Construction hoisting device
By designing a construction hoisting device that includes a box, wheels, hoisting frame and winch, the problem of water leakage and splashing in the traditional mud bucket lifting method is solved, efficient and stable mud bucket lifting and cleaning is achieved, and the construction quality and efficiency.
Patent Information
- Application Number
- CN202420595910.8
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-03-26
- Publication Date
- 2024-10-11
- Estimated Expiration
- 2034-03-26
AI Technical Summary
The traditional mud bucket lifting method can easily lead to mud leakage and splashing, affecting construction quality and efficiency. It is also inconvenient to handle the remaining cement, resulting in material waste.
A construction hoisting device including a box, wheels, hoisting frame, winch, hanging plate and support frame is designed. Through the combination of wheels and hoisting frame, the mud bucket can be steadily lifted and cleaned. The support frame and legs ensure the stability of the device. , and can be stored to reduce space usage.
It effectively prevents mud spills and splashes, improves construction efficiency and quality, provides a safe and efficient lifting tool, and reduces pollution and material waste at the construction site.
Smart Images

Figure CN221821660U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of hoisting, in particular to a construction hoisting device. Background Art
[0002] When painting high walls and ceilings, the traditional method of lifting mud buckets mainly relies on manpower, and workers are usually required to lift mud buckets from low to high. This method has some problems, one of which is that mud is prone to leakage and splashing. Due to the limitations of manual lifting, it is difficult for construction workers to fully control the mud bucket during the lifting process, which may cause mud to overflow and affect the cleanliness and work quality of the construction site. In addition, throwing the mud bucket down after use will cause the remaining cement to splash, which not only causes material waste, but also reduces the quality and efficiency of construction, and requires a lot of additional cement knocking work during the construction work acceptance period.
[0003] Therefore, the current mud bucket lifting technology has a series of problems, including but not limited to water leakage, splashing, unstable construction quality, etc. In view of this, the utility model patent application proposes a new type of construction hoisting device, which aims to solve the defects of the traditional lifting method, is easy to move and use, and improves the construction efficiency and quality when painting high walls and ceilings. Utility Model Content
[0004] The utility model aims to solve at least one of the technical problems existing in the prior art. To this end, the utility model proposes a construction hoisting device to solve the above-mentioned problem.
[0005] In order to achieve the above purpose, the utility model proposes a construction hoisting device.
[0006] As a further solution of the utility model:
[0007] A construction hoisting device comprises a box body, the front ends of the left and right sides of the box body are fixedly connected with wheels, the top of the box body is provided with a first groove, the rear ends of the side walls of the first groove are fixedly connected with a first rotating shaft, the first rotating shaft is rotatably connected with a hoisting frame, a winch is sleeved on the top end of the hoisting frame, and a hoisting rope is fixedly wound around the outside of the winch;
[0008] The first slide grooves are symmetrically provided on the opposite sides of the columns of the two sides of the hanging frame, and the first slide grooves are slidably connected with the hanging plates, and the four corners of the hanging plates are fixedly connected with the hanging ears, and the hanging ears are fixedly connected with the hanging ropes;
[0009] A second slide groove is also symmetrically provided at the bottom of the first groove, a slider is slidably connected to the second slide groove, the slider is rotatably connected to the support frame, a fixing block is fixedly connected to the center of the front side of the columns on both sides of the hanging frame, and the other end of the support frame is rotatably connected to the fixing block;
[0010] A second groove is also formed at the front end of the bottom of the first groove;
[0011] A third groove is also provided at the rear end of the bottom of the box body, and a support foot is rotatably connected to the third groove.
[0012] Furthermore, a fourth groove is provided in the center of the rear side surface of the box body, and a drawer is slidably connected in the fourth groove.
[0013] Furthermore, a storage battery is fixedly installed in the box, and an interface for charging is opened on the front side of the box.
[0014] Furthermore, a handlebar for controlling movement is fixedly connected to the front side of the box.
[0015] Furthermore, the hanging frame rotates toward the front side to fit into the first groove, and the width of the horizontal cross section of the hanging plate is the same as that of the hanging frame.
[0016] Furthermore, the battery and the winch are electrically connected.
[0017] Compared with the prior art, the beneficial effects of the utility model are:
[0018] The utility model has a compact structure and complete functions. Through the reasonable layout of components such as wheels, hoisting frames, winches, and hanging plates, the efficient hoisting of mud buckets and the cleaning of construction sites are achieved. The support frame and foot design make the device stable during work, and it can be easily folded up after work to reduce the occupied space. The overall design takes into account the operational requirements of the construction site. Through the cooperation of various components, the construction efficiency is effectively improved, providing construction personnel with a safe and efficient hoisting tool. BRIEF DESCRIPTION OF THE DRAWINGS
[0019] Figure 1 It is a front view schematic diagram of the structure of the utility model;
[0020] Figure 2 It is a three-dimensional diagram of the utility model;
[0021] Figure 3 It is a top perspective view of the utility model;
[0022] Figure 4 It is a bottom-up stereogram of the present utility model;
[0023] Figure 5 for Figure 1 Cross-sectional view along the AA direction.
[0024] In the figure: 1, box body; 2, wheel; 3, handlebar; 4, first groove; 5, lifting frame; 6, winch; 7, first rotating shaft; 8, first slide; 9, hanging plate; 10, lifting ear; 11, support foot; 12, drawer; 13, support frame; 14, second groove; 15, second slide; 16, slider; 17, fixing block; 18, third groove; 19, fourth groove. DETAILED DESCRIPTION
[0025] The technical solution of the utility model will be described clearly and completely in conjunction with the embodiments below. Obviously, the described embodiments are only part of the embodiments of the utility model, not all of them. Based on the embodiments of the utility model, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the utility model.
[0026] like Figure 1-5 As shown, a construction hoisting device comprises a box body 1, wheels 2 are fixedly connected to the front ends of the left and right sides of the box body 1, a first groove 4 is opened on the top of the box body 1, a first rotating shaft 7 is fixedly connected between the rear ends of the side walls of the first groove 4, a hoisting frame 5 is rotatably connected to the first rotating shaft 7, a winch 6 is sleeved on the top end of the hoisting frame 5, and a hoisting rope is fixedly wound around the outer side of the winch 6;
[0027] The first slide grooves 8 are symmetrically provided on the opposite sides of the columns of the hanging frame 5. The first slide grooves 8 are slidably connected with the hanging plates 9. The four corners of the hanging plates 9 are fixedly connected with the hanging ears 10. The hanging ears 10 are fixedly connected with the hanging ropes.
[0028] A second slide groove 15 is also symmetrically provided at the bottom of the first groove 4, a slider 16 is slidably connected to the second slide groove 15, the slider 16 is rotatably connected to the support frame 13, and a fixing block 17 is fixedly connected to the center of the front side of the two side columns of the hanging frame 5, and the other end of the support frame 13 is rotatably connected to the fixing block 17;
[0029] A second groove 14 is also formed at the bottom front end of the first groove 4;
[0030] A fourth groove 19 is provided in the center of the rear side of the box body 1, and a drawer 12 is slidably connected in the fourth groove 19;
[0031] A battery is also fixedly installed in the box 1, and an interface for charging is provided on the front side of the box 1;
[0032] A third groove 18 is also provided at the rear end of the bottom of the box body 1, and the third groove 18 is rotatably connected to the support leg 11;
[0033] The front side of the box body 1 is also fixedly connected with a handlebar 3 for controlling movement;
[0034] The hanging frame 5 rotates forward to fit into the first groove 4, the width of the horizontal cross section of the hanging plate 9 is the same as that of the hanging frame 5, and the battery and the winch 6 are electrically connected;
[0035] Working principle: first, fully charge the battery, then rotate and stand the hoisting frame 5 from the first groove 4, at this time, the support frame 13 will also be brought by the hoisting frame 5 to slide out of the second slide groove 15, fix the support frame 13, stand the support leg 11 downward from the third groove 18 on the ground, place the mud bucket on the hanging plate 9, start the winch 6 to lift the hanging plate 9 upward, the hanging plate 9 rises in the first slide groove 8, so that the mud bucket is easy for the workers to obtain, and the empty mud bucket is brought downward to avoid the remaining mud splashing and solidifying at the construction site during the process of throwing the empty mud bucket downward. When the work is completed, the device is cleaned and put away, the support frame 13 enters the second slide groove 15, the hoisting frame 5 enters the first groove 4, the bottom of the winch 6 enters the second groove 14, the support leg 11 enters the third groove 18, the drawer 12 is pulled out of the fourth groove 19, the cleaned mud bucket is placed in the drawer 12, and the handlebar 3 is pushed to move and leave;
[0036] The above embodiments are only used to illustrate the technical method of the utility model rather than to limit it. Although the utility model is described in detail with reference to the preferred embodiments, ordinary technicians in the field should understand that the technical method of the utility model can be modified or replaced by equivalents without departing from the spirit and scope of the technical method of the utility model.
Claims
1. A construction hoisting device, characterized in that: The invention comprises a box body (1), the front ends of the left and right sides of the box body (1) are fixedly connected to wheels (2), the top of the box body (1) is provided with a first groove (4), the rear ends of the side walls of the first groove (4) are fixedly connected to a first rotating shaft (7), the first rotating shaft (7) is rotatably connected to a hanging frame (5), a winch (6) is sleeved on the top end of the hanging frame (5), and a hanging rope is fixedly wound around the outside of the winch (6); The first slide grooves (8) are symmetrically provided on the opposite surfaces of the two side columns of the hanging frame (5), and the first slide grooves (8) are slidably connected with a hanging plate (9), and the four corners of the hanging plate (9) are fixedly connected with hanging ears (10), and the hanging ears (10) are fixedly connected with hanging ropes; A second slide groove (15) is also symmetrically provided at the bottom of the first groove (4), a slider (16) is slidably connected to the second slide groove (15), the slider (16) is rotatably connected to the support frame (13), a fixing block (17) is fixedly connected to the center of the front side of the two side columns of the hanging frame (5), and the other end of the support frame (13) is rotatably connected to the fixing block (17); A second groove (14) is also formed at the front end of the bottom of the first groove (4); A third groove (18) is also provided at the rear end of the bottom of the box body (1), and the third groove (18) is rotatably connected to a support foot (11).
2. A construction hoisting device according to claim 1, characterized in that: A fourth groove (19) is provided in the center of the rear side surface of the box body (1), and a drawer (12) is slidably connected in the fourth groove (19).
3. A construction hoisting device according to claim 2, characterized in that: A storage battery is also fixedly installed in the box body (1), and an interface for charging is provided on the front side of the box body (1).
4. A construction hoisting device according to claim 3, characterized in that: The front side of the box body (1) is also fixedly connected with a handlebar (3) for controlling movement.
5. A construction hoisting device according to claim 4, characterized in that: The hanging frame (5) rotates toward the front side to fit into the first groove (4), and the width of the horizontal cross section of the hanging plate (9) is the same as that of the hanging frame (5).
6. A construction hoisting device according to claim 5, characterized in that: The storage battery and the winch (6) are electrically connected.