Drilling pile structure suitable for large offshore bridge

By designing multi-layer piers and bored pile structures inserted into slightly weathered dacite at different depths in large offshore bridges, combined with steel casings and steel cages, the stability and reliability problems of offshore bridges under complex geological conditions are solved. , achieving stable support and construction safety of the bridge.

CN221822891UActive Publication Date: 2024-10-11CHINA TIESIJU CIVIL ENGINEERING GROUP CO LTD +1
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420269784.7
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-02-04
Publication Date
2024-10-11
Estimated Expiration
2034-02-04

AI Technical Summary

Technical Problem

Under complex geological conditions, it is difficult for the bored pile structure of large offshore bridges to ensure stability and reliability. Especially in sea erosion trenches and undulating terrain, traditional designs cannot meet the support needs of bridges.

Method used

A structure is designed that includes the first bored pile, the second bored pile and the third bored pile, which are located at different pier positions. The bottom of the bored pile is inserted into the slightly weathered dacite and gradually increases in depth. Steel casings and steel cages of different diameters are set up to ensure the stability and reliability of the bored piles.

Benefits of technology

Through reasonable pier position design and bored pile structure, the stability and reliability of large offshore bridges are ensured, adaptable to complex geological conditions, and the construction safety and service life of the bridge are improved.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN221822891U_ABST
    Figure CN221822891U_ABST
Patent Text Reader

Abstract

The utility model discloses a bored pile structure suitable for a large offshore bridge. The bored pile structure comprises a plurality of first bored piles, a plurality of second bored piles and a plurality of third bored piles. The multiple first drilling piles are located at a first pier position, the multiple second drilling piles are located at a second pier position, the multiple third drilling piles are located at a third pier position, the distances between the first pier position, the second pier position and the third pier position and the shoreside are gradually increased, and the heights of the seabed surfaces at the first pier position, the second pier position and the third pier position are gradually reduced; the tops of the first drilling pile, the second drilling pile and the third drilling pile are flush, the bottoms of the first drilling pile, the second drilling pile and the third drilling pile are all inserted into the slightly weathered quartz rock, and the depths of the bottoms are gradually increased; a first steel casing is arranged at the first drilled pile, a second steel casing is arranged at the second drilled pile, a third steel casing is arranged at the third drilled pile, and the diameters of the first steel casing, the second steel casing and the third steel casing are sequentially increased. The bored pile structure can ensure the stability and reliability of the large offshore bridge.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of bridge construction, and in particular to a bored pile structure suitable for large offshore bridges. Background Art

[0002] The description in this section merely provides background information related to the disclosure of this specification and does not constitute prior art.

[0003] For large or extra-large bridges with complex foundation engineering and high pier costs, and when they are close to cities and have dense railways and highways and need to build railway bridges and highway bridges to connect the lines, in order to reduce costs and shorten construction period, it is possible to consider building a bridge that is shared by both highways and railways, which is called a dual-use highway-rail bridge.

[0004] In some areas, there are many mountains and hills in the territory, which are island hilly areas. The island terrain is undulating, with a ridge or watershed in the center. The altitude is generally between 200 and 300 meters. There are small plains distributed between the mountains and the seashore. The coastline is winding, mainly bedrock and muddy coast, with a small amount of sandy coast. The construction of a dual-use highway-rail bridge in this area, after exploration, the bedrock is exposed near the sea area at the starting point of the dual-use highway-rail bridge, the mountain is steep, the slope angle is nearly vertical, the bedrock is severely eroded by the sea, and the sea erosion landform is relatively developed, mainly sea erosion grooves, among which the maximum width of the sea erosion groove is about 2m, and it can extend up to tens of meters; the end of the dual-use highway-rail bridge is located in the low hilly area. The waters of the bridge site are about 2.7km wide, the sea areas on both sides of the center line are wide, the rising and falling tides are relatively strong at the center line of the bridge, the scouring is strong, the seabed terrain is undulating, and the maximum water depth is about 93m. The water depth is greater than 60m within a range of about 1km. There is an underwater reef near the starting point - Wanzhan Reef (the minimum water depth is about 16m). The terrain near the reef is quite undulating.

[0005] In view of the complex geological conditions in the area, in order to ensure the reliability of the highway-railway dual-use bridge, it is necessary to reasonably design the bored pile positions of the bridge.

[0006] It should be noted that the above introduction to the technical background is only for the convenience of providing a clear and complete description of the technical solutions of this specification and for the convenience of understanding by those skilled in the art. It cannot be considered that the above technical solutions are well known to those skilled in the art simply because they are described in the background technology section of this specification. Summary of the invention

[0007] In view of the deficiencies in the prior art, one purpose of this specification is to provide a bored pile structure suitable for large offshore bridges, which can ensure the stability and reliability of large offshore bridges.

[0008] To achieve the above-mentioned purpose, the embodiment of this specification provides a bored pile structure suitable for a large offshore bridge, including a first bored pile, a second bored pile and a third bored pile;

[0009] wherein the number of the first bored piles, the second bored piles and the third bored piles are all multiple, multiple first bored piles are located at the first pier position, multiple second bored piles are located at the second pier position, multiple third bored piles are located at the third pier position, the distances between the first pier position, the second pier position and the third pier position and the shore gradually increase, and the heights of the seabed surfaces at the first pier position, the second pier position and the third pier position gradually decrease; the seabed covering layer at the first pier position includes silt, the seabed covering layer at the second pier position includes silt, silty clay and silty clay distributed from top to bottom, the seabed covering layer at the third pier position includes silt, silty clay and silty clay distributed from top to bottom, and the seabed covering layer at the second pier position has the largest thickness; The seabed covering layer below the first pier position includes strongly weathered dacite, weakly weathered dacite and slightly weathered dacite distributed from top to bottom, and the seabed covering layers below the second and third pier positions include fully weathered dacite, strongly weathered dacite, weakly weathered dacite and slightly weathered dacite distributed from top to bottom; the tops of the first bored pile, the second bored pile and the third bored pile are flush, the bottoms of the first bored pile, the second bored pile and the third bored pile are all inserted into the slightly weathered dacite, and the depth of the bottom gradually increases; a first steel casing is arranged at the first bored pile, a second steel casing is arranged at the second bored pile, and a third steel casing is arranged at the third bored pile, and the diameters of the first steel casing, the second steel casing and the third steel casing increase successively.

[0010] As a preferred embodiment, a first steel cage is arranged at the first bored pile, a second steel cage is arranged at the second bored pile, and a third steel cage is arranged at the third bored pile; the first steel cage is installed in the first steel casing after the first steel casing is lowered, the second steel cage is installed in the second steel casing after the second steel casing is lowered, and the third steel cage is installed in the third steel casing after the third steel casing is lowered; concrete construction is carried out after the first steel cage, the second steel cage or the third steel cage is installed.

[0011] As a preferred embodiment, the first steel cage, the second steel cage, and the third steel cage each include at least two circles of main reinforcement, and the main reinforcement is provided with multiple stiffening rings along the axial direction, and the stiffening ring includes a horizontal plate, an inner vertical plate, and an outer vertical plate; the horizontal plate is provided with an inner edge and an outer edge, and the inner edge is evenly provided with a plurality of first semicircular holes recessed outward along the circumference, and the outer edge is evenly provided with a plurality of second semicircular holes recessed inward along the circumference, the diameter of the first semicircular hole is smaller than the diameter of the second semicircular hole, and a plurality of oblong through holes are evenly provided along the circumference between the inner edge and the outer edge, the inner vertical plate is located between the first semicircular hole and the oblong through hole, and the outer vertical plate is located between the second semicircular hole and the oblong through hole.

[0012] As a preferred embodiment, the first steel cage, the second steel cage, and the third steel cage all use annular stirrups with a diameter of 16 mm, the annular stirrups use HRB400E steel bars, and the main bars use HRB500E steel bars; the first semicircular hole is sleeved on the outside of the inner circle main reinforcement, and the second semicircular hole is located on the inside of the outer circle main reinforcement; the distance between adjacent stiffening rings is 3m, and the thickness of the horizontal plate, inner vertical plate and outer vertical plate are all 20mm.

[0013] As a preferred embodiment, a plurality of acoustic detection tubes are provided in the first, second and third steel cages, and the acoustic detection tubes are connected and fixed to the stiffening rings by welding; the stiffening rings are reinforced by cross braces; the third steel cage has the largest number of acoustic detection tubes, and the main reinforcement diameter of the third steel cage is the largest.

[0014] As a preferred implementation, the first bored pile, the second bored pile and the third bored pile are all made of C45 underwater concrete, and the minimum steel bar protective layer thickness is 75 mm.

[0015] As a preferred embodiment, the diameters of the first bored pile and the second bored pile are 3.5 m, and the diameter of the third bored pile is 4.5 m; the diameter of the first steel casing is 380 cm, the diameter of the second steel casing is 400 cm, and the diameter of the third steel casing is 500 cm, and the thicknesses of the first steel casing, the second steel casing and the third steel casing are all 3 cm.

[0016] As a preferred embodiment, the seabed elevation at the first pier position is -1m~0m, the seabed elevation at the second pier position is -0.9m~-2m, and the seabed elevation at the third pier position is -32m~-22m; the bottom elevation of the first bored pile is -18.5m, the bottom elevation of the second bored pile is -42.5m, and the bottom elevation of the third bored pile is -61.0m.

[0017] As a preferred embodiment, the thickness of the seabed covering layer at the first pier position is 2.5-10.7 m; the thickness of the seabed covering layer at the second pier position is 22.7-28.8 m; and the thickness of the seabed covering layer at the third pier position is 7.5-18.6 m.

[0018] As a preferred embodiment, the thickness of the fully weathered dacite is 0.5 to 5.0 m; the thickness of the strongly weathered dacite is 0.2 to 6.2 m; the thickness of the weakly weathered dacite is 0.4 to 16.0 m; the rock penetration depth of the first bored pile is 7.23 to 15.40 m, the rock penetration depth of the second bored pile is 12.23 to 18.87 m, and the rock penetration depth of the third bored pile is 12.97 to 23.42 m.

[0019] Beneficial effects:

[0020] The bored pile structure suitable for large offshore bridges provided in this embodiment is achieved by selecting appropriate first pier positions, second pier positions and third pier positions, and respectively arranging a plurality of first bored piles, second bored piles and third bored piles at each pier position, so that the top of each bored pile is flush and the bottom is inserted into slightly weathered dacite, and the depth of the bottom of the first bored pile, the second bored pile and the third bored pile is gradually increased, and the diameters of the first steel casing, the second steel casing and the third steel casing arranged at each bored pile are increased successively, so that the bored pile structure is stable and reliable, thereby ensuring the stability and reliability of large offshore bridges.

[0021] With reference to the following description and the accompanying drawings, the specific embodiments of the present invention are disclosed in detail, indicating the manner in which the principles of the present invention can be adopted. It should be understood that the embodiments of the present invention are not limited in scope thereby.

[0022] Features described and / or illustrated with respect to one embodiment may be used in the same or similar manner in one or more other embodiments, combined with features in other embodiments, or substituted for features in other embodiments.

[0023] It should be emphasized that the term “include / comprises” when used herein refers to the presence of features, integers, steps or components, but does not exclude the presence or addition of one or more other features, integers, steps or components. BRIEF DESCRIPTION OF THE DRAWINGS

[0024] In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings required for use in the embodiments or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the present invention. For those skilled in the art, other drawings can be obtained based on these drawings without paying any creative labor.

[0025] Figure 1 This is a schematic structural diagram of a bored pile structure applicable to a large offshore bridge provided in this embodiment at a first pier position;

[0026] Figure 2 This is a schematic structural diagram of a bored pile structure applicable to a large offshore bridge provided in this embodiment at the second pier position;

[0027] Figure 3 This is a schematic structural diagram of a bored pile structure suitable for a large offshore bridge provided in this embodiment at the third pier position;

[0028] Figure 4This is a schematic structural diagram of an inner vertical plate or an outer vertical plate provided in this embodiment;

[0029] Figure 5 This is a schematic structural diagram of a horizontal plate provided in this embodiment;

[0030] Figure 6 This is a schematic structural diagram of a stiffening ring provided in this embodiment;

[0031] Figure 7 This is a schematic diagram of the structure of a stiffening ring provided in this embodiment corresponding to an acoustic detection tube and a cross brace;

[0032] Figure 8 A schematic diagram of the structure of another horizontal plate provided in this embodiment;

[0033] Fig. 9 This is a schematic diagram of the structure of another stiffening ring provided in this embodiment.

[0034] Description of reference numerals:

[0035] 1. First pier position; 2. Second pier position; 3. Third pier position; 4. First bored pile; 5. Second bored pile; 6. Third bored pile; 7. Seabed surface; 8. Silt; 9. Silt silty clay; 10. Silty clay; 11. Fully weathered dacite; 12. Strongly weathered dacite; 13. Weakly weathered dacite; 14. Slightly weathered dacite; 15. Abutment; 16. Bridge centerline; 17. Main reinforcement; 18. Stiffening ring; 19. Horizontal plate; 20. Inner edge; 21. Outer edge; 22. First semicircular hole; 23. Second semicircular hole; 24. Long round through hole; 25. Inner vertical plate; 26. Outer vertical plate; 27. Acoustic detection tube; 28. Cross brace; 29. ​​Vertical plate. DETAILED DESCRIPTION

[0036] In order to enable those skilled in the art to better understand the technical solutions in the present invention, the technical solutions in the embodiments of the present invention will be clearly and completely described below in conjunction with the drawings in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work should fall within the scope of protection of the present invention.

[0037] It should be noted that when an element is referred to as being "disposed on" another element, it may be directly on the other element or there may be another element centered thereon. When an element is considered to be "connected to" another element, it may be directly connected to the other element or there may be another element centered thereon at the same time. The terms "vertical", "horizontal", "left", "right" and similar expressions used herein are for illustrative purposes only and do not represent the only implementation method.

[0038] Unless otherwise defined, all technical and scientific terms used herein have the same meaning as those commonly understood by those skilled in the art of the present invention. The terms used herein in the specification of the present invention are only for the purpose of describing specific embodiments and are not intended to limit the present invention. The term "and / or" used herein includes any and all combinations of one or more related listed items.

[0039] See also Figures 1 to 9 The embodiment of the present application provides a bored pile structure suitable for a large offshore bridge, including a first bored pile 4 , a second bored pile 5 and a third bored pile 6 .

[0040] The number of the first bored piles 4, the second bored piles 5 and the third bored piles 6 are all multiple, multiple first bored piles 4 are located at the first pier position 1, multiple second bored piles 5 are located at the second pier position 2, multiple third bored piles 6 are located at the third pier position 3, the distances between the first pier position 1, the second pier position 2 and the third pier position 3 and the shore gradually increase, and the heights of the seabed surfaces 7 at the first pier position 1, the second pier position 2 and the third pier position 3 gradually decrease. Figure 1 As shown, the seabed cover at the first pier position 1 includes silt 8. Figure 2 As shown, the seabed covering layer at the second pier position 2 includes silt 8, silty silty clay 9, and silty clay 10 distributed from top to bottom. Figure 3As shown, the seabed cover layer at the third pier position 3 includes silt 8, silty clay 10 and silty silty clay 9 distributed from top to bottom. The seabed cover layer at the second pier position 2 has the largest thickness. The seabed cover layer below the first pier position 1 includes strongly weathered dacite 12, weakly weathered dacite 13 and slightly weathered dacite 14 distributed from top to bottom, and the seabed cover layers below the second pier position 2 and the third pier position 3 both include fully weathered dacite 11, strongly weathered dacite 12, weakly weathered dacite 13 and slightly weathered dacite 14 distributed from top to bottom. The tops of the first bored pile 4, the second bored pile 5 and the third bored pile 6 are flush and are all provided with a cap 15. The bottoms of the first bored pile 4, the second bored pile 5 and the third bored pile 6 are all inserted into the slightly weathered dacite 14, and the depth of the bottom gradually increases. A first steel casing is arranged at the first bored pile 4, a second steel casing is arranged at the second bored pile 5, and a third steel casing is arranged at the third bored pile 6. The diameters of the first steel casing, the second steel casing and the third steel casing increase in sequence.

[0041] The bored pile structure suitable for large offshore bridges provided in this embodiment is achieved by selecting a suitable first pier 1, a second pier 2 and a third pier 3, and respectively arranging a plurality of first bored piles 4, a second bored pile 5 and a third bored pile 6 at each pier, so that the top of each bored pile is flush and the bottom is inserted into the slightly weathered dacite 14, and the depth of the bottom of the first bored pile 4, the second bored pile 5 and the third bored pile 6 is gradually increased, and the diameters of the first steel casing, the second steel casing and the third steel casing arranged at each bored pile are increased successively, so that the bored pile structure is stable and reliable, thereby ensuring the stability and reliability of large offshore bridges.

[0042] In this embodiment, the diameter of the first bored pile 4 and the second bored pile 5 may be 3.5 m, and the diameter of the third bored pile 6 is 4.5 m. The diameter of the first steel casing is 380 cm, the diameter of the second steel casing is 400 cm, and the diameter of the third steel casing is 500 cm. The thickness of the first steel casing, the second steel casing and the third steel casing are all 3 cm.

[0043] Preferably, the number of the first bored piles 4, the second bored piles 5 and the third bored piles 6 are all 8, which are arranged in two rows. Figures 1 to 3 As shown, each row is provided with 4 bored piles, which are symmetrically arranged about the center line 16 of the bridge.

[0044] In this embodiment, the first bored pile 4, the second bored pile 5 and the third bored pile 6 are all made of C45 underwater concrete, and the minimum steel protection layer thickness is 75mm. The first steel casing, the second steel casing and the third steel casing are all permanent steel casings, and the material is Q235B, so as to further ensure the stability and reliability of the bored piles.

[0045] Specifically, the first pier 1 and the second pier 2 are located in the shallows area, the seabed surface 7 at the first pier 1 has an elevation of -1m to 0m, and the seabed surface 7 at the second pier 2 has an elevation of -0.9m to -2m. The seabed surface 7 at the third pier 3 has large fluctuations, and the slope direction is basically consistent with the bridge axis. The seabed surface 7 has an elevation of -32m to -22m, and the elevation changes by 10m. Preferably, the bottom elevation of the first bored pile 4 is -18.5m, the bottom elevation of the second bored pile 5 is -42.5m, and the bottom elevation of the third bored pile 6 is -61.0m. The top elevation of the cap 15 is +4m.

[0046] In this embodiment, the seabed cover gradually deepens from the shore to the sea area, and is mainly composed of fluidized silt 8, silty silty clay 9, and hard plastic silty clay 10. The underlying bedrock is dacite. The thickness of the seabed cover at the first pier 1 is 2.5 to 10.7 m; the thickness of the seabed cover at the second pier 2 is 22.7 to 28.8 m; the thickness of the seabed cover at the third pier 3 is 7.5 to 18.6 m. A joint-dense zone is locally developed in the bedrock, and the rock mass in the zone is broken or relatively broken. The fully weathered layer is 5.0 to 7.8 m thick; the strongly weathered layer is 0.6 to 1.8 m thick; the weakly weathered layer is 25.5 m thick, and the burial depth increases with the thickening of the cover layer.

[0047] Specifically, the thickness of the fully weathered dacite 11 is 0.5-5.0 m; the thickness of the strongly weathered dacite 12 is 0.2-6.2 m; the thickness of the weakly weathered dacite 13 is 0.4-16.0 m. The rock penetration depth of the first bored pile 4 is 7.23-15.40 m, the rock penetration depth of the second bored pile 5 is 12.23-18.87 m, and the rock penetration depth of the third bored pile 6 is 12.97-23.42 m, so as to ensure the strength of each bored pile.

[0048] In this embodiment, a first steel cage is arranged at the first bored pile 4, a second steel cage is arranged at the second bored pile 5, and a third steel cage is arranged at the third bored pile 6. The first steel cage is installed in the first steel casing after the first steel casing is lowered, the second steel cage is installed in the second steel casing after the second steel casing is lowered, and the third steel cage is installed in the third steel casing after the third steel casing is lowered. After the first steel cage, the second steel cage, or the third steel cage is installed, concrete construction is carried out, so that the bored piles provide stable support for the bridge.

[0049] Specifically, the first steel cage, the second steel cage, and the third steel cage all include at least two circles of main bars 17. Three circles of main bars 17 can be set at the local variable cross-section positions of the second steel cage and the third steel cage. The main bars 17 of the third steel cage have the largest diameter. The diameter of the inner ring main bars 17 of the first and second steel cages is 36 mm, and the diameter of the outer ring main bars 17 is 40 mm; the diameter of the main bars 17 of the third steel cage can be 50 mm. The main bars 17 are made of HRB500E steel bars. The first steel cage, the second steel cage, and the third steel cage all use annular stirrups with a diameter of 16 mm, and the annular stirrups are made of HRB400E steel bars. The stirrup spacing below the bottom of the pedestal 15 is divided into 10 cm and 15 cm, and the stirrup spacing above the bottom of the pedestal 15 is 20 cm.

[0050] In this embodiment, the main reinforcement 17 is provided with multiple stiffening rings 18 along the axial direction. In order to ensure the rigidity, strength and stability of each steel cage during construction, one type of stiffening ring 18 is designed for the first steel cage, and three types of stiffening rings 18 are designed for the second and third steel cages. The distance between adjacent stiffening rings 18 is preferably 3m.

[0051] like Figures 4 to 6 As shown, the reinforcing ring 18 includes a horizontal plate 19, an inner vertical plate 25 and an outer vertical plate 26. The horizontal plate 19, the inner vertical plate 25 and the outer vertical plate 26 are all 20 mm thick, in a circular shape, and made of steel plates. Figure 5 As shown, the horizontal plate 19 is provided with an inner edge 20 and an outer edge 21, the inner edge 20 is provided with a plurality of first semicircular holes 22 that are concave outwards uniformly along the circumference, and the outer edge 21 is provided with a plurality of second semicircular holes 23 that are concave inwards uniformly along the circumference, and the diameter of the first semicircular holes 22 is smaller than the diameter of the second semicircular holes 23. A plurality of oblong through holes 24 are uniformly provided between the inner edge 20 and the outer edge 21 along the circumference. The inner vertical plate 25 is located between the first semicircular holes 22 and the oblong through hole 24, and the outer vertical plate 26 is located between the second semicircular holes 23 and the oblong through hole 24.

[0052] like Figure 7As shown, the first semicircular hole 22 is sleeved on the outside of the inner ring main reinforcement 17, and the second semicircular hole 23 is located on the inside of the outer ring main reinforcement 17. A plurality of sonic detection tubes 27 are evenly spaced circumferentially in the first, second and third steel cages, and the sonic detection tubes 27 are connected and fixed to the stiffening ring 18 by welding, and specifically, L50*50*5 angle steel can be welded and fixed to the stiffening ring 18. The number of sonic detection tubes 27 in the third steel cage is the largest, which can be 6, and the number of sonic detection tubes 27 in the first and second steel cages is 5. The diameter of the sonic detection tube 27 is 57mm and the thickness is 3mm. The stiffening ring 18 is reinforced with a cross brace 28. The cross brace 28 in the first and second steel cages can be welded with No. 8 channel steel, and the cross brace 28 in the third steel cage can be welded with No. 10 channel steel.

[0053] For the second and third steel cages, the reinforcing rings 18 can also be selected from Figure 8 and Fig. 9 The design shown includes a horizontal plate 19 and a vertical plate 29. The inner edge 20 of the horizontal plate 19 is smooth, and only the outer edge 21 is evenly provided with a plurality of inwardly recessed second semicircular holes 23 along the circumferential direction. The second semicircular holes 23 and the vertical plate 29 are located inside the main rib 17.

[0054] It should be noted that, in the description of this specification, the terms "first", "second", etc. are only used for descriptive purposes and to distinguish similar objects. There is no order of precedence between the two, and they cannot be understood as indicating or implying relative importance. In addition, in the description of this specification, unless otherwise specified, the meaning of "plurality" is two or more.

[0055] Any numerical value cited herein includes all values ​​of lower and upper values ​​that increase by one unit from the lower limit to the upper limit, and there is at least a two-unit interval between any lower value and any higher value. For example, if the value of the quantity of a component or a process variable (such as temperature, pressure, time, etc.) is stated to be from 1 to 90, preferably from 20 to 80, and more preferably from 30 to 70, the purpose is to illustrate that values ​​such as 15 to 85, 22 to 68, 43 to 51, 30 to 32 are also explicitly listed in the specification. For values ​​less than 1, one unit is appropriately considered to be 0.0001, 0.001, 0.01, 0.1. These are merely examples that are intended to be clearly expressed, and it can be considered that all possible combinations of numerical values ​​listed between the lowest value and the highest value are clearly stated in the specification in a similar manner.

[0056] Unless otherwise indicated, all ranges include the endpoints and all numbers between the endpoints. "About" or "approximately" used with a range applies to both endpoints of the range. Thus, "about 20 to 30" is intended to cover "about 20 to about 30", including at least the specified endpoints.

[0057] All articles and references disclosed, including patent applications and publications, are incorporated herein by reference for all purposes. The term "consisting essentially of..." to describe a combination should include the identified elements, ingredients, parts or steps and other elements, ingredients, parts or steps that do not substantially affect the basic novel characteristics of the combination. The use of the terms "comprising" or "including" to describe a combination of elements, ingredients, parts or steps herein also contemplates embodiments that consist essentially of these elements, ingredients, parts or steps. By using the term "may", it is intended to indicate that any attribute described that "may" include is optional.

[0058] Multiple elements, ingredients, parts or steps can be provided by a single integrated element, ingredient, part or step. Alternatively, a single integrated element, ingredient, part or step can be divided into separate multiple elements, ingredients, parts or steps. The disclosure "one" or "an" used to describe an element, ingredient, part or step is not intended to exclude other elements, ingredients, parts or steps.

[0059] It should be understood that the above description is for illustration and not for limitation. Many embodiments and many applications beyond the examples provided will be apparent to those skilled in the art upon reading the above description. Therefore, the scope of the present teachings should not be determined with reference to the above description, but should be determined with reference to the appended claims and the full scope of equivalents possessed by such claims. For the purpose of comprehensiveness, all articles and references, including disclosures of patent applications and publications, are incorporated herein by reference. The omission of any aspect of the subject matter disclosed herein in the preceding claims is not intended to be a waiver of the subject matter, nor should it be considered that the inventors did not consider the subject matter to be part of the disclosed inventive subject matter.

Claims

1. A bored pile structure suitable for large offshore bridges, characterized in that: including a first bored pile, a second bored pile and a third bored pile; wherein the number of the first bored piles, the second bored piles and the third bored piles are all multiple, multiple first bored piles are located at the first pier position, multiple second bored piles are located at the second pier position, multiple third bored piles are located at the third pier position, the distances between the first pier position, the second pier position and the third pier position and the shore gradually increase, and the heights of the seabed surfaces at the first pier position, the second pier position and the third pier position gradually decrease; the seabed covering layer at the first pier position includes silt, the seabed covering layer at the second pier position includes silt, silty clay and silty clay distributed from top to bottom, the seabed covering layer at the third pier position includes silt, silty clay and silty clay distributed from top to bottom, and the seabed covering layer at the second pier position has the largest thickness; The seabed covering layer below the first pier position includes strongly weathered dacite, weakly weathered dacite and slightly weathered dacite distributed from top to bottom, and the seabed covering layers below the second and third pier positions include fully weathered dacite, strongly weathered dacite, weakly weathered dacite and slightly weathered dacite distributed from top to bottom; the tops of the first bored pile, the second bored pile and the third bored pile are flush, the bottoms of the first bored pile, the second bored pile and the third bored pile are all inserted into the slightly weathered dacite, and the depth of the bottom gradually increases; a first steel casing is arranged at the first bored pile, a second steel casing is arranged at the second bored pile, and a third steel casing is arranged at the third bored pile, and the diameters of the first steel casing, the second steel casing and the third steel casing increase successively.

2. The bored pile structure suitable for large offshore bridges according to claim 1, characterized in that: A first steel cage is arranged at the first bored pile, a second steel cage is arranged at the second bored pile, and a third steel cage is arranged at the third bored pile; the first steel cage is installed in the first steel casing after the first steel casing is lowered, the second steel cage is installed in the second steel casing after the second steel casing is lowered, and the third steel cage is installed in the third steel casing after the third steel casing is lowered; concrete construction is carried out after the first steel cage, the second steel cage or the third steel cage is installed.

3. The bored pile structure suitable for large offshore bridges according to claim 2, characterized in that: The first steel cage, the second steel cage and the third steel cage all include at least two circles of main reinforcement, and the main reinforcement is provided with multiple stiffening rings along the axial direction, and the stiffening ring includes a horizontal plate, an inner vertical plate and an outer vertical plate; the horizontal plate is provided with an inner edge and an outer edge, and the inner edge is evenly provided with a plurality of first semicircular holes recessed outward along the circumference, and the outer edge is evenly provided with a plurality of second semicircular holes recessed inward along the circumference, the diameter of the first semicircular hole is smaller than the diameter of the second semicircular hole, and a plurality of oblong through holes are evenly provided between the inner edge and the outer edge along the circumference, the inner vertical plate is located between the first semicircular hole and the oblong through hole, and the outer vertical plate is located between the second semicircular hole and the oblong through hole.

4. The bored pile structure suitable for large offshore bridges according to claim 3 is characterized in that: The first steel cage, the second steel cage and the third steel cage all use annular stirrups with a diameter of 16 mm, the annular stirrups are made of HRB400E steel bars, and the main bars are made of HRB500E steel bars; the first semicircular hole is arranged on the outside of the inner circle main bars, and the second semicircular hole is located on the inside of the outer circle main bars; the distance between adjacent stiffening rings is 3m, and the thickness of the horizontal plate, inner vertical plate and outer vertical plate are all 20mm.

5. The bored pile structure suitable for large offshore bridges according to claim 3, characterized in that: The first steel cage, the second steel cage and the third steel cage are each provided with a plurality of sonic detection tubes, which are connected and fixed to the stiffening rings by welding; the stiffening rings are reinforced by cross braces; the third steel cage has the largest number of sonic detection tubes, and the main reinforcement diameter of the third steel cage is the largest.

6. The bored pile structure suitable for large offshore bridges according to claim 2, characterized in that: The first bored pile, the second bored pile and the third bored pile are all made of C45 underwater concrete, and the minimum protective layer thickness of the steel bars is 75 mm.

7. The bored pile structure suitable for large offshore bridges according to claim 1, characterized in that: The diameters of the first bored pile and the second bored pile are 3.5 m, and the diameter of the third bored pile is 4.5 m; the diameter of the first steel casing is 380 cm, the diameter of the second steel casing is 400 cm, and the diameter of the third steel casing is 500 cm; the thicknesses of the first steel casing, the second steel casing and the third steel casing are all 3 cm.

8. The bored pile structure suitable for large offshore bridges according to claim 1, characterized in that: The seabed elevation at the first pier position is -1m~0m, the seabed elevation at the second pier position is -0.9m~-2m, and the seabed elevation at the third pier position is -32m~-22m; the bottom elevation of the first bored pile is -18.5m, the bottom elevation of the second bored pile is -42.5m, and the bottom elevation of the third bored pile is -61.0m.

9. The bored pile structure suitable for large offshore bridges according to claim 1, characterized in that: The thickness of the seabed covering layer at the first pier position is 2.5 to 10.7 m; the thickness of the seabed covering layer at the second pier position is 22.7 to 28.8 m; and the thickness of the seabed covering layer at the third pier position is 7.5 to 18.6 m.

10. The bored pile structure suitable for large offshore bridges according to claim 1, characterized in that: The thickness of the fully weathered dacite is 0.5 to 5.0 m; the thickness of the strongly weathered dacite is 0.2 to 6.2 m; the thickness of the weakly weathered dacite is 0.4 to 16.0 m; the rock penetration depth of the first bored pile is 7.23 to 15.40 m, the rock penetration depth of the second bored pile is 12.23 to 18.87 m, and the rock penetration depth of the third bored pile is 12.97 to 23.42 m.