Road widening structure
During the widening and reconstruction of highways in permafrost areas, the road widening structure with drainage mechanisms and guardrails was designed to solve the problems of longitudinal cracks and rainwater accumulation caused by the difference between the old and new roadbeds, and improve the stability and safety of the road.
Patent Information
- Application Number
- CN202322445803.5
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2023-09-09
- Publication Date
- 2024-10-11
- Estimated Expiration
- 2033-09-09
AI Technical Summary
When highways are widened and reconstructed in permafrost areas, the difference between the old and new roadbeds leads to longitudinal cracks, which affects road performance. The lack of a drainage system after widening leads to accumulation of rainwater and causes traffic accidents.
Design a road widening structure, including widening roads on both sides of the original road, and a drainage mechanism inside the widened road, including drainage pavement, drainage holes, connecting pipes and drainage pipes. The drainage mechanism is connected to the original road, and the guardrail is used for Prevent the vehicle from rolling over.
It effectively solves the problem of rainwater accumulation, avoids traffic accidents, and improves the drainage capacity of the road.
Smart Images

Figure CN221822660U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of road widening, in particular to a road widening structure. Background Art
[0002] When building expressways in permafrost areas, if widening and reconstruction are carried out on the existing secondary roads in permafrost areas, the project investment can be greatly saved. Since the roadbed of the widened part is different from the original old road in terms of permafrost degradation and foundation consolidation, after the roadbed is widened, the new and old roadbeds will produce differential settlement, which will then be reflected to the pavement structure layer, causing longitudinal cracks between the new and old roadbeds, seriously affecting the road performance. The G214 National Highway in Qinghai Province (Gonghe to Yushu section) currently under construction encountered engineering problems in the widening of the old road during the construction process. Since the roadbed widening project has not been carried out in permafrost areas before, there are no corresponding disposal measures for the roadbed widening problem in permafrost areas.
[0003] For example, the publication number is CN203212964U, which is a widening structure of a highway roadbed with a stone-like structure for ice-rich and ice-saturated sections. The utility model has a widened roadbed on the side of the original roadbed slope; the original roadbed slope of the original roadbed is treated with slope cutting and then a slope excavation step is set; a base gravel layer is set from the bottom edge of the slope excavation step to the foot of the widened roadbed, and a base geogrid is laid on the base gravel layer. A stone layer, a permeable geotextile, a crushed stone layer, a gravel layer and a geogrid are laid on the base geogrid in sequence, and a widened roadbed filling layer is filled on the geogrid. The utility model has low construction cost, long service life, strong bearing capacity, good waterproofness, and effectively solves the engineering problem of widening old roads encountered in the process of road construction in permafrost areas, filling the gap in this technical field.
[0004] However, the road was widened too long without a drainage system, so rainwater easily accumulated in the middle of the road, causing traffic accidents. Utility Model Content
[0005] The purpose of this section is to summarize some aspects of the embodiments of the utility model and briefly introduce some preferred embodiments. Some simplifications or omissions may be made in this section and the abstract of the specification and the name of the utility model to avoid blurring the purpose of this section, the abstract of the specification and the name of the utility model, and such simplifications or omissions cannot be used to limit the scope of the utility model.
[0006] Therefore, the purpose of the utility model is to provide a road widening structure that can solve the problem that the road is widened too long but no drainage system is set up, rainwater easily accumulates in the middle of the road, causing traffic accidents.
[0007] In order to solve the above technical problems, the utility model provides a road widening structure, which adopts the following technical solution: it includes an original road, a separation belt is provided on the top of the original road, the left and right sides of the original road are fixedly connected with widened roads, drainage mechanisms are provided in the two groups of widened roads, and guardrails are fixedly connected to the sides of the tops of the two groups of widened roads that are away from each other.
[0008] Optionally, the widened road includes a gravel layer, which is laid at the bottom of both sides of the original road, a crushed stone layer is laid on top of the gravel layer, a roadbed filling layer is arranged on top of the crushed stone layer, and an asphalt layer is arranged on top of the roadbed filling layer.
[0009] By adopting the above technical solution, the original road can be widened.
[0010] Optionally, the roadbed filling layer is made of reinforced concrete, the drainage mechanism is arranged in the roadbed filling layer, and the drainage mechanism is connected to the original road.
[0011] By adopting the above technical solution, a drainage mechanism is provided.
[0012] Optionally, the drainage mechanism includes a drainage pavement, which is arranged on the top left side of the roadbed filling layer, and is fixedly connected to the right top of the original pavement. Drainage holes are opened on the drainage pavement, and the drainage holes penetrate the drainage pavement. A drainage component is provided at the bottom of the drainage pavement.
[0013] By adopting the above technical solution, water on the road surface can be drained.
[0014] Optionally, the drainage component includes a connecting pipe, which is fixedly connected to the bottom of the drainage pavement, the connecting pipe is connected to the drainage hole, the bottom of the connecting pipe is connected to a drainage pipe, the drainage pipe is fixedly connected in the roadbed filling layer, and the right side of the drainage pipe passes through the roadbed filling layer.
[0015] By adopting the above technical solution, water is discharged through pipes.
[0016] Optionally, the guardrail includes a column, and a cross bar is fixedly connected to the top of the column.
[0017] By adopting the above technical solution, a guardrail is set.
[0018] In summary, the utility model includes at least one of the following beneficial effects: a drainage mechanism is provided in the widened road to avoid traffic accidents caused by rainwater being concentrated on the road surface. BRIEF DESCRIPTION OF THE DRAWINGS
[0019] In order to more clearly illustrate the technical solutions of the embodiments of the utility model, the drawings required for describing the embodiments are briefly introduced below. Obviously, the drawings described below are only some embodiments of the utility model. For ordinary technicians in this field, other drawings can be obtained based on these drawings without creative work.
[0020] Figure 1 It is a schematic diagram of the structure of the utility model;
[0021] Figure 2 It is a schematic diagram of the cross-sectional structure of the utility model;
[0022] Figure 3 It is an enlarged structural schematic diagram of section A of the present invention.
[0023] Explanation of the reference numerals: 1. original road; 2. isolation zone; 3. widened road; 301. gravel layer; 302. crushed stone layer; 303. roadbed filling layer; 304. asphalt layer; 4. drainage mechanism; 401. drainage pavement; 402. drainage hole; 403. connecting pipe; 404. drainage pipe; 5. guardrail; 501. column; 502. cross bar. DETAILED DESCRIPTION
[0024] The following is combined with Figure 1-3 The utility model is described in further detail.
[0025] Embodiment 1
[0026] Reference Figure 1 In order to achieve drainage of the widened road surface in this embodiment, the utility model discloses a road widening structure, including an original road 1, a separation strip 2 is provided on the top of the original road 1, widened roads 3 are fixedly connected to the left and right sides of the original road 1, drainage mechanisms 4 are provided in the two groups of widened roads 3, and guardrails 5 are fixedly connected to the sides of the tops of the two groups of widened roads 3 that are away from each other.
[0027] Based on the above features, the working principle of this embodiment is as follows: a separation strip 2 for distinguishing traffic is set on the top of the original road 1, and a widened road 3 is set on both sides of the original road 1 to widen the original road 1. A drainage mechanism 4 is set in the widened road 3 to drain the accumulated water on the top of the original road 1 and the widened road 3. A guardrail 5 is set on the top of the widened road 3 to prevent vehicles from rolling over on the highway.
[0028] Embodiment 2
[0029] Reference Figure 2In order to widen the original road in this embodiment, based on the same concept as the above-mentioned embodiment 1, the road widening structure also includes a widened road 3 including a gravel layer 301, the gravel layer 301 is laid on the bottom of both sides of the original road 1, and a crushed stone layer 302 is laid on the top of the gravel layer 301. A roadbed filling layer 303 is arranged on the top of the crushed stone layer 302, and an asphalt layer 304 is arranged on the top of the roadbed filling layer 303. The roadbed filling layer 303 is composed of reinforced concrete, and a drainage mechanism 4 is arranged in the roadbed filling layer 303, and the drainage mechanism 4 is connected to the original road 1.
[0030] Based on the above characteristics, the working principle of this embodiment is: a gravel layer 301 is laid at the bottom of both sides of the original road 1 to isolate the forest belt from the road surface to prevent fire, a crushed stone layer 302 is laid on the top of the gravel layer 301 to play a buffering role, and a roadbed filling layer 303 is laid on the top of the crushed stone layer 302 to fix the drainage mechanism 4.
[0031] Embodiment 3
[0032] Reference Figure 3 In order to achieve drainage after widening the road, based on the same concept as the above-mentioned embodiment 1, the road widening structure also includes a drainage mechanism 4 including a drainage pavement 401, which is arranged on the top left side of the roadbed filling layer 303, and the drainage pavement 401 is fixedly connected to the right top of the original road surface 1. A drainage hole 402 is opened on the drainage pavement 401, and the drainage hole 402 penetrates the drainage pavement 401. A drainage component is provided at the bottom of the drainage pavement 401, and the drainage component includes a connecting pipe 403, which is fixedly connected to the bottom of the drainage pavement 401, and the connecting pipe 403 is connected to the drainage hole 402. The bottom of the connecting pipe 403 is connected with a drainage pipe 404, and the drainage pipe 404 is fixedly connected in the roadbed filling layer 303. The right side of the drainage pipe 404 penetrates the roadbed filling layer 303. The guardrail 5 includes a column 501, and a crossbar 502 is fixedly connected to the top of the column 501.
[0033] Based on the above characteristics, the working principle of this embodiment is: water on the top of the original road 1 and the widened road 3 enters the connecting pipe 403 through the drainage hole 402 opened on the drainage pavement 401, the connecting pipe 403 discharges the water into the drainage pipe 404, and the drainage pipe 404 discharges the water.
[0034] The above are all preferred embodiments of the present utility model, and are not intended to limit the protection scope of the present utility model. Therefore, any equivalent changes made based on the structure, shape, and principle of the present utility model should be included in the protection scope of the present utility model.
Claims
1. A road widening structure, comprising an existing road (1), characterized in that: A separation zone (2) is provided on the top of the original road (1), and widened roads (3) are fixedly connected to the left and right sides of the original road (1), and drainage mechanisms (4) are provided in the two groups of widened roads (3). The two groups of widened roads (3) are fixedly connected to the sides away from each other at the top, and guardrails (5) are fixedly connected. The widened roads (3) include a gravel layer (301), and the gravel layer (301) is laid on the bottom of both sides of the original road (1). A crushed stone layer (302) is laid on the top of the gravel layer (301), and a roadbed filling layer (303) is provided on the top of the crushed stone layer (302). An asphalt layer (304) is provided on the top of the roadbed filling layer (303), and the roadbed filling layer (303) is composed of reinforced concrete. The drainage mechanism (4) is arranged in the roadbed filling layer (303), and the drainage mechanism (4) is connected to the original road (1). The drainage mechanism (4) comprises a drainage pavement (401), the drainage pavement (401) being arranged on the left side of the top of a roadbed filling layer (303), the drainage pavement (401) being fixedly connected to the top of the right side of the original road (1), the drainage pavement (401) being provided with a drainage hole (402), the drainage hole (402) penetrating the drainage pavement (401), a drainage component being arranged at the bottom of the drainage pavement (401), the drainage component comprising a connecting pipe (403), the connecting pipe (403) being fixedly connected to the bottom of the drainage pavement (401), the connecting pipe (403) being connected to the drainage hole (402), the bottom of the connecting pipe (403) being connected to a drainage pipe (404), the drainage pipe (404) being fixedly connected in the roadbed filling layer (303), the right side of the drainage pipe (404) penetrating the roadbed filling layer (303).
2. A road widening structure according to claim 1, characterized in that: The guardrail (5) comprises a column (501), and a crossbar (502) is fixedly connected to the top of the column (501).
Citation Information