Formaldehyde replacement device for formaldehyde production equipment
By using a combined device of spiral diversion electric heating plate and cooling cover in formaldehyde production equipment, the problems of low heating efficiency and inconvenient cooling of the oxidation chamber are solved, and the efficiency and energy utilization of formaldehyde preparation are improved.
Patent Information
- Application Number
- CN202323548479.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2023-12-26
- Publication Date
- 2024-10-18
- Estimated Expiration
- 2033-12-26
AI Technical Summary
The oxidation chamber in the existing formaldehyde production equipment uses heating fins to contact the mixed gas for heating. The heating efficiency is low, consumes a lot of energy, and requires external cooling parts to cool the gas, which is inconvenient to use.
A formaldehyde replacement device including a tank, an electric heater, a catalytic converter, a cooling cover and a condenser is designed. The electric heater is equipped with a spiral diversion electric heating plate distributed in an annular array to form a spiral gas flow channel and improve the gas flow rate. The contact efficiency with the heated surface and the cooling and liquefaction of formaldehyde gas through the cooling cover.
It improves gas heating and catalytic treatment efficiency, extends gas flow time, improves formaldehyde preparation efficiency, reduces energy consumption, and facilitates gas cooling and liquefaction processing.
Smart Images

Figure CN221847105U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of formaldehyde production, in particular to a formaldehyde replacement device used for formaldehyde production equipment. Background Art
[0002] Formaldehyde production is to evaporate methanol and react with oxygen in the air at a certain temperature and on a catalyst to produce formaldehyde gas that dissolves in water to form a formaldehyde solution. In this process, an oxidative dehydrogenation reaction occurs in the oxidation chamber under the action of the high temperature of the heating element and the electrolytic silver catalyst, and the gas becomes a formaldehyde solution after cooling.
[0003] However, currently the oxidation chamber uses a heating fin plate to contact the mixed gas for heating, which has a low heating efficiency and consumes a lot of energy. At the same time, an external cooling component is required to cool the treated gas in the oxidation chamber, which is inconvenient to use. Utility Model Content
[0004] 1. Technical issues to be solved
[0005] In view of the deficiencies in the prior art, the utility model provides a formaldehyde replacement device for formaldehyde production equipment, which solves the problem that the current oxidation chamber uses a heating fin plate to contact with the mixed gas for heating, has low heating efficiency, consumes a large amount of energy, and requires an external cooling component to cool the treated gas in the oxidation chamber, which is inconvenient to use.
[0006] (II) Technical solution
[0007] In order to achieve the above-mentioned purpose, the utility model specifically adopts the following technical solutions:
[0008] A formaldehyde replacement device for formaldehyde production equipment comprises a tank body, an electric heater, a catalyst, a cooling hood and a condenser, wherein the electric heater is arranged in the inner cavity of the tank body, spiral flow-guiding electric heating plates distributed in a ring array are arranged in the electric heater, the catalyst is arranged in the tank body below the electric heater, the cooling hood is arranged at the lower port position of the tank body, the condenser is arranged under the cooling hood, and a top cover is arranged at the bottom of the tank body and a bottom cover is arranged at the bottom.
[0009] Furthermore, a sleeve is fixedly connected to the outer edge of the spiral guide heating plate of the electric heater, the sleeve is embedded in the internal cavity of the tank body and abuts against the inner wall of the tank body, and a spiral gas flow channel is formed between the sleeve and the spiral guide heating plate, and both ends of the spiral guide heating plate are integrally provided with guide end plates parallel to the center axis of the tank body.
[0010] Furthermore, a plug-in ring plate is integrally provided at the edge of the cooling hood, the plug-in ring plate is plugged into the port of the tank body, and a liquid accumulation groove is formed at the transition portion between the plug-in ring plate and the cooling hood, a liquid leakage hole distributed in a circular array is opened at the bottom of the liquid accumulation groove, and a lap ring plate is integrally provided on the outer side wall of the plug-in ring plate, and the lap ring plate is lapped on the flange plate at the lower port of the tank body.
[0011] Furthermore, flange plates are provided at the upper and lower ports of the tank body, the flange plate at the edge of the top cover is fixedly connected to the flange plate at the upper part of the tank body by bolts, a feed pipe is integrally provided on the top cover, and the flange plate at the edge of the bottom cover is fixedly connected to the flange plate at the lower part of the tank body by bolts, a discharge pipe is integrally provided on the bottom cover, and sealing gaskets are arranged between the flange plates that conflict with each other.
[0012] (III) Beneficial effects
[0013] Compared with the prior art, the utility model provides a formaldehyde replacement device for formaldehyde production equipment, which has the following beneficial effects:
[0014] The utility model utilizes the spiral guide heating plate of the electric heater to form a spiral gas flow channel in the internal cavity of the tank body, thereby extending the flow time and path of the gas to be treated, improving the contact efficiency between the gas to be treated and the spiral guide heating plate, and effectively heating the gas to be treated entering the tank body, so as to improve the catalytic treatment efficiency of the gas to be treated. At the same time, a cooling hood is used to cool and liquefy the treated gaseous formaldehyde, thereby improving the formaldehyde preparation efficiency. BRIEF DESCRIPTION OF THE DRAWINGS
[0015] Figure 1 It is a schematic diagram of the structure of the utility model;
[0016] Figure 2 It is a cross-sectional view of the utility model;
[0017] Figure 3 It is a structural schematic diagram of the electric heater in the utility model;
[0018] Figure 4 It is a cross-sectional view of the cooling cover in the present utility model.
[0019] In the figure: 1. tank body; 101. top cover; 102. feed pipe; 103. bottom cover; 104. discharge pipe; 2. electric heater; 201. spiral guide electric heating plate; 202. sleeve; 3. catalyst; 4. cooling cover; 401. plug-in ring plate; 402. lap ring plate; 403. liquid accumulation groove; 404. leakage hole; 5. condenser. DETAILED DESCRIPTION
[0020] The following will be combined with the drawings in the embodiments of the utility model to clearly and completely describe the technical solutions in the embodiments of the utility model. Obviously, the described embodiments are only part of the embodiments of the utility model, not all of the embodiments. Based on the embodiments in the utility model, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the utility model.
[0021] Example
[0022] like Figure 1 , Figure 2 , Figure 3 and Figure 4 As shown, an embodiment of the utility model proposes: a formaldehyde replacement device for formaldehyde production equipment, including a tank body 1, an electric heater 2, a catalyst 3, a cooling cover 4 and a condenser 5, the electric heater 2 is arranged in the inner cavity of the tank body 1, and the electric heater 2 is provided with a spiral guide electric heating plate 201 distributed in a ring array, which is convenient for effectively heating the gas to be treated entering the tank body 1, so as to improve the catalytic treatment efficiency of the gas to be treated and ensure the stable preparation of formaldehyde, and the catalyst 3 is arranged in the tank body 1 below the electric heater 2, and the gas to be treated entering the tank body 1 is heated. Under the action of catalysis, an oxidative dehydrogenation reaction occurs to complete the preparation operation of formaldehyde. A cooling hood 4 is arranged at the lower port position of the tank body 1, and a condenser 5 is arranged at the lower part of the cooling hood 4. The prepared formaldehyde gas is cooled by the cooperation of the two to change it from a gaseous state to a liquid state, which is convenient for transportation and the next step of processing, thereby improving the efficiency of formaldehyde preparation. In addition, a top cover 101 is arranged at the bottom of the tank body 1, and a bottom cover 103 is arranged at the bottom, so as to seal the two ends of the tank body 1 to form a closed vessel for processing gas, which is stably and effectively processed to complete the preparation of formaldehyde.
[0023] like Figure 2 and Figure 3As shown, in some embodiments, a sleeve 202 is fixedly connected to the outer edge of the spiral guide electric heating plate 201 of the electric heater 2, and the sleeve 202 is embedded in the internal cavity of the tank body 1 and abuts against the inner wall of the tank body 1, so that the entire electric heater 2 can be stably rotated in the internal cavity of the tank body 1 by using the sleeve 202. During use, it is powered on to heat the gas to be treated entering the tank body 1, so that the gas to be treated is catalyzed by the catalyst 3 to prepare formaldehyde, and a space is formed between the sleeve 202 and the spiral guide electric heating plate 201. The spiral gas flow channel changes the straight gas flow channel into a spiral channel, prolongs the flow time and path of the gas to be treated, improves the contact efficiency between the gas to be treated and the spiral guide heating plate 201, ensures that the gas to be treated is well heated, and facilitates subsequent catalytic treatment. In addition, both ends of the spiral guide heating plate 201 are integrally provided with guide end plates parallel to the central axis of the tank body 1, which is convenient for changing the direction of gas flow, so that the gas flows in the direction of the central axis of the tank body 1 and is directly blown onto the catalyst 3, thereby improving the preparation efficiency of formaldehyde.
[0024] like Figure 2 and Figure 4 As shown, in some embodiments, a plug-in ring plate 401 is integrally provided at the edge of the cooling cover 4, and the plug-in ring plate 401 is plugged into the port of the tank body 1, so that the cooling cover 4 can be stably installed on the tank body 1, so that the cooling cover 4 can be stably placed in the internal cavity of the tank body 1, and the replaced formaldehyde gas can be cooled, liquefied, smoothly discharged, and processed in the next process, and a liquid accumulation groove 403 is formed at the transition portion between the plug-in ring plate 401 and the cooling cover 4, and a ring-shaped bottom of the liquid accumulation groove 403 is provided. The leakage holes 404 distributed in an array facilitate the smooth collection of the cooled liquid on the cooling hood 4 into the liquid accumulation groove 403, and the liquid drips from the leakage holes 404 to be discharged into the bottom cover 103, and a lap ring plate 402 is integrally provided on the outer wall of the plug-in ring plate 401, and the lap ring plate 402 is overlapped on the flange plate at the lower port of the tank body 1, so that the cooling hood 4 can be fixed in the cavity limited at the port of the tank body 1 by using the lap ring plate 402, so as to ensure stable use and perform cooling and liquefaction operations on the gaseous formaldehyde gas.
[0025] like Figure 1 and Figure 2As shown, in some embodiments, flange plates are provided at both the upper and lower ports of the tank body 1, and the flange plate at the edge of the top cover 101 is fixedly connected to the flange plate on the upper part of the tank body 1 by bolts, so that the top cover 101 can be stably installed on the tank body 1, so that the two can be stably used together, and a feed pipe 102 is integrally provided on the top cover 101, so that the formaldehyde material delivery pipeline in the production process can be stably connected to the feed pipe 102, so that it can be stably delivered to the internal cavity of the tank body 1, so as to facilitate its processing, and the edge of the bottom cover 103 The flange plate at the bottom is fixedly connected to the flange plate at the lower part of the tank body 1 by bolts, so that the bottom cover 103 can be stably installed on the tank body 1 so that the two can be stably used together. The bottom cover 103 is integrally provided with a discharge pipe 104, so that the pipeline for conveying materials can be stably connected to the bottom cover 103, and the formaldehyde prepared in the tank body 1 can be smoothly discharged, so as to continuously process the formaldehyde material and perform the formaldehyde preparation operation. Sealing gaskets are arranged between the flange plates that conflict with each other to seal the gaps at the connection parts to ensure stable use.
[0026] Finally, it should be noted that the above description is only a preferred embodiment of the utility model and is not intended to limit the utility model. Although the utility model is described in detail with reference to the above embodiments, those skilled in the art can still modify the technical solutions recorded in the above embodiments or replace some of the technical features therein by equivalents. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the utility model shall be included in the protection scope of the utility model.
Claims
1. A formaldehyde replacement device for formaldehyde production equipment, comprising a tank (1), an electric heater (2), a catalyst (3), a cooling hood (4) and a condenser (5), characterized in that: An electric heater (2) is arranged in the internal cavity of the tank body (1), a spiral flow-guiding electric heating plate (201) distributed in a ring array is arranged in the electric heater (2), a catalyst (3) is arranged in the tank body (1) below the electric heater (2), a cooling cover (4) is arranged at the lower port position of the tank body (1), a condenser (5) is arranged at the lower part of the cooling cover (4), and a top cover (101) is arranged at the bottom of the tank body (1), and a bottom cover (103) is arranged at the bottom.
2. A formaldehyde replacement device for formaldehyde production equipment according to claim 1, characterized in that: A sleeve (202) is fixedly connected to the outer edge of the spiral flow-guiding electric heating plate (201) of the electric heater (2); the sleeve (202) is embedded in the internal cavity of the tank body (1) and abuts against the inner wall of the tank body (1); a spiral gas flow channel is formed between the sleeve (202) and the spiral flow-guiding electric heating plate (201); and both ends of the spiral flow-guiding electric heating plate (201) are integrally provided with flow-guiding end plates parallel to the central axis of the tank body (1).
3. A formaldehyde replacement device for formaldehyde production equipment according to claim 1, characterized in that: A plug-in ring plate (401) is integrally provided at the edge of the cooling hood (4), the plug-in ring plate (401) is plugged into the port of the tank body (1), and a liquid accumulation groove (403) is formed at the transition between the plug-in ring plate (401) and the cooling hood (4), a liquid leakage hole (404) distributed in a circular array is provided at the bottom of the liquid accumulation groove (403), and a lap ring plate (402) is integrally provided on the outer wall of the plug-in ring plate (401), and the lap ring plate (402) is lapped on the flange plate at the lower port of the tank body (1).
4. A formaldehyde replacement device for formaldehyde production equipment according to claim 1, characterized in that: The upper and lower ends of the tank body (1) are both provided with flange plates, the flange plate at the edge of the top cover (101) is fixedly connected to the flange plate at the upper part of the tank body (1) by bolts, a feed pipe (102) is integrally provided on the top cover (101), and a flange plate at the edge of the bottom cover (103) is fixedly connected to the flange plate at the lower part of the tank body (1) by bolts, a discharge pipe (104) is integrally provided on the bottom cover (103), and sealing gaskets are arranged between the flange plates that contact each other.