Beidou tower inclination and settlement monitoring and early warning device
Through the Beidou tower tilt and settlement monitoring and early warning device, the use of inclinometers, settlement meters, crack meters, piezometers and Beidou satellite navigation systems solves the problems of subjectivity and untimeliness of manual observation in traditional tower maintenance, and achieves real-time monitoring of towers. Safety monitoring and early warning improve safety.
Patent Information
- Application Number
- CN202420531305.4
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-03-19
- Publication Date
- 2024-10-15
- Estimated Expiration
- 2034-03-19
AI Technical Summary
Traditional tower maintenance relies on regular inspections and manual observations, which is subjective and untimely. It cannot meet the needs of real-time monitoring of towers, making it difficult to detect and eliminate safety hazards in a timely manner.
Design a Beidou tower tilt settlement monitoring and early warning device, including a power tower, installation frame, inclinometer, settlement meter, crack meter, piezometer, distribution box, RTU, GNSS receiver and Beidou receiver, and real-time detection through these devices The tilt, settlement and surface data of the tower are transmitted in real time through the Beidou satellite navigation system.
It achieves real-time monitoring of the tower, can detect tilt and settlement abnormalities in a timely manner, improves safety, reduces the subjectivity and untimeliness of manual inspections, and meets the needs of real-time safety monitoring of the tower.
Smart Images

Figure CN221840410U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of power towers, in particular to a Beidou pole tower inclination and settlement monitoring and early warning device. Background Art
[0002] With the steady construction of the national West-East Power Transmission Project, more and more power towers are put into use and maintain a strong growth momentum. This may be one of the largest but most difficult assets to manage and maintain in all walks of life around the world;
[0003] The monitoring of pole tower construction is similar to the monitoring of general projects. The purpose is to ensure the safety of the entire process of pole tower construction and avoid construction accidents. In the construction of pole towers, there are many accidents such as pole tower tilting and collapse due to deviations in the construction process and problems such as soil quality and rainfall. In the construction process of pole towers, due to geological disasters such as landslides, rainfall, and ground subsidence, the collapse of pole towers will cause huge casualties and economic losses. The monitoring of pole tower construction is still in its infancy in my country. In many pole tower constructions in the past, my country did not pay much attention to the monitoring of its surrounding environment. However, with the rapid development of my country's economy, the construction of pole towers has become more complicated, and the forms of pole towers tend to be diversified. The original single form can no longer meet the needs of pole tower construction. Therefore, various large-scale pole towers are being built more and more, and the geological conditions of the construction sites are becoming more and more complicated. At the same time, the construction difficulty is increasing, and the requirements for construction accuracy and safety are becoming higher and higher. Therefore, in the construction process, it is urgent to monitor the surrounding environment;
[0004] Among them, overhead lines are one of the main methods of transmitting electricity at home and abroad. One of the important components is the transmission tower (power tower), which is used to support the aerial conductor and ground wire. Generally, the transmission tower is composed of equilateral angle steel and combined angle steel. Some parts (such as tower feet, etc.) are welded into a combination of several steel plates. Compared with general engineering structures, the transmission tower line system is a typical space truss structure with the characteristics of high structure and large span, which makes its structure quite fragile. Under the influence of natural environment and external conditions, earthquakes, landslides, bad climate, aging oxidation, potential human theft and destruction and other factors will bring certain safety hazards to the tower. The foundation of the tower is prone to slippage, tilting, cracking and other phenomena, which will cause the displacement of the tower base, deformation, tilting and even collapse of the tower, so there is an urgent need to monitor the status of the transmission tower;
[0005] At present, traditional tower maintenance mainly relies on regular inspections and manual observations, which are very necessary safety protection measures. However, the above measures are somewhat subjective and untimely. Some parameters are difficult to measure manually, and it is not easy to find problems in time, which cannot meet the needs of real-time monitoring of towers. In order to eliminate safety hazards of towers and avoid safety incidents of towers, advanced technologies and equipment are needed to conduct real-time safety monitoring of towers.
[0006] Most of the maintenance of communication towers is carried out by manual methods such as plumb bobbers to check whether there is any physical damage on the surface of the tower, such as tower tilt, rust or deformation of steel structure, loose screws, missing nuts, etc. Superficial tower maintenance engineers use these surface physical phenomena to simply judge whether the working status of the transmission tower is normal. This is not only inefficient, but also cannot monitor the status of the tower, make early predictions of tower tilt, and promptly eliminate possible safety hazards to ensure the normal operation of the transmission tower. Utility Model Content
[0007] In order to solve the above problems, the utility model proposes a Beidou pole tower inclination and settlement monitoring and early warning device. This technical solution solves the problem that traditional tower maintenance in the above background technology mainly relies on regular inspections and manual observations, which are very necessary safety protection measures, but the above measures are subjective and untimely, some parameters are difficult to measure manually, and it is not easy to find problems in time, which cannot meet the needs of real-time monitoring of towers.
[0008] To achieve the above-mentioned purpose, the utility model provides a Beidou pole tower tilt settlement monitoring and early warning device, comprising a power tower, a mounting frame and the ground, wherein a plurality of inclinometers for detecting the inclination of the power tower are fixedly connected to the surface of the power tower, a connecting piece is provided at the top of the mounting frame, and a settlement meter is provided on the surface of the connecting piece;
[0009] A plurality of crack meters and a plurality of piezometers are respectively provided under the power tower, a plurality of clamps 2 are respectively provided on the surface of the mounting frame, a distribution box is fixedly connected to the surface of the clamps 2, and a 4G communication module of the RTU, a GNSS receiver and a Beidou receiver are respectively provided inside the distribution box.
[0010] Optionally, two installation grooves are provided on the surface of the ground, inner walls of the two installation grooves are provided with steel frames, inner walls of the two installation grooves are poured with concrete, and the power tower and the installation frame are respectively installed on two concrete surfaces.
[0011] Optionally, the crack meter and piezometer are respectively installed on the inner wall of the ground.
[0012] Optionally, the outer surface of the mounting frame is provided with a plurality of clamps, the surface of the clamps is fixedly connected to a connecting frame, the surface of the connecting frame is fixedly connected to a solar panel, and the interior of the distribution box is respectively provided with a battery, a solar controller and a photovoltaic off-grid inverter.
[0013] Optionally, the connecting member includes a connecting flange fixedly connected to the top of the mounting frame, a plurality of reinforcing plates arranged at the bottom of the connecting flange, and a plurality of bolts arranged at the through holes of the connecting flange;
[0014] The surface of the bolt passes through the reserved hole on the edge of the sedimentation instrument and the hole of the connecting flange. The surface of the bolt is threadedly connected with a nut. One side of the reinforcement plate is welded to the mounting frame, and the other side of the reinforcement plate is welded to the connecting flange.
[0015] Optionally, a mounting seat is provided at the bottom end of the mounting frame, and a plurality of fixing openings are provided on the surface of the mounting seat.
[0016] Compared with the prior art, the beneficial effects of the utility model are:
[0017] The application has a reasonable structure. The inclination angle of the power tower is detected by an inclinometer. The crack meter and piezometer installed inside the ground respectively detect the cracks and seepage pressure data on the surface. Then, the settlement data of the installation area is detected by a settlement meter. Then, all the detected data is transmitted to the terminal through a GNSS receiver, which is convenient for monitoring personnel to monitor various safety data of the power tower (transmission tower) in real time.
[0018] In order to better understand and implement the present invention, the present invention is described in detail below with reference to the accompanying drawings. BRIEF DESCRIPTION OF THE DRAWINGS
[0019] Figure 1 It is a schematic diagram of the overall structure of the utility model;
[0020] Figure 2 This is a schematic diagram of the three-dimensional structure of the mounting frame in the utility model;
[0021] In the figure: 1. power tower; 2. mounting frame; 3. inclinometer; 4. settlement meter; 5. distribution box; 6. solar panel; 7. clamp 1; 8. clamp 2; 9. crack meter; 10. piezometer; 11. ground; 12. connecting frame; 13. connecting piece; 1301. connecting flange; 1302. bolt; 1303. reinforcement plate; 14. mounting base. DETAILED DESCRIPTION
[0022] The following will be combined with the embodiments of the utility model to clearly and completely describe the technical solutions in the embodiments of the utility model. Obviously, the described embodiments are only part of the embodiments of the utility model, not all of the embodiments. Based on the embodiments of the utility model, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the utility model.
[0023] See also Figure 1 - Figure 2 The utility model provides a Beidou pole tower tilt settlement monitoring and early warning device, comprising a power tower 1, a mounting frame 2 and a ground 11, a plurality of inclinometers 3 for detecting the inclination of the power tower 1 are fixedly connected to the surface of the power tower 1, a connecting piece 13 is provided at the top of the mounting frame 2, and a settlement meter 4 is provided on the surface of the connecting piece 13;
[0024] A plurality of crack meters 9 and a plurality of piezometers 10 are respectively provided under the power tower 1, a plurality of clamps 8 are respectively provided on the surface of the mounting frame 2, a distribution box 5 is fixedly connected to the surface of the clamps 8, a 4G communication module of the RTU, a GNSS receiver and a Beidou receiver are respectively provided inside the distribution box 5, and the crack meters 9 and the piezometers 10 are respectively installed on the inner wall of the ground 11.
[0025] After the equipment is installed, when it is used, the inclination angle of the power tower 1 is detected by the inclinometer 3, and the internal crack meter 9 and the osmometer 10 installed on the ground 11 detect the surface cracks and seepage pressure data respectively. Then, the settlement data of the installation area is detected by the settlement meter 4, and then all the detected data are transmitted to the terminal through the GNSS receiver, so that the monitoring personnel can monitor the various safety data of the power tower 1 in real time. When the power tower 1 is installed in a remote area, the detected data is transmitted to the terminal through the Beidou receiver (based on the Beidou satellite navigation system);
[0026] The Beidou satellite navigation system transmission solution also integrates redundant communication of Beidou short messages, that is, the communication of Beidou short messages is added to the transmission method of the on-site RTU. This method can not only solve the data transmission problem in areas without public network signals such as China Mobile or China Unicom, but also solve the emergency data transmission problem when the public network base station is also damaged under special circumstances.
[0027] Furthermore, two installation grooves are provided on the surface of the ground 11, and the inner walls of the two installation grooves are provided with steel bars, and the inner walls of the two installation grooves are poured with concrete, and the power tower 1 and the installation frame 2 are respectively installed on the two concrete surfaces;
[0028] A mounting seat 14 is disposed at the bottom end of the mounting frame 2 , and a plurality of fixing openings are formed on the surface of the mounting seat 14 .
[0029] Specifically, the strength of the foundation is increased by concrete, and a mounting groove is opened at the bottom of the mounting frame 2. Then, the expansion bolt passes through the fixing opening on the surface of the mounting seat 14 and is inserted into the mounting groove, so as to fix the mounting frame 2.
[0030] Furthermore, the outer surface of the mounting frame 2 is provided with a plurality of clamps 7, the surface of the clamps 7 is fixedly connected with a connecting frame 12, the surface of the connecting frame 12 is fixedly connected with a solar panel 6, and the interior of the distribution box 5 is respectively provided with a battery, a solar controller and a photovoltaic off-grid inverter.
[0031] Specifically, the solar panel 6 is conveniently fixed by the clamp 7 and the connecting frame 12. The working principles of the solar panel 6, the battery, the solar controller and the photovoltaic off-grid inverter are all existing technologies and will not be described in detail here.
[0032] Furthermore, the connecting member 13 includes a connecting flange 1301 fixedly connected to the top of the mounting frame 2, a plurality of reinforcing plates 1303 arranged at the bottom of the connecting flange 1301, and a plurality of bolts 1302 arranged at the through holes of the connecting flange 1301;
[0033] The surface of the bolt 1302 passes through the reserved hole on the edge of the sedimentation meter 4 and the connecting flange 1301. The surface of the bolt 1302 is threadedly connected with a nut. One side of the reinforcement plate 1303 is welded to the mounting frame 2, and the other side of the reinforcement plate 1303 is welded to the connecting flange 1301.
[0034] Specifically, by removing the bolts 1302 and the nuts, the sedimentation meter 4 and the connecting flange 1301 can be separated to facilitate maintenance or replacement of the sedimentation meter 4.
[0035] The above disclosure is only a preferred embodiment of the present invention, which certainly cannot be used to limit the scope of rights of the present invention. Therefore, equivalent changes made according to the claims of the present invention still fall within the scope covered by the present invention.
Claims
1. A Beidou tower tilt settlement monitoring and early warning device, characterized in that: It comprises an electric power tower (1), a mounting frame (2) and the ground (11); a plurality of inclinometers (3) for detecting the inclination of the electric power tower (1) are fixedly connected to the surface of the electric power tower (1); a connecting piece (13) is provided at the top end of the mounting frame (2); and a settlement meter (4) is provided on the surface of the connecting piece (13); A plurality of crack meters (9) and a plurality of piezometers (10) are respectively arranged below the power tower (1), a plurality of clamps (8) are respectively arranged on the surface of the mounting frame (2), a distribution box (5) is fixedly connected to the surface of the clamps (8), and a 4G communication module of an RTU, a GNSS receiver and a Beidou receiver are respectively arranged inside the distribution box (5).
2. A Beidou pole tower tilt settlement monitoring and early warning device according to claim 1, characterized in that: The surface of the ground (11) is provided with two installation grooves, the inner walls of the two installation grooves are provided with steel bars, the inner walls of the two installation grooves are poured with concrete, and the power tower (1) and the installation frame (2) are respectively installed on two concrete surfaces.
3. A Beidou pole tower tilt settlement monitoring and early warning device according to claim 2, characterized in that: The crack meter (9) and the piezometer (10) are respectively installed on the inner wall of the ground (11).
4. A Beidou pole tower tilt settlement monitoring and early warning device according to claim 1, characterized in that: The outer surface of the mounting frame (2) is provided with a plurality of clamps (7), the surface of the clamps (7) is fixedly connected to a connecting frame (12), the surface of the connecting frame (12) is fixedly connected to a solar power generation panel (6), and the distribution box (5) is provided with a storage battery, a solar controller and a photovoltaic off-grid inverter respectively inside.
5. The Beidou pole tower tilt settlement monitoring and early warning device according to claim 1 is characterized in that: The connecting member (13) comprises a connecting flange (1301) fixedly connected to the top of the mounting frame (2), a plurality of reinforcing plates (1303) arranged at the bottom of the connecting flange (1301), and a plurality of bolts (1302) arranged at the through holes of the connecting flange (1301); The surface of the bolt (1302) passes through the reserved hole on the edge of the sedimentation meter (4) and the hole of the connecting flange (1301), and a nut is threadedly connected to the surface of the bolt (1302). One side of the reinforcing plate (1303) is welded to the mounting frame (2), and the other side of the reinforcing plate (1303) is welded to the connecting flange (1301).
6. A Beidou pole tower tilt settlement monitoring and early warning device according to claim 1, characterized in that: A mounting seat (14) is provided at the bottom end of the mounting frame (2), and a plurality of fixing openings are provided on the surface of the mounting seat (14).