Artificial slope protection structure for ecological restoration
By using components such as fixed anchors, support blocks, filters, and springs in the artificial slope protection structure, the problems of sediment and garbage clogging in rainwater and loose brick layers are solved, achieving a stronger slope protection structure and a longer service life.
Patent Information
- Application Number
- CN202420630686.1
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-03-29
- Publication Date
- 2024-10-11
- Estimated Expiration
- 2034-03-29
AI Technical Summary
In the existing artificial slope protection structure, the sediment and garbage carried in the rainwater can easily block the through holes, causing the rainwater to overflow the drain board and the slope protection bricks to loosen, which causes problems in construction and use.
An artificial slope protection structure for ecological restoration is designed, which uses components such as fixed anchors, support blocks, filters, and springs to filter rainwater through the filter, and the springs buffer the impact of rainwater, thereby improving the firmness and service life of the brick layer.
It effectively prevents sediment and garbage from clogging the drainage pipes, prevents rainwater from overflowing the water collection tank and impacting the brick layer, improves the firmness and service life of the slope protection structure, and simplifies the structure and installation process.
Smart Images

Figure CN221822935U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of artificial slope protection, in particular to an artificial slope protection structure for ecological restoration. Background Art
[0002] After the construction of artificial slope protection, slope protection bricks are generally piled on the surface of the slope protection to reinforce the slope protection. The reinforced slope protection is conducive to soil retention, which can enable the plants on the slope protection to grow better and repair the ecology.
[0003] Through searching, it was found that CN218175874U discloses an artificial slope protection structure for ecological restoration in the field of slope protection technology, including a main body, including slope protection bricks tightly paved on the slope, and the slope protection bricks are provided with planting soil covering the slope; a guide component, including a fixed plate inserted into the slope, and anchor rods inserted into the slope are arranged around the fixed plate, and the fixed plate is fitted with the top of the slope protection bricks at the top, and a connecting structure is arranged on the fixed plate, and a water flow plate is arranged on the connecting structure. Rainwater flowing down from the top of the slope passes through the fixed plate and the water flow plate, flows into the groove, and then passes through the through hole and the water flow pipe to discharge the rainwater directly to the bottom of the slope, thereby avoiding the problem of rainwater flowing down from the top of the slope directly impacting the slope protection bricks for a long time, which is easy to cause loosening.
[0004] However, there are still some problems and shortcomings in the use process:
[0005] By setting up water pipes and through holes, rainwater can be discharged directly to the bottom of the slope. However, rainwater often carries a lot of mud and garbage, which makes the through holes easily blocked. Once the through holes are blocked, rainwater will overflow the water flow board, and the slope protection bricks will still be impacted by the rainwater, causing the slope protection bricks to loosen. Therefore, there is room for improvement. Utility Model Content
[0006] The purpose of the utility model is to provide an artificial slope protection structure for ecological restoration to solve the problems raised in the above-mentioned background technology.
[0007] To achieve the above-mentioned purpose, the utility model provides the following technical solutions: an artificial slope protection structure for ecological restoration, comprising a slope protection body and fixed anchors, the lower end side of the slope protection body is provided with a cement lower sill, the upper end side of the slope protection body is provided with a cement upper sill, the surface of the slope protection body is paved with a planting layer, the surface of the planting layer is paved with a brick layer, the fixed anchors penetrate the planting layer and the brick layer and are inserted and fixed inside the slope protection body, the top of the fixed anchor is fixedly connected to a support block, the surface of the support block is provided with a through hole, the inner wall of the through hole is provided with a drainage pipe, the upper end of the drainage pipe is fixedly connected to a water collecting tank, and the drainage pipe extends to the inner bottom of the water collecting tank, T-shaped grooves are provided on both sides of the inner wall of the water collecting tank, the inner wall of the T-shaped groove is slidably connected with a T-shaped slider, and the side of the T-shaped slider is fixedly connected with a filter.
[0008] Preferably, a carrying pole is fixedly connected to the surface of the filter screen, and there are two carrying poles which are symmetrically arranged at both ends of the filter screen surface.
[0009] Preferably, a compression plate is fixedly connected to the outer surface of the fixing anchor, and the compression plate is in close contact with the surface of the brick layer.
[0010] Preferably, the drain pipe and the support block are slidably connected, and a spring sleeved on the outer surface of the drain pipe is fixedly connected to the surface of the support block.
[0011] Preferably, a shielding plate is fixedly connected to the surface of the water collecting tank, and the shielding plate is located above the spring and is slidably connected to the support block.
[0012] Preferably, the brick layer includes a plurality of hexagonal bricks and trapezoidal bricks, the surface of the hexagonal bricks is provided with circular through holes, and the diameter of the circular through holes is larger than the diameter of the fixing anchors, the trapezoidal bricks are arranged between the hexagonal bricks at intervals, and the trapezoidal bricks are respectively in conflict with the cement upper sill and the cement lower sill.
[0013] Preferably, the surface of the cement upper sill is threadedly connected with limiting bolts.
[0014] Beneficial Effects
[0015] The utility model provides an artificial slope protection structure for ecological restoration, which has the following beneficial effects:
[0016] 1. The artificial slope protection structure for ecological restoration can support the drainage pipe and the water collecting tank by setting fixed anchor nails and support blocks. By setting a T-shaped slide, the filter net can be easily installed in the water collecting tank. By setting a hand column, the filter net can be easily pulled and disassembled for cleaning. The filter net can be used to filter the rainwater entering the water collecting tank, effectively avoiding the situation where mud and garbage block the entrance of the drainage pipe, thereby avoiding the situation where rainwater overflows the water collecting tank and impacts the brick layer.
[0017] 2. The artificial slope protection structure for ecological restoration can limit the upper and lower ends of the brick layer by setting cement upper and lower sills, and can apply extrusion pressure to the surface of the brick layer by setting a compression plate. In summary, the firmness of the brick layer laying and installation can be effectively improved, and the overall service life of the slope protection structure can be improved.
[0018] 3. The artificial slope protection structure for ecological restoration, by setting a spring and utilizing the drainage pipe to slide in the through hole on the surface of the support block, can convert the impact force generated by rainwater hitting the water collection tank into the elastic potential energy of the spring, thereby playing a role in buffering the impact force of rainwater. Compared with the existing technology, the structure is simpler and the installation is more convenient. BRIEF DESCRIPTION OF THE DRAWINGS
[0019] Figure 1 It is a schematic diagram of the three-dimensional structure of the utility model;
[0020] Figure 2 This is a schematic diagram of the front section structure of the utility model;
[0021] Figure 3 Utility Model Figure 2 A is an enlarged structural diagram;
[0022] Figure 4 It is a schematic diagram of the three-dimensional structure of the water collecting tank of the utility model when viewed from above.
[0023] In the figure: 1. Slope protection body; 2. Fixed anchor nails; 3. Cement lower sill; 4. Cement upper sill; 5. Planting layer; 6. Brick layer; 7. Support block; 8. Drain pipe; 9. Water collecting tank; 10. T-shaped slide; 11. T-shaped slider; 12. Filter; 13. Hand column; 14. Pressing plate; 15. Spring; 16. Shielding plate; 17. Hexagonal brick; 18. Trapezoidal brick; 19. Circular through hole; 20. Limit bolt. DETAILED DESCRIPTION
[0024] The following will be combined with the drawings in the embodiments of the utility model to clearly and completely describe the technical solutions in the embodiments of the utility model. Obviously, the described embodiments are only part of the embodiments of the utility model, not all of the embodiments. Based on the embodiments in the utility model, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the utility model.
[0025] See also Figure 1-4The utility model provides a technical solution: an artificial slope protection structure for ecological restoration, comprising a slope protection body 1 and fixed anchor nails 2, the lower end side of the slope protection body 1 is provided with a cement lower sill 3, the upper end side of the slope protection body 1 is provided with a cement upper sill 4, the surface of the slope protection body 1 is paved with a planting layer 5, the surface of the planting layer 5 is paved with a brick layer 6, the fixed anchor nails 2 penetrate the planting layer 5 and the brick layer 6 and are inserted and fixed inside the slope protection body 1, the top of the fixed anchor nail 2 is fixedly connected with a support block 7, the surface of the support block 7 is provided with a through hole, the inner wall of the through hole is provided with a drainage pipe 8, the upper end of the drainage pipe 8 is fixedly connected with a water collecting box 9, and the drainage pipe 8 extends to the inner bottom of the water collecting box 9, and T-shaped grooves 10 are provided on both sides of the inner wall of the water collecting box 9, the inner wall of the T-shaped groove 10 is slidably connected with a T-shaped slider 11, and the side of the T-shaped slider 11 is fixedly connected with a filter screen 12.
[0026] The surface of the filter screen 12 is fixedly connected with a carrying column 13. There are two carrying columns 13 and they are symmetrically arranged at both ends of the surface of the filter screen 12. By setting the fixed anchor nails 2 and the support blocks 7, the drain pipe 8 and the water collecting tank 9 can be supported. By setting the T-shaped slide groove 10, the filter screen 12 can be easily installed in the water collecting tank 9. By setting the carrying column 13, the filter screen 12 can be easily pulled and disassembled for cleaning. The filter screen 12 can be used to filter rainwater entering the water collecting tank 9, which effectively avoids the situation where mud and garbage block the entrance of the drain pipe 8, thereby avoiding the situation where rainwater overflows the water collecting tank 9 and impacts the brick layer 6.
[0027] The outer surface of the fixed anchor 2 is fixedly connected with a clamping plate 14, and the clamping plate 14 is tightly attached to the surface of the brick layer 6. The upper and lower ends of the brick layer 6 can be limited by setting the cement upper sill 4 and the cement lower sill 3. By setting the clamping plate 14, an extrusion force can be applied to the surface of the brick layer 6. In summary, the firmness of the laying and installation of the brick layer 6 can be effectively improved, and the overall service life of the slope protection structure can be improved.
[0028] The drain pipe 8 and the support block 7 are slidably connected, and the surface of the support block 7 is fixedly connected with a spring 15 which is sleeved on the outer surface of the drain pipe 8. By setting the spring 15 and utilizing the drain pipe 8 to slide in the through hole on the surface of the support block 7, the impact force generated by rainwater impacting the water collection tank 9 can be converted into the elastic potential energy of the spring 15, thereby playing a role in buffering the impact force of rainwater. Compared with the existing technology, the structure is simpler and the installation is more convenient.
[0029] A shielding plate 16 is fixedly connected to the surface of the water collecting box 9. The shielding plate 16 is located above the spring 15 and is slidably connected to the support block 7. The shielding plate 16 can prevent rainwater from contacting the spring 15, thereby effectively preventing the spring 15 from corroding and rusting.
[0030] The brick layer 6 includes a plurality of hexagonal bricks 17 and trapezoidal bricks 18. A circular through hole 19 is provided on the surface of the hexagonal brick 17, and the diameter of the circular through hole 19 is larger than the diameter of the fixed anchor 2. The trapezoidal bricks 18 are arranged at intervals between the hexagonal bricks 17, and the trapezoidal bricks 18 are respectively in conflict with the cement upper sill 4 and the cement lower sill 3. By arranging a plurality of hexagonal bricks 17 and trapezoidal bricks 18, plane paving can be completed. By arranging the circular through hole 19, it is convenient to insert the fixed anchor 2 and to plant ecological green plants.
[0031] The surface of the cement upper sill 4 is threadedly connected with a limit bolt 20. By setting the limit bolt 20, the water collecting box 9 can be limited, effectively preventing the water collecting box 9 from being drawn away from the upper end.
[0032] Working principle: When the artificial slope protection structure for ecological restoration is being installed, the cement upper sill 4 and the cement lower sill 3 can be built with cement at the upper and lower ends of the slope protection body 1, and then the planting layer 5 can be laid on the side of the slope protection body 1 and located between the cement upper sill 4 and the cement lower sill 3, and then the brick layer 6 can be laid on the surface of the planting layer 5. Next, multiple fixing anchors 2 can be inserted and fixed in the circular through holes 19 of the hexagonal bricks 17, and the pressing plate 14 can be pressed against the brick layer 6, and then ... then multiple fixing anchors 2 can be inserted and fixed in the circular through holes 19 of the hexagonal bricks 17, and the pressing plate 14 can be pressed against the brick layer 6, and then multiple fixing anchors 2 can be inserted and fixed in the circular through holes 19 of the hexagonal bricks 17, and then multiple fixing anchors 2 can be inserted and fixed in the circular through holes 19 of the hexagonal bricks 17, and the fixing anchors 2 can be inserted and fixed in the circular through holes 19 of the hexagonal bricks 17, and the fixing anchors 2 can be inserted and fixed in the circular through holes A drainage pipe 8 is inserted into the through hole on the surface of the support block 7, and finally the T-shaped sliders 11 at both ends of the filter screen 12 are slid into the T-shaped slide groove 10, and the limit bolts 20 are tightened; when rainwater enters the water collecting tank 9, the filter screen 12 can be used to filter the rainwater to prevent garbage and soil from clogging the drainage pipe 8. The rainwater entering the water collecting tank 9 will be discharged from the drainage pipe 8 into the bottom of the slope protection body 1, thereby effectively preventing rainwater from directly impacting the slope protection body 1 and causing the brick layer 6 to loosen.
[0033] In the drawings of the embodiments disclosed in the present utility model, only the structures related to the embodiments disclosed in the present utility model are involved, and other structures can refer to the general design. In the absence of conflict, the same embodiment and different embodiments of the present utility model can be combined with each other;
[0034] Finally: The above description is only a preferred embodiment of the present utility model and is not intended to limit the present utility model. Any modifications, equivalent substitutions, improvements, etc. made within the spirit and principles of the present utility model should be included in the protection scope of the present utility model.
Claims
1. An artificial slope protection structure for ecological restoration, comprising a slope protection body (1) and fixed anchors (2), characterized in that: The lower end side surface of the slope protection body (1) is provided with a cement lower sill (3), the upper end side surface of the slope protection body (1) is provided with a cement upper sill (4), the surface of the slope protection body (1) is paved with a planting layer (5), the surface of the planting layer (5) is paved with a brick layer (6), the fixed anchor (2) penetrates the planting layer (5) and the brick layer (6) and is inserted and fixed inside the slope protection body (1), the top of the fixed anchor (2) is fixedly connected to a support block (7), the surface of the support block (7) is provided with a through hole, the inner wall of the through hole is provided with a drainage pipe (8), the upper end of the drainage pipe (8) is fixedly connected to a water collecting box (9), and the drainage pipe (8) extends to the inner bottom of the water collecting box (9), the inner wall of the water collecting box (9) is provided with T-shaped grooves (10), the inner wall of the T-shaped groove (10) is slidably connected to a T-shaped slider (11), and the side of the T-shaped slider (11) is fixedly connected to a filter screen (12).
2. The artificial slope protection structure for ecological restoration according to claim 1, characterized in that: The surface of the filter screen (12) is fixedly connected with a carrying pole (13), and there are two carrying poles (13) which are symmetrically arranged at two ends of the surface of the filter screen (12).
3. The artificial slope protection structure for ecological restoration according to claim 1, characterized in that: A compression plate (14) is fixedly connected to the outer surface of the fixing anchor (2), and the compression plate (14) is in close contact with the surface of the brick layer (6).
4. The artificial slope protection structure for ecological restoration according to claim 1, characterized in that: The drain pipe (8) and the support block (7) are slidably connected, and a spring (15) sleeved on the outer surface of the drain pipe (8) is fixedly connected to the surface of the support block (7).
5. The artificial slope protection structure for ecological restoration according to claim 1, characterized in that: A shielding plate (16) is fixedly connected to the surface of the water collecting box (9); the shielding plate (16) is located above the spring (15) and is slidably connected to the support block (7).
6. The artificial slope protection structure for ecological restoration according to claim 1, characterized in that: The brick layer (6) comprises a plurality of hexagonal bricks (17) and trapezoidal bricks (18). A circular through hole (19) is provided on the surface of the hexagonal brick (17), and the diameter of the circular through hole (19) is larger than the diameter of the fixing anchor (2). The trapezoidal bricks (18) are arranged between the hexagonal bricks (17) at intervals, and the trapezoidal bricks (18) are respectively in conflict with the cement upper sill (4) and the cement lower sill (3).
7. The artificial slope protection structure for ecological restoration according to claim 1, characterized in that: The surface of the cement upper sill (4) is threadedly connected with a limiting bolt (20).