Hydrogen bromide circulating absorption system

By designing a hydrogen bromide circulation absorption system, using multi-layer absorption towers and circulation tanks for circulation absorption and cooling, combined with the tail gas treatment system, the problem of hydrogen bromide tail gas and acidic substance treatment is solved, and the purity and safety of hydrogen bromide are improved. safety, avoiding equipment corrosion and personnel hazards.

CN221846670UActive Publication Date: 2024-10-18NANTONG STAR GRAPHITE EQUIP CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420329971.X
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-02-22
Publication Date
2024-10-18
Estimated Expiration
2034-02-22

AI Technical Summary

Technical Problem

The existing system cannot effectively handle the exhaust gas after hydrogen bromide synthesis and remove acidic substances in the mixture, resulting in threats to personnel life safety and equipment corrosion problems.

Method used

A hydrogen bromide circulation absorption system is designed, including a multi-layer absorption tower, circulation tank, cooler and pump set. The acidic medium is extracted through the circulation absorption and cooling process, and the exhaust gas treatment system is used to further purify the exhaust gas to ensure that acidic substances and toxic substances are Safe emission of gases.

Benefits of technology

It effectively improves the purity of hydrogen bromide, ensures the safety of personnel and the environment, avoids corrosion of equipment by acidic media, and achieves safe treatment of exhaust gas.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN221846670U_ABST
    Figure CN221846670U_ABST
Patent Text Reader

Abstract

The utility model relates to the technical field of hydrogen bromide absorption, and particularly discloses a hydrogen bromide circulating absorption system which comprises a first absorption tower, a first circulating tank, a first cooler, a first circulating pump set, a second absorption tower, a second circulating tank, a second cooler, a second circulating pump set and a tail gas treatment system, a lower inlet of the first absorption tower is connected with a hydrogen bromide synthesis system, a lower outlet of the first absorption tower is communicated with a first inlet in the top of the first circulation tank, a bottom outlet of the first circulation tank is communicated with an inlet of the first circulation pump set, and an outlet of the first circulation pump set is connected with a first pipeline, a second pipeline and a third pipeline in parallel. The first pipeline is communicated with a second inlet in the top of the first circulating tank. The hydrogen bromide mixture is circularly absorbed and cooled, so that the acid medium in the hydrogen bromide mixture is extracted, the acid medium is conveyed into the external system, and the tail gas of the acid medium is also conveyed into the external system after being treated by the tail gas treatment system, so that the purity of hydrogen bromide is effectively improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model belongs to the technical field of hydrogen bromide absorption, in particular to a hydrogen bromide circulation absorption system. Background Art

[0002] Hydrogen bromide is an inorganic compound with the chemical formula HBr. It is miscible with water, ethanol and acetic acid. It is a colorless gas under standard conditions. It is mainly used to manufacture various bromine compounds. It can also be used in the pharmaceutical, dye, and fragrance industries. Hydrogen bromide emits smoke in the air, has a suffocating odor, and is toxic. Over time, it will endanger the safety of human life. Therefore, the tail gas of hydrogen bromide needs to be strongly washed before it can be discharged.

[0003] The hydrogen bromide synthesized by the hydrogen bromide synthesis system contains a certain amount of acid, and the acidic medium has a certain corrosiveness, and the hydrogen bromide and the acid have a good mixed absorption effect, so the mixture needs to be repeatedly cooled and absorbed to remove the acidic substances in the hydrogen bromide to improve the yield of hydrogen bromide. However, there is no system in the existing system that can circulate the cooling and absorption of the hydrogen bromide mixture. Therefore, a utility model of a hydrogen bromide circulation absorption system is urgently needed to solve the above problems. Utility Model Content

[0004] The utility model aims to provide a hydrogen bromide circulation absorption system, which solves the above-mentioned problem that the exhaust gas will affect the lives of people if it is not properly treated and discharged, and the problem that the acidic substances in the hydrogen bromide mixture are not completely removed.

[0005] In order to solve the above technical problems, the utility model provides a hydrogen bromide circulation absorption system, comprising a first absorption tower, a first circulation tank, a first cooler, a first circulation pump group, a second absorption tower, a second circulation tank, a second cooler, a second circulation pump group and a tail gas treatment system, wherein the lower inlet of the first absorption tower is connected to the hydrogen bromide synthesis system,

[0006] The lower outlet of the first absorption tower is communicated with the first inlet at the top of the first circulation tank, the bottom outlet of the first circulation tank is communicated with the inlet of the first circulation pump group, the outlet of the first circulation pump group is connected in parallel with a first pipeline, a second pipeline and a third pipeline, the first pipeline is communicated with the second inlet at the top of the first circulation tank, the second pipeline is communicated with the bottom inlet of the first cooler, the third pipeline is connected with an external system, the outlet of the first cooler is communicated with the upper inlet of the first absorption tower, the top outlet of the first absorption tower is communicated with the lower inlet of the second absorption tower,

[0007] The lower outlet of the second absorption tower is communicated with the first inlet at the top of the second circulation tank, the bottom outlet of the second circulation tank is communicated with the second circulation pump group, the outlet of the second circulation pump group is connected in parallel with a fourth pipeline, a fifth pipeline and a first circulation pipeline, the fourth pipeline is communicated with the second inlet at the top of the second circulation tank, the fifth pipeline is communicated with the second cooler, the first circulation pipeline is communicated with the upper inlet of the first absorption tower, the second cooler outlet is communicated with the middle inlet of the second absorption tower, the upper inlet of the second absorption tower is connected to the first pure water inlet pipeline, and the top outlet is communicated with the exhaust gas treatment system.

[0008] Furthermore, the tail gas treatment system includes an alkali washing tower and a third circulation pump group. The bottom outlet of the alkali washing tower is connected to the third circulation pump group, and the middle inlet is connected to the top outlet of the second absorption tower. The third circulation pump group includes at least two third circulation pumps. At least two of the third circulation pumps are arranged in parallel, and their outlets are respectively connected to the upper spray inlet of the alkali washing tower and the off-site system. The top outlet of the alkali washing tower is connected to a vent pipe, and the vent pipe is connected to an induced draft fan through a pipe. The alkali washing tower is connected in parallel with a production water inlet pipe and an alkali solution feed pipe.

[0009] Furthermore, a second circulation pipeline is connected to the pipeline between the hydrogen bromide synthesis system and the first absorption tower, and the other end of the second circulation pipeline is communicated with the third inlet at the top of the first circulation tank.

[0010] Furthermore, a third circulation pipeline is connected to the pipeline between the first absorption tower and the second absorption tower, and the other end of the third circulation pipeline is communicated with the third inlet at the top of the second circulation tank.

[0011] Furthermore, a fourth inlet is provided on the top of the second circulation tank, and the fourth inlet is connected to a second pure water inlet pipe, and a pneumatic switch valve is provided on the second pure water inlet pipe.

[0012] Furthermore, a pneumatic diaphragm regulating valve is provided on the third pipeline.

[0013] Furthermore, a first on-site installation instrument and a first DCS instrument are provided on the outside of the first circulation tank, the first on-site installation instrument and the first DCS instrument are connected, and the first DCS instrument is connected to the pneumatic diaphragm regulating valve through a wire.

[0014] Furthermore, a second on-site instrument and a second DCS instrument are provided on the outside of the second circulation tank, the second on-site instrument is connected to the second DCS instrument, and the second DCS instrument is connected to the pneumatic switch valve through a wire.

[0015] The beneficial effects of the utility model are as follows: the hydrogen bromide mixture in the utility model is circulated, absorbed and cooled through the first absorption tower, the second absorption tower, the first cooler, the second cooler, the first circulation tank, the second circulation tank, the first circulation pump group and the second circulation pump group, so as to extract the acidic medium in the hydrogen bromide mixture, and transport the acidic medium to the off-site system, and the tail gas thereof is also transported to the off-site system after being treated by the tail gas treatment system, so as to effectively improve the purity of the hydrogen bromide;

[0016] The utility model respectively provides a first locally installed instrument, a first DCS instrument, a second locally installed instrument and a second DCS instrument on the outer sides of the first circulation tank and the second circulation tank, and connects the first DCS instrument and the second DCS instrument with control unit signals to detect the conditions of the gases in the first circulation tank and the second circulation tank in real time, and then controls the pressure and pressure of the gases in the two circulation tanks at any time through a pneumatic diaphragm regulating valve and a pneumatic switch valve, so as to prevent the risk of explosion of the first circulation tank and the second circulation tank. BRIEF DESCRIPTION OF THE DRAWINGS

[0017] In order to more clearly illustrate the technical solution of the present invention, the drawings required for use in the embodiments or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative work.

[0018] Figure 1 This is the overall structural diagram of the hydrogen bromide circulation absorption system of the utility model;

[0019] In the figure: 1-first absorption tower, 2-first circulation tank, 3-first cooler, 4-first circulation pump group, 5-second absorption tower, 6-second circulation tank, 7-second cooler, 8-second circulation pump group, 9-tail gas treatment system, 10-hydrogen bromide synthesis system, 11-out-of-bounds system, 12-first pure water inlet pipeline, 13-first circulation pipeline, 14-second circulation pipeline, 15-third circulation pipeline, 16-second pure water inlet pipeline, 17-pneumatic switch valve, 18-pneumatic diaphragm regulating valve, 19-first on-site installation instrument, 20-first One DCS instrument, 21-first inlet, 22-second inlet, 23-third inlet, 24-second on-site instrument, 25-second DCS instrument, 41-first pipeline, 42-second pipeline, 43-third pipeline, 61-first inlet, 62-second inlet, 63-third inlet, 64-fourth inlet, 81-fourth pipeline, 82-fifth pipeline 91-alkali washing tower, 92-third circulating pump group, 93-venting pipeline, 94-induced draft fan, 95-production water inlet pipeline, 96-alkali solution feed pipeline, 911-spray inlet. DETAILED DESCRIPTION

[0020] The following will be combined with the drawings of the utility model specification to clearly and completely describe the technical solutions in the utility model embodiments. Obviously, the described embodiments are only part of the embodiments of the utility model, not all of the embodiments. Based on the embodiments of the utility model, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the utility model.

[0021] In a specific embodiment of the present invention, Figure 1 As shown, a hydrogen bromide circulating absorption system is specifically disclosed, comprising a first absorption tower 1, a first circulation tank 2, a first cooler 3, a first circulation pump group 4, a second absorption tower 5, a second circulation tank 6, a second cooler 7, a second circulation pump group 8 and a tail gas treatment system 9, the first absorption tower 1 is a packing absorption tower, the second absorption tower 5 is a bubble-cap absorption tower, the lower outlet of the first absorption tower 1 is connected to the first inlet 21 at the top of the first circulation tank 2, and the bottom outlet of the first circulation tank 2 is connected to the inlet of the first circulation pump group 4,

[0022] The number of the first circulation pump groups 4 is at least two, and in this embodiment, two are preferably provided. The two first circulation pumps are arranged in parallel, and the outlet of the first circulation pump group 4 is connected in parallel with a first pipeline 41, a second pipeline 42 and a third pipeline 43, the first pipeline 41 is connected to the second inlet 22 at the top of the first circulation tank 2, the second pipeline 42 is connected to the bottom inlet of the first cooler 3, the outlet of the first cooler 3 is connected to the upper inlet of the first absorption tower 1, the top outlet of the first absorption tower 1 is connected to the lower inlet of the second absorption tower 5, the third pipeline 43 is connected to the external system 11, the third pipeline 43 is provided with a pneumatic diaphragm regulating valve 18, and the lower inlet of the first absorption tower 1 is connected to the hydrogen bromide synthesis system 10,

[0023] A first on-site instrument 19 and a first DCS instrument 20 are provided outside the first circulation tank 2 . The first on-site instrument 19 and the first DCS instrument 20 are connected. The first DCS instrument 20 is connected to the pneumatic diaphragm regulating valve 18 through a wire.

[0024] The lower outlet of the second absorption tower 5 is connected to the first inlet 61 at the top of the second circulation tank 6, the bottom outlet of the second circulation tank 6 is connected to the second circulation pump group 8, the outlet of the second circulation pump group 8 is connected in parallel with the fourth pipeline 81, the fifth pipeline 82 and the first circulation pipeline 13, the fourth pipeline 81 is connected to the second inlet 62 at the top of the second circulation tank 6, the fifth pipeline 82 is connected to the second cooler 7, the first circulation pipeline 13 is connected to the upper inlet of the first absorption tower 1, the outlet of the second cooler 7 is connected to the middle inlet of the second absorption tower 5, the upper inlet of the second absorption tower 5 is connected to the first pure water inlet pipeline 12, and the top outlet is connected to the exhaust gas treatment system 9.

[0025] A third circulation pipeline 15 is connected to the pipeline between the first absorption tower 1 and the second absorption tower 5 , and the other end of the third circulation pipeline 15 is communicated with the third inlet 63 at the top of the second circulation tank 6 .

[0026] The tail gas treatment system 9 includes an alkali washing tower 91 and a third circulation pump group 92. The bottom outlet of the alkali washing tower 91 is connected to the third circulation pump group 92, and the middle inlet is connected to the top outlet of the second absorption tower 5. The third circulation pump group 92 includes at least two third circulation pumps. At least two third circulation pumps are arranged in parallel, and their outlets are respectively connected to the upper spray inlet 911 of the alkali washing tower 91 and the off-site system 11. The top outlet of the alkali washing tower 91 is connected to a vent pipe 93, and the vent pipe 93 is connected to an induced draft fan 94 through a pipe. The alkali washing tower 91 is connected in parallel with a production water inlet pipe 95 and an alkali solution feed pipe 96.

[0027] A second circulation pipeline 14 is connected to the pipeline between the hydrogen bromide synthesis system 10 and the first absorption tower 1. The other end of the second circulation pipeline 14 is connected to the third inlet 23 at the top of the first circulation tank 2. A fourth inlet 64 is provided on the top of the second circulation tank 6. The fourth inlet 64 is connected to the second pure water inlet pipeline 16. A pneumatic switch valve 17 is provided on the second pure water inlet pipeline 16.

[0028] A second on-site instrument 24 and a second DCS instrument 25 are provided on the outside of the second circulation tank 6 . The second on-site instrument 24 and the second DCS instrument 25 are connected. The second DCS instrument 25 is connected to the pneumatic switch valve 17 through a wire.

[0029] The first DCS meter 20 and the second DCS meter 25 are connected to a control unit.

[0030] The workflow of this utility model:

[0031] A part of the hydrogen bromide mixture in the hydrogen bromide synthesis system 10 is transported to the first absorption tower 1 for absorption. The hydrogen bromide mixture after absorption in the first absorption tower 1 is transported from the bottom outlet to the first inlet 21 at the top of the first circulation tank 2, and enters the first circulation tank 2 from the first inlet 21. Another part of the hydrogen bromide mixture in the hydrogen bromide synthesis system 10 enters the first circulation tank 2. The cold and hot hydrogen bromide mixtures in the first circulation tank 2 are mixed. The first circulation pump group 4 extracts the mixed hydrogen bromide mixture in the first circulation tank 2. At the beginning, the valve on the second pipeline 42 is opened to allow the warm hydrogen bromide mixture to enter the upper part of the first absorption tower 1 after being cooled by the first cooler 3. The cooled hydrogen bromide mixture entering the first absorption tower 1 reacts with the heated hydrogen bromide mixture in the first absorption tower 1 to obtain a part of gas. This part of gas is transported from the top of the first absorption tower 1 to the second absorption tower 5 and the second circulation tank 6.

[0032] The gas mixture with a lower density continues to enter the first circulation part transport tank 2 from the bottom of the first absorption tower 1, and then the gas mixture in the first circulation tank 2 is extracted by the first circulation pump group 4 and transported in two ways. One way enters the first cooler 3 for cooling and then enters the upper part of the first absorption tower 1, and then reacts with the heated hydrogen bromide mixture in the first absorption tower 1 to obtain a part of gas, which continues to be circulated and transported to the second absorption tower 5 and the second circulation tank 6, and the other way enters the first circulation tank 2 for mixing. The mixed gas mixture is then circulated, absorbed, cooled, and then absorbed.

[0033] During the cyclic absorption process, when the first DCS instrument 20 outside the first circulation tank 2 detects a specified pressure, the first DCS instrument 20 sends a signal to the control unit, and the control unit controls the pneumatic diaphragm regulating valve 18 to open, and the acidic medium obtained by the cyclic absorption is transported to the outside system 11 through the third pipeline 43;

[0034] A part of the gas in the first absorption tower 1 enters the second absorption tower 5 for absorption treatment, and then is transported from the bottom outlet to the first inlet 61 at the top of the second circulation tank 6, and enters the second circulation tank 6 from the first inlet 61; the other part enters the second circulation tank 6, and the cold and hot hydrogen bromide mixtures in the second circulation tank 6 are mixed with each other. The second circulation pump group 8 extracts the mixed hydrogen bromide mixture in the second circulation tank 6, and initially opens the valve on the fourth pipeline 81 to allow the warm hydrogen bromide mixture to enter the upper part of the second absorption tower 5 after being cooled by the second cooler 7, and then enters the second circulation tank 6 for continuous circulation after being circulated at least once;

[0035] During the cycle absorption, the first pure water inlet pipe 12 adds pure water to the upper part of the second absorption tower 5, and the pure water reacts with the cooled hydrogen bromide mixture entering the second absorption tower 5 and the heated hydrogen bromide mixture in the second absorption tower 5 to obtain useful gas and waste gas.

[0036] After the useful gas is transported to the second circulation tank 6 from the bottom outlet of the second circulation tank 6, it is extracted by the second circulation pump group 8 and transported to the second cooler 7, the second circulation tank 6 and the second absorption tower 5 for circulation absorption, cooling and re-absorption;

[0037] After circulating at least twice, the second circulating pump group 8 transports the hydrogen bromide mixture to the top of the first absorption tower 1 through the first circulating pipeline 13, and enters the first absorption tower 1 from the top inlet for circulating reaction, and then after circulating absorption, cooling and re-absorption in the first absorption tower 1, the acidic medium inside is transported to the external system 11;

[0038] During the cyclic absorption process, when the second DCS instrument 25 outside the second circulation tank 6 detects the specified pressure, the second DCS instrument 25 sends a signal to the control unit, and the control unit controls the pneumatic switch valve 17 to open, and adds pure water to the second circulation tank 6 through the second pure water inlet pipe 16 to balance the temperature and pressure in the second circulation tank 6.

[0039] The waste gas is transported from the top of the second absorption tower 5 to the alkali washing tower 91. After the alkali washing tower 91 performs alkali washing on the waste gas, the waste gas is circulated and transported to the alkali washing tower 91 through the third circulation pump group 92 for circulated alkali washing. Finally, the waste gas is transported to the off-site system 11. After being treated by the tail gas treatment system 9, the waste gas is also transported to the off-site system 11, thereby effectively improving the purity of hydrogen bromide, and preventing environmental pollution, and preventing the toxic gas of hydrogen bromide from endangering the lives of people and animals and plants.

[0040] The utility model can effectively remove the acidic substances in the hydrogen bromide mixture to improve the yield and purity of the hydrogen bromide, solve the problem that the hydrogen bromide containing the acidic substances is corrosive, and avoid the problem that the contacted objects are corroded.

[0041] The above disclosure is only a preferred embodiment of the present invention, and certainly cannot be used to limit the scope of rights of the present invention. Therefore, equivalent changes made according to the claims of the present invention are still within the scope covered by the present invention.

Claims

1. A hydrogen bromide circulation absorption system, characterized in that: The invention comprises a first absorption tower (1), a first circulation tank (2), a first cooler (3), a first circulation pump group (4), a second absorption tower (5), a second circulation tank (6), a second cooler (7), a second circulation pump group (8) and a tail gas treatment system (9), wherein the lower inlet of the first absorption tower (1) is connected to a hydrogen bromide synthesis system (10), The lower outlet of the first absorption tower (1) is communicated with the first inlet (21) at the top of the first circulation tank (2), the bottom outlet of the first circulation tank (2) is communicated with the inlet of the first circulation pump group (4), the outlet of the first circulation pump group (4) is connected in parallel with a first pipeline (41), a second pipeline (42) and a third pipeline (43), the first pipeline (41) is communicated with the second inlet (22) at the top of the first circulation tank (2), the second pipeline (42) is communicated with the bottom inlet of the first cooler (3), the third pipeline (43) is connected to an off-site system (11), the outlet of the first cooler (3) is communicated with the upper inlet of the first absorption tower (1), the top outlet of the first absorption tower (1) is communicated with the lower inlet of the second absorption tower (5), The lower outlet of the second absorption tower (5) is in communication with the first inlet (61) at the top of the second circulation tank (6), the bottom outlet of the second circulation tank (6) is in communication with the second circulation pump group (8), the outlet of the second circulation pump group (8) is connected in parallel with a fourth pipeline (81), a fifth pipeline (82) and a first circulation pipeline (13), the fourth pipeline (81) is in communication with the second inlet (62) at the top of the second circulation tank (6), the fifth pipeline (82) is in communication with the second cooler (7), the first circulation pipeline (13) is in communication with the upper inlet of the first absorption tower (1), the outlet of the second cooler (7) is in communication with the middle inlet of the second absorption tower (5), the upper inlet of the second absorption tower (5) is connected with a first pure water inlet pipeline (12), and the top outlet is in communication with the tail gas treatment system (9).

2. A hydrogen bromide circulation absorption system according to claim 1, characterized in that: The tail gas treatment system (9) comprises an alkali washing tower (91) and a third circulation pump group (92). The bottom outlet of the alkali washing tower (91) is connected to the third circulation pump group (92), and the middle inlet is connected to the top outlet of the second absorption tower (5). The third circulation pump group (92) comprises at least two third circulation pumps. At least two of the third circulation pumps are arranged in parallel, and their outlets are respectively connected to the upper spray inlet (911) of the alkali washing tower (91) and the off-site system (11). The top outlet of the alkali washing tower (91) is connected to a venting pipe (93), and the venting pipe (93) is connected to an induced draft fan (94) through a pipe. The alkali washing tower (91) is connected in parallel with a production water inlet pipe (95) and an alkali solution feed pipe (96).

3. A hydrogen bromide circulation absorption system according to claim 1, characterized in that: A second circulation pipeline (14) is connected to the pipeline between the hydrogen bromide synthesis system (10) and the first absorption tower (1), and the other end of the second circulation pipeline (14) is connected to the third inlet (23) at the top of the first circulation tank (2).

4. A hydrogen bromide circulation absorption system according to claim 1, characterized in that: A third circulation pipeline (15) is connected to the pipeline between the first absorption tower (1) and the second absorption tower (5), and the other end of the third circulation pipeline (15) is connected to the third inlet (63) at the top of the second circulation tank (6).

5. A hydrogen bromide circulation absorption system according to claim 1, characterized in that: A fourth inlet (64) is provided at the top of the second circulation tank (6), and the fourth inlet (64) is connected to a second pure water inlet pipeline (16), and a pneumatic switch valve (17) is provided on the second pure water inlet pipeline (16).

6. A hydrogen bromide circulation absorption system according to claim 1, characterized in that: The third pipeline (43) is provided with a pneumatic diaphragm regulating valve (18).

7. A hydrogen bromide circulation absorption system according to claim 6, characterized in that: A first locally installed instrument (19) and a first DCS instrument (20) are provided on the outside of the first circulation tank (2); the first locally installed instrument (19) and the first DCS instrument (20) are connected; and the first DCS instrument (20) and the pneumatic diaphragm regulating valve (18) are connected via a wire.

8. A hydrogen bromide circulation absorption system according to claim 5, characterized in that: A second locally installed instrument (24) and a second DCS instrument (25) are provided on the outside of the second circulation tank (6); the second locally installed instrument (24) and the second DCS instrument (25) are connected; and the second DCS instrument (25) is connected to the pneumatic switch valve (17) via a wire.