Building waste crushing device for building construction
By using water spray cooling, brush plate cleaning and atomizing nozzle spray design in the construction waste crushing device, the problems of dust splashing and inconvenient transmission of fragments are solved, and a cleaner and more efficient crushing process is achieved.
Patent Information
- Application Number
- CN202420105847.5
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-01-16
- Publication Date
- 2024-10-22
- Estimated Expiration
- 2034-01-16
AI Technical Summary
Existing construction waste crushing devices used in construction can easily cause dust to fly around during operation, polluting the environment. The crushing rollers are prone to high temperatures and the crushed fragments cannot be actively transported, resulting in inconvenient processing.
A device including a crushing cavity roller, a brush plate, a water spray hole, a conveyor belt and an atomizing nozzle is designed. Through water spraying to cool down, the brush plate cleans the debris, the conveyor belt transports garbage, and the atomizing nozzle is used to spray dust. Realize dust removal and conveying.
It effectively solves the problems of dust splashing and fragment transmission, reduces the temperature of the crushing roller, and ensures that the crushed construction waste can be smoothly transported for the next step of processing.
Smart Images

Figure CN221868585U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of construction waste treatment, in particular to a construction waste crushing device for building construction. Background Art
[0002] Construction waste refers to the slag, abandoned soil, abandoned materials, silt and other waste generated during the construction, laying, demolition and repair of various buildings, structures, pipelines, etc. by construction units or individuals. It needs to be treated accordingly to meet the requirements of environmental protection construction.
[0003] After searching, a Chinese patent with the announcement number CN215506975U discloses a construction waste crushing device for construction, including a device body, a feed port fixedly installed on the upper outer surface of the device body, a crushing mechanism arranged inside the device body, support rods fixedly installed on the four corners of the lower outer surface of the device body, and a screen arranged at the bottom of the inner cavity of the device body. The patent drives the rotation of the rotating shaft through the operation of the rotating motor, and the rotating shaft drives the rotation of the rotating roller, and the construction waste is squeezed and crushed by the set driven roller and the rotating shaft, so as to facilitate crushing.
[0004] Based on the above search and the prior art, it is found that the existing construction waste crushing device is easy to cause dust to fly around when the crushing device is in operation, polluting the surrounding environment, and the crushing roller in the device is easy to heat up during the crushing process, which is inconvenient for people to use. After the crushing is completed, the fragments of the device cannot be actively transmitted out, and the fragments are easy to accumulate, which is not convenient for multiple construction waste crushing.
[0005] For this reason, we propose a construction waste crushing device for construction. Utility Model Content
[0006] In order to solve the above technical problems, the utility model proposes a construction waste crushing device for construction.
[0007] The technical solution to achieve the purpose of the utility model is: a construction waste crushing device for construction, including an equipment shell, a feeding end is fixedly installed on the top of the equipment shell, a discharging end is fixedly installed on the bottom of the equipment shell, and a conveying assembly is also included, and the conveying assembly is arranged below the discharging end; a dust removal assembly, the dust removal assembly includes a pair of crushing chamber rollers rotatably installed inside the equipment shell, and the two crushing chamber rollers are engaged with each other, one end of the two crushing chamber rollers are both movable through the equipment shell and fixedly connected with mutually engaged gears, a bracket one is fixedly installed on the outer wall of one side of the equipment shell, a stirring motor is fixedly installed on the bracket one, and the output shaft of the stirring motor is fixedly connected to one of the crushing chamber rollers, a group of support springs are fixedly installed on the inner walls of both sides of the equipment shell, and a brush plate is fixedly installed on each group of the support springs, the brush plate is C-shaped, and a plurality of bristles are fixedly installed on the brush plate, a plurality of water spray holes connected to the inside are opened on the crushing chamber roller, and one end of the two crushing chamber rollers is connected with a T-shaped water pipe, and the T-shaped water pipe is rotatably connected to the crushing chamber roller through a sealed bearing.
[0008] Preferably, the conveying assembly includes a pair of brackets two fixedly mounted on the outer walls on both sides of the equipment shell, the lower ends of the brackets two are fixedly connected to a conveyor belt shell, a conveyor belt is arranged inside the conveyor belt shell, a plurality of support columns are fixedly mounted on the lower surface of the conveyor belt shell, a pair of rotating shafts are rotatably mounted inside the conveyor belt shell, the conveyor belt is sleeved on two rotating shafts, a retarder motor is fixedly mounted on the outer wall of one side of the conveyor belt shell, and the output shaft of the retarder motor is fixedly connected to the adjacent rotating shaft.
[0009] Preferably, rubber anti-leakage belts are fixedly installed on both sides of the conveyor belt.
[0010] Preferably, a pair of water passage cavities are opened at the lower end of the discharge end, and two groups of atomizing nozzles are arranged at the lower end of the discharge end, each group of atomizing nozzles is fixedly connected to the water passage cavity, and the water passage cavity is fixedly connected to a water pipe.
[0011] Preferably, a water pump is fixed to an outer wall of one side of the equipment shell, the output end of the water pump is fixedly connected to the T-shaped water pipe and the water pipe, the input end of the water pump is fixedly connected to the water supply pipe, and the water supply pipe is connected to an external water supply system.
[0012] Preferably, a material guide plate is fixedly mounted on the inner wall of the feeding end.
[0013] Compared with the prior art, the present invention has the following significant advantages:
[0014] When the construction waste is put into the device for crushing, the water spray holes on the two crushing chamber rollers start to spray water, which can remove dust and cool down the two crushing chamber rollers at the same time. The brush plate and bristles are set to clean the debris on the two crushing chamber rollers when they rotate, and the support spring plays a vibrating role to make the cleaning more complete. The water-passing cavity and two groups of atomizing nozzles set at the discharge end spray the crushed construction waste when it falls into the conveyor belt, which solves the dust scattered by the vibration caused by the fragments falling on the conveyor belt, and further achieves the dust removal effect. The crushed construction waste is transported out through the conveyor belt for the next step of processing.
[0015] The existing problems of dust splashing and construction waste transmission are solved. BRIEF DESCRIPTION OF THE DRAWINGS
[0016] The utility model is further explained below in conjunction with the accompanying drawings and embodiments:
[0017] Figure 1 It is a schematic diagram of the first viewing angle structure provided by the utility model in one embodiment;
[0018] Figure 2 It is a schematic diagram of a second viewing angle structure provided in one embodiment of the utility model;
[0019] Figure 3 It is a schematic diagram of the structure of the discharge end provided in one embodiment of the utility model;
[0020] Figure 4 It is a schematic diagram of the structure of the feeding end provided in one embodiment of the utility model.
[0021] Figure 5 This is a schematic diagram of the cross-sectional structure of the grinding chamber roller provided in one embodiment of the utility model.
[0022] Description of reference numerals:
[0023] 1. Equipment housing; 2. Gear; 3. Feeding end; 4. Stirring motor; 5. Bracket 1; 6. Discharging end; 61. Water passage chamber; 7. Rotating shaft; 8. Conveyor belt; 9. Support column; 10. Conveyor belt housing; 11. Rubber anti-leakage belt; 12. Bracket 2; 13. Water pump; 14. T-shaped water pipe; 141. Water pipe; 142. Water supply pipe; 15. Support spring; 16. Water spray hole; 17. Atomizing nozzle; 18. Crushing chamber roller; 19. Brush; 20. Brush plate; 21. Guide plate; 22. Slow-speed motor. DETAILED DESCRIPTION
[0024] The utility model is described in detail below, and the technical solutions in the embodiments of the utility model are clearly and completely described. Obviously, the described embodiments are only part of the embodiments of the utility model, not all of the embodiments. Based on the embodiments of the utility model, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the utility model.
[0025] The utility model provides a construction waste crushing device for construction through improvement. The technical solution of the utility model is:
[0026] like Figure 1-Figure 5 As shown, a construction waste crushing device for construction includes an equipment shell 1, a feeding end 3 is fixedly installed at the top of the equipment shell 1, a discharging end 6 is fixedly installed at the bottom of the equipment shell 1, and also includes a conveying component, which is arranged below the discharging end 6;
[0027] The dust removal assembly includes a pair of grinding chamber rollers 18 rotatably mounted inside the equipment shell 1, and the two grinding chamber rollers 18 are meshed with each other, one end of the two grinding chamber rollers 18 are movable through the equipment shell 1 and fixedly connected with gears 2 that mesh with each other, a bracket 5 is fixedly mounted on the outer wall of one side of the equipment shell 1, a stirring motor 4 is fixedly mounted on the bracket 5, and the output shaft of the stirring motor 4 is fixedly connected to one of the grinding chamber rollers 18, a group of supporting springs 15 are fixedly mounted on the inner walls of both sides of the equipment shell 1, and a brush plate 20 is fixedly mounted on each group of supporting springs 15, the brush plate 20 is C-shaped, and a plurality of bristles 19 are fixedly mounted on the brush plate 20, a plurality of water spray holes 16 connected with the interior are opened on the grinding chamber roller 18, one end of the two grinding chamber rollers 18 are connected with a T-shaped water pipe 14, and the T-shaped water pipe 14 is rotatably connected to the grinding chamber roller 18 through a sealed bearing.
[0028] In summary, after starting the stirring motor 4, construction waste is put in. When the construction waste is put into the device for crushing, the water spray holes 16 on the two crushing chamber rollers 18 start to spray water, which can remove dust and cool down the two crushing chamber rollers 18 at the same time. Through the provided brush plates 20 and bristles 19, the debris on the two crushing chamber rollers 18 are cleaned when the two crushing chamber rollers 18 rotate, the support spring 15 plays a vibrating role to make the cleaning more complete, and the T-shaped water pipe 14 supplies water to the crushing chamber rollers 18.
[0029] Furthermore, the conveying assembly includes a pair of brackets 12 fixedly mounted on the outer walls of both sides of the equipment shell 1, the lower end of the bracket 12 is fixedly connected to the conveyor belt shell 10, a conveyor belt 8 is arranged inside the conveyor belt shell 10, a plurality of support columns 9 are fixedly mounted on the lower surface of the conveyor belt shell 10, a pair of rotating shafts 7 are rotatably mounted inside the conveyor belt shell 10, the conveyor belt 8 is sleeved on the two rotating shafts 7, a retarder motor 22 is fixedly mounted on the outer wall of one side of the conveyor belt shell 10, and the output shaft of the retarder motor 22 is fixedly connected to the adjacent rotating shaft 7.
[0030] With the above structure, a pair of brackets 12 fix the equipment housing 1 above the conveyor belt 8. When the retarder motor 22 is started, the conveyor belt 8 rotates. When the construction debris falls onto the conveyor belt 8, the construction debris is conveyed out for the next step of processing.
[0031] Furthermore, rubber anti-leakage belts 11 are fixedly installed on both sides of the conveyor belt 8 .
[0032] With the above structure, the rubber anti-leakage belt 11 can prevent the construction debris from falling out of the conveyor belt 8.
[0033] Furthermore, a pair of water passage cavities 61 are opened at the lower end of the discharge end 6 , and two groups of atomizing nozzles 17 are arranged at the lower end of the discharge end 6 , each group of atomizing nozzles 17 is fixedly connected to the water passage cavity 61 , and the water passage cavity 61 is fixedly connected to a water pipe 141 .
[0034] By means of the above structure, a pair of water passage chambers 61 are opened at the lower end of the discharge end 6 to supply water to the atomizing nozzle 17. The atomizing nozzle 17 sprays the crushed construction waste when it falls into the conveyor belt 8, thereby solving the dust released by the vibration generated when the fragments fall into the conveyor belt 8, and further achieving the dust removal effect.
[0035] Furthermore, a water pump 13 is fixed to an outer wall of one side of the equipment shell 1, and the output end of the water pump 13 is fixedly connected to the T-shaped water pipe 14 and the water pipe 141, and the input end of the water pump 13 is fixedly connected to the water supply pipe 142, and the water supply pipe 142 is connected to an external water supply system.
[0036] With the above structure, the water introduced into the water supply pipe 142 can be pressurized by the water pump 13, so that the water can be sprayed out through the T-shaped water pipe 14 and the water spray holes 16 and the atomizing nozzle 17 in the water pipe 141 to achieve a spraying operation.
[0037] Furthermore, a material guide plate 21 is fixedly mounted on the inner wall of the feeding end 3 .
[0038] With the above structure, the guide plate 21 is arranged to allow the construction waste to fall accurately into between the two crushing chamber rollers 18 .
[0039] The specific working method is: after starting the stirring motor 4, the construction waste is put in, and the guide plate 21 is set to make the construction waste fall accurately between the two crushing chamber rollers 18. When the construction waste is put into the device for crushing, the water spray holes 16 on the two crushing chamber rollers 18 start to spray water, which can remove dust and cool down the two crushing chamber rollers 18 at the same time. Through the brush plate 20 and the bristles 19, the debris on the two crushing chamber rollers 18 is cleaned when the two crushing chamber rollers 18 rotate, and the support spring 15 plays a vibrating role to make the cleaning more complete. After the crushing is completed, the construction waste falls into the conveyor belt 8, and the atomizing nozzle 17 sprays the crushed construction waste when it falls into the conveyor belt 8, which solves the dust scattered by the vibration caused by the fragments falling on the conveyor belt 8, and further achieves the dust removal effect. When the construction debris falls on the conveyor belt 8, the construction debris is conveyed out for the next step of processing.
[0040] The technical means disclosed in the utility model are not limited to the technical means disclosed in the above technical means, but also include technical solutions composed of equivalent replacement of the above technical features. Matters not covered in the utility model belong to the common knowledge of those skilled in the art.
Claims
1. A construction waste crushing device for construction, comprising an equipment housing (1), a feeding end (3) being fixedly mounted on the top end of the equipment housing (1), and a discharging end (6) being fixedly mounted on the bottom end of the equipment housing (1), characterized in that: It also includes a conveying assembly, which is arranged below the discharge end (6); A dust removal component, the dust removal component comprising a pair of crushing chamber rollers (18) rotatably mounted inside an equipment shell (1), the two crushing chamber rollers (18) meshing with each other, one end of the two crushing chamber rollers (18) movably passing through the equipment shell (1) and fixedly connected to mutually meshing gears (2), a bracket (5) fixedly mounted on one side outer wall of the equipment shell (1), a stirring motor (4) fixedly mounted on the bracket (5), an output shaft of the stirring motor (4) fixedly connected to one of the crushing chamber rollers (18), the equipment shell A group of support springs (15) are fixedly mounted on the inner walls of both sides of the body (1), and a brush plate (20) is fixedly mounted on each group of the support springs (15). The brush plate (20) is in a C-shaped structure, and a plurality of bristles (19) are fixedly mounted on the brush plate (20). A plurality of water spray holes (16) connected to the interior are opened on the grinding chamber roller (18), and one end of the two grinding chamber rollers (18) are connected to a T-shaped water pipe (14), and the T-shaped water pipe (14) is rotatably connected to the grinding chamber roller (18) through a sealed bearing.
2. The construction waste crushing device for construction according to claim 1, characterized in that: The conveying assembly comprises a pair of brackets (12) fixedly mounted on the outer walls of both sides of the equipment shell (1); the lower end of the brackets (12) is fixedly connected to a conveyor belt shell (10); a conveyor belt (8) is arranged inside the conveyor belt shell (10); a plurality of support columns (9) are fixedly mounted on the lower surface of the conveyor belt shell (10); a pair of rotating shafts (7) are rotatably mounted inside the conveyor belt shell (10); the conveyor belt (8) is sleeved on two rotating shafts (7); a retarding motor (22) is fixedly mounted on the outer wall of one side of the conveyor belt shell (10); and the output shaft of the retarding motor (22) is fixedly connected to the adjacent rotating shaft (7).
3. A construction waste crushing device for construction according to claim 2, characterized in that: Rubber anti-leakage belts (11) are fixedly installed on both sides of the conveyor belt (8).
4. The construction waste crushing device for construction according to claim 1, characterized in that: A pair of water passage cavities (61) are provided at the lower end of the discharge end (6), and two groups of atomizing nozzles (17) are provided at the lower end of the discharge end (6), each group of atomizing nozzles (17) is fixedly connected to the water passage cavity (61), and the water passage cavity (61) is fixedly connected to a water pipe (141).
5. The construction waste crushing device for construction according to claim 1, characterized in that: A water pump (13) is fixed to an outer wall of one side of the equipment housing (1); the output end of the water pump (13) is fixedly connected to a T-shaped water pipe (14) and a water pipe (141); the input end of the water pump (13) is fixedly connected to a water supply pipe (142); and the water supply pipe (142) is connected to an external water supply system.
6. The construction waste crushing device for construction according to claim 1, characterized in that: A material guide plate (21) is fixedly mounted on the inner wall of the feeding end (3).