring 44 is fixedly connected to the end of the through hole 3 away from the ball 43, and the fixing ring 45 is fixedly sleeved on the moving rod 41, and the limiting ring 44 is adapted to the through hole 3 and is slidably connected, and a spring 46 is fixedly connected between the limiting ring 44 and the fixing ring 45.

[0027] Four plug-in components 5 are evenly arranged on the inner wall of the pile body 1, and the four plug-in components 5 correspond to the four rows of through holes 3 respectively. The plug-in components 5 include a fixing bar 51 and a plug-in bar 52. The side where the slide groove 53 is located on the fixing bar 51 is fixedly connected to the inner wall of the pile body 1. A slide groove 53 is opened on one side of the fixing bar 51, and the slide groove 53 is connected to the through hole 3. The plug-in bar 52 is adapted to the slide groove 53 and is slidably connected. A plurality of slope grooves 54 are evenly opened on one side of the plug-in bar 52, and the number of the slope grooves 54 is the same as the number of each row of through holes 3.

[0028] A plurality of casting assemblies 6 are evenly fixedly connected between the four fixing bars 51 from top to bottom. The casting assemblies 6 include two first hanging rings 61 and two second hanging rings 62. The two first hanging rings 61 are respectively fixedly connected to the two opposite fixing bars 51 and are on the same horizontal plane. The two second hanging rings 62 are respectively fixedly connected to the other two opposite fixing bars 51 and are on the same horizontal plane. The positions of the two second hanging rings 62 are lower than the positions of the two first hanging rings 61. There is a A first connecting rod 63 and a second connecting rod 64 are arranged between the two second hanging rings 62. The first connecting rod 63 and the second connecting rod 64 are staggered downwardly. Both ends of the first connecting rod 63 and the second connecting rod 64 are fixedly connected with L-shaped hooks 65. The L-shaped hooks 65 match the first hanging ring 61 and the second hanging ring 62. The L-shaped hooks 65 at both ends of the first connecting rod 63 are respectively hooked in the round holes of the two first hanging rings 61, and the L-shaped hooks 65 at both ends of the second connecting rod 64 are respectively hooked in the round holes of the two second hanging rings 62.

[0029] It should be noted that the utility model is a construction pile. When the construction pile needs to be cast, the pile body 1 needs to be lowered into the pile hole first. The ground nail 2 at the bottom of the pile body 1 can be inserted into the soil at the bottom of the pile hole to fix the bottom of the pile body 1. Then, the four plug-in strips 52 are respectively inserted into the slide grooves 53 of the four fixing strips 51, and the side of the slope groove 54 on the plug-in strip 52 is inserted toward the inner wall of the pile body 1. The inclined surface of the slope groove 54 at the bottom is in contact with the ball 43 on the plug-in assembly 5 at the top. The ball 43 rolls on the inclined surface of the ramp groove 54. As the plug-in strip 52 moves downward, the inclined surface of the ramp groove 54 presses the ball 43 into the through hole 3, thereby driving the moving rod 41 to move out of the through hole 3. At this time, the spring 46 is in a compressed state, so that the pin 42 fixedly connected to the end of the moving rod 41 is inserted into the soil on the side wall of the pile hole, and the vertical surface of the plug-in strip 52 just blocks the through hole 3. When the plug-in strip 52 is fully inserted into the slide groove 53, the vertical surface of the plug-in strip 52 just blocks a number of through holes 3. Figure 3As shown, at this time, the nail 42 on the moving rod 41 of the pile body 1 is inserted into the side wall of the pile hole to be fixed in the horizontal direction, so as to avoid the pile body 1 from shaking during the subsequent concrete pouring process. After the pile body 1 is fixed in the pile hole, the staff pours concrete from the top of the pile body 1 to the inside of the pile body 1. After the concrete pouring solidifies, due to the setting of several pouring components 6 evenly distributed from top to bottom inside the pile body 1, the strength of the concrete is more stable and stress concentration is avoided. Compared with the existing construction engineering piles, the utility model can improve the stability of the pile body in the pile hole through design, avoid the shaking of the pile body block during the concrete pouring process to affect the structural strength of the engineering pile, and reinforce the poured concrete by setting the pouring component to avoid stress concentration, thereby reducing the cracking of the concrete in the pile body during the use of the engineering pile, increasing the strength of the entire engineering pile, improving the quality and safety performance of the engineering pile, and reducing safety hazards.

[0030] The above shows and describes the basic principle and main features of the utility model and the advantages of the utility model. Those skilled in the art should understand that the utility model is not limited by the above embodiments. The above embodiments and descriptions are only for explaining the principle of the utility model. Without departing from the spirit and scope of the utility model, the utility model may have various changes and improvements, which fall within the scope of the utility model to be protected. The scope of protection claimed by the utility model is defined by the attached claims and their equivalents.

Claims

1. A construction engineering pile, comprising a pile body (1), characterized in that: The bottom end of the pile body (1) is evenly fixedly connected with a plurality of ground nails (2); the pile body (1) is evenly provided with a plurality of through holes (3); each through hole (3) is provided with a side plug-in component (4); the inner wall of the pile body (1) is evenly provided with four plug-in components (5); and a plurality of casting components (6) are evenly provided between the plug-in components (5).

2. A construction engineering pile according to claim 1, characterized in that: The pile body (1) is an annular structure, and a plurality of through holes (3) are evenly distributed in four rows on the pile body (1), and the four plug-in components (5) correspond one-to-one to the four rows of through holes (3).

3. A construction engineering pile according to claim 1, characterized in that: The side insertion assembly (4) comprises a moving rod (41), one end of which is evenly and fixedly connected to a plurality of inserting pins (42), the other end of which is rollingly connected to a ball (43), a limiting ring (44) and a fixing ring (45) are sleeved on the moving rod (41), and a spring (46) is fixedly connected between the limiting ring (44) and the fixing ring (45).

4. A construction engineering pile according to claim 3, characterized in that: The moving rod (41) is slidably connected to the limiting ring (44); the diameter of the ball (43) is smaller than the diameter of the through hole (3); the limiting ring (44) is fixedly connected to one end of the through hole (3) away from the ball (43); and the fixing ring (45) is fixedly sleeved on the moving rod (41).

5. A construction engineering pile according to claim 1, characterized in that: The plug-in assembly (5) comprises a fixing strip (51) and a plug-in strip (52); a sliding groove (53) is provided on one side of the fixing strip (51); and a plurality of slope grooves (54) are evenly provided on one side of the plug-in strip (52).

6. A construction engineering pile according to claim 5, characterized in that: The side of the slide groove (53) on the fixing strip (51) is fixedly connected to the inner wall of the pile body (1), and is adapted to the plug-in strip (52) and the slide groove (53), and is slidably connected. The slide groove (53) is connected to the through hole (3), and the number of the slope grooves (54) is the same as the number of each row of through holes (3).

7. A construction engineering pile according to claim 5, characterized in that: The casting assembly (6) comprises two first hanging rings (61) and two second hanging rings (62); a first connecting rod (63) is arranged between the two first hanging rings (61); a second connecting rod (64) is arranged between the two second hanging rings (62); and both ends of the first connecting rod (63) and the second connecting rod (64) are fixedly connected with L-shaped hooks (65).

8. A construction engineering pile according to claim 7, characterized in that: The two first hanging rings (61) are respectively fixedly connected to two opposite fixing bars (51), and the two second hanging rings (62) are respectively fixedly connected to the other two opposite fixing bars (51). The L-shaped hooks (65) match the first hanging rings (61) and the second hanging rings (62). The L-shaped hooks (65) at both ends of the first connecting rod (63) are respectively hooked in the circular holes of the two first hanging rings (61), and the L-shaped hooks (65) at both ends of the second connecting rod (64) are respectively hooked in the circular holes of the two second hanging rings (62). The first connecting rod (63) and the second connecting rod (64) are staggeredly distributed downward.

Citation Information

Cited By

  • Construction engineering pile and pile machine

    CN223647049U