Rapid repairing and reinforcing structure for forehead wall of ore loading chamber of ore pass in mining area
By using reinforced steel plates, steel cages and elastic buffers on the front wall of the tunnel loading chamber in the mining area, the rapid repair and reinforcement structure solves the problems of low efficiency and high risk of traditional repair methods, and improves the impact resistance and performance of the front wall. The repair efficiency extends the service life of the slide shaft.
Patent Information
- Application Number
- CN202420384361.X
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-02-29
- Publication Date
- 2024-10-08
- Estimated Expiration
- 2034-02-28
AI Technical Summary
The traditional repair method of the tunnel wall in the mining area has low repair efficiency, large investment, and high construction risk. It is also easy to be damaged again after repair, affecting the normal production of the mine.
A quick-repair reinforced structure using reinforced steel plates, steel cage cast-in bodies and elastic buffer bodies. The reinforced steel plates are laid on the inside and outside of the front wall. The steel cage cast-in bodies fill wall holes or pits. Fixed bolts connect the reinforced steel plates and steel cages to provide elastic buffers. The body is located in the ore bin and is fixedly connected to the reinforced steel plate to form a reinforced structure for the impact site.
It improves the impact resistance of the front wall, reduces the failure rate, extends the life cycle of the shaft, and improves the mining capacity of the stope.
Smart Images

Figure CN221810849U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to a quick repair and reinforcement structure for the front wall of a ore chamber in a mining area chute, belonging to the technical field of mining. Background Art
[0002] The mining chute is one of the most important mining and development systems in underground metal mines. All the ore and rock mined in the mining area are temporarily stored and transported here. The stability of the mining chute is directly related to the continuity of mine production. Due to the complex environment of the chute engineering and the long-term impact load and external forces such as ore-rock friction, its stability is poor. In particular, large-scale underground mines with large production capacity and soft and broken ore and rock often have chute collapse, deformation and damage problems, which seriously affect the normal production of the mine and threaten the safety of personnel and equipment. The front wall of the mining chute loading chamber is the most vulnerable part inside the chute. Figure 1 As shown, the ore falls through the screen and chute onto the cast body at the bottom of the ore bin and then moves toward one side of the front wall, causing a great impact on the front wall, resulting in holes or pits in the front wall. The traditional repair method is to dismantle the front wall and re-cast it. Not only is the repair efficiency low, the investment is large, and the construction risk is high, but it also cannot fundamentally solve the problem. After the front wall is repaired, it is sometimes damaged again soon, seriously affecting the normal production. Therefore, it is very necessary to seek new front wall repair methods. Utility Model Content
[0003] The purpose of the utility model is to provide a rapid repair and reinforcement structure for the front wall of the ore loading chamber in the mining area to address the shortcomings of the prior art, so as to improve the impact resistance and repair efficiency of the front wall, reduce the failure rate of the front wall, and ensure the normal production.
[0004] In order to achieve the above purpose, the utility model adopts the following technical solutions:
[0005] A rapid repair and reinforcement structure for the front wall of a ore loading chamber in a mining area chute, comprising a reinforcing steel plate, a steel cage casting, fixing bolts and an elastic buffer body. The reinforcing steel plates are laid on the inner and outer sides of the front wall and cover the wall holes or pits on the front wall. The steel cage casting is filled in the wall holes or pits on the front wall. The steel cage casting and the reinforcing steel plates on the inner and outer sides of the front wall are connected together by fixing bolts. The elastic buffer body is located in the ore bin below the chute and is fixedly connected to the reinforcing steel plates on the inner side of the front wall.
[0006] The above-mentioned rapid repair and reinforcement structure of the front wall of the mining area chute chamber, the elastic buffer body is a rubber plate attached to the surface of the reinforced steel plate.
[0007] The rapid repair and reinforcement structure of the front wall of the ore loading chamber in the above-mentioned mining area, multiple reinforcing steel plates are arranged on the inner and outer sides of the front wall, and the multiple reinforcing steel plates on each side are laid along the surface of the front wall, and adjacent reinforcing steel plates are connected by connecting steel plates.
[0008] The above-mentioned rapid repair and reinforcement structure of the front wall of the mining area chute loading chamber, the connecting steel plate and the reinforcement steel plate are welded together, and any two adjacent reinforcement steel plates are welded together.
[0009] The above-mentioned rapid repair and reinforcement structure of the front wall of the mining area chute loading chamber, the connecting steel plate is an L-shaped steel plate, and bolt holes matching the fixing bolts are provided on the connecting steel plate.
[0010] The utility model utilizes reinforcing steel plates, steel cage castings and elastic buffer bodies to specifically reinforce the parts of the front wall that are most susceptible to impact. It not only has a simple structure, convenient construction and high repair efficiency, but also can improve the stress state of the front wall, reduce the impact of ore on the front wall, reduce the failure rate of the front wall, extend the life cycle of the chute, and effectively improve the mining capacity of the mine. BRIEF DESCRIPTION OF THE DRAWINGS
[0011] The utility model is further described in detail below in conjunction with the accompanying drawings and specific implementation methods.
[0012] Figure 1 It is a schematic diagram of the structure of the chute and the ore bin;
[0013] Figure 2 It is a structural schematic diagram of the utility model;
[0014] Figure 3 It is a structural diagram of the reinforced steel plate.
[0015] The numbers in the figure are as follows: 1. grating, 2. chute, 3. bottom casting of ore bin, 4. front wall, 5. wall hole, 6. reinforcement steel plate, 7. elastic buffer, 8. fixing bolt, 9. steel cage casting, 10. connecting plate, 11. bolt hole, 12. ore bin. DETAILED DESCRIPTION
[0016] In view of the shortcomings of the prior art, the utility model provides a rapid repair and reinforcement structure for the front wall of a chute loading chamber in a mining area. The reinforcement structure is not only simple in structure, convenient in construction, and high in repair efficiency, but also can specifically reinforce the parts of the front wall that are most susceptible to impact, thereby improving the stress state of the front wall, reducing the impact of ore on the front wall, reducing the failure rate of the front wall, extending the life cycle of the chute, and effectively improving the mining capacity of the mining area.
[0017] See also Figure 1 , Figure 2 and Figure 3The grating 1 is located directly above the chute 2 for unloading ore. The grating 1 has a specification of 3m×3m and a mesh size of 700mm×700mm. The grating 1 is used to control the size of ore entering the chute to prevent large pieces of ore from impacting the chute wall and prolong the stability of the chute. The ore bin is located below the chute 2 and is combined with the wall 4 for temporary storage of ore. The wall 4 is located on one side of the ore bin and has a thickness of 650mm. The wall 4 is the main pressure-bearing structure of the ore bin. The utility model mainly includes an elastic buffer body 7, a reinforcing steel plate 6, a steel cage casting body 9, a connecting steel plate 10 and a fixing bolt 8. The steel cage casting body 9 is filled in the wall hole 5 or the pit of the front wall 4. The inner side (the side located in the ore bin is the inner side) and the outer side of the front wall 4 are both paved with reinforcing steel plates 6 to cover the wall hole 5 or the pit. The inner and outer reinforcing steel plates 6 of the front wall 4 and the steel cage casting body 9 are connected together by fixing bolts 8. The elastic buffer body 7 is fixed together with the reinforcing steel plate 6 on the inner side of the front wall 4 to buffer the impact of the ore. When the wall hole 5 or the pit impacted on the front wall 4 is large, a plurality of reinforcing steel plates 6 are arranged on the inner and outer sides of the front wall 4. The reinforcing steel plates 6 on each side are laid along the surface of the front wall 4. Adjacent reinforcing steel plates 6 are connected by connecting steel plates 10. The connecting steel plates 10 are welded to the reinforcing steel plates 6. Any two adjacent reinforcing steel plates 6 are also welded together.
[0018] The specification of the reinforcement steel plate 6 is 1.0×2.0m. Each reinforcement steel plate 6 is fixed by four 36mm fixing bolts 8. The elastic buffer body 7 is 2.5m high and 100mm thick.
[0019] The fixing bolt 8 is made of round steel with a diameter of 36mm. The steel cage casting body 9 and the reinforcement steel plate 6 form the main body of the front wall. When pouring concrete for the front wall 4, it should be poured symmetrically in layers. The thickness of each layer does not exceed 300mm, and the vibration range of the vibrating rod is 500mm.
[0020] The connecting steel plate 10 is an L-shaped steel plate with a thickness of 8 mm. Bolt holes 11 are processed on the connecting steel plate 10, and the fixing bolts 8 pass through the bolt holes 11 to ensure the firmness of the connection.
[0021] The diameter of the structural steel bars tied inside the steel cage casting 9 is 8mm, the mesh size is 400mm×400mm, the diameter of the horizontal steel bars tied is 25mm, the mesh size is 200mm×200mm, and the diameter of the vertical steel bars tied is 20mm, the mesh size is 200mm×200mm.
[0022] The utility model adopts a reinforced steel plate 6 and an elastic buffer body 7 to provide rigid and flexible protection for the front wall, which can buffer the impact of ore generated during unloading and placing, offset the impact force and friction force on the front wall, and ensure the normal use of the chute.
Claims
1. A rapid repair and reinforcement structure for the front wall of a ore chamber in a mining area, characterized in that: The structure includes a reinforcing steel plate (6), a steel cage casting (9), fixing bolts (8) and an elastic buffer (7), wherein the reinforcing steel plate (6) is laid on the inner and outer sides of the front wall (4) and covers the wall hole (5) or pit on the front wall (4), the steel cage casting (9) fills the wall hole (5) or pit on the front wall (4), the steel cage casting (9) and the reinforcing steel plates (6) on the inner and outer sides of the front wall (4) are connected together by fixing bolts (8), and the elastic buffer (7) is located in a ore bin (12) below the chute (2) and is fixedly connected to the reinforcing steel plate (6) on the inner side of the front wall (4).
2. The rapid repair and reinforcement structure for the front wall of a chute in a mining area according to claim 1 is characterized in that: The elastic buffer body (7) is a rubber plate attached to the surface of the reinforcement steel plate (6).
3. A rapid repair and reinforcement structure for the front wall of a chute in a mining area according to claim 1 or 2, characterized in that: A plurality of reinforcing steel plates (6) are arranged on the inner and outer sides of the front wall (4); the plurality of reinforcing steel plates (6) on each side are laid along the surface of the front wall (4); and adjacent reinforcing steel plates (6) are connected by connecting steel plates (10).
4. The rapid repair and reinforcement structure for the front wall of a chute in a mining area according to claim 3 is characterized in that: The connecting steel plate (10) and the reinforcing steel plate (6) are welded together, and any two adjacent reinforcing steel plates (6) are welded together.
5. The rapid repair and reinforcement structure for the front wall of a chute in a mining area according to claim 4 is characterized in that: The connecting steel plate (10) is an L-shaped steel plate, and is provided with bolt holes (11) matching the fixing bolts (8).