Construction engineering concrete post-pouring rapid assembly and disassembly supporting system
By designing a prefabricated post-cast belt beam-slab back-top support system and utilizing components such as columns, corbels, and cantilever parts, the existing technology problems of repeated installation and dismantling of post-cast belt-back roof brackets and the complexity of the overall structure have been achieved, and a rapid Installation and dismantling, safe and efficient construction results.
Patent Information
- Application Number
- CN202420186112.X
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-01-25
- Publication Date
- 2024-10-18
- Estimated Expiration
- 2034-01-25
AI Technical Summary
In existing construction projects, post-poured roof supports are repeatedly installed and dismantled or the overall structure is complex, which affects construction efficiency and safety, and is prone to irregular erection problems.
A prefabricated post-cast belt beam-slab back-top support system is designed, which uses components such as columns, corbels, cantilever parts and post-cast belt joists, and is connected through bolts and threaded casings to form an adjustable support component. Commonly used Peripheral materials and auxiliary materials enable rapid installation, disassembly and reuse to avoid frequent changes in stress within the structure.
It achieves rapid installation, disassembly and reuse of support components, reduces material loss, occupies a small area, has high safety and stability, avoids frequent changes in structural stress, forms an overall support system, and improves construction efficiency and safety.
Smart Images

Figure CN221856315U_ABST
Abstract
Description
Technical Field
[0001] The utility model belongs to the technical field of building construction, and in particular relates to a post-casting quick installation and disassembly support system for building engineering concrete. Background Art
[0002] Post-cast strips are concrete strips with a certain width reserved in beams, slabs (including foundation slabs), walls and other structures to avoid being affected by factors such as ambient temperature changes, concrete shrinkage, and structural unevenness. The width of the post-cast strip is generally 60 to 100 cm, and the time for additional concrete pouring varies from 14 to 60 days after the concrete pouring of the two sides of the structure is completed. Because the beams and slabs on both sides of the post-cast strip are in a cantilever state for a long time before the concrete pouring of the post-cast strip is completed and reaches a certain strength, the beam and slab formwork supports on both sides cannot be removed or immediately re-topped after removal.
[0003] At present, the top-return brackets on both sides of the post-casting strip in construction projects mostly use simple combined steel pipe brackets to return the cantilever beams (hereinafter referred to as "top-return bracket form 1") or use ordinary fastener steel pipe brackets to return the beams and slabs as a whole (hereinafter referred to as "top-return bracket form 2"). For the top-return bracket form 1, after the concrete of the beams and slabs on both sides of the post-casting strip reaches a certain strength, the formwork and brackets are removed and then installed independently to achieve the purpose of returning the beams and slabs. After the time for pouring concrete in the post-casting strip is reached, the support frame and formwork of the post-casting strip are installed, and the concrete of the post-casting strip is poured. The advantage is that the bracket occupies a small area and can minimize the impact of the bracket on the construction; the disadvantage is that it is repeatedly installed and disassembled, and the top-return bracket does not form an integral support system with the post-casting strip support frame. For the top-return bracket form 2, because it is an integral bracket, it occupies a large area, which affects the transportation of flat materials and the construction of adjacent parts; and the common problem of irregular erection (excessive spacing between vertical poles, too high sweeping poles, and too long free sections) is prone to occur during the erection of ordinary fastener brackets. Therefore, it is particularly necessary to study an assembled post-cast beam-slab top support component which is safe, stable, reliable, and can be installed and disassembled multiple times and can be reused. Utility Model Content
[0004] The utility model aims to provide a construction engineering concrete post-casting rapid installation and disassembly support system, which solves the problems of repeated installation and disassembly of existing return top brackets or complicated overall structure.
[0005] The purpose of the utility model is achieved through the following technical solutions:
[0006] A construction engineering concrete post-casting rapid installation and disassembly support system includes a cantilever portion of a beam body and a casting area of a beam body post-casting strip between the cantilever portions of the beam body, and also includes a column, a cantilever portion top support is provided on the top of the column, a cantilever portion main beam is supported on the cantilever portion top support, a cantilever portion bottom mold is supported on the cantilever portion main beam, and the cantilever portion bottom mold supports the cantilever portion of the beam body, a corbel is also provided on the top of the column, a post-casting strip support beam is provided between the corbels on both sides of the casting area of the beam body post-casting strip, a post-casting strip top support is provided on the post-casting strip support beam, a post-casting strip main beam is supported on the post-casting strip top support, a post-casting strip main beam is supported on the post-casting strip bottom mold, and the casting area of the beam body post-casting strip is above the post-casting strip bottom mold.
[0007] Furthermore, the columns are I-beams, the corbels are angle steels, and the post-cast strip support beams are channel steels.
[0008] Furthermore, a bottom plate is welded to the bottom of the column, the bottom plate is fixed to the ground by bolts, and a top plate is welded to the top of the column.
[0009] Furthermore, both sides of the column are provided with corbels, and the column and the corbels are welded and connected.
[0010] Furthermore, the corbel is connected to the post-cast strip joist by bolts.
[0011] Furthermore, the cantilever part support and / or post-cast strip support include a lower support sleeve and an upper support sleeve, the lower support sleeve is arranged on the column, the lower support sleeve and the upper support sleeve are threadedly matched, and a U-shaped support is provided on the top of the upper support tube, and the U-shaped support supports the main beam.
[0012] Furthermore, the lower support sleeve is welded to the column, and the upper support bracket is welded to the U-shaped support.
[0013] Furthermore, the main beam of the cantilever part and / or the main beam of the post-cast zone are square steel tubes or square timbers.
[0014] Furthermore, the bottom formwork of the cantilever part and / or the bottom formwork of the post-casting strip is an aluminum film plate or a wooden formwork.
[0015] Furthermore, the casting area of the beam body post-casting strip is an inverted trapezoidal cross-section or a rectangular cross-section.
[0016] Beneficial effects of the utility model:
[0017] 1. The supporting components are prefabricated structures. The components used are all commonly used peripheral materials and auxiliary materials on the construction site. Through reasonable design and processing, they can be quickly installed and disassembled and reused, thereby reducing the loss of circulating materials.
[0018] 2. The supporting poles are erected together with the beam and slab support frames, and are removed after the concrete pouring of the post-cast zone is completed and reaches a certain strength. They always act under the cantilever beam formwork system to avoid frequent changes in the internal stress state of the structural beam.
[0019] 3. The supporting member can be used independently as a single pole or as a group of two poles. The supporting pole is set up together with the beam and slab support frame. After the formwork support frame is removed, it is independently supported under the cantilever beam formwork system. Compared with the second form of the return support, it occupies a smaller area and has higher safety and stability. Before pouring the post-casting strip concrete, the two poles are connected by connecting the joists, and the top support, square wood and formwork are installed on them to form the post-casting strip formwork system.
[0020] The aforementioned main scheme of the utility model and its further options can be freely combined to form multiple schemes, all of which are schemes that can be adopted and protected by the utility model; and in the utility model, (non-conflicting options) options and other options can also be freely combined. After understanding this scheme, those skilled in the art can understand that there are many combinations based on the existing technology and common knowledge, all of which are technical schemes to be protected by the utility model, and they are not exhaustively listed here. BRIEF DESCRIPTION OF THE DRAWINGS
[0021] Figure 1 It is the front view of the structure of the utility model.
[0022] Figure 2 It is a side view of the structure of the utility model.
[0023] In the figure: 1-bottom plate, 2-column, 3-bolt, 4-corbel, 5-post-cast strip support beam, 6-top plate, 7-cantilever part top support, 8-post-cast strip top support, 9-cantilever part main beam, 10-post-cast strip main beam, 11-cantilever part bottom formwork, 12-post-cast strip bottom formwork, 13-cantilever part of beam body, 14-post-cast strip of beam body. DETAILED DESCRIPTION
[0024] The present invention will be further described below in conjunction with specific embodiments and drawings.
[0025] refer to Figure 1 and Figure 2 As shown, a post-cast concrete quick installation and disassembly support system for construction engineering is an assembled component as a whole, including a base plate 1, a column 2, a bolt 3, a corbel 4, a post-cast strip support beam 5, a top plate 6, a cantilever part top support 7, a post-cast strip top support 8, a cantilever part main beam 9, a post-cast strip main beam 10, a cantilever part bottom formwork 11 and a post-cast strip bottom formwork 12, and construction work is carried out on the casting area of the beam body cantilever part 13 and the beam body post-cast strip 14 between the beam body cantilever parts 13.
[0026] The top of the column 2 is provided with a cantilever part top support 7, on which the cantilever part main beam 9 is supported, on which the cantilever part bottom form 11 is supported, and the cantilever part bottom form 11 supports the cantilever part 13 of the beam body. The supporting components of the cantilever part are erected together with the beam and slab formwork supports on both sides of the post-casting zone. After the beam and slab are poured with concrete and reach a certain strength, the beam and slab supports are removed, and the column supporting components are retained independently.
[0027] A corbel 4 is also provided on the top of the column 2, and a post-casting strip 14 of the beam body is poured between the corbels 4 on both sides of the opposite sides of the pouring area of the post-casting strip 14. A post-casting strip top support 8 is provided on the post-casting strip joist 5, and a post-casting strip main beam 10 is supported on the post-casting strip top support 8. A post-casting strip bottom formwork 12 is supported on the post-casting strip main beam 10, and the top of the post-casting strip bottom formwork 12 is the pouring area of the beam body post-casting strip 14.
[0028] When the time for pouring the post-casting belt is reached, the post-casting belt support beam is installed to connect the two vertical poles, and the formwork system of the post-casting belt beam and the formwork support system of the post-casting waiting board are installed. When the post-casting belt pouring concrete reaches a certain strength, the entire support system is dismantled and cleaned for recycling.
[0029] Column 2 is an I-beam, which is the main load-bearing component of the support system.
[0030] A steel base plate 1 with a thickness of 10 to 20 mm is welded to the bottom of the column 2. Bolt holes are reserved on the base plate. The base plate 1 is fixed to the ground by bolts 3. The steel base plate effectively expands the ground contact area of the column and can make the supporting member more stable by driving expansion screws or anchor bolts into the bolt holes.
[0031] A top plate 6 with a thickness of 10 to 20 mm is welded to the top of the column 2 to enhance the structural strength of the column 2 .
[0032] The corbel 4 is an angle steel, and is disposed on both sides of the column 2. The column 2 is welded to the corbel 4, and the corbel is used to support the post-casting belt joist.
[0033] The post-casting strip support beam 5 is a channel steel, and a certain length of post-casting strip support is welded at equal distances in the middle. Bolt holes are opened on the end channel steel wings, and the corbel 4 is connected to the post-casting strip support beam 5 by bolts 3.
[0034] The cantilever part support 7 and the post-casting strip support 8 both include a lower support sleeve and an upper support sleeve. The lower support sleeve is welded on the column 2. The lower support sleeve and the upper support sleeve are threadedly matched. A U-shaped support is welded on the top of the upper support bracket. The U-shaped support supports the main beam. The formwork support can be adjusted within a certain height range in the form of a threaded sleeve.
[0035] The cantilever part main beam 9 and the post-casting strip main beam 10 are both square steel tubes or square wood, arranged longitudinally at the bottom of the bottom mold to ensure the stability of the bottom mold. The cantilever part bottom mold 11 and / or the post-casting strip bottom mold 12 are aluminum film plates or wooden templates.
[0036] The pouring area of the beam body post-casting strip 14 has an inverted trapezoidal cross section, which can facilitate the construction during post-casting, or has a rectangular cross section.
[0037] The workflow of this utility model:
[0038] 1. Determine the location and width of the post-casting strip according to the design or specification requirements, and accurately mark the buried position of the base plate (considering that the width of the post-casting strip is mostly 60-100cm, the center distance between the buried positions of two vertical poles in the same group can be 100-140cm). Clean and level the concrete base surface within the installation range of the vertical pole base plate, install the vertical pole, and drive the expansion bolts into the bolt holes reserved in the vertical pole base plate to fix the vertical pole to the concrete base surface.
[0039] 2. Install a height-adjustable cantilever top support on the top of the column, adjust the top support elevation, install the cantilever main beam (square wood) and the cantilever bottom formwork, accurately adjust the bottom formwork elevation through the butterfly nut of the top support, reinforce the formwork system, install steel bars, and install a concrete interception net at the position reserved for the post-casting strip, pour the beam and slab concrete, and form the cantilever part of the beam body. After the beam and slab concrete reaches a certain strength, remove the remaining formwork and support system. At this time, the beams and slabs on both sides of the post-casting strip are only topped back through this support member.
[0040] 3. After the time limit for the post-casting strip is reached, install the post-casting strip support beam, which is fixed to the brackets of the two I-beam vertical poles by bolts. Install the adjustable post-casting strip top support on the support beam, install the square wood and post-casting strip formwork, and remove the concrete interception net and clean up the construction slag and debris before installing the formwork.
[0041] 4. Install the post-casting strip formwork and support system, and pour the post-casting strip beam and slab concrete after checking that there are no problems to form the post-casting strip of the beam body. After the concrete reaches a certain strength, remove the entire support system and clean, recycle and reuse the components of the support system.
[0042] The above basic examples and further optional examples of the utility model can be freely combined to form multiple embodiments, which are all embodiments that can be adopted and claimed for protection by the utility model. In the scheme of the utility model, each optional example can be arbitrarily combined with any other basic examples and optional examples.
[0043] The above description is only a preferred embodiment of the present invention and is not intended to limit the present invention. Any modifications, equivalent substitutions and improvements made within the spirit and principles of the present invention should be included in the protection scope of the present invention.
Claims
1. A construction engineering concrete post-casting rapid installation and disassembly support system, comprising a beam body cantilever portion (13) and a casting area of a beam body post-casting strip (14) between the beam body cantilever portions (13), and also comprising a column (2), characterized in that: The top of the column (2) is provided with a cantilever part top support (7), the cantilever part top support (7) supports the cantilever part main beam (9), the cantilever part main beam (9) supports the cantilever part bottom form (11), the cantilever part bottom form (11) supports the cantilever part (13) of the beam body, and the top of the column (2) is also provided with a corbel (4), and a post-casting strip supporting beam (5) is provided between the corbels (4) on both sides of the pouring area of the beam body post-casting strip (14), and the post-casting strip top support (8) is provided on the post-casting strip supporting beam (5), and the post-casting strip top support (8) supports the post-casting strip main beam (10), and the post-casting strip main beam (10) supports the post-casting strip bottom form (12), and the top of the post-casting strip bottom form (12) is the pouring area of the beam body post-casting strip (14).
2. The post-casting rapid installation and disassembly support system for construction engineering concrete according to claim 1 is characterized by: The upright column (2) is an I-beam, the corbel (4) is an angle steel, and the post-casting belt support beam (5) is a channel steel.
3. The post-casting rapid installation and disassembly support system for construction engineering concrete according to claim 1 or 2, characterized in that: A bottom plate (1) is welded to the bottom of the column (2), the bottom plate (1) is fixed to the ground by bolts (3), and a top plate (6) is welded to the top of the column (2).
4. The post-casting rapid installation and disassembly support system for construction engineering concrete according to claim 1 or 2, characterized in that: Corbels (4) are provided on both sides of the column (2), and the column (2) and the corbels (4) are connected by welding.
5. The post-casting rapid installation and disassembly support system for construction engineering concrete according to claim 1 or 2, characterized in that: The corbel (4) is connected to the post-casting belt support beam (5) through bolts (3).
6. The post-casting rapid installation and disassembly support system for construction engineering concrete according to claim 1 is characterized by: The cantilever part support (7) and / or post-cast strip support (8) include a lower support sleeve and an upper support sleeve, wherein the lower support sleeve is arranged on the column (2), the lower support sleeve and the upper support sleeve are threadedly matched, and a U-shaped support is arranged on the top of the upper support bracket, and the U-shaped support supports the main beam.
7. The post-casting rapid installation and disassembly support system for construction engineering concrete according to claim 6 is characterized by: The lower support sleeve is welded to the column (2), and the upper support bracket is welded to the U-shaped bracket.
8. The post-casting rapid installation and disassembly support system for construction engineering concrete according to claim 1 is characterized by: The cantilever portion main beam (9) and / or the post-casting zone main beam (10) are square steel tubes or square wood.
9. The post-casting rapid installation and disassembly support system for construction engineering concrete according to claim 1 is characterized by: The cantilever part bottom mold (11) and / or the post-casting strip bottom mold (12) are aluminum film plates or wooden templates.
10. The post-casting rapid installation and disassembly support system for construction engineering concrete according to claim 1 is characterized by: The casting area of the beam body post-casting strip (14) is an inverted trapezoidal cross section or a rectangular cross section.