Black-process asphalt flue gas purification system

By using a multi-pipe heater combination system in the asphalt flue gas purification system, the flue gas temperature is increased and the coke powder and flue gas are fully mixed, which solves the problems of asphalt flue gas solidification and low purification efficiency, and achieves efficient flue gas Purification and coke powder recovery.

CN221859259UActive Publication Date: 2024-10-18SHANDONG CHENYANG NEW CARBON MATERIALS
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202323290692.1
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2023-12-04
Publication Date
2024-10-18
Estimated Expiration
2033-12-04

AI Technical Summary

Technical Problem

Existing technology cannot effectively control the temperature of asphalt flue gas, causing condensation and blockage in the flue pipes, affecting purification efficiency, and existing electric tar collectors cannot meet environmental protection requirements.

Method used

The first pipe heater and the second pipe heater are respectively used to increase the temperature of the flue gas to keep it above the dew point, ensure that the coke powder and flue gas are fully mixed, and prevent the asphalt flue gas from solidifying and adhering to the pipe wall. The combined system of mixing reactor, cyclone separator and bag dust collector achieves purification.

Benefits of technology

It improves flue gas purification efficiency, prevents asphalt flue gas from solidifying, extends the service life of the system, meets environmental protection requirements, and improves the binder utilization rate in the production process by recycling coke powder.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN221859259U_ABST
    Figure CN221859259U_ABST
Patent Text Reader

Abstract

The utility model relates to a black-process asphalt flue gas purification system, and belongs to the technical field of flue gas purification. Comprising a coke powder storage tank and an air conveying device, a flue gas inlet of a Venturi mixing reactor is communicated with a flue gas collecting pipe through a first pipeline heater, a flue gas outlet of the Venturi mixing reactor is communicated with a flue gas inlet of a cyclone separator through a pipeline A, a regulating valve is installed on the pipeline A, and a gas outlet of the cyclone separator is communicated with a gas outlet of the Venturi mixing reactor. A flue gas outlet of the cyclone separator is communicated with a flue gas inlet of the bag-type dust collector through a second pipeline, a second pipeline heater is mounted on a feed port of the Venturi mixing reactor, and the coke powder storage tank is communicated with the second pipeline heater through an air conveying device. The device has the following beneficial effects that the first pipeline heater and the second pipeline heater are additionally arranged and are used for increasing the temperature of the flue gas, the temperature of the flue gas is kept above a dew point, the coke powder and the flue gas are fully mixed in the reactor and the pipeline by increasing the temperature, the purification efficiency is improved, and the asphalt flue gas is prevented from being solidified and adhered to the wall of the pipeline.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to a black asphalt flue gas purification system, belonging to the technical field of flue gas purification. Background Art

[0002] The carbon manufacturing industry usually uses petroleum coke as raw material, and processes it into various specifications of carbon products through raw material preparation, batching, kneading, molding, roasting and other processes through calcination and asphalt as a binder. In each production process, a large amount of production dust overflows, especially in the molding workshop, where a large amount of pollutants such as asphalt fume, dust and water vapor are generated during the asphalt melting, kneading and molding process.

[0003] In order to purify different pollutants in the gas, several methods are usually used. One is the electrostatic capture method; this method is simple to operate and easy to use; but as the operation time increases, the tar and impurities adhering to the plate affect the purification efficiency and normal operation of the point tar collector. Although many manufacturers use plate heating and spraying technology to solve the problem of plate oil adhesion, the electric tar collector still cannot meet the existing environmental protection requirements.

[0004] At present, the black method of asphalt flue gas adsorption is an ideal equipment for treating asphalt flue gas in the current carbon industry. However, the current technical considerations are not comprehensive and have the following disadvantages: if the flue gas temperature is not well controlled, the flue gas will condense and block the flue pipe in a short time.

[0005] In order to solve one of the above problems, a black asphalt flue gas purification system is urgently needed. Utility Model Content

[0006] In view of the above deficiencies in the prior art, the technical problem to be solved by the utility model is: how to achieve the purpose of increasing the temperature of the flue gas by adding a first pipe heater and a second pipe heater, maintaining the flue gas temperature above the dew point, increasing the temperature so that the coke powder and the flue gas are fully mixed in the reactor and the pipeline, improving the purification efficiency, and preventing the asphalt flue gas from solidifying and adhering to the pipeline wall. For this purpose, a black method asphalt flue gas purification system is provided.

[0007] The black asphalt flue gas purification system described in the utility model is characterized in that the black asphalt flue gas purification system includes a Venturi mixing reactor, wherein the two ends of the Venturi mixing reactor are respectively arranged as a flue gas inlet and a flue gas outlet, and one side of the Venturi mixing reactor is provided with a feed port connected to its inner cavity, and is characterized in that: it also includes a coke powder storage tank and an air delivery device, the flue gas inlet of the Venturi mixing reactor is connected to the flue gas collection pipe through a first pipe heater, the flue gas outlet of the Venturi mixing reactor is connected to the flue gas inlet of a cyclone separator through a pipe A, a regulating valve is installed on the pipe A, the flue gas outlet of the cyclone separator is connected to the flue gas inlet of a bag filter through a second pipe, a second pipe heater is installed on the feed port of the Venturi mixing reactor, and the coke powder storage tank is connected to the second pipe heater through the air delivery device.

[0008] The regulating valve is used to control the air flow rate so that the Venturi mixing reactor can achieve the best effect.

[0009] Preferably, the first pipe heater comprises a pipe body and a plurality of heating elements, wherein the plurality of heating elements are sequentially attached to the pipe body along an extension direction of the pipe body, so that the pipe body is divided into a plurality of heated sections which are sequentially arranged along an extension direction thereof and correspond to the heating elements.

[0010] Preferably, the heating element is a heating resistance wire, which is connected to a power supply via a power cord, and a temperature control switch for controlling the on / off of the circuit is provided on the power cord. A temperature sensor is provided in the pipe A between the Venturi mixing reactor and the cyclone separator, and the temperature sensor is electrically connected to a signal input end of the controller, and a signal output end of the temperature sensor is electrically connected to the temperature control switch.

[0011] Preferably, the pipeline body is wrapped with a thermal insulation layer.

[0012] Preferably, two ends of the pipeline body are respectively provided with a connecting flange A and a connecting flange B for connecting to a flue gas collection pipe and a venturi mixing reactor.

[0013] Preferably, the structure of the second pipeline heater is the same as that of the first pipeline heater, and can also be connected to a temperature sensor and a controller to achieve automatic control of heating and temperature rise.

[0014] Preferably, the cyclone separator includes a cyclone separator body including a straight cylinder, an air inlet pipe is arranged on the side wall of the straight cylinder, an air outlet pipe connected to the induced draft fan is arranged on the upper end face of the straight cylinder, the induced draft fan is connected to the flue gas inlet of the bag collector through a second pipe, a conical barrel is arranged at the bottom of the straight cylinder, a star-shaped discharger for discharging impurities is arranged at the bottom of the conical barrel, and the discharge port of the star-shaped discharger is connected to a recovery bin for receiving the discharge of the star-shaped discharger.

[0015] Preferably, the induced draft fan is a variable frequency induced draft fan.

[0016] Preferably, the air delivery device comprises a Roots blower, the Roots blower is connected to the second pipe heater via a feed pipe, one end of the feed pipe close to the Roots blower is connected to a coke powder storage tank, and coke powder is stored in the coke powder storage tank.

[0017] Preferably, the bag dust collector includes a pulse bag dust collector, including a cylinder, wherein the cylinder has a dust bag mounting bracket built in, the dust bag mounting bracket divides the inner cavity of the cylinder into two parts, an upper part, and an air outlet pipe connected to the upper cavity is provided on the upper outer wall of the cylinder, an induced draft fan is connected to the air outlet pipe, and a dust collecting pipe connected to the lower cavity is provided on the bottom outer wall of the cylinder, and the dust collecting pipe is connected to the second pipe.

[0018] Preferably, the flue gas collection pipe includes a plurality of groups of third pipe heaters arranged at intervals, and adjacent third pipe heaters are connected by connecting pipes. They are all used to increase the temperature of the flue gas, keep the flue gas temperature above the dew point, increase the temperature so that the coke powder and the flue gas are fully mixed in the reactor and the pipe, and improve the purification efficiency. Prevent the asphalt flue gas from solidifying and adhering to the pipe wall.

[0019] Preferably, the regulating valve is an electrically controlled butterfly valve.

[0020] Compared with the prior art, the utility model has the following beneficial effects:

[0021] The black asphalt flue gas purification system described in the utility model is used to increase the temperature of the flue gas by adding a first pipeline heater and a second pipeline heater, so as to keep the flue gas temperature above the dew point. The temperature is increased so that the coke powder and the flue gas are fully mixed in the reactor and the pipeline, thereby improving the purification efficiency and preventing the asphalt flue gas from solidifying and adhering to the pipeline wall.

[0022] The black method asphalt flue gas purification system described in the utility model sends the collected flue gas into the Venturi mixing reactor through the first pipeline heater, and at the same time, the calcined coke powder in the coke powder storage tank is sent into the Venturi mixing reactor through the air delivery device, the asphalt flue gas is fully mixed with the coke powder in the Venturi mixing reactor, the Venturi mixing reactor provides the necessary mixing conditions, the flue gas is mixed with the coke powder sprayed out at a high speed from the throat of the Venturi reactor, which is sufficient to make the asphalt flue gas adsorbed by the fine coke powder, and the fine coke powder adsorbed with the asphalt flue gas becomes the carrier coke powder.

[0023] In the black asphalt flue gas purification system described in the utility model, the coke powder is firstly sent into the cyclone separator for purification along with the air flow, and then sent into the bag dust collector for purification. The coke powder collected by the cyclone separator and the bag dust collector is recovered and collected and sent into the batching bin again for standby use, and is used as batching for the production process. BRIEF DESCRIPTION OF THE DRAWINGS

[0024] In order to more clearly illustrate the specific embodiments of the present invention or the technical solutions in the prior art, the following is a brief introduction to the drawings required for the specific embodiments or the description of the prior art. In all the drawings, similar elements or parts are generally identified by similar reference numerals. In the drawings, the elements or parts are not necessarily drawn according to the actual scale.

[0025] Figure 1 It is a structural schematic diagram of the utility model;

[0026] Figure 2 This is a schematic diagram of the external structure of the cyclone separator of the utility model;

[0027] Figure 3 is a structural schematic diagram of a first pipeline heater;

[0028] Figure 4 It is a structural schematic diagram of a flue gas collection tube;

[0029] In the figure: 1, Venturi mixing reactor 2, cyclone separator 2.1, straight cylinder 2.2, air inlet pipe 2.3, air outlet pipe 2.4, conical barrel 2.5, star-shaped discharger 2.6, recovery bin 2.7, induced draft fan 3, bag filter 4, regulating valve 5, first pipeline heater 5.1, pipeline body 5.2, heating element 6, flue gas collection pipe 6.1, third pipeline heater 6.2, connecting pipeline 7, coke powder storage tank 8, air delivery device 9, second pipeline heater 10, temperature sensor 11, controller. DETAILED DESCRIPTION

[0030] The utility model is further described below in conjunction with the accompanying drawings:

[0031] The present invention is further described below through specific embodiments, but is not intended to limit the present invention. Any modifications, equivalent substitutions, improvements, etc. made within the spirit and principle of the present invention should be included in the protection scope of the present invention.

[0032] Embodiment 1, as Figure 1 As shown, the black asphalt flue gas purification system comprises a venturi mixing reactor 1, wherein the two ends of the venturi mixing reactor 1 are respectively arranged as a flue gas inlet and a flue gas outlet, and one side of the venturi mixing reactor 1 is provided with a feed port connected to its inner cavity, and further comprises a coke powder storage tank 7 and an air conveying device 8, wherein the flue gas inlet of the venturi mixing reactor 1 is connected to the flue gas collection pipe 6 through a first pipe heater 5, and the flue gas outlet of the venturi mixing reactor 1 is connected to the flue gas inlet of the cyclone separator 2 through a pipe A, and a regulating valve 4 is installed on the pipe A, and the flue gas outlet of the cyclone separator 2 is connected to the flue gas inlet of the bag filter 3 through a second pipe, and a second pipe heater 9 is installed on the feed port of the venturi mixing reactor 1, and the coke powder storage tank 7 is connected to the second pipe heater 9 through the air conveying device 8.

[0033] The collection ends of the flue gas collection pipe 6 extend to the positions of the asphalt storage tank, kneading pot, and vibration molding machine where large flue gas is generated. The collected flue gas is sent to the Venturi mixing reactor 1 through the first pipeline heater 5. At the same time, the calcined coke powder in the coke powder storage tank 7 is sent to the Venturi mixing reactor 1 through the air delivery device 8. The asphalt flue gas is fully mixed with the coke powder in the Venturi mixing reactor 1. The Venturi mixing reactor 1 provides the necessary mixing conditions. The flue gas is mixed with the coke powder ejected at high speed from the throat of the Venturi reactor, which is sufficient to make the asphalt flue gas adsorbed by the fine coke powder. The fine coke powder adsorbed with the asphalt flue gas becomes the carrier coke powder. The carrier coke powder first enters the cyclone separator 2 with the air flow for purification, and then enters the bag dust collector 3 for purification. The coke powder collected by the cyclone separator 2 and the bag dust collector 3 is recycled and collected and enters the batching bin again for standby use as a batching for the production process.

[0034] The first pipeline heater 5 and the second pipeline heater 9 are used to increase the temperature of the flue gas, keep the flue gas temperature above the dew point, increase the temperature so that the coke powder and the flue gas are fully mixed in the reactor and the pipeline, and improve the purification efficiency, and prevent the asphalt flue gas from solidifying and adhering to the pipeline wall.

[0035] Embodiment 2, as Figure 1As shown, the black asphalt flue gas purification system comprises a venturi mixing reactor 1, wherein the two ends of the venturi mixing reactor 1 are respectively arranged as a flue gas inlet and a flue gas outlet, and one side of the venturi mixing reactor 1 is provided with a feed port connected to its inner cavity, and further comprises a coke powder storage tank 7 and an air conveying device 8, wherein the flue gas inlet of the venturi mixing reactor 1 is connected to the flue gas collection pipe 6 through a first pipe heater 5, and the flue gas outlet of the venturi mixing reactor 1 is connected to the flue gas inlet of the cyclone separator 2 through a pipe A, and a regulating valve 4 is installed on the pipe A, and the flue gas outlet of the cyclone separator 2 is connected to the flue gas inlet of the bag filter 3 through a second pipe, and a second pipe heater 9 is installed on the feed port of the venturi mixing reactor 1, and the coke powder storage tank 7 is connected to the second pipe heater 9 through the air conveying device 8.

[0036] Furthermore, the first pipe heater 5 includes a pipe body 5.1 and a plurality of heating elements 5.2, wherein the plurality of heating elements 5.2 are sequentially attached to the pipe body 5.1 along the extension direction of the pipe body 5.1, so that the pipe body is divided into a plurality of heated sections which are sequentially arranged along the extension direction thereof and correspond to the heating elements.

[0037] Further, refer to Figure 3 The heating element 5.2 is a heating resistance wire, which is connected to a power supply through a power line. A temperature control switch for controlling the on-off of the circuit is arranged on the power line. A temperature sensor 10 is arranged in the pipeline A between the Venturi mixing reactor 1 and the cyclone separator 2. The temperature sensor 10 is electrically connected to the signal input end of the controller 11, and the signal output end of the temperature sensor 10 is electrically connected to the temperature control switch.

[0038] The controller 11 can be a single chip microcomputer or a PLC controller, and is used to receive the temperature signal collected by the temperature sensor 10. When the temperature is lower than the preset temperature, the heating element 5.2 is controlled to be turned on; when the temperature is higher than or equal to the preset temperature, the heating element 5.2 is controlled to be turned off.

[0039] The utility model relates to a method in which the modification of the prior art by the specific implementation method is in the hardware part, and the computer program involved is a simple program that can be easily realized by those skilled in the art using the existing computer program development platform and the well-known programming method.

[0040] Herein, the temperature sensor 10 and the controller 11 are merely a simple use of their functions, and do not involve improvements to the method procedures and the like.

[0041] Furthermore, two ends of the pipeline body 5.1 are respectively provided with a connecting flange A and a connecting flange B for connecting to the flue gas collection pipe 6 and the Venturi mixing reactor 1.

[0042] Furthermore, the structure of the second pipe heater 9 is the same as that of the first pipe heater 5 , and can also be connected to the temperature sensor 10 and the controller 11 to achieve automatic control of heating and temperature rise.

[0043] Further, refer to Figure 2 The cyclone separator 2 includes a cyclone separator body including a straight cylinder 2.1, an air inlet pipe 2.2 is arranged on the side wall of the straight cylinder 2.1, an air outlet pipe 2.3 connected to an induced draft fan 2.7 is arranged on the upper end surface of the straight cylinder 2.1, and the induced draft fan 2.7 is connected to the smoke inlet of the bag filter 3 through a second pipeline, a conical barrel 2.4 is arranged at the bottom of the straight cylinder 2.1, and a star-shaped discharger 2.5 for discharging impurities is arranged at the bottom of the conical barrel 2.4, and the discharge port of the star-shaped discharger 2.5 is connected to a recovery bin 2.6 for receiving the discharge of the star-shaped discharger 2.5.

[0044] Furthermore, the induced draft fan is a variable frequency induced draft fan.

[0045] Furthermore, the air delivery device 8 includes a Roots blower, which is connected to the second pipe heater 9 through a feed pipe. One end of the feed pipe close to the Roots blower is connected to a coke powder storage tank 7, and the coke powder storage tank 7 stores coke powder.

[0046] Furthermore, the bag dust collector 3 includes a pulse bag dust collector, including a cylinder, the cylinder having a dust bag mounting frame built in the cylinder, the dust bag mounting frame divides the inner cavity of the cylinder into two parts, an upper and lower part, an air outlet pipe connected to the upper cavity is provided on the upper outer wall of the cylinder, an induced draft fan is connected to the air outlet pipe, and a dust collecting pipe connected to the lower cavity is provided on the bottom outer wall of the cylinder, and the dust collecting pipe is connected to the second pipe.

[0047] Further, refer to Figure 4 The flue gas collection pipe 6 includes a plurality of groups of third pipe heaters 6.1 arranged at intervals, and adjacent third pipe heaters 6.1 are connected by connecting pipes 6.2. They are used to increase the temperature of the flue gas, keep the flue gas temperature above the dew point, increase the temperature so that the coke powder and the flue gas are fully mixed in the reactor and the pipe, and improve the purification efficiency. Prevent the asphalt flue gas from solidifying and adhering to the pipe wall.

[0048] Furthermore, the regulating valve 4 is an electrically controlled butterfly valve.

[0049] The black asphalt flue gas purification system described in the utility model is used to increase the temperature of the flue gas by adding a first pipeline heater and a second pipeline heater, so as to keep the flue gas temperature above the dew point. The temperature is increased so that the coke powder and the flue gas are fully mixed in the reactor and the pipeline, thereby improving the purification efficiency and preventing the asphalt flue gas from solidifying and adhering to the pipeline wall.

[0050] The black method asphalt flue gas purification system described in the utility model sends the collected flue gas into the Venturi mixing reactor through the first pipeline heater, and at the same time, the calcined coke powder in the coke powder storage tank is sent into the Venturi mixing reactor through the air delivery device, the asphalt flue gas is fully mixed with the coke powder in the Venturi mixing reactor, the Venturi mixing reactor provides the necessary mixing conditions, the flue gas is mixed with the coke powder sprayed out at a high speed from the throat of the Venturi reactor, which is sufficient to make the asphalt flue gas adsorbed by the fine coke powder, and the fine coke powder adsorbed with the asphalt flue gas becomes the carrier coke powder.

[0051] In the black asphalt flue gas purification system described in the utility model, the coke powder is firstly sent into the cyclone separator for purification along with the air flow, and then sent into the bag dust collector for purification. The coke powder collected by the cyclone separator and the bag dust collector is recovered and collected and sent into the batching bin again for standby use, and is used as batching for the production process.

[0052] The above shows and describes the basic principle, main features and advantages of the utility model. Those skilled in the art should understand that the utility model is not limited by the above embodiments. The above embodiments and descriptions are only for explaining the principles of the present invention. Without departing from the spirit and scope of the utility model, the utility model may have various changes and improvements, which fall within the scope of the utility model to be protected. The scope of protection claimed by the present utility model is defined by the attached claims and their equivalents.

[0053] The matters not described in detail in the present invention are all known technologies to those skilled in the art.

Claims

1. A black asphalt flue gas purification system, characterized in that: A black asphalt flue gas purification system comprises a venturi mixing reactor, wherein the two ends of the venturi mixing reactor are respectively arranged as a flue gas inlet and a flue gas outlet, and one side of the venturi mixing reactor is provided with a feed port connected to its inner cavity, and is characterized in that: it also comprises a coke powder storage tank and an air delivery device, the flue gas inlet of the venturi mixing reactor is connected to the flue gas collection pipe through a first pipe heater, the flue gas outlet of the venturi mixing reactor is connected to the flue gas inlet of a cyclone separator through a pipe A, a regulating valve is installed on the pipe A, the flue gas outlet of the cyclone separator is connected to the flue gas inlet of a bag filter through a second pipe, a second pipe heater is installed on the feed port of the venturi mixing reactor, and the coke powder storage tank is connected to the second pipe heater through the air delivery device.

2. The black asphalt flue gas purification system according to claim 1 is characterized in that: The first pipe heater includes a pipe body and a plurality of heating elements, wherein the plurality of heating elements are sequentially attached to the pipe body along an extension direction of the pipe body, so that the pipe body is divided into a plurality of heated sections which are sequentially arranged along an extension direction thereof and correspond to the heating elements.

3. The black asphalt flue gas purification system according to claim 2 is characterized in that: The heating element is a heating resistance wire, which is connected to a power supply through a power line. A temperature control switch for controlling the on and off of the circuit is provided on the power line. A temperature sensor is provided in the pipe A between the Venturi mixing reactor and the cyclone separator. The temperature sensor is electrically connected to a signal input end of a controller, and a signal output end of the temperature sensor is electrically connected to the temperature control switch.

4. The black asphalt flue gas purification system according to claim 3 is characterized in that: The two ends of the pipeline body are respectively provided with a connecting flange A and a connecting flange B for connecting with the flue gas collection pipe and the Venturi mixing reactor.

5. The black asphalt flue gas purification system according to claim 4 is characterized in that: The structure of the second pipe heater is the same as that of the first pipe heater.

6. The black asphalt flue gas purification system according to claim 5 is characterized in that: The cyclone separator includes a cyclone separator body including a straight cylinder, an air inlet pipe is arranged on the side wall of the straight cylinder, an air outlet pipe connected with the induced draft fan is arranged on the upper end face of the straight cylinder, the induced draft fan is connected with the smoke inlet of the bag filter through a second pipe, a conical barrel is arranged at the bottom of the straight cylinder, a star-shaped discharger for discharging impurities is arranged at the bottom of the conical barrel, and the discharge port of the star-shaped discharger is connected to a recovery bin for receiving the discharge of the star-shaped discharger.

7. The black asphalt flue gas purification system according to claim 1 is characterized in that: The air delivery device includes a Roots blower, which is connected to the second pipeline heater through a feed pipe. One end of the feed pipe close to the Roots blower is connected to a coke powder storage tank, and coke powder is stored in the coke powder storage tank.

8. The black asphalt flue gas purification system according to claim 1 is characterized in that: The bag dust collector includes a pulse bag dust collector, including a cylinder, a dust bag mounting bracket is built into the cylinder, the dust bag mounting bracket divides the inner cavity of the cylinder into an upper part and an lower part, an air outlet pipe connected to the upper cavity is provided on the upper outer wall of the cylinder, an induced draft fan is connected to the air outlet pipe, a dust collecting pipe connected to the lower cavity is provided on the bottom outer wall of the cylinder, and the dust collecting pipe is connected to the second pipeline.

9. The black asphalt flue gas purification system according to claim 1, characterized in that: The smoke collection pipe comprises a plurality of groups of third pipe heaters arranged at intervals, and adjacent third pipe heaters are connected via a connecting pipe.