Supporting and positioning tool of wall aluminum formwork for pouring shear wall

By using an inverted T-shaped guide frame and a cylinder with a "mouth" cross-section to close the gap space in the support of the wall aluminum formwork, the time-consuming and labor-intensive control of the verticality and flatness of the wall formwork and the problem of root rot are solved, and the problem is achieved Efficient construction and reduced project costs.

CN221823398UActive Publication Date: 2024-10-11SHANXI NO 3 CONSTR ENG
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420082217.0
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-01-12
Publication Date
2024-10-11
Estimated Expiration
2034-01-12

AI Technical Summary

Technical Problem

In the cast-in-place construction of high-rise buildings, the existing technology is time-consuming and labor-intensive to control the verticality and flatness after the wall aluminum formwork is supported, and root rot is prone to occur during concrete pouring after filling with mortar.

Method used

Design a stereotyped inverted T-shaped guide frame, by setting a cylinder with a "mouth" cross-section at the bottom of the guide frame to close the strip-shaped void space, and use the vertical vertical plates of the guide frame to control the verticality and flatness of the wall aluminum formwork , simplify the installation procedure and avoid root rot.

Benefits of technology

It greatly simplifies the process of adjusting the verticality and flatness of the wall formwork, avoids root rot after pouring, improves construction efficiency, and reduces project costs.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN221823398U_ABST
    Figure CN221823398U_ABST
Patent Text Reader

Abstract

The utility model discloses an erecting and positioning tool of a wall aluminum formwork for pouring a shear wall, and solves the problems of how to simplify the erecting perpendicularity control program of the wall formwork and avoid the root rot phenomenon after the shear wall is poured. A shaped inverted-T-shaped guide frame capable of controlling the perpendicularity of a wall erecting formwork is designed, a barrel with a square section is arranged on the inner side of the lower end of the inverted-T-shaped guide frame, the wall erecting formwork is connected to the inverted-T-shaped guide frame in an abutting mode, and the square barrel at the bottom end of the inverted-T-shaped guide frame is arranged in a strip-shaped gap space on the outer side of angle steel under a wall aluminum formwork. The strip-shaped space is sealed, and the perpendicularity of the wall aluminum formwork is controlled by the vertical plate of the guide frame, so that the perpendicularity control procedure of erecting the wall aluminum formwork is simplified, and the root rotting phenomenon of a poured wall is avoided.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to a formwork system for casting a shear wall, in particular to a supporting and positioning tool and a supporting and positioning method for a wall aluminum formwork used for casting a shear wall. Background Art

[0002] In the cast-in-place construction of high-rise buildings, aluminum formworks have begun to be widely used. Aluminum formworks have the characteristics of easy construction, energy saving and environmental protection, long service life, and can be formed into various shapes and specifications with high forming precision, and are increasingly recognized and accepted by the market; the on-site shear wall casting is carried out on the completed floor slab, and the construction process is: the wall line of the pre-cast shear wall is released on the completed floor slab, and the wall control line is released at 200 mm on both sides of the wall line, the steel bars in the shear wall are tied and welded, and the aluminum formwork for the cast wall is supported; since angle steels are provided on the lower bottom surface of the existing aluminum formwork for the cast wall, when the wall formworks on both sides are supported, a strip-shaped gap space will be formed on the outside of the angle steel just below the wall aluminum formwork. In order to ensure the verticality and stability of the aluminum membrane plate, the existing technology is to fill the strip-shaped space with cement mortar; when the above-mentioned strip-shaped gap space is filled, the 200 mm control lines on both sides of the wall line are used to control the gap space. The verticality and flatness of the wall formwork are checked as a benchmark, and finally, the concrete of the wall is poured. This existing construction method has the following problems: (1) Due to the poor flatness of the completed floor slab, there is a gap between the bottom surface of the angle steel at the lower end of the wall aluminum formwork and the surface of the floor slab. When the strip gap space outside the angle steel directly below the wall aluminum formwork is filled with cement mortar, some of the filling mortar will enter between the two wall formworks from the gap. When the shear wall concrete is subsequently poured, the newly poured concrete will form a two-layer skin with the solidified cement mortar that entered earlier, resulting in root rot in the poured shear wall. (2) After the wall formwork is set up, the process of checking the verticality and flatness of the formwork is time-consuming and labor-intensive, especially the process of laying out the 200 mm control line consumes a lot of manpower and time. How to simplify the verticality control procedure of the wall formwork and avoid root rot after the shear wall is poured has become an urgent problem that needs to be solved on site. Summary of the invention

[0003] The invention provides a support and positioning tool for an aluminum wall formwork for casting a shear wall, which solves the technical problem of how to simplify the verticality and flatness control procedure of the wall formwork support and avoid root rot after the shear wall is cast.

[0004] The present invention solves the above technical problems through the following technical solutions:

[0005] The overall concept of the present invention is as follows: a standardized inverted T-shaped guide frame capable of controlling the verticality and flatness of a wall formwork is designed, and a cylinder with a "mouth"-shaped cross section is arranged on the inner side of the lower end of the inverted T-shaped guide frame, the wall formwork is abutted against the inverted T-shaped guide frame, the "mouth"-shaped cylinder at the bottom end of the inverted T-shaped guide frame is arranged in a strip-shaped gap space outside the angle steel just below the wall aluminum formwork, the strip space is closed, and the vertical vertical plate of the guide frame is used to control the verticality and flatness of the wall aluminum formwork, thereby simplifying the verticality and flatness control procedure of setting up the wall aluminum formwork and avoiding root rot during the cast wall.

[0006] A support and positioning tool for a wall aluminum formwork for casting a shear wall, comprising a cast concrete floor slab, a left vertical formwork and a right vertical formwork, a left wall line for casting a shear wall and a right wall line for casting a shear wall are arranged on the concrete floor slab, a left pressure plate fixing bolt is pre-embedded on the concrete floor slab on the left side of the shear wall casting left wall line, a right pressure plate fixing bolt is pre-embedded on the concrete floor slab on the right side of the shear wall casting right wall line, a left angle steel is arranged on the lower bottom surface of the left vertical formwork, a right angle steel is arranged on the lower bottom surface of the right vertical formwork, and a left angle steel is arranged on the left side of the shear wall casting left wall line A left inverted T-shaped guide frame is arranged on the concrete floor slab on the side, and the left inverted T-shaped guide frame is composed of a horizontal plate and a vertical upright plate. The vertical upright plate is arranged on the horizontal plate, and the vertical upright plate forms a 90-degree angle with the horizontal plate. A cylinder with a "mouth"-shaped cross-section is fixedly arranged on the horizontal plate on the right side of the vertical upright plate; a left side vertical formwork is arranged on the left inverted T-shaped guide frame, and a left side angle steel arranged on the lower bottom surface of the left side vertical formwork is clamped between the right side vertical surface and the top end surface of the cylinder with a "mouth"-shaped cross-section; a left side pressure plate is arranged on the left side pressure plate fixing bolt, and the left side pressure plate is pressed onto the top end surface of the left part of the horizontal plate.

[0007] The height of the cylinder is equal to the inner height of the left angle steel vertical plate, and the top surface width of the cylinder is equal to the inner width of the left angle steel horizontal plate; a first tension bolt through-hole is provided on the vertical vertical plate, and a second tension bolt through-hole is provided on the vertical vertical plate of the right inverted T-shaped guide frame; a fixing bolt through-hole is provided at the center of the left pressure plate, and a support platform is fixedly provided on the lower bottom surface of the left end of the left pressure plate, and the thickness of the support platform is equal to the thickness of the horizontal plate.

[0008] A steel butterfly-shaped clamp is arranged on the top surface of the left pressure plate, and the upper end of the left pressure plate fixing bolt passes through the fixing bolt passing hole and the steel butterfly-shaped clamp in sequence and is screwed together with the left fixing nut.

[0009] A right inverted T-shaped guide frame is arranged on the concrete floor slab on the right side of the right wall line of the shear wall casting. The structure of the right inverted T-shaped guide frame is exactly the same as that of the left inverted T-shaped guide frame. A right vertical formwork is arranged on the right inverted T-shaped guide frame. Tension bolts are inserted between the vertical plate of the left inverted T-shaped guide frame, the left vertical formwork, the right vertical formwork and the vertical plate of the right inverted T-shaped guide frame. A right pressure plate is arranged on the right top end surface of the horizontal plate of the right inverted T-shaped guide frame, and the right pressure plate is connected to the pre-embedded right pressure plate fixing bolts.

[0010] A method for supporting and positioning an aluminum wall formwork for casting a shear wall, comprising a cast concrete floor slab, a left vertical formwork and a right vertical formwork, a left angle steel being arranged on the lower bottom surface of the left vertical formwork, and a right angle steel being arranged on the lower bottom surface of the right vertical formwork; characterized by the following steps:

[0011] The first step is to set the left wall line and the right wall line of the shear wall casting on the concrete floor slab. The space between the left wall line and the right wall line is the precast shear wall casting space. The left pressure plate fixing bolts are pre-embedded on the concrete floor slab on the left side of the shear wall casting left wall line, and the right pressure plate fixing bolts are pre-embedded on the concrete floor slab on the right side of the shear wall casting right wall line.

[0012] The second step is to make a left inverted T-shaped guide frame and a right inverted T-shaped guide frame with exactly the same structure. The specific process is: respectively make a rectangular aluminum horizontal plate and a rectangular aluminum vertical stand plate, and fix the vertical stand plate to the top end surface of the horizontal plate, so that the vertical stand plate forms a 90-degree angle with the horizontal plate. On the top end surface of the horizontal plate on the right side of the vertical stand plate, a cylinder with a "mouth"-shaped cross-section is fixedly installed, and the right side elevation of the cylinder and the right end elevation of the horizontal plate are arranged on the same elevation, so that the same elevation forms a 90-degree angle with the horizontal plate, and the height of the same elevation is equal to the inner side height of the left angle steel stand plate; the top end surface of the cylinder is at a 90-degree angle with the vertical stand plate, and the top surface width of the cylinder is equal to the inner side width of the left angle steel horizontal plate; the right inverted T-shaped guide frame is made in the same way;

[0013] Step 3: Place a left inverted T-shaped guide frame on the concrete floor slab on the left side of the left wall line of the shear wall casting, support the left vertical formwork on the left inverted T-shaped guide frame, clamp the left angle steel between the right vertical surface and the top surface of the cylinder with a "mouth"-shaped cross section, and the left vertical surface of the left vertical formwork is connected to the vertical plate of the left inverted T-shaped guide frame;

[0014] Step 4: Adjust the left inverted T-shaped guide frame so that the inner end of the vertical plate of the left angle steel set on the lower bottom surface of the left vertical template coincides with the left wall line of the shear wall casting, press the left pressure plate onto the top surface of the left part of the horizontal plate, and position and fix the left inverted T-shaped guide frame through the left pressure plate fixing bolt and the left fixing nut;

[0015] Step 5: Use the same method as Step 3 and Step 4 to position and fix the right inverted T-shaped guide frame on the outside of the right wall line of the shear wall casting, and support the right vertical formwork on the right inverted T-shaped guide frame;

[0016] Step 6. Set up the internal support of the formwork between the left vertical formwork and the right vertical formwork. Then, connect the tension bolts between the vertical plates of the left inverted T-shaped guide frame, the left vertical formwork, the right vertical formwork and the vertical plates of the right inverted T-shaped guide frame to complete the support and positioning of the wall aluminum formwork.

[0017] The present invention effectively controls and positions the two wall templates through a standardized aluminum inverted T-shaped guide frame, greatly simplifies the verticality and flatness adjustment process of the wall template, and overcomes the defect of concrete pouring wall root rot in the traditional process; the construction process is simple, the project cost is low, and the line laying only needs to lay out the positioning line of the wall, and there is no need to lay the control line 200 mm inside the wall line. The process of sealing the gap of the wall bottom template with mortar is also omitted, the construction efficiency is greatly improved, and the entire tooling and template can be reused. BRIEF DESCRIPTION OF THE DRAWINGS

[0018] Figure 1 It is a schematic diagram of the structure of the present invention;

[0019] Figure 2 It is a schematic diagram of the positioning structure of two inverted T-shaped guide frames of the present invention;

[0020] Figure 3 It is a structural schematic diagram of a left inverted T-shaped guide frame 6 of the present invention;

[0021] Figure 4 It is a structural schematic diagram of the left side vertical template 3 of the present invention;

[0022] Figure 5 It is a structural schematic diagram of the left side pressure plate 14 of the present invention;

[0023] Figure 6 It is a schematic diagram of the structure of the steel butterfly-shaped card 17 of the present invention. DETAILED DESCRIPTION

[0024] The present invention is described in detail below in conjunction with the accompanying drawings:

[0025] A support and positioning tool for a wall aluminum formwork for casting a shear wall, comprising a cast concrete floor slab 1, a left vertical formwork 3 and a right vertical formwork 5, a shear wall casting left wall line 2 and a shear wall casting right wall line 22 are arranged on the concrete floor slab 1, the shear wall casting left wall line 2 and the shear wall casting right wall line 22 are arranged parallel to each other, a left pressure plate fixing bolt 13 is pre-embedded on the concrete floor slab 1 on the left side of the shear wall casting left wall line 2, and a left pressure plate fixing bolt 13 is pre-embedded on the shear wall casting left wall line 2. On the concrete floor slab 1 on the right side of the right wall line 22, a right pressure plate fixing bolt 19 is pre-embedded, and the left pressure plate fixing bolt 13 and the right pressure plate fixing bolt 19 are pre-embedded on both sides of the precast shear wall when the concrete floor slab 1 is cast; a left angle steel 4 is arranged on the lower bottom surface of the left vertical formwork 3, and a right angle steel is arranged on the lower bottom surface of the right vertical formwork 5. The left angle steel 4 is an existing component on the existing formed aluminum wall formwork and is an inherent structural component of the rental aluminum formwork. On the concrete floor slab 1 on the left side of the left wall line 2 of the shear wall casting, a left inverted T-shaped guide frame 6 is arranged. The left inverted T-shaped guide frame 6 is composed of a horizontal plate 9 and a vertical upright plate 10. The vertical upright plate 10 is arranged on the horizontal plate 9, and the vertical upright plate 10 is at a 90-degree angle with the horizontal plate 9. On the horizontal plate 9 on the right side of the vertical upright plate 10, a cylinder 8 with a "mouth"-shaped cross section is fixedly arranged; a left vertical template 3 is arranged on the left inverted T-shaped guide frame 6, and a left vertical template 3 is arranged on the lower bottom surface of the left vertical template 3. The side angle steel 4 is clamped between the right side vertical surface and the top end surface of the cylinder 8 with a "mouth"-shaped cross-section; a left side pressure plate 14 is arranged on the left side pressure plate fixing bolt 13, and the left side pressure plate 14 is pressed on the top end surface of the left part of the horizontal plate 9; the present invention uses a pre-formed inverted T-shaped guide frame to position the wall formwork, first fixes two inverted T-shaped guide frames on both sides of the wall line, and then sets the wall formwork on the inverted T-shaped guide frame, and achieves the verticality and flatness standards of the wall formwork through the standard inverted T-shaped guide frame.

[0026] The height of the cylinder 8 is equal to the inner height of the left angle steel 4 vertical plate, and the top surface width of the cylinder 8 is equal to the inner width of the horizontal plate of the left angle steel 4. When the left vertical formwork 3 is supported on the left inverted T-shaped guide frame 6, the cylinder 8 and the vertical vertical plate 10 are used to limit the left vertical formwork 3, so that the verticality and horizontality of the left vertical formwork 3 meet the design requirements, thereby eliminating the traditional step of adjusting the verticality of the formwork through the 200 mm positioning line on the outside of the wall; a first tension bolt through-hole 11 is provided on the vertical vertical plate 10, and a second tension bolt through-hole 12 is provided on the vertical vertical plate of the right inverted T-shaped guide frame 7; a fixing bolt through-hole 15 is provided at the center of the left pressure plate 14, and a support platform 16 is fixedly provided on the lower bottom surface of the left end of the left pressure plate 14, and the thickness of the support platform 16 is equal to the thickness of the horizontal plate 9, thereby increasing the positioning and pressing area of ​​the left pressure plate 14, and realizing reliable fixation of the left inverted T-shaped guide frame 6.

[0027] A steel butterfly-shaped clip 17 is provided on the top surface of the left pressure plate 14 , and the upper end of the left pressure plate fixing bolt 13 passes through the fixing bolt through hole 15 and the steel butterfly-shaped clip 17 in sequence and is screwed together with the left fixing nut 18 ; the steel butterfly-shaped clip 17 increases the downward pressing area of ​​the left pressure plate 14 .

[0028] On the concrete floor slab 1 on the right side of the right wall line 22 of the shear wall casting, a right inverted T-shaped guide frame 7 is arranged, and the structure of the right inverted T-shaped guide frame 7 is exactly the same as that of the left inverted T-shaped guide frame 6. A right vertical formwork 5 is arranged on the right inverted T-shaped guide frame 7, and tension bolts 20 are inserted between the vertical vertical plate 10 of the left inverted T-shaped guide frame 6, the left vertical formwork 3, the right vertical formwork 5 and the vertical vertical plate of the right inverted T-shaped guide frame 7; a right pressure plate 21 is arranged on the right top end surface of the horizontal plate of the right inverted T-shaped guide frame 7, and the right pressure plate 21 is connected to the pre-buried right pressure plate fixing bolts 19; before supporting the two wall formworks, it is only necessary to first position and fix the two inverted T-shaped guide frames to achieve accurate control of the verticality of the two wall formworks.

[0029] A method for supporting and positioning an aluminum wall formwork for casting a shear wall, comprising a cast concrete floor slab 1, a left vertical formwork 3 and a right vertical formwork 5, a left angle steel 4 is arranged on the lower bottom surface of the left vertical formwork 3, and a right angle steel is arranged on the lower bottom surface of the right vertical formwork 5; it is characterized by the following steps:

[0030] The first step is to set a shear wall casting left wall line 2 and a shear wall casting right wall line 22 on the concrete floor slab 1, and the space between the shear wall casting left wall line 2 and the shear wall casting right wall line 22 is a precast shear wall casting space; on the concrete floor slab 1 on the left side of the shear wall casting left wall line 2, a left pressure plate fixing bolt 13 has been pre-embedded, and on the concrete floor slab 1 on the right side of the shear wall casting right wall line 22, a right pressure plate fixing bolt 19 has been pre-embedded;

[0031] The second step is to make a left inverted T-shaped guide frame 6 and a right inverted T-shaped guide frame 7 with exactly the same structure. The specific process is: respectively make a rectangular aluminum horizontal plate 9 and a rectangular aluminum vertical stand 10, and fix the vertical stand 10 to the top end surface of the horizontal plate 9, so that the vertical stand 10 is at a 90-degree angle with the horizontal plate 9. On the top end surface of the horizontal plate 9 on the right side of the vertical stand 10, a cylinder 8 with a "mouth"-shaped cross section is fixedly installed, and the right side elevation of the cylinder 8 and the right end elevation of the horizontal plate 9 are arranged on the same elevation, so that the same elevation is at a 90-degree angle with the horizontal plate 9, and the height of the same elevation is equal to the inner side height of the left side angle steel 4 stand; make the top end surface of the cylinder 8 and the vertical stand 10 at a 90-degree angle, and make the top surface width of the cylinder 8 equal to the inner side width of the left side angle steel 4 horizontal plate; use the same method to complete the right inverted T-shaped guide frame 7; the two inverted T-shaped guide frames can be processed in the factory to ensure that they have high verticality and flatness;

[0032] The third step is to place a left inverted T-shaped guide frame 6 on the concrete floor slab 1 on the left side of the left wall line 2 of the shear wall casting, support the left side vertical template 3 on the left inverted T-shaped guide frame 6, and clamp the left angle steel 4 between the right side vertical surface and the top surface of the cylinder 8 with a "mouth"-shaped cross section. The left side vertical surface of the left vertical template 3 is abutted against the vertical vertical plate 10 of the left inverted T-shaped guide frame 6. The left inverted T-shaped guide frame 6 and the cylinder 8 with a "mouth"-shaped cross section can be integrated and processed;

[0033] Step 4: Adjust the left inverted T-shaped guide frame 6 so that the inner end of the vertical plate of the left angle steel 4 set on the lower bottom surface of the left vertical template 3 coincides with the left wall line 2 of the shear wall casting, press the left pressure plate 14 onto the top surface of the left part of the horizontal plate 9, and position and fix the left inverted T-shaped guide frame 6 by the left pressure plate fixing bolt 13 and the left fixing nut 18;

[0034] Step 5: Using the same method as Step 3 and Step 4, position and fix the right inverted T-shaped guide frame 7 on the outside of the right wall line 22 of the shear wall casting, and support the right vertical formwork 5 on the right inverted T-shaped guide frame 7;

[0035] Step 6: Set up the inner support of the formwork between the left vertical formwork 3 and the right vertical formwork 5, and then connect the tension bolts 20 between the vertical plates 10 of the left inverted T-shaped guide frame 6, the left vertical formwork 3, the right vertical formwork 5 and the vertical plates of the right inverted T-shaped guide frame 7 to complete the support and positioning of the wall aluminum formwork.

[0036] A first tension bolt through hole 11 is provided on the vertical upright plate 10, and a second tension bolt through hole 12 is provided on the vertical upright plate of the right inverted T-shaped guide frame 7; a fixing bolt through hole 15 is provided at the center of the left pressure plate 14, and a support platform 16 is fixedly provided on the lower bottom surface of the left end of the left pressure plate 14, and the thickness of the support platform 16 is equal to the thickness of the horizontal plate 9.

[0037] When the left pressure plate 14 is fixed by the left pressure plate fixing bolt 13 and the left fixing nut 18, a steel butterfly-shaped clip 17 should be placed on the top surface of the left pressure plate 14 first, and the upper end of the left pressure plate fixing bolt 13 passes through the fixing bolt through hole 15 and the steel butterfly-shaped clip 17 in turn, and then is screwed together with the left fixing nut 18, thereby firmly fixing the left inverted T-shaped guide frame 6.

[0038] The present invention ingeniously uses a cylinder with a "mouth"-shaped cross-section at the bottom end of an inverted T-shaped guide frame to fill the gap space outside the left angle steel arranged on the lower bottom surface of the existing aluminum wall vertical formwork, thereby eliminating the traditional problem of easy root rot after the later pouring of the concrete wall caused by filling the gap space with cement mortar when supporting the wall formwork, and achieves the effect of saving the back ribs at the lower part of the two wall formworks.

Claims

1. A support and positioning tool for a wall aluminum formwork for casting a shear wall, comprising a cast concrete floor slab (1), a left vertical formwork (3) and a right vertical formwork (5), wherein a left wall line (2) for casting a shear wall and a right wall line (22) for casting a shear wall are arranged on the concrete floor slab (1), a left pressure plate fixing bolt (13) is pre-embedded on the concrete floor slab (1) on the left side of the shear wall casting left wall line (2), and a right pressure plate fixing bolt (19) is pre-embedded on the concrete floor slab (1) on the right side of the shear wall casting right wall line (22), a left angle steel (4) is arranged on the lower bottom surface of the left vertical formwork (3), and a right angle steel is arranged on the lower bottom surface of the right vertical formwork (5); characterized in that: A left inverted T-shaped guide frame (6) is arranged on the concrete floor slab (1) on the left side of the left wall line (2) of the shear wall casting. The left inverted T-shaped guide frame (6) is composed of a horizontal plate (9) and a vertical upright plate (10). The vertical upright plate (10) is arranged on the horizontal plate (9), and the vertical upright plate (10) forms an angle of 90 degrees with the horizontal plate (9). A cylinder (8) with a "mouth"-shaped cross section is fixedly arranged on the horizontal plate (9) on the right side of the vertical upright plate (10); a left vertical template (3) is arranged on the left inverted T-shaped guide frame (6), and a left angle steel (4) arranged on the lower bottom surface of the left vertical template (3) is clamped between the right vertical surface and the top surface of the cylinder (8) with a "mouth"-shaped cross section; a left pressure plate (14) is arranged on the left pressure plate fixing bolt (13), and the left pressure plate (14) is pressed on the top surface of the left portion of the horizontal plate (9).

2. The supporting and positioning tool for the aluminum formwork for casting shear walls according to claim 1 is characterized in that: The height of the cylinder (8) is equal to the inner height of the vertical plate of the left angle steel (4), and the top width of the cylinder (8) is equal to the inner width of the horizontal plate of the left angle steel (4); a first tension bolt through hole (11) is provided on the vertical plate (10), and a second tension bolt through hole (12) is provided on the vertical plate of the right inverted T-shaped guide frame (7); a fixing bolt through hole (15) is provided at the center of the left pressure plate (14), and a support platform (16) is fixedly provided on the lower bottom surface of the left end of the left pressure plate (14), and the thickness of the support platform (16) is equal to the thickness of the horizontal plate (9).

3. The supporting and positioning tool for the aluminum formwork for casting shear wall according to claim 2 is characterized in that: A steel butterfly-shaped clamp (17) is provided on the top surface of the left pressure plate (14), and the upper end of the left pressure plate fixing bolt (13) passes through the fixing bolt passing hole (15) and the steel butterfly-shaped clamp (17) in sequence and is then screwed together with the left fixing nut (18).

4. The supporting and positioning tool for the aluminum formwork for casting shear walls according to claim 3 is characterized in that: A right inverted T-shaped guide frame (7) is arranged on the concrete floor slab (1) on the right side of the right wall line (22) of the shear wall casting. The structure of the right inverted T-shaped guide frame (7) is completely the same as that of the left inverted T-shaped guide frame (6). A right vertical template (5) is arranged on the right inverted T-shaped guide frame (7). Tension bolts (20) are inserted between the vertical vertical plate (10) of the left inverted T-shaped guide frame (6), the left vertical template (3), the right vertical template (5) and the vertical vertical plate of the right inverted T-shaped guide frame (7). A right pressure plate (21) is arranged on the right top end surface of the horizontal plate of the right inverted T-shaped guide frame (7). The right pressure plate (21) is connected to the pre-buried right pressure plate fixing bolts (19).