Improved vertically-arranged heater
By removing the connecting pipe and setting a reserved gap, the improved vertically arranged heater solves the problems of heavy welding workload and difficult insulation construction of traditional heaters, achieving lower manufacturing costs and convenient on-site construction.
Patent Information
- Application Number
- CN202322756263.2
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2023-10-15
- Publication Date
- 2024-10-15
- Estimated Expiration
- 2033-10-15
AI Technical Summary
Traditional vertically arranged heaters require heavy welding work, high steel consumption, and difficult top insulation construction. In particular, the installation of connecting pipes makes on-site insulation construction inconvenient.
Design an improved vertically arranged heater. By removing the connecting pipe, the upper header of the convection pipe row is directly connected to the top header. A reserved gap is set to facilitate the installation of the insulation layer and dust cleaning device, and the top header is placed Arrange the convection pipes on the rear upper side of the header to facilitate maintenance and pipeline arrangement.
It reduces the welding workload of the Unicom pipe, reduces the difficulty of installing the top insulation layer, saves the use of equipment steel, reduces manufacturing costs, and simplifies on-site insulation construction and dust cleaning operations.
Smart Images

Figure CN221839896U_ABST
Abstract
Description
Technical Field
[0001] The utility model belongs to the technical field of heaters, and particularly relates to an improved vertically arranged heater. Background Art
[0002] A heater is a device that can convert electrical energy, fuel or other forms of energy into thermal energy and is used to heat fluids or objects. The main function of a heater is to heat the fluid or object to increase its temperature, thereby achieving the purpose of heating. There are many types of heaters, the most common ones are electric heaters, steam heaters, thermal oil heaters, flame heaters, etc. In industrial production and daily life, heaters are widely used in heating water, heating air, heating oil, heating food, etc.
[0003] Traditional vertically arranged heaters use a connecting pipe to connect the flow tube row header to the top header (see the attached manual for details). Figure 1 and attached Figure 2 ), not only is the welding workload large, but the steel consumption is also large, which increases the manufacturing cost of the equipment. The setting of the connecting pipe also makes the insulation construction on the top of the equipment more difficult, and it is not convenient to carry out on-site insulation construction. Therefore, we hope to design a welding equipment with a new structure to solve this problem. Utility Model Content
[0004] In view of the deficiencies in the prior art, the utility model aims to provide an improved vertically arranged heater to solve the problems raised in the above-mentioned background technology.
[0005] The utility model is realized by the following technical scheme: an improved vertically arranged heater, comprising: a bottom header, a convection tube bundle, a top header and a top insulation layer, wherein the lower end of the convection tube bundle is fixedly connected to the rear side of the bottom header, the rear side of the upper end of the convection tube bundle is fixedly connected to the lower end of the top header, and the top insulation layer is installed at the upper end of the convection tube bundle;
[0006] The convection tube bundle is modularly composed of a plurality of convection tube rows, wherein the convection tube row comprises an upper header of the convection tube row, a lower header of the convection tube row and convection tubes;
[0007] A plurality of equally spaced convection tubes are welded to the lower side of each convection tube row upper header, and the convection tube row upper header is fixedly connected to the upper surface of the convection tube row lower header through the plurality of convection tubes.
[0008] As a preferred embodiment, the rear end of each of the convection tube row upper headers is fixedly connected to the lower end of the top header, and each of the convection tube row lower headers is fixedly connected to the rear side of the bottom header. In the original structure, the convection tube row upper header is connected to the top header through a connecting pipe. After the improvement, the connecting pipe is directly removed, and the rear end of the convection tube row upper header is directly connected to the top header, which greatly reduces the workload of connecting pipe welding and can completely free up the space on the top of the convection tube row upper header, making it easier to install the top insulation layer, greatly reducing the difficulty of installing the top insulation layer.
[0009] As a preferred embodiment, the top insulation layer is placed on the upper side of multiple convection tube row upper headers, the top insulation layer is located on the front side of the top header, and the rear side of the top insulation layer is not directly connected to the front side of the top header. In the original structure, the top header is placed in the middle of the upper side of the convection tube bundle. After the improvement, the top header is placed on the upper rear side of the convection tube row upper header, which is convenient for top header maintenance and pipeline layout.
[0010] As a preferred embodiment, a plurality of reserved gaps are arranged between the plurality of convection tube rows on the convection tube bundle, and the width of the reserved gaps is greater than the width of at least one convection tube row. In the original structure, the convection tube rows are precisely and consistently arranged, which makes cleaning more difficult. After the improvement, a plurality of reserved gaps are arranged between the plurality of convection tube rows to facilitate the installation of a cleaning device.
[0011] After adopting the above technical solution, the beneficial effects of the utility model are as follows: by removing the connecting pipe originally connected between the upper header of the convection tube row and the top header, the rear end of the upper header of the convection tube row is directly connected to the top header, which greatly reduces the workload of connecting pipe welding, and can completely free up the space on the top of the upper header of the convection tube row, which is convenient for installing the top insulation layer, greatly reducing the difficulty of installing the top insulation layer, and at the same time eliminating the use of connecting pipes, also reducing the use of equipment steel, saving equipment manufacturing costs;
[0012] By placing the top header on the upper rear side of the upper header of the convection tube row, it is convenient to inspect the top header and arrange the pipelines. At the same time, multiple reserved gaps are set between multiple convection tube rows to facilitate the installation of the cleaning device. BRIEF DESCRIPTION OF THE DRAWINGS
[0013] In order to more clearly illustrate the embodiments of the utility model or the technical solutions in the prior art, the drawings required for use in the embodiments or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the utility model. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative labor.
[0014] Figure 1This is a schematic diagram of the main structure before improvement.
[0015] Figure 2 To improve the front side view structure diagram
[0016] Figure 3 It is a schematic diagram of a front view of an improved vertically arranged heater of the utility model.
[0017] Figure 4 It is a schematic side view of an improved vertically arranged heater of the utility model.
[0018] In the figure, 100-bottom header;
[0019] 200-convection tube bundle, 210-convection tube row upper header, 220-convection tube row lower header, 230-reserved gap, 240-convection tube row;
[0020] 300-top header;
[0021] 400-Top insulation layer. DETAILED DESCRIPTION
[0022] The following will be combined with the drawings in the embodiments of the utility model to clearly and completely describe the technical solutions in the embodiments of the utility model. Obviously, the described embodiments are only part of the embodiments of the utility model, not all of the embodiments. Based on the embodiments of the utility model, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the utility model.
[0023] See also Figures 1 to 4 The utility model provides a technical solution: an improved vertically arranged heater, comprising: a bottom header 100, a convection tube bundle 200, a top header 300 and a top insulation layer 400, the lower end of the convection tube bundle 200 is fixedly connected to the rear side of the bottom header 100, the rear side of the upper end of the convection tube bundle 200 is fixedly connected to the lower end of the top header 300, and the top insulation layer 400 is installed on the upper end of the convection tube bundle 200;
[0024] The convection tube bundle 200 is modularly composed of a plurality of convection tube rows 240, and the convection tube row 240 includes a convection tube row upper header 210, a convection tube row lower header 220, and convection tubes;
[0025] A plurality of equally spaced convection tubes are welded to the lower side of each convection tube row upper header 210 , and the convection tube row upper header 210 is fixedly connected to the upper surface of the convection tube row lower header 220 through the plurality of convection tubes.
[0026] See also Figures 1 to 4The rear end of each convection tube row upper header 210 is fixedly connected to the lower end of the top header 300, and each convection tube row lower header 220 is fixedly connected to the rear side of the bottom header 100. In the original structure, the convection tube row upper header 210 is connected to the top header 300 through a connecting pipe. After the improvement, the connecting pipe is directly removed, and the rear end of the convection tube row upper header 210 is directly connected to the top header 300, which greatly reduces the workload of connecting pipe welding and can completely free up the space on the top of the convection tube row upper header 210, making it easier to install the top insulation layer 400, greatly reducing the difficulty of installing the top insulation layer 400.
[0027] As the first embodiment of the utility model, the connecting pipe originally connected between the upper header 210 of the convection tube bank and the top header 300 is removed, and the rear end of the upper header 210 of the convection tube bank is directly connected to the top header 300. In actual operation, the material in the convection tube can directly enter the top header 300. When installing the equipment on site, since the connecting pipe is omitted, the staff can reduce the workload of this part of the connecting pipe, and the space on the top of the upper header 210 of the convection tube bank can be completely vacated, which is convenient for installing the top insulation layer 400 and facilitating on-site insulation construction, greatly reducing the difficulty of installing the top insulation layer 400. At the same time, the use of the connecting pipe is eliminated, the use of equipment steel is reduced, and the equipment manufacturing cost is saved. In practice, the bottom header 100 on the lower end side of the convection tube bundle 200 is eliminated in the improved structure, which greatly reduces the welding workload of the overall equipment and the insulation workload of the bottom header 100. On-site installation can reduce one sewage pipeline and valve.
[0028] See also Figures 1 to 4 The top insulation layer 400 is placed on the upper side of the multiple convection tube row upper headers 210, the top insulation layer 400 is located on the front side of the top header 300, and the rear side of the top insulation layer 400 is not directly connected to the front side of the top header 300. In the original structure, the top header 300 is placed in the middle of the upper side of the convection tube bundle 200. After the improvement, the top header 300 is placed on the upper rear side of the convection tube row upper header 210, which is convenient for the maintenance of the top header 300 and the pipeline layout.
[0029] A plurality of reserved gaps 230 are arranged between the plurality of convection tube rows 240 on the convection tube bundle 200. The width of the reserved gaps 230 is greater than the width of at least one convection tube row 240. In the original structure, the convection tube rows 240 are precisely and consistently arranged, which makes cleaning more difficult. After improvement, a plurality of reserved gaps 230 are arranged between the plurality of convection tube rows 240, which not only facilitates the installation of the convection tube rows 240, but also facilitates subsequent maintenance and cleaning.
[0030] As the second embodiment of the utility model, by placing the top header 300 on the upper rear side of the convection tube row upper header 210, it is convenient to inspect the top header 300 and arrange the pipelines, and at the same time, multiple reserved gaps 230 are set between multiple convection tube rows 240. When the workers install the convection tube rows 240, a cleaning device can be installed in the reserved multiple gaps 230 to facilitate the cleaning device to clean the convection tube rows 240 later.
[0031] The above description is only a preferred embodiment of the present invention and is not intended to limit the present invention. Any modifications, equivalent substitutions, improvements, etc. made within the spirit and principles of the present invention should be included in the protection scope of the present invention.
Claims
1. An improved vertically arranged heater, comprising: A bottom header (100), a convection tube bundle (200), a top header (300), and a top insulation layer (400), characterized in that the lower end of the convection tube bundle (200) is fixedly connected to the rear side of the bottom header (100), the rear side of the upper end of the convection tube bundle (200) is fixedly connected to the lower end of the top header (300), and the top insulation layer (400) is installed on the upper end of the convection tube bundle (200); The convection tube bundle (200) is modularly composed of a plurality of convection tube rows (240), wherein the convection tube rows (240) include a convection tube row upper header (210), a convection tube row lower header (220), and convection tubes; A plurality of convection tubes distributed at equal intervals are welded to the lower side of each convection tube row upper header (210), and the convection tube row upper header (210) is fixedly connected to the upper surface of the convection tube row lower header (220) via the plurality of convection tubes.
2. An improved vertically arranged heater as claimed in claim 1, characterized in that: The rear end of each of the convection tube row upper headers (210) is fixedly connected to the lower end of the top header (300), and each of the convection tube row lower headers (220) is fixedly connected to the rear side of the bottom header (100).
3. An improved vertically arranged heater as claimed in claim 2, characterized in that: The top insulation layer (400) is placed on the upper side of the plurality of convection tube row upper headers (210), the top insulation layer (400) is located on the front side of the top header (300), and the rear side of the top insulation layer (400) is not directly connected to the front side of the top header (300).
4. An improved vertically arranged heater as claimed in claim 1, characterized in that: A plurality of reserved gaps (230) are provided between the plurality of convection tube rows (240) on the convection tube bundle (200), and the width of the reserved gaps (230) is greater than the width of at least one convection tube row (240).