Fabricated slope steel trestle

By introducing the design of adjustment components and inclined support rods into the slope steel trestle, the problem of inaccurate slope adjustment is solved, the stability of the bridge body and construction efficiency are improved, and the stable construction of the slope steel trestle under different terrains is ensured .

CN221810514UActive Publication Date: 2024-10-08CHINA RAILWAY BEIJING ENG BUREAU GRP TIANJIN ENG CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202323485680.4
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2023-12-20
Publication Date
2024-10-08
Estimated Expiration
2033-12-20

AI Technical Summary

Technical Problem

The existing slope steel trestle cannot adjust the slope effectively and accurately due to the fixed thickness of the steel gasket when adjusting the slope, resulting in slight deviations during the construction process and affecting construction efficiency and stability.

Method used

A prefabricated slope steel trestle is designed, which uses adjustment components to drive the gaskets to move. The stability of the bridge body is improved through connecting pieces, fixing bolts and inclined support rods, and the adjustment frame and limit grooves are used to ensure close contact between the bridge body and the gaskets. , achieving precise angle adjustment.

Benefits of technology

It realizes the disassembly and assembly of the steel wire bridge body, improves the stability and angle adjustment accuracy of the bridge body, avoids the gap between the gasket and the bridge body, and ensures the stability and efficiency of the construction.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN221810514U_ABST
    Figure CN221810514U_ABST
Patent Text Reader

Abstract

The utility model discloses an assembly type slope steel trestle, which relates to the field of construction trestles and comprises a steel wire bridge body, a plurality of gaskets are uniformly arranged at the bottom end of the steel wire bridge body, a bearing seat is arranged at the bottom end of each gasket, an adjusting component is arranged at the bottom end of each bearing seat, and a plurality of supporting rods are arranged on the periphery of the bottom end of each adjusting component. Piers are arranged at the bottom ends of the supporting rods; a plurality of connecting pieces are evenly arranged at the top of the steel wire bridge body, fixing bolts matched with the steel wire bridge body are arranged on the outer sides of the connecting pieces, and a plurality of haunched steel bars are evenly arranged on the outer sides of the tops of the bridge piers. Under the action of the adjusting assembly, the gasket can be driven to move, and the steel wire bridge body is driven by the gasket to adjust the angle, so that the inclination angle of the steel wire bridge body is adjusted according to requirements, a gap between the gasket and the steel wire bridge body is avoided, and the stability of the steel wire bridge body is ensured.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the field of construction trestles, in particular to an assembled slope steel trestle. Background Art

[0002] With the acceleration of urbanization and the decreasing land resources, various types of urban buildings have begun to develop underground spaces, which is specifically manifested in the increasingly deep foundations of buildings, especially in recent years, more and more ultra-deep foundation pit projects with large land areas and complex plane shapes have appeared. In the process of foundation pit construction, foundation pit support solutions are an indispensable item.

[0003] Slope steel trestle is a special bridge design that has a strong steel structure that can adapt to various terrains, including slopes. This type of bridge is often used to cross valleys, rivers or other difficult to pass places.

[0004] For example, Chinese patent CN206768570U discloses a foundation pit assembled steel trestle, which improves construction efficiency, saves construction costs, and is environmentally friendly and pollution-free.

[0005] The steel trestle ramp is provided with a hinged slope adjustment plate, and the slope is adjusted by adding steel gaskets. Although the slope can be adjusted by adding steel gaskets, the thickness of the steel gaskets is fixed and the slope angle cannot be adjusted effectively and accurately. Slight deviations are prone to occur during the adjustment process, resulting in the inability to carry out effective construction later.

[0006] Currently, no effective solution has been proposed for the problems in the related technologies. Utility Model Content

[0007] In view of the problems in the related technology, the utility model proposes an assembled slope steel trestle to overcome the above technical problems existing in the existing related technology.

[0008] To this end, the specific technical solutions adopted by the utility model are as follows:

[0009] An assembled slope steel trestle comprises a steel wire bridge body, a plurality of gaskets are evenly arranged at the bottom end of the steel wire bridge body, a bearing seat is arranged at the bottom end of the gasket, an adjustment component is arranged at the bottom end of the bearing seat, a plurality of support rods are arranged around the bottom end of the adjustment component, and bridge piers are arranged at the bottom ends of the plurality of support rods; a plurality of connecting plates are evenly arranged at the top of the steel wire bridge body, fixing bolts matching the steel wire bridge body are arranged at the outer side of the connecting plates, and a plurality of axil reinforcement bars are evenly arranged at the outer side of the top of the bridge pier.

[0010] Furthermore, in order to further increase the stability of the steel wire bridge body, a number of inclined support rods are staggeredly arranged at both ends of the outer side of the steel wire bridge body.

[0011] Furthermore, in order to ensure that the bottom end of the steel wire bridge body can be in closer contact with the gasket, thereby ensuring the stability of the entire steel wire bridge body, an adjustment frame that cooperates with the gasket is provided at the bottom end of the steel wire bridge body, and limiting grooves that cooperate with the gasket are opened around the adjustment frame.

[0012] Furthermore, in order to drive the gasket to move under the action of the adjusting component, and use the gasket to drive the steel wire bridge body to adjust the angle, so as to adjust the inclination angle of the steel wire bridge body according to needs, avoid the existence of a gap between the gasket and the steel wire bridge body, and ensure the stability of the steel wire bridge body, a mounting frame with a placement groove that matches the gasket is opened on the top of the adjusting component, and limiting strip grooves that match the gasket are opened around the inside of the mounting frame, and a threaded rod that matches the bearing seat is interspersed in the middle of the mounting frame, and a rotating handle is provided at the bottom end of the threaded rod, and a plurality of arc-shaped grooves are opened on the outside of the rotating handle.

[0013] The beneficial effects of the utility model are:

[0014] 1. The utility model enables the entire steel wire bridge body to be disassembled and assembled under the assembly action of the connecting plates and fixing bolts, and at the same time, under the action of the inclined support rods, the stability of the steel wire bridge body can be further improved.

[0015] 2. Under the action of the adjustment component, the utility model can drive the gasket to move, and use the gasket to drive the steel wire bridge body to adjust the angle, so as to adjust the inclination angle of the steel wire bridge body according to needs, avoid the existence of a gap between the gasket and the steel wire bridge body, and ensure the stability of the steel wire bridge body. BRIEF DESCRIPTION OF THE DRAWINGS

[0016] In order to more clearly illustrate the embodiments of the utility model or the technical solutions in the prior art, the drawings required for use in the embodiments will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the utility model. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative work.

[0017] Figure 1 It is a structural schematic diagram of an assembled slope steel trestle according to an embodiment of the utility model;

[0018] Figure 2 yes Figure 1 A partial enlarged view of the middle A;

[0019] Figure 3 yes Figure 1 A partial enlarged view of point B in the middle;

[0020] Figure 4It is one of the partial cross-sectional views of an assembled slope steel trestle according to an embodiment of the utility model;

[0021] Figure 5 yes Figure 4 A partial enlarged view of point C in the middle;

[0022] Figure 6 This is a second partial cross-sectional view of an assembled slope steel trestle according to an embodiment of the utility model;

[0023] Figure 7 yes Figure 6 A partial enlarged view of point D in the middle;

[0024] Figure 8 It is a structural schematic diagram of an adjustment component in an assembled slope steel trestle according to an embodiment of the utility model.

[0025] In the figure:

[0026] 1. Steel wire bridge body; 101. Adjustment frame; 102. Limiting groove; 2. Gasket; 3. Bearing seat; 4. Adjustment assembly; 401. Mounting frame; 402. Limiting strip groove; 403. Threaded rod; 404. Turning handle; 405. Arc groove; 5. Support rod; 6. Bridge pier; 7. Connecting plate; 8. Fixing bolt; 9. Axillary reinforcement; 10. Inclined support rod. DETAILED DESCRIPTION

[0027] To further illustrate each embodiment, the present invention provides drawings, which are part of the disclosure of the present invention and are mainly used to illustrate the embodiments. They can be used in conjunction with the relevant descriptions in the specification to explain the operating principles of the embodiments. With reference to these contents, ordinary technicians in the field should be able to understand other possible implementation methods and advantages of the present invention. The components in the figures are not drawn to scale, and similar component symbols are generally used to represent similar components.

[0028] According to an embodiment of the utility model, a prefabricated slope steel trestle is provided.

[0029] The present invention is now further described in conjunction with the accompanying drawings and specific implementation methods. Figure 1-Figure 8As shown, the assembled slope steel trestle according to the embodiment of the utility model includes a steel wire bridge body 1, a plurality of gaskets 2 are evenly arranged at the bottom end of the steel wire bridge body 1, a bearing seat 3 is arranged at the bottom end of the gasket 2, an adjusting assembly 4 is arranged at the bottom end of the bearing seat 3, a plurality of support rods 5 are arranged around the bottom end of the adjusting assembly 4, and a pier 6 is arranged at the bottom end of the plurality of support rods 5; a plurality of connecting plates 7 are evenly arranged at the top of the steel wire bridge body 1, a fixing bolt 8 matching the steel wire bridge body 1 is arranged at the outer side of the connecting plate 7, a plurality of axilla reinforcement bars 9 are evenly arranged at the outer side of the top of the pier 6, and a plurality of inclined support rods 10 are staggered at both ends of the outer side of the steel wire bridge body 1.

[0030] With the help of the above-mentioned technical scheme, the utility model can disassemble and assemble the entire steel wire bridge body 1 under the assembly action of the connecting plate 7 and the fixing bolt 8. At the same time, under the action of the inclined support rod 10, the stability of the steel wire bridge body can be further improved. At the same time, under the action of the adjustment component 4, the gasket 2 can be driven to move, and the gasket 2 can be used to drive the steel wire bridge body 1 to adjust the angle, so as to adjust the inclination angle of the steel wire bridge body 1 according to the needs, avoid the existence of a gap between the gasket and the steel wire bridge body 1, and ensure the stability of the steel wire bridge body 1.

[0031] In one embodiment, for the above-mentioned steel wire bridge body 1, an adjustment frame 101 that cooperates with the gasket 2 is provided at the bottom end of the steel wire bridge body 1, and limiting grooves 102 that cooperate with the gasket 2 are opened around the adjustment frame 101, so that under the limiting action of the adjustment frame 101 and the limiting groove 102, it is ensured that the bottom end of the steel wire bridge body 1 can be in closer contact with the gasket, thereby ensuring the stability of the entire steel wire bridge body 1.

[0032] In one embodiment, for the above-mentioned adjustment component 4, a mounting frame 401 with a placement groove that cooperates with the gasket 2 is provided on the top of the adjustment component 4, and limiting strip grooves 402 that cooperate with the gasket 2 are provided around the inside of the mounting frame 401. A threaded rod 403 that cooperates with the bearing seat 3 is interspersed in the middle of the mounting frame 401, and a rotating handle 404 is provided at the bottom end of the threaded rod 403. A plurality of arc-shaped grooves 405 are provided on the outside of the rotating handle 404. Under the action of the adjustment component 4, the gasket 2 can be driven to move, and the gasket 2 can be used to drive the steel wire bridge body 1 to adjust the angle, so as to adjust the inclination angle of the steel wire bridge body 1 according to needs, avoid the existence of a gap between the gasket and the steel wire bridge body 1, and ensure the stability of the steel wire bridge body 1.

[0033] The working principle of the adjustment component 4 is as follows: first, according to the angle to be adjusted, the handle 404 is rotated through the arc groove 405, thereby driving the threaded rod 403 to rotate under the action of the handle 404, so that during the rotation of the threaded rod 403, it cooperates with the bearing seat 3, and during the rising process of the threaded rod 403, it drives the gasket 2 to squeeze the steel wire bridge body 1, and realizes the angle adjustment of the steel wire bridge body 1.

[0034] In order to facilitate understanding of the above technical solution of the present invention, the working principle or operation method of the present invention in the actual process is described in detail below.

[0035] In actual application, the steel wire bridge body 1 is assembled by connecting pieces 7 and fixing bolts 8, and after the steel wire bridge body 1 is assembled, inclined support rods 10 are staggered at both ends to increase the stability of the steel wire bridge body 1, reduce the pressure on the bridge body, and provide additional stability. The bridge piers 6 and the reinforcing steel bars 9 also provide support for the stability of the overall structure, and the angle of the steel wire bridge body 1 is adjusted by adjusting components 4 and gaskets.

[0036] The working principle of the adjustment component 4 is as described above.

[0037] To sum up, with the aid of the above-mentioned technical scheme of the utility model, under the assembly action of the connecting plate 7 and the fixing bolt 8, the utility model makes it possible for the entire steel wire bridge body 1 to be disassembled and assembled. At the same time, under the action of the inclined support rod 10, the stability of the steel wire bridge body can be further improved. At the same time, under the action of the adjusting component 4, the gasket 2 can be driven to move, and the gasket 2 can be used to drive the steel wire bridge body 1 to adjust the angle, so as to adjust the inclination angle of the steel wire bridge body 1 according to the needs, avoid the existence of a gap between the gasket and the steel wire bridge body 1, and ensure the stability of the steel wire bridge body 1.

[0038] In the present utility model, unless otherwise clearly stipulated and limited, the terms such as "installation", "setting", "connection", "fixation" and "screw-on" should be understood in a broad sense. For example, it can be a fixed connection, a detachable connection, or an integrated connection; it can be a mechanical connection or an electrical connection; it can be a direct connection or an indirect connection through an intermediate medium, it can be the internal connection of two elements or the interaction relationship between two elements. Unless otherwise clearly defined, ordinary technicians in this field can understand the specific meanings of the above terms in the utility model according to the specific circumstances.

[0039] The above description is only a preferred embodiment of the present invention and is not intended to limit the present invention. Any modifications, equivalent substitutions, improvements, etc. made within the spirit and principles of the present invention should be included in the protection scope of the present invention.

Claims

1. An assembled slope steel trestle bridge, comprising a steel wire bridge body (1), characterized in that: A plurality of gaskets (2) are evenly arranged at the bottom end of the steel wire bridge body (1), a bearing seat (3) is arranged at the bottom end of the gasket (2), an adjustment component (4) is arranged at the bottom end of the bearing seat (3), a plurality of support rods (5) are arranged around the bottom end of the adjustment component (4), and bridge piers (6) are arranged at the bottom ends of the plurality of support rods (5); A plurality of connecting plates (7) are evenly arranged on the top of the steel wire bridge body (1), and fixing bolts (8) matching with the steel wire bridge body (1) are arranged on the outer sides of the connecting plates (7).

2. The assembled slope steel trestle according to claim 1, characterized in that: A plurality of axil reinforcement bars (9) are evenly arranged on the outer side of the top of the bridge pier (6).

3. The assembled slope steel trestle according to claim 1 or 2, characterized in that: A plurality of inclined support rods (10) are arranged alternately at both ends of the outer side of the steel wire bridge body (1).

4. The assembled slope steel trestle according to claim 1, characterized in that: An adjustment frame (101) matching with the gasket (2) is provided at the bottom end of the steel wire bridge body (1), and limiting grooves (102) matching with the gasket (2) are provided around the adjustment frame (101).

5. The assembled slope steel trestle according to claim 4, characterized in that: The top of the adjustment component (4) is provided with a mounting frame (401) having a placement groove that matches the gasket (2); the interior of the mounting frame (401) is provided with limiting strip grooves (402) that match the gasket (2); a threaded rod (403) that matches the bearing seat (3) is inserted through the middle of the mounting frame (401); and a rotating handle (404) is provided at the bottom end of the threaded rod (403).

6. The assembled slope steel trestle according to claim 5, characterized in that: A plurality of arc-shaped grooves (405) are formed on the outer side of the rotating handle (404).