Prestressed anchor rod pile structure

Through the variable diameter steel cage and centering bracket structure, combined with three-wing expansion and high-pressure grouting technology, the problems of high anchor construction costs and insufficient pullout resistance are solved, and an efficient and stable anchoring effect is achieved.

CN221798526UInactive Publication Date: 2024-10-01CHINA CONSTR SECOND ENG BUREAU LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420358567.5
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-02-27
Publication Date
2024-10-01
Estimated Expiration
Not applicable · inactive patent

AI Technical Summary

Technical Problem

The existing anchor construction technology has problems such as high construction cost, unstable expansion diameter, low efficiency, and poor applicability to hard geological rock formations. Moreover, the pull-out resistance of prestressed anchor piles is weak and the construction is cumbersome.

Method used

Using a variable-diameter steel cage and centering bracket structure, a stepped shaft-shaped pile foundation hole is formed through a three-wing reaming drill bit, and combined with high-pressure grouting or concrete pouring, a prestressed anchor pile is formed to improve pullout resistance and construction efficiency.

Benefits of technology

It significantly improves anchorage stability and pullout resistance, simplifies the construction process, reduces costs, improves construction efficiency, and is suitable for different geological conditions.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN221798526U_ABST
    Figure CN221798526U_ABST
Patent Text Reader

Abstract

The utility model discloses a pre-stressed anchor rod pile structure which comprises a pile foundation hole, a variable-diameter reinforcement cage installed at the inner bottom of the pile foundation hole, a guide cap installed at the bottom of the variable-diameter reinforcement cage and an anchor rod installed at the top of the variable-diameter reinforcement cage, and concrete is poured in the pile foundation hole to form a pre-stressed pile. A plurality of centering brackets are arranged on the outer side of the anchor rod; an external thread connecting part is arranged at the top of the anchor rod, and a locking nut is mounted on the external thread connecting part; a base plate is installed on the top of the anchor rod, and a prestress spring is arranged between the base plate and the ground. The structure can be integrally constructed and manufactured and can be subsequently poured together with a building bottom plate to form a tensile or compression-resistant system, the pulling resistance is remarkably improved, the structure is simple and compact, the construction efficiency is high, the anchoring stability of the whole structure is high, and the application prospect is wide.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of building prestressed anchor pile construction, in particular to a prestressed anchor pile structure. Background Art

[0002] In underground engineering design, if the basement is buried deep or the water head is large, and the vertical deadweight load of the structure is less than the buoyancy of the groundwater, anti-floating anchors or anti-floating piles are usually used to meet the anti-floating design requirements. The enlarged head anchor is a friction-end pressure anchor that can provide greater pull-out bearing capacity and higher pull-out efficiency than ordinary anti-floating anchors. In recent years, it has gradually begun to be used in the anti-floating design of construction projects. However, most anchors are still ordinary anchors, and the diameter of the anchor head is fixed. After the anchor is lowered, its diameter cannot be expanded. The plain concrete enlarged head anchor formed after pouring concrete does not significantly improve the pull-out resistance. In addition, the commonly used hole expansion technologies for soil layers at present include high-pressure jet cutting and mechanical cutting hole expansion. The high-pressure jet cutting method uses a rotating high-pressure jet beam (liquid or gas-liquid mixture) to cut the soil of the anchoring section of the expansion head to form the required hole diameter. Because it requires a high-pressure grouting pump and an additional process of replacing the waste slag cut off, there are problems such as high construction cost, unstable hole expansion diameter, and low hole expansion efficiency. It is also difficult to expand holes for harder geological rock formations, and its applicability is relatively limited. The existing mechanical cutting hole expansion is mostly for large-diameter bored pile construction, and is not applicable to prestressed anchor pile construction with smaller borehole diameters. The invention patent with application number CN202211432283.8 discloses a combined foundation of micro piles and prestressed anchor rods and its construction method, and its construction method is: S1. Excavate the soil to the cushion layer elevation at the designed position, construct the pile hole of the micro pile, lower the steel cage and pour fine stone concrete; S2. Construct the anchor hole of the prestressed anchor rod, first lower the steel pipe in the center, then lower the reinforcement body with casing into the steel pipe, inject grouting into the anchor hole to the hole mouth, and then inject more grouting into the steel pipe; S3. Construct the cushion layer, tie the lower step foundation steel bars and the upper step foundation steel bars, install the combined anchor plate, and pour concrete; S4. After the concrete strength reaches the requirement, tension the prestressed anchor rod to the design load and then lock it, install the connecting reinforcement and pour the anchor cover. The combined foundation includes a foundation and micro piles and prestressed anchor rods arranged on the foundation. The present invention forms a combined foundation through micro piles, prestressed anchor rods and foundation. The micro piles can ensure the bearing capacity of the foundation. The prestressed anchor rods can significantly reduce or even eliminate the accumulated deformation of the foundation caused by repeated vibration of the transmission tower, greatly improving the safety of the transmission tower foundation. However, the anchor piles of the structure have the same diameter, the pull-out resistance is relatively weak, and the construction is relatively cumbersome. Utility Model Content

[0003] The utility model aims to provide a prestressed anchor pile structure, which can be constructed and manufactured in an integrated manner, and can be subsequently cast together with the building base plate to form a tensile or compressive system, which significantly improves the pull-out resistance, has a simple and compact structure, high construction efficiency, strong anchoring stability of the overall structure, and broad application prospects.

[0004] In order to achieve the above purpose, the utility model adopts the following technical solutions:

[0005] A prestressed anchor pile structure comprises a pile foundation hole, a variable diameter steel cage installed at the bottom of the pile foundation hole, a guide cap installed on the bottom of the variable diameter steel cage and an anchor installed on the top of the variable diameter steel cage, concrete is poured in the pile foundation hole to form a prestressed pile; a plurality of centering brackets are arranged on the outside of the anchor; an external threaded connection portion is arranged on the top of the anchor, and a locking nut is installed on the external threaded connection portion; a pad is installed on the top of the anchor, and a prestressed spring is arranged between the pad and the ground.

[0006] Preferably, the pile foundation hole is in the shape of a stepped shaft with a large bottom and a small top.

[0007] Preferably, the variable diameter steel cage includes an axial rod, a plurality of vertical bars arranged in the circumferential direction of the axial rod, spiral stirrups wrapped around the plurality of vertical bars, a pressure plate fixedly mounted on the bottom of the axial rod, a flexible mechanism mounted on the axial rod and a ring-mounted fixture mounted on the axial rod, the guide cap is fixedly mounted on the pressure plate; the bottom end of the anchor rod is fixedly connected to the top end of the axial rod.

[0008] Preferably, two of the movable mechanisms are provided.

[0009] Preferably, a restraining rope is provided on the outer side of the vertical reinforcement, and when the restraining rope is in a locked state, the variable diameter steel cage is in a retracted state; when the restraining rope is in an open state, the variable diameter steel cage is in an expanded state.

[0010] Preferably, the centering bracket includes a fixed support plate, a plurality of centering diagonal support rods hingedly mounted on the fixed support plate, a plurality of limit rods fixedly mounted on the fixed support plate, a sliding plate slidably mounted on the limit rods, and a return spring installed between the sliding plate and the fixed support plate. The plurality of limit rods are circumferentially arranged along the center hole of the fixed support plate, and the fixed support plate is fixedly mounted on the anchor rod.

[0011] In the utility model, the variable diameter steel cage can pass through a relatively fine hole and then enter a relatively large hole. By changing its own diameter, it forms an anchoring shape with a thick bottom and a thin top. The variable diameter steel cage simplifies the construction of the pile foundation hole, and the formed anchor pile has a good anchoring ability, which enhances the stability of the overall structure. The top of the anchor is exposed on the ground and can be cast together with the building floor later to form a tensile or compressive system, which can significantly improve the pull-out resistance of the building structure. The centering bracket can ensure that the anchor is in the middle position of the pile foundation hole, improving the stability of the overall structure after the subsequent concrete pouring. BRIEF DESCRIPTION OF THE DRAWINGS

[0012] Figure 1 It is a schematic cross-sectional view of the overall structure of the utility model;

[0013] Figure 2 This is a schematic diagram of the variable diameter steel cage of the utility model in a folded state;

[0014] Figure 3 This is a schematic diagram of the centering bracket structure of the utility model;

[0015] In the figure: 1. Pile foundation hole; 2. Variable diameter steel cage; 3. Guide cap; 4. Anchor rod; 5. Centering bracket; 6. Locking nut; 7. Pad; 8. Prestressed spring; 20. Axial rod; 21. Vertical reinforcement; 22. Spiral stirrups; 23. Pressure plate; 24. Active mechanism; 25. Ring fixture; 26. Constraint rope; 50. Fixed support plate; 51. Centering diagonal support rod; 52. Limit rod; 53. Sliding plate; 54. Reset spring. DETAILED DESCRIPTION

[0016] The utility model is further described below in conjunction with the accompanying drawings:

[0017] like Figure 1 , Figure 2 and Figure 3 A prestressed anchor pile structure shown in the figure comprises a pile foundation hole 1, a variable diameter steel cage 2 installed at the bottom of the pile foundation hole 1, a guide cap 3 installed on the bottom of the variable diameter steel cage 2 and an anchor 4 installed on the top of the variable diameter steel cage 2, and concrete is poured in the pile foundation hole 1 to form a prestressed pile. The pile foundation hole 1 is in the shape of a stepped shaft with a large bottom and a small top. The pile foundation hole 1 is formed by an integrated construction using a three-wing reamer drill bit, that is, a three-wing reamer drill bit is used to drill downward, and after drilling to a specified depth, the three-wing reamer is unfolded to expand the hole at the bottom to form a bottom space with a larger diameter, thereby forming a pile foundation hole 1 that is in the shape of a stepped shaft with a large bottom and a small top as a whole. Using a three-wing reamer drill bit for operation improves the efficiency of the construction of the pile foundation hole 1, reduces the overall construction cost, and saves labor.

[0018] After drilling, the variable diameter steel cage 2 in the contracted state is placed in the hole. When the variable diameter steel cage 2 is lowered to the designated position, the restraining rope 26 is opened to expand the variable diameter steel cage 2 in the contracted state, and then high pressure grouting or concrete is poured into the hole of the anchor rod 4 to form a prestressed pile. The variable diameter steel cage 2 includes an axial rod 20 located at the axial center position, a plurality of vertical bars 21 arranged in the circumferential direction of the axial rod 20, a spiral hoop 22 wound on the plurality of vertical bars 21, a pressure plate 23 fixedly mounted on the bottom of the axial rod 20, an active mechanism 24 mounted on the axial rod 20, and a ring-mounted fixture 25 mounted on the axial rod 20. The guide cap 3 is fixedly mounted on the pressure plate 23 by a fastener. The bottom end of the anchor rod 4 is fixedly connected to the top end of the axial rod 20 by a fastener or a clamp. In this embodiment, one ring-mounted fixture 25 is provided, and two active mechanisms 24 are provided, and the two active mechanisms 24 are provided at intervals. When the two active mechanisms 24 are in a contracted state, the variable diameter steel cage 2 is in a retracted state, and when the two active mechanisms 24 are in a flattened state, the variable diameter steel cage 2 is in an expanded state. A restraining rope 26 is provided on the outer side of the vertical reinforcement 21. When the restraining rope 26 is in a locked state, the variable diameter steel cage 2 is in a retracted state; when the restraining rope 26 is in an open state, the variable diameter steel cage 2 is in an expanded state. Under normal circumstances, the restraining rope 26 is in a locked state. After the operator opens the locked restraining rope 26 on the ground, the active mechanism 24 in the contracted state is opened to a flattened state, so that the variable diameter steel cage 2 is expanded. The spiral stirrups 22 are made of spring steel. The variable diameter steel cage 2 adopts products purchased on the market, and the detailed working principle will not be introduced in detail.

[0019] A plurality of centering brackets 5 are arranged at vertical intervals on the outer side of the anchor rod 4, and the interval between two adjacent centering brackets 5 is 2m. The centering bracket 5 comprises a fixed support plate 50, a plurality of centering diagonal struts 51 hingedly mounted on the fixed support plate 50 through a pin shaft, a plurality of limit rods 52 fixedly mounted on the fixed support plate 50 through nuts, a sliding plate 53 slidably mounted on the limit rods 52, and a reset spring 54 installed between the sliding plate 53 and the fixed support plate 50. The plurality of limit rods 52 and the plurality of centering diagonal struts 51 are all arranged circumferentially along the central hole of the fixed support plate 50, and the fixed support plate 50 is fixedly mounted on the anchor rod 4 through fasteners. The reset spring 54 is a tension spring. Under normal conditions, the sliding plate 53 squeezes the centering diagonal struts 51 under the tension of the reset spring 54, so that the centering diagonal struts 51 are in an open state, and the installation position of the anchor rod 4 in the pile foundation hole 1 is in the middle position. When the anchor rod 4 deviates laterally, the centering bracket 5 has a certain correction ability, and the centering ability is strong.

[0020] An external threaded connection part is integrally provided at the top position of the anchor rod 4, a locking nut 6 is installed on the external threaded connection part, a pad 7 is installed on the top of the anchor rod 4, a prestressed spring 8 is provided between the pad 7 and the ground, and the prestressed spring 8 improves the anti-floating ability of the structure.

[0021] During construction, first drill a hole. After the site is leveled and hardened, use a total station to measure the elevation of the construction site to determine the depth of the hole. At the same time, perform line measurement. According to the elevation and horizontal distance required by the design, use a level and a steel ruler to determine the hole position and make markings. The hole spacing error in the horizontal and vertical directions of the anchor rod shall not exceed 100mm. After the drilling rig is in place, level and fix the machine, check the horizontality and verticality of the drilling rig, and ensure that the drill bit is aligned with the center of the hole position so that it is on a plumb line. After the hole is aligned with the center of the hole position, turn on the drilling rig and drill it to the designed depth. After the hole is drilled to the designed depth, replace the reaming drill bit with a retractable three-wing reaming knife for reaming construction. There is a central plug rod in the center of the entire reaming drill bit, and the lower part of the plug rod is connected to the retractable cutting wing of the reaming drill bit. Before the reaming drill bit enters the hole, it must be tested for overall strength on the ground. The main content is whether the welding parts of each component are firm, whether the pin connection is safe and reliable, and carefully check whether the reaming drill bit reaming knife wing is flexible in contraction and expansion. When the air pump is pressurized, the pressure drop between the inner cavity of the drill bit and the annulus pushes the plug rod mechanism downward, thereby driving the retractable cutting wings of the reaming drill bit to extend outward to a certain designed angle, and cutting out the designed aperture while the drill bit rotates; when the high-pressure gas stops being injected, the pressure drop is lower than the force of the spring, and the plug rod is reset by the spring, and the reaming drill bit automatically retracts the cutting wings. When the reaming drill bit is lowered to the bottom of the hole, mark the active drill rod or fix the corresponding stroke limiter on the reaming drill bit to determine the end point of the bottom expansion. At this time, the hole expansion coefficient should be considered. Because the reaming drill bit is lowered to the bottom of the hole, it is not in a completely contracted state, but slightly opened. Therefore, when determining the end point of the bottom expansion stroke, it should be reduced as appropriate compared to the actual measured stroke on the ground. Slowly apply pressure during drilling, gradually open the reaming blades, cut the rock layer step by step to expand the bottom, and control the high-pressure gas injection value according to the designed reaming diameter so that the reaming blades are expanded to the angle required for the designed aperture. Use the lowest gear speed during drilling. During normal drilling, if there are no abnormal conditions, the drill tool shall not be lifted without reason. After the hole is finally formed, the residual slag in the hole is removed. At the same time, the on-site engineer and quality inspector measure the hole depth and anchor hole deflection. If it meets the design requirements, the next process should be carried out as soon as possible.

[0022] Lower the variable diameter steel cage anchor pile, pass the prepared rod through the center tube of the variable diameter steel cage and lock it with the matching high-strength nut, and over-tighten the nut by two threads; at the same time, lock the top of the center tube of the variable diameter steel cage with a limit nut to prevent the steel cage from sliding up and down. Insert the fine stone concrete conduit along the rod body to the variable diameter steel cage to the bottom (the 2m section at the end of the conduit can also be a hose) and install the guide cap (so as not to affect the installation of the guide cap). During installation, pay attention not to affect the rebound of the steel cage; the upper fine stone concrete delivery pipe is lightly tied and fixed with the rod body with a wire tie so as not to affect the later extraction. Use a thin steel wire rope as a traction rope shackle to buckle the variable diameter limit pin switch of the variable diameter steel cage. At this time, the steel wire rope is strictly prohibited from being pulled. The variable diameter steel cage anchor pile is assembled. Lower the variable diameter steel cage anchor pile: Before the anchor pile is placed in the drill hole, the quality of the anchor pile system should be checked again to ensure that the assembly meets the design requirements. After passing the inspection, the anchor pile is hoisted by a drilling rig or manually lifted along the hole wall to be anchored. When lowering, the fine stone concrete delivery pipe, wire rope and anchor pile are put into the hole simultaneously; the length of the anchor pile inserted into the hole should not be less than 95% of the design requirements. After the anchor pile is lowered, the anchor rod shall not be hit or lifted at will. After the variable diameter steel cage anchor pile is installed to the design elevation, the verticality is controlled (hole slope ≤1.0%), and then the variable diameter limit pin is pulled out by a mechanical winch or manually pulling the traction rope to release the constraint. It is forbidden to pause in the middle to ensure that the steel cage is opened at one time. When all the limit pins are pulled out, the variable diameter steel cage will automatically unfold, and then prepare to pour fine stone concrete.

[0023] For high-pressure grouting or concrete pouring, the sand for concrete pouring should be mixed with medium sand (3:7 of extra-fine sand and artificial sand); the particle size of coarse aggregate should be 5-12mm (determined by the selected pouring equipment), and admixtures should be added to underwater concrete pouring. The construction and use of concrete conduits should comply with the following regulations: the wall thickness should be 3-5mm, the outer diameter should be 68-70mm; the diameter manufacturing deviation should not exceed 2mm, the segmented length of the conduit can be determined according to the process requirements, the bottom pipe length should not be less than 4m, the joint should use double-threaded square buckle quick joints, and the conduit should be assembled and pressure tested before use. The conduit should be cleaned inside and outside after each pouring. The water stopper used should have good water-proof performance and should ensure smooth discharge; the water stopper should be made of spherical bladder or fine stone concrete with the same strength grade as the pile body concrete. When starting to pour concrete, the distance from the bottom of the conduit to the bottom of the hole should be 300-500mm to ensure sufficient concrete reserves. The conduit should be buried not less than 0.8m below the concrete pouring surface at one time; the depth of the pipe buried in the concrete should be 2-6m; it is strictly forbidden to lift the conduit out of the concrete pouring surface, and the speed of lifting the conduit should be controlled; the last pouring volume should be controlled, and the over-pouring height should be 0.8-1.0m. After chiseling out the slurry, the exposed concrete strength of the pile top must reach the design grade.

[0024] Prestressed tensioning and locking: After the strength of the concrete or grouting body of the anchor reaches 90%, clean the floating slurry above the design elevation of the anchor pile top, level it with cement mortar, and bury the anchor pad at the top of the anchor. Set the prestressed nut on the threaded steel bar above the anchor pad, mechanically connect it with the pad and prestressed steel bar, tighten the prestressed nut in time, and use the matching torque wrench to apply prestress to the deformation position required by the design, or use a jack or other equipment to apply prestress to the load required by the design, and lock it with an anchor. The rated pressure of the test loading device (jack, oil pump) must be greater than the test pressure. The test measuring instruments (pressure gauge, dynamometer, displacement meter) should meet the accuracy required by the test. The anchor pad and the nuts used to lock the prestressing are painted with anti-corrosion paint, and the cushion layer is poured. Then, a water-expandable waterproofing strip is placed at the bottom of the upper end of the cushion layer and the lower end of the bottom plate. The protective device is applied to the prestressed nut, which means that the spiral stirrup is put on the prestressed nut, and the spiral stirrup and the foundation bottom plate steel bars on the base are tied. Avoid collision with the prestressed steel bars during the tying process. Install the anchor accessories and set the anchor structure at the top of the anchor rod main bar according to the requirements of the engineering design and specifications. Finally, the foundation concrete foundation bottom plate is cast with the formwork, and it is cast together with the building bottom plate to form an anti-floating, anti-tension or anti-compression system.

[0025] The above embodiments are only some descriptions of the concept and implementation of the utility model, and are not intended to limit the concept and implementation of the utility model. Under the concept of the utility model, technical solutions that have not been substantially changed are still within the scope of protection.

Claims

1. A prestressed anchor pile structure, characterized in that: It comprises a pile foundation hole, a variable diameter steel cage installed at the bottom of the pile foundation hole, a guide cap installed on the bottom of the variable diameter steel cage and an anchor rod installed on the top of the variable diameter steel cage, and concrete is poured in the pile foundation hole to form a prestressed pile; a plurality of centering brackets are arranged on the outside of the anchor rod; an external threaded connection part is arranged on the top of the anchor rod, and a locking nut is installed on the external threaded connection part; a pad is installed on the top of the anchor rod, and a prestressed spring is arranged between the pad and the ground.

2. The prestressed anchor pile structure according to claim 1, characterized in that: The pile foundation hole is in a stepped shaft shape with a large bottom and a small top.

3. The prestressed anchor pile structure according to claim 1 or 2, characterized in that: The variable diameter steel cage includes an axial rod, a plurality of vertical bars arranged in the circumferential direction of the axial rod, spiral stirrups wrapped around the plurality of vertical bars, a pressure plate fixedly installed on the bottom of the axial rod, a flexible mechanism installed on the axial rod and a ring-mounted fixture installed on the axial rod, the guide cap is fixedly installed on the pressure plate; the bottom end of the anchor rod is fixedly connected to the top end of the axial rod.

4. The prestressed anchor pile structure according to claim 3, characterized in that: Two of the movable mechanisms are provided.

5. The prestressed anchor pile structure according to claim 4, characterized in that: A restraining rope is arranged on the outer side of the vertical reinforcement. When the restraining rope is in a locked state, the variable diameter steel cage is in a retracted state; when the restraining rope is in an open state, the variable diameter steel cage is in an extended state.

6. The prestressed anchor pile structure according to claim 1, characterized in that: The centering bracket includes a fixed support plate, a plurality of centering diagonal support rods hingedly mounted on the fixed support plate, a plurality of limit rods fixedly mounted on the fixed support plate, a sliding plate slidably mounted on the limit rods, and a return spring installed between the sliding plate and the fixed support plate. The plurality of limit rods are circumferentially arranged along the center hole of the fixed support plate, and the fixed support plate is fixedly mounted on the anchor rod.