Large bent cap supporting structure based on small-diameter cross-core steel bar
By using small-diameter steel rods in the steel rod method and combining the design of the upper and lower wing plates, a negative bending moment is formed to offset the positive bending moment, which solves the problem of insufficient bending resistance in the steel rod method. problem, the spacing between the through-core steel rods and the pier steel bars is matched, which improves construction safety and structural stability.
Patent Information
- Application Number
- CN202420304301.2
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-02-19
- Publication Date
- 2024-10-22
- Estimated Expiration
- 2034-02-19
AI Technical Summary
The existing through-hole steel rod method does not consider the bending resistance in the construction of bridge cap beams, resulting in the design diameter of the steel rod being too small and insufficient strength, which poses safety risks. Moreover, after considering the bending resistance, the diameter of the through-hole steel rod is different from the pier body. The spacing of steel bars does not match, causing construction difficulties.
A small-diameter through-core steel rod is used in combination with the upper and lower wing plates. The upper wing plate is pulled and the lower wing plate is in contact with the pier to form a negative bending moment, which offsets the positive bending force formed by the upper load force of the steel rod. moment, reducing the bending resistance requirements of the steel rods, and adjusting the contact stress through the pretensioning component to ensure that the contact stress between the structural parts and the pier body is within a reasonable range.
It effectively reduces the design diameter of the core steel rod, solves the problem of excess shear resistance and insufficient bending resistance, avoids the problem of mismatch between the core steel rod and the pier steel bar, and improves construction safety and structural stability. .
Smart Images

Figure CN221877775U_ABST
Abstract
Description
Technical Field
[0001] The utility model belongs to the technical field of building engineering, and in particular relates to a large cap beam supporting structure based on a small-diameter through-core steel rod. Background Art
[0002] Bridge construction is common in urban road and highway construction. Common structural forms of bridge substructures include cylindrical piers, rectangular piers, thin-walled piers, vase piers, etc. Except for vase piers, other types of piers often support the superstructure of the bridge and its bridge load through a cantilevered cap beam that is much larger than the pier itself in horizontal dimensions. Therefore, the cap beam is very important in bridge construction.
[0003] In the prior art, common construction techniques for cap beams include: the support method, the clamp method, and the through-steel rod method. Among them, the construction process of the support method has the following disadvantages: (1) The installation and disassembly of the support is labor-intensive, and pre-stressing measures need to be taken during construction to eliminate non-elastic deformation, which requires a lot of manpower, material resources, and construction time. (2) The support method has a long construction period and needs to occupy the construction site for a long time, affecting other construction work. (3) The support method has high requirements on the bearing capacity of the foundation and requires strict treatment of the foundation, otherwise it is easy to cause the support to sink or deform. (4) When constructing in deep water or rivers, the installation and fixation of the support is difficult. (5) For high piers, the support method has a large amount of work and is not suitable from a cost perspective. (6) The support method takes a long time to set up and has a large workload. It requires high skills and experience of the construction personnel, otherwise it is easy to have quality and safety risks. (7) A large number of workers are required to work during the erection of the support, and the protection requirements are high, which poses a great safety hazard. (8) The support structure system is huge, and measures need to be taken to prevent support resonance during construction to avoid additional dynamic loads caused by natural weather factors such as wind, rain, and snow that pose a threat to the safety of construction workers.
[0004] In view of the above problems, the two bracket-free processes, the clamp method and the through-steel rod method, have become the mainstream cap beam construction processes. However, the construction process of the clamp method also has many disadvantages, mainly including: (1) The clamp method is only applicable to the construction of cylindrical pier cap beams, not to the construction of rectangular piers and thin-walled piers, so its scope of application is relatively small. (2) The processing and installation precision of the clamp is high, and it needs to be processed and manufactured by professional manufacturers. It is advisable to match and customize the cylindrical pier formwork. Otherwise, the clamp is prone to loosening or deformation, affecting the stability of the entire cap beam formwork and support, and posing a major safety hazard. (3) The installation and disassembly of the clamp is labor-intensive, requiring a large amount of manpower and equipment, and consuming a lot of time and equipment resources. (4) Each clamp is customized for a cylindrical pier with a fixed diameter. Therefore, for projects with a variety of column diameters, a large number of clamps with different column diameters need to be customized for turnover. For cap beams with large loads, "double clamps and triple clamps" are often used for support, so the amount of steel used is very high, which increases the construction cost. (5) When the clamp method is subjected to a large load, the clamp is prone to deformation or damage. In severe cases, it may even cause the clamp to be "injured" and crush the concrete surface of the cylindrical pier, causing damage to the appearance of the pier. (6) The working principle of the clamp method is to use the friction between the clamp and the cylindrical pier to support the upper cap beam concrete, formwork and support load. The support principle is not reliable. Since the dynamic friction is smaller than the static friction, once the upper load exceeds the static friction of the clamp due to calculation negligence or work error, "sudden" support collapse events are likely to occur. It is difficult to warn and the safety reserve is insufficient. (7) The construction process of the clamp method is relatively complex and the operation is relatively difficult. Experienced construction personnel are required to ensure the reliability of the construction. The clamp method requires the use of large-scale mechanical equipment for installation and fixing, and has high requirements for the site. When constructing in deep water or rivers, the installation and fixing of the clamp is difficult, and special construction measures need to be taken for hoisting and fixing.
[0005] In summary, although the hoop method has advantages over the bracket method, such as less steel consumption, less installation and disassembly work, shorter construction period, less requirements on the bearing capacity of the site foundation, and a simple system, its application range is small and it is only applicable to cylindrical piers. In addition, the customized processing and installation are complicated and have great limitations.
[0006] The through-steel rod method is the same as the hoop method. It does not require the erection of a support. It is particularly convenient for construction in mountainous areas or sites without suitable supports. It also has the following advantages: (1) The through-steel rod method is not only applicable to cylindrical pier cap beams, but also to rectangular piers and thin-walled piers, and has a wide range of applications. (2) The processing and installation of the through-steel rod are simple, the operation is simple, and the reliability is high. (3) The size of the steel rod is only related to the upper load. The same specification of steel rods can be used for different column diameters or pier sizes. It is insensitive to changes in pier size, has strong versatility, and requires little steel. (4) The through-steel rod is fixed by installing it in a PVC sleeve pre-buried in the pier to support the upper cap beam concrete, formwork and support load, and the support is relatively safe and reliable. (5) The through-steel rod method has fewer components, is easy to install, and has lower requirements for machinery and equipment and sites. Therefore, the through-steel rod method has a wide range of applications, strong versatility, a simple system, and low cost. It is a cap beam support-free construction process with good adaptability.
[0007] Although the through-steel rod method has strong adaptability, the current process design and construction of the through-steel rod method do not take into account the bending resistance of the through-steel rod, which may lead to quality and safety risks. Specifically, in the construction process design of the through-steel rod method, it is usually believed that the cantilevered part of the through-steel rod bears the upper load transmitted by the jack, and the part of the steel rod that passes through the pier body transmits the upper load to the pier body. The steel rod itself only bears shear stress, so only the shear resistance of the steel rod is verified. In fact, the shear resistance of the steel rod usually far exceeds the requirements of the upper load. Fig.14 As shown in the figure, due to the structural reasons of the jack, unloading device, etc., there will be an offset e between the center line of the force F1 of the upper load on the steel bar and the edge of the outer contour of the pier. The existence of this offset will cause the force of the jack on the steel bar to form a downward positive bending moment M1 on the steel bar.
[0008] M1=F1·e
[0009] According to experience, according to the conventional jack size, the tensile stress formed by this bending moment at the top of the steel bar section is very large, which is the decisive factor in determining the diameter and strength of the steel bar. In addition, this bending moment is very sensitive to the change of the offset e. As the offset e increases, the positive bending moment M1 increases sharply.
[0010] Therefore, since the conventional through-steel rod method process design only considers the shear resistance of the steel rod and omits the bending performance verification, the design diameter of the steel rod is too small and the design strength is too small, so that the design parameters of the steel rod are actually not matched with the upper load. In this way, the through-steel rod is prone to bending instability and crushing of the reserved holes during use, which may lead to the collapse of the cap beam formwork system in severe cases.
[0011] In this regard, the applicant supplemented the bending performance verification of the through-steel rods and found that the obtained design parameters of the through-steel rods were too high and the diameter of the steel rods was too large. For large cap beams, the upper load is large, the corresponding pier column bearing capacity requirements are also higher, and the pier body reinforcement is denser. Considering the bending performance verification, the diameter of the steel rod is often larger than the spacing of the pier body steel bars, which leads to the following difficulties in the construction process: First, in actual construction, workers need to cut off the steel bars near the embedded holes, but this will cause quality and safety hazards. Second, by pre-embedding double rows of reserved holes, double rows of small-diameter through-steel rods are used to replace large-diameter through-steel rods for support, but this will not only make it more difficult to seal the reserved holes after construction is completed, but once a disturbance occurs during the pouring process, the relative elevations of the two rows of reserved holes will change, which will easily lead to uneven load distribution, the actual working conditions deviate from the calculated working conditions, and the force system will be out of control. From the above, it can be seen that by supplementing the bending performance verification of the through-steel rods, the calculated diameter of the steel rods will increase, resulting in a mismatch between the calculated diameter of the through-steel rods and the spacing of the pier body steel bars.
[0012] Based on the above, in order to overcome the problem that the calculated diameter of the through-steel rod does not match the spacing of the pier body steel bars after considering the bending performance, the applicant proposed another idea, that is, to reduce the calculated diameter of the through-steel rod so that it is smaller than the spacing of the pier body steel bars, but to improve the strength performance of the through-steel rod itself, that is, the through-steel rod is made of a higher strength material or process to compensate for the strength of the through-steel rod so that it meets the bending performance requirements. However, the reduction in the diameter of the steel rod will cause the moment of inertia of the bending section of the steel rod to decrease in a fourth power ratio, which will greatly increase the bending tensile stress on the upper surface of the steel rod, resulting in a significant increase in the design strength of the steel rod, and the strength performance of the existing models of through-steel rods is difficult to meet the requirements. For example, under the conditions of the same upper load force F1 and offset e, after the size of the through-steel rod is reduced from 120mm to 90mm, the original tensile stress of 200MPa will rise sharply to 632MPa. This makes the commonly used Q235 or Q345 steel rods completely unable to meet the design requirements, and low-alloy high-strength steel rods such as 40Cr need to be used. However, in actual applications, low-alloy high-strength steel bars such as 40Cr are delivered in a hot-rolled state and need to be heat-treated to reach the standard yield strength. For small-diameter steel bars of 90mm, heat treatment can no longer penetrate the entire steel bar, and the average yield strength of the steel bar after heat treatment is difficult to test, making the strength of the through-hole steel bars actually used unable to evenly meet the requirements of the calculated working conditions.
[0013] In summary, in the existing through-steel rod method design and construction, since only the shear resistance of the through-steel rod is calculated without considering the bending resistance of the steel rod, the design parameters of the steel rod do not actually match the upper load, which poses a great safety hazard. However, since the spacing of the pier body steel bars limits the diameter of the steel rod, and the strength performance of the existing steel rods is limited, it is difficult to consider the bending resistance of the steel rod in actual construction. Utility Model Content
[0014] In view of the above problems, the utility model provides a large cap beam supporting structure based on small diameter through steel rods, which solves the problem of conflict between the pier body reinforcement spacing, the through steel rod diameter and the steel rod bending performance when the shear resistance and bending resistance calculations of the through steel rods are considered simultaneously.
[0015] The utility model is achieved through the following technical solutions.
[0016] A large cap beam support structure based on a small diameter through-core steel rod comprises a pier, a jack, a fixed sleeve pre-buried in the pier, a through-core steel rod inserted in the fixed sleeve and having two ends exposed from the pier to form a support end, and a support beam arranged above the through-core steel rod, characterized in that it also comprises:
[0017] A lower wing assembly, the lower wing assembly comprising a movable sleeve and a lower wing plate sleeved on the supporting end of the through-core steel rod, a sleeve limit pin used to fix the movable sleeve to prevent the movable sleeve from rotating relative to the through-core steel rod or sliding out of the through-core steel rod, a column-holding assembly used to wrap and tighten the lower wing plate and fix it on both sides of the pier column, and a support platform arranged on the movable sleeve to carry the jack; one side of the lower wing plate is connected to the movable sleeve, and the other side abuts against the outer wall of the pier column to generate contact stress and transmit it to the through-core steel rod through the fixed sleeve to form a negative bending moment, thereby partially offsetting the positive bending moment formed by the upper load force of the through-core steel rod;
[0018] An upper wing assembly, the upper wing assembly comprising an upper wing plate arranged above the lower wing plate, the upper wing plate being directly or indirectly tension-fixed on both sides of the pier column to generate a tension force and transmit it to the through-core steel rod through the pre-tensioning assembly to form a negative bending moment, thereby partially offsetting the positive bending moment formed by the upper load force of the through-core steel rod;
[0019] A pre-tensioning assembly, wherein the pre-tensioning assembly is symmetrically arranged on both sides of the through-core steel rod and connected between the upper wing plate and the lower wing plate, so as to apply a pre-tensioning force between the upper wing plate and the lower wing plate; and
[0020] A contact pad is filled between the contact surfaces of the upper wing plate, the lower wing plate, the column assembly and the outer wall of the pier.
[0021] Preferably, the lower wing assembly further comprises a horizontal bubble tube arranged on the supporting platform.
[0022] Preferably, the column embracing assembly includes a pier embracing plate and a pier tightening belt, one end of the pier embracing plate is hinged to one side of the lower wing plate, and the other end is overlapped on the outer wall of the pier; the pier tightening belt is connected between the pier embracing plates on both sides of the pier, and is used to embrace, tighten and fix the lower wing plate to both sides of the pier through the cooperation of the pier tightening belt and the pier embracing plate.
[0023] Preferably, the upper wing assembly further comprises a plurality of upper wing plate stiffening ribs arranged at both ends of the back side of the upper wing plate, and the plurality of upper wing plate stiffening ribs cooperate with the upper wing plate to form a groove for clamping the contact pad.
[0024] Preferably, the lower wing assembly further comprises: a plurality of sleeve stiffening ribs connected between the movable sleeve and the lower wing plate and uniformly arranged along the circumferential direction.
[0025] Preferably, the pre-tensioning assembly includes an upper connecting rib connected to the upper wing plate, a lower connecting rib connected to the lower wing plate, and a steel bar-sleeve connecting mechanism connected between the upper connecting rib and the lower connecting rib; the steel bar-sleeve connecting mechanism includes a threaded sleeve and a threaded steel bar threadedly connected to the threaded sleeve.
[0026] Preferably, the upper wing plate is directly fixed to both sides of the pier below the support beam by tensioning screws; alternatively, the upper wing plate is installed on the belly of the support beam, and the support beam is tightened and fixed to the pier by tensioning screws, so that the upper wing plate is indirectly fixed to both sides of the pier by tensioning screws.
[0027] Preferably, when the upper wing plate is indirectly fixed to both sides of the pier by tension, the upper wing plate is installed at the belly position below the center line of the support beam, and the support beam is tightened and fixed to the pier by tensioning screws at a position above its center line.
[0028] Compared with the prior art, the beneficial effects of the utility model are:
[0029] 1) The utility model takes into account the shearing capacity and bending performance of the through-steel rod at the same time, and innovatively generates negative bending moment by pulling the upper wing plate against the lower wing plate and abutting the pier column to form horizontal forces of "upward pulling and downward pressing" to offset the positive bending moment formed by the upper load force of the steel rod, thereby greatly reducing the bending performance required by the through-steel rod itself, thereby achieving the purpose of reducing the design diameter of the through-steel rod. It not only solves the defect that the conventional small-diameter through-steel rod has excess shearing performance and insufficient bending performance, but also cleverly resolves the conflict between the pier body reinforcement spacing, the through-steel rod diameter and the bending performance of the steel rod when the through-steel rod method is used in the construction of large cap beams, while considering the shearing capacity and bending performance of the through-steel rod.
[0030] 2) In the utility model, the contact stress between the upper wing plate, the lower wing plate and the pier body can be flexibly adjusted by setting a pre-tensioning component, so as to ensure that the contact stress between the structural member and the pier body is maintained within a reasonable allowable range at various stages during the construction process such as tensioning the tensioning screw and design working conditions; the lower wing plate, the upper wing plate and the contact pad can increase the contact area between the structural member and the pier body, reduce the contact stress, and avoid the problem of scratches or crushing the surface caused by the traditional corbel structure directly supporting the pier body surface; the column holding component adopts a "three-petal and two-hinged" structure, and through the cooperation of the pier column embracing plate and the pier column tightening belt, it can adapt to the contact buffering requirements of different column diameters, avoiding the problem of customizing column holding components of different sizes for different column diameters.
[0031] 3) In the present invention, different structures can be selected to install the upper wing plate according to the installation height of the upper wing plate to reduce the tension force required for the upper wing plate, thereby reducing the difficulty of the tension construction of the upper wing plate and the parameter requirements for the upper wing plate, tension screws and other structural parts. BRIEF DESCRIPTION OF THE DRAWINGS
[0032] Figure 1 This is a schematic diagram of the main structure of the support structure of the utility model;
[0033] Figure 2 It is a left-side structural schematic diagram of the support structure of the utility model;
[0034] Figure 3 for Figure 1 Schematic diagram of the cross section at AA;
[0035] Figure 4 It is a schematic diagram of the top view of the structure of the lower wing assembly of the utility model;
[0036] Figure 5 This is a schematic diagram of the main structure of the lower wing assembly of the utility model;
[0037] Figure 6 It is a left-side structural schematic diagram of the lower wing assembly of the utility model;
[0038] Figure 7 This is a schematic diagram of the main structure of the upper wing assembly of the utility model;
[0039] Figure 8 It is a left-side structural schematic diagram of the upper wing assembly of the utility model;
[0040] Fig. 9 It is a schematic diagram of the top view of the structure of the upper wing assembly in the utility model;
[0041] Fig.10 It is a structural schematic diagram of the utility model when the lower wing assembly is installed on a small diameter pier;
[0042] Fig.11It is a structural schematic diagram of the utility model when the lower wing assembly is installed on a large diameter pier;
[0043] Fig.12 This is a schematic diagram of the main structure of a preferred embodiment of the support structure of the utility model;
[0044] Fig.13 It is a left-side structural schematic diagram of a preferred embodiment of the support structure of the utility model;
[0045] Fig.14 It is a schematic diagram of the force of the steel bar in the prior art when the bending resistance is not considered;
[0046] Fig.15 It is a force diagram of the steel rod in the supporting structure of the utility model;
[0047] Fig.16 It is a schematic diagram of the force on the support beam when the upper wing plate is installed on the belly of the support beam;
[0048] The meanings of the symbols in the above figure are:
[0049] Lower wing plate 1, column embracing assembly 2, pier column embracing plate 201, pier column tightening belt 202, contact pad 203, movable sleeve 3, upper wing plate 4, pre-tensioning assembly 5, upper connecting rib 501, lower connecting rib 502, threaded sleeve 503, threaded steel bar 504, sleeve stiffening rib 6, upper wing plate stiffening rib 7, horizontal bubble tube 8, support platform 9, pier column 10, fixed sleeve 11, through-steel rod 12, support beam 13, jack 14, tension screw 15, sleeve limit pin 16. DETAILED DESCRIPTION
[0050] In order to facilitate the understanding of the present invention, the present invention will be described in more detail below with reference to the relevant drawings. Several embodiments of the present invention are given in the drawings, but the present invention can be implemented in different forms and is not limited to the embodiments described in the text. On the contrary, these embodiments are provided to make the content disclosed in the present invention more thorough and comprehensive.
[0051] Unless otherwise defined, all technical and scientific terms used herein have the same meaning as commonly understood by technicians in the technical field of the present invention. The terms used in the specification of the present invention are only for the purpose of describing specific embodiments and are not intended to limit the present invention. The term "and / or" used herein includes any and all combinations of one or more related listed items.
[0052] The utility model is further described in detail below in conjunction with the accompanying drawings.
[0053] Example 1
[0054] A large cap beam support structure based on small diameter through-steel rods, see Figures 1 to 12 , which includes a pier 10, a jack 14, a fixing sleeve 11 embedded in the pier, a through-core steel rod 12 inserted into the fixing sleeve 11 and with both ends exposed from the pier to form a supporting end, a supporting beam 13 arranged above the through-core steel rod 12, a lower wing assembly, an upper wing assembly, a pre-tensioning assembly 5, and a contact pad 203; wherein:
[0055] The fixed sleeve 11 is a PVC pipe, which is pre-buried in the pier when the pier is cast;
[0056] The lower wing assembly comprises a movable sleeve 3 and a lower wing plate 1 sleeved on the supporting end of the through-core steel rod, a sleeve limit pin 16 for fixing the movable sleeve 3 to prevent the movable sleeve 3 from rotating relative to the through-core steel rod 12 or sliding out of the through-core steel rod 12, a column holding assembly 2 for tightening and fixing the lower wing plate 1 around the pier column, and a support platform 9 for carrying a jack 14 arranged on the movable sleeve 3; one side of the lower wing plate 1 is connected to the movable sleeve 3, and the other side abuts against the outer wall of the pier column to generate contact stress and transmit it to the through-core steel rod 12 through the fixed sleeve 11 to form a negative bending moment, thereby partially offsetting the positive bending moment formed by the upper load force of the through-core steel rod;
[0057] The upper wing assembly includes an upper wing plate 4 arranged above the lower wing plate 1, and the upper wing plate 4 is directly or indirectly fixed to both sides of the pier 10 in tension, so as to generate a tension force and transmit it to the through-core steel rod 12 through the pre-tensioning assembly 5 to form a negative bending moment, thereby partially offsetting the positive bending moment formed by the upper load force of the through-core steel rod;
[0058] The pre-tensioning assembly 5 is symmetrically arranged on both sides of the through-core steel rod 12 and connected between the upper wing plate 4 and the lower wing plate 1, so as to apply a pre-tensioning force between the upper wing plate 4 and the lower wing plate 1;
[0059] The contact pad 203 is filled between the contact surfaces of the upper wing plate 4, the lower wing plate 1, the column assembly 2 and the outer wall of the pier column, so as to avoid direct contact between the components and the surface of the pier body, which may cause scratches or crushing on the surface of the pier body; the contact pad 203 is made of rubber, and the rubber material should not be too hard, and the maximum elastic stress of the contact pad 203 should be ensured to be at an appropriate level;
[0060] Based on the above structure, Fig.15 As shown in the figure, when the size and specification parameters of the jack and the unloading device are determined, the force F1 and the offset e of the upper load on the through-steel rod are known, and the positive bending moment M1 formed by the upper load force can be calculated by the following formula:
[0061] M1=F1×e
[0062] Since the upper wing plate 4 is fixed to the pier column by tension, and the upper wing plate 4 is connected to the lower wing plate 1 through the pre-tensioning assembly 5, and the lower wing plate 1 is connected to the through-core steel rod 12 under the fixation of the movable sleeve 3, the upper wing plate can generate a tension force and transmit it to the through-core steel rod through the pre-tensioning assembly 5 to form a negative bending moment M 21 , thereby partially offsetting the positive bending moment M1 formed by the upper load force of the through-steel rod; while the negative bending moment M 21 The following formula can be used for calculation:
[0063] M 21 =F2×h
[0064] At the same time, one side of the lower wing plate 1 abuts against the outer wall of the pier to form the contact stress of the lower wing plate, which is transmitted to the through-core steel rod through the fixed sleeve to form a negative bending moment M 22 , which can also partially offset the positive bending moment M1 formed by the upper load force of the through-core steel rod; while the negative bending moment M 22 The following formula can be used for calculation:
[0065] M 22 =S×h1
[0066] In addition, the negative bending moment M formed by the through-steel rod itself can be calculated by the through-steel rod bending stress N 23 , and the negative bending moment M 23 The following formula can be used for calculation:
[0067] M 23 =N×e
[0068] When the system of the utility model reaches force balance:
[0069] M1=M 21 +M 22 +M 23
[0070] In the above calculation formulas, F1 is the upper load force, that is, the force of the upper load of the through-steel rod (the load of the jack and the unloading device) on the through-steel rod; e is the offset, that is, the horizontal distance between the center line of the force of the upper load of the through-steel rod on the steel rod and the edge of the outer contour of the pier column; N is the bending stress of the through-steel rod; S is the contact stress between the lower wing plate and the surface of the pier body; h1 is the vertical distance between the horizontal center line of the through-steel rod and the bottom edge of the lower wing plate; h is the installation height of the upper wing plate, that is, the vertical distance between the horizontal center line of the upper wing plate and the horizontal center line of the through-steel rod; F2 is the tensile force of the upper wing plate;
[0071] Therefore, the utility model can generate a negative bending moment M by pulling the upper wing plate 4 and abutting the lower wing plate 1 against the pier to form a horizontal force of "upward pulling and downward pressing" respectively. 21 , negative bending moment M 22, to jointly offset the positive bending moment M1 formed by the upper load force, thereby greatly reducing the negative bending moment M required by the through-core steel rod itself 23 , thereby achieving the purpose of reducing the design diameter of the through-steel rod; in other words, even if the through-steel rod with a small diameter is used, the utility model can still meet the design requirements under the condition of considering the bending resistance calculation;
[0072] In summary, it can be seen that the above-mentioned structural design based on the utility model not only makes up for the defects of small-diameter through-steel rods with excess shear resistance and insufficient bending resistance, but also avoids the problem of interference between the through-steel rods and the dense steel skeleton due to their excessively large diameter, thereby resolving the conflict between the pier body steel bar spacing, the through-steel rod diameter and the steel rod bending resistance when considering the shear resistance and bending resistance of the through-steel rods at the same time.
[0073] In order to ensure that the supporting platform is horizontal during installation, further, in a preferred embodiment, the lower wing assembly also includes a horizontal bubble tube 8 arranged on the supporting platform 9.
[0074] Further, in a preferred embodiment, see Fig.10 and Fig.11 The column embracing assembly 2 includes a pier column embracing plate 201 and a pier column tightening belt 202. One end of the pier column embracing plate 201 is hinged to one side of the lower wing plate 1, and the other end is overlapped on the outer wall of the pier column; the pier column tightening belt 202 is connected between the pier column embracing plates 201 on both sides of the pier column, so as to embrace, tighten and fix the lower wing plate 1 to both sides of the pier column through the cooperation of the pier column tightening belt 202 and the pier column embracing plate 201; based on this structural setting, by adopting a "three-petal two-hinged" structure, that is, a pier column tightening belt 202 is connected between two pier column embracing plates 201 to form "three petals", and the two ends of the two pier column embracing plates 201 that are far away from each other are respectively connected to the pier column The lower wing plates on both sides are hinged to form "two hinges", thus forming a "three-petal two-hinge" column embracing assembly to meet the needs of embracing and tightening the lower wing plates on piers of different column diameters, avoiding the problem of customizing column embracing assemblies of different sizes for piers of different diameters; preferably, the pier embracing plate 201 is a rigid arc-shaped steel plate, so that it can better fit the surface of the pier to reduce the amount of contact pads; the pier tightening belt 202 is a flexible steel belt to achieve the effect of tightening the paired lower wing plates on both sides of the pier; the pier embracing plate 201 and the pier tightening belt 202 can be connected by positioning holes, bolts, buckles, etc., so as to facilitate the adjustment of the overall connection length.
[0075] Further, in a preferred embodiment, see Figures 4 to 6The lower wing assembly also includes a plurality of sleeve stiffening ribs 6 connected between the movable sleeve 3 and the lower wing plate 1 and evenly arranged along the circumferential direction; the plurality of sleeve stiffening ribs 6 can strengthen the connection strength between the movable sleeve and the lower wing plate and the stiffness of the entire lower wing plate, and at the same time can stably transfer the contact stress between the lower wing plate and the pier column to the movable sleeve and the through-steel rod in sequence.
[0076] Further, in a preferred embodiment, see Figures 7 to 9 The upper wing assembly also includes a plurality of upper wing plate stiffening ribs 7 arranged at both ends of the back side of the upper wing plate, and the plurality of upper wing plate stiffening ribs 7 cooperate with the upper wing plate to form a groove for clamping the contact pad; preferably, the plurality of upper wing plate stiffening ribs 7 are arranged at the position where the upper wing plate is installed with the tension screw, or at the welding and bolt connection position with the belly of the support beam, so that the tension force generated by the upper wing plate can be more concentratedly transmitted to the through-core steel rod to form a larger negative bending moment, so as to partially offset the positive bending moment formed by the load force on the upper part of the steel plate.
[0077] Further, in a preferred embodiment, see Figure 1 , Figure 2 The pre-tensioning assembly 5 of the utility model includes an upper connecting rib 501 connected to the upper wing plate 4, a lower connecting rib 502 connected to the lower wing plate 1, and a steel bar-sleeve connecting mechanism connected between the upper connecting rib 501 and the lower connecting rib 502; the steel bar-sleeve connecting mechanism includes a threaded sleeve 503, and a threaded steel bar 504 threadedly connected to the threaded sleeve 503, so that the threaded sleeve 503 can be twisted to adjust the connection length of the steel bar-sleeve connecting mechanism to apply pre-tension between the upper wing plate and the lower wing plate.
[0078] Further, in a preferred embodiment, see Figure 1 , Fig.12 and Fig.15 The pre-tensioning assembly 5 of the utility model includes an upper connecting rib 501 connected to the upper wing plate 4, which is connected to the lower wing plate 1. The upper wing plate 4 of the utility model is directly tensioned and fixed to the two sides of the pier column below the support beam by tensioning screws, or the upper wing plate 4 is installed on the belly of the support beam 13, and the support beam 13 is tightened and fixed to the pier column by tensioning screws, so that the upper wing plate 4 is indirectly tensioned and fixed to the two sides of the pier column; because the same negative bending moment M is reached 21 In the case of , the tension force F2 of the upper wing plate is inversely proportional to its installation height h. If the installation height h of the upper wing plate is too low, a larger tension force F2 needs to be provided. The increase in the tension force will obviously increase the construction difficulty and increase the parameter requirements of the structural parts. In general, the tension force F2 of the upper wing plate can only be adjusted within a limited range. If the negative bending moment M 21At a lower level, the upper wing plate can generally be fixed directly to both sides of the pier column below the support beam by using tension screws. At this time, the tension force F2 of the upper wing plate forms a negative bending moment M under this installation height condition. 21 The design requirements can be met; if the negative bending moment M required by the upper wing plate is 21 When the upper wing is at a higher level, due to the actual construction, the distance between the support beam and the lower wing plate is limited. If the installation height h of the upper wing plate reaches its limit, the upper wing plate is installed on both sides of the pier column at the lower edge of the support beam. At this time, if the negative bending moment M formed by the upper wing plate 21 If it is still difficult to meet the requirements, the installation height of the upper wing plate should be further increased. To this end, under the adjustment range of the tension force F2 of the upper wing plate, in order to achieve the required negative bending moment M 21 The upper wing plate 4 can be installed on the belly of the support beam 13, and the support beam 13 can be tightened and fixed to the pier column by tensioning screws, so that the upper wing plate 4 is indirectly fixed to both sides of the pier column, thereby increasing the installation height of the upper wing plate 4 and reducing the tension force F2 requirement of the upper wing plate, so that the upper wing plate forms the required negative bending moment M 21 .
[0079] As shown in Figure 12 and Fig.16 As shown, when the upper wing plate is indirectly installed on the pier column through the support beam, it is considered that the lower wing plate will apply pre-tension to the upper wing plate through the pre-tensioning assembly and generate a bending moment on the support beam, which will cause the support beam to have a risk of overturning. Further, in a preferred embodiment, when the upper wing plate 4 is indirectly fixed to both sides of the pier column, the upper wing plate 4 is installed at the belly position below the center line of the support beam 13, and the support beam 13 is tightened and fixed to both sides of the pier column by tensioning screws at a position above its center line; Fig.16 As shown, the pre-tensioning assembly applies pre-tension to the upper wing plate and generates a bending moment M3 on the support beam. The tensioning of the tensioning screw rod generates a bending moment M4 on the support beam. By controlling M3=M4, the adverse effect of the pre-tensioning assembly on the support beam can be offset. Specifically, Fig.16 The force relationship in can be obtained:
[0080] M4=F4×f
[0081] M3=F3×h3
[0082] Among them, F3 is the force exerted on the support beam when the tensioning screw is tightened; h3 is the vertical distance between the horizontal center line of the tensioning screw and the horizontal center line of the support beam; F4 is the pretension force applied by the pretensioning assembly; f is the horizontal distance between the vertical center line of the pretensioning assembly and the vertical center line of the support beam;
[0083] From the above calculations, it can be seen that satisfying the following condition F3×h3=F4×f can keep the support beam balanced and not prone to rollover.
[0084] Example 2
[0085] The construction method of the support structure of the utility model comprises the following steps:
[0086] 1. Parameter design and verification
[0087] 1.1 Design Preparation
[0088] Collect all cap beam drawings during the design preparation stage. Organize and count the following parameter indicators: pier type (rectangular pier, cylindrical pier), pier diameter (size), cap beam volume, upper support system structure type and size, construction load, jack and unloading device size, pier body reinforcement spacing; take the sum of the cap beam volume, construction load and the maximum value of each load of the upper support system as the total design load to facilitate universal design and ensure that it can be applied to all bridge piers in the project after a single verification; determine the allowable contact stress index of the upper and lower wing plates according to the pier body concrete strength grade.
[0089] 1.2 Determination of structural component design parameters
[0090] 1.2.1 Selection of diameter of fixed casing and through-core steel rod
[0091] For fixed sleeves: the diameter of the fixed sleeves should be 20mm larger than the diameter of the through-core steel rods, and the diameter of the fixed sleeves should be smaller than the spacing of the pier reinforcement bars;
[0092] For the through-steel rod: according to the design total load in step 1.1, the shear strength of the through-steel rod is verified according to the Q235 material. The minimum diameter of the through-steel rod that meets the shear strength is the lower limit of the through-steel rod diameter, and the through-steel rod diameter is 20mm smaller than the fixed sleeve diameter.
[0093] 1.2.2 Determination of the upper wing panel installation height and installation structure
[0094] like Fig.15 As shown, when the system of the utility model reaches force balance: M1 = M 21 +M 22 +M 23 ; and, M1=F1×e,M 22 =S×h1,M 23 =N×e,M 21 =F2×h; hence, F1×e=F2×h+N×e+S×h1;
[0095] Then we can get:
[0096]
[0097] Therefore, the installation height h of the upper wing plate can be calculated and determined according to the above formula: Among them, F1 is the upper load force, that is, the force of the upper load of the through-steel rod (the load of the jack and the unloading device) on the through-steel rod; e is the offset, that is, the horizontal distance between the center line of the force of the upper load of the through-steel rod on the steel rod and the edge of the outer contour of the pier column; N is the bending stress of the through-steel rod; S is the contact stress between the lower wing plate and the surface of the pier body; h1 is the vertical distance between the horizontal center line of the through-steel rod and the bottom edge of the lower wing plate; h is the installation height of the upper wing plate, that is, the vertical distance between the horizontal center line of the upper wing plate and the horizontal center line of the through-steel rod; F2 is the tensile force of the upper wing plate;
[0098] When the installation height h of the upper wing plate is lower than the height position of the lower edge of the support beam, the installation structure is selected in which the upper wing plate is directly fixed to both sides of the pier column below the support beam by tension screws;
[0099] On the contrary, when the installation height h of the upper wing plate is higher than the height position of the lower edge of the support beam, the upper wing plate 4 is installed at the belly position below the center line of the support beam 13, and the support beam 13 is tightened and fixed to the installation structure on both sides of the pier column at a position above its center line by tensioning screws;
[0100] 1.2.3 Parameter selection of column assembly
[0101] (1) Select the initial size of the "three-petal two-hinged" column assembly according to conventional size;
[0102] (2) Take the maximum column diameter and determine the geometric dimensions of the “three-petal two-hinged”, steel strip and contact pad by drawing;
[0103] (3) Take the minimum column diameter and verify the geometric dimensions of the “three-petal two-hinged”, steel belt and contact pad by drawing;
[0104] (4) According to the difference between the geometric dimensions of the contact pad determined in Items (2) and (3) above, the maximum deformation degree required for the contact pad is determined, thereby determining the parameter requirements of the rubber material. The rubber material should not be too hard, and the maximum elastic stress should be ensured to be at an appropriate level.
[0105] (5) The tightening force between the pier column tightening belt 202 and the pier column surrounding plate 201 is determined based on the maximum elastic stress of the contact pad.
[0106] 1.2.4 All structural parts are made of Q235 steel, and the geometric parameters of other structural parts are set according to the conventional dimensions.
[0107] 1.3 Calculation of bending resistance and contact stress
[0108] Finite element software is used to perform modeling analysis according to the design parameters determined in step 1.2 without applying prestress, and the design parameters of the structural parts are adjusted to verify the following indicators and adjust the dimensions of the structural parts so that the bending performance and contact stress distribution of the structural parts are within the appropriate range:
[0109] (1) The tensile stress at the junction of the through-steel rod and the outer surface of the pier body can be controlled by adjusting the installation height position h of the upper and lower wing plates and the height dimensions of the upper and lower wing plates;
[0110] (2) The compressive stress at the lower part of the interface between the through-steel rod and the pier body can be controlled by adjusting the diameter of the steel rod;
[0111] (3) The extreme value and distribution of stress of the overall structural parts, which can be controlled by adjusting the dimensions of each part of the structural parts;
[0112] (4) The contact stress between the upper and lower wing plates, the support beam and the pier body surface, which can be controlled by adjusting the bending moment distribution between the upper and lower wing plates and the height dimensions of the upper and lower wing plates;
[0113] (5) The stiffness and deformation of the upper wing plate, which can be controlled by adjusting the size of the upper wing plate stiffening ribs;
[0114] (6) When the upper wing plate is installed on the web of the supporting beam and indirectly fixed on both sides of the pier, the anti-overturning condition of the supporting beam shall also be verified;
[0115] 1.4 Prestress calculation
[0116] According to the finite element model determined in step 1.3 and the design parameters of the structural components, by applying prestress on the prestressing components, according to the change of the contact stress between the upper wing plate, the lower wing plate, the support beam and the pier body surface, the appropriate prestress level is selected as a safety reserve;
[0117] 2. Support structure construction
[0118] 2.1 According to the design parameters of the structural parts after the bending performance and contact stress verification in step 1.3, the fixed casing is embedded in sequence, the pier body is cast, the through-core steel rod is inserted, the lower wing assembly is installed, the upper wing assembly is installed, and the tension screw is installed. Specifically:
[0119] (1) Pre-buried fixed casing
[0120] Install the fixed sleeve 11 at the position passing through the diameter in the middle of the cylindrical pier, or at the point where the long side of the square pier is divided into three equal parts;
[0121] (2) Casting of pier body
[0122] Cast the pier body according to the conventional process, and take care to avoid vibration touching the fixed casing and causing displacement;
[0123] (3) Insert the through-core steel rod
[0124] After the pier body strength meets the construction requirements, the through-core steel rod 12 is inserted into the casing;
[0125] (4) Install the lower wing assembly
[0126] The lower wing plate 1 is symmetrically inserted into the supporting end of the through-core steel rod 12, and adjusted to a horizontal state by means of a horizontal tube. Then, a movable sleeve is installed, and the movable sleeve is fixed with a sleeve limit pin. Then, the pier column embracing plate is fitted onto the surface of the cylindrical pier, and the pier column tightening belt is fixed to the pier column embracing plate by means of buckles, so that the lower wing plate 1 is encircled, tightened, and fixed on both sides of the pier column.
[0127] (5) Install the upper wing assembly
[0128] According to the upper wing panel installation height and installation structure determined in step 1.2, the upper wing panels 4 are installed above the lower wing panels 1, and the upper wing panels 1 are temporarily fixed by pre-tensioning components to prevent the upper wing panels 4 from loosening and falling.
[0129] 6) Install the tension screw
[0130] According to the installation height and installation structure of the upper wing plate determined in step 1.2, the upper wing plate 4 is directly fixed to the two sides of the pier column below the support beam by means of tension screws, and then the tension screws are tightened for the first time, and the axial force of the tension screws is controlled not to be too large, so that the contact pad at the position of the upper wing plate fits the surface of the cylindrical pier to produce a certain elastic deformation; or, the upper wing plate 4 is installed at the belly position below the center line of the support beam 13, and the support beam 13 is tightened and fixed to the two sides of the pier column by means of tension screws at a position above its center line, and then the tension screws are tightened for the first time, and the axial force of the tension screws is controlled not to be too large, so that the support beam is controlled to be in a balanced state;
[0131] 2.2 Apply prestress through the prestressing assembly according to the prestressing level selected in step 1.4;
[0132] 2.3 Install the jack and unloading device
[0133] Place and install the jack and unloading device to the designed position.
[0134] 2.4 Install the upper support structure
[0135] Install the upper support structure and tie the steel bars.
[0136] 2.5 Tensioning screw
[0137] The tensioning screws are tightened again. The secondary tensioning should make the contact pad at the upper wing plate fit the surface of the cylindrical pier and produce the required elastic deformation.
[0138] The above description of the utility model in combination with the accompanying drawings is an exemplary description. Obviously, the specific implementation of the utility model is not limited to the above-mentioned method. As long as the non-substantial improvements are made by adopting the method concept and technical solution of the utility model, or the concept and technical solution of the utility model are directly applied to other occasions without improvement, they are all within the protection scope of the utility model.
Claims
1. A large cap beam support structure based on a small diameter through-core steel rod, comprising a pier, a jack, a fixed sleeve pre-buried in the pier, a through-core steel rod inserted in the fixed sleeve and having both ends exposed to the pier to form a support end, and a support beam arranged above the through-core steel rod, characterized in that Also includes: A lower wing assembly, the lower wing assembly comprising a movable sleeve and a lower wing plate sleeved on the supporting end of the through-core steel rod, a sleeve limit pin used to fix the movable sleeve to prevent the movable sleeve from rotating relative to the through-core steel rod or sliding out of the through-core steel rod, a column-holding assembly used to wrap and tighten the lower wing plate and fix it on both sides of the pier column, and a support platform arranged on the movable sleeve to carry the jack; one side of the lower wing plate is connected to the movable sleeve, and the other side abuts against the outer wall of the pier column to generate contact stress and transmit it to the through-core steel rod through the fixed sleeve to form a negative bending moment, thereby partially offsetting the positive bending moment formed by the upper load force of the through-core steel rod; An upper wing assembly, the upper wing assembly comprising an upper wing plate arranged above the lower wing plate, the upper wing plate being directly or indirectly tension-fixed on both sides of the pier column to generate a tension force and transmit it to the through-core steel rod through the pre-tensioning assembly to form a negative bending moment, thereby partially offsetting the positive bending moment formed by the upper load force of the through-core steel rod; A pre-tensioning assembly, wherein the pre-tensioning assembly is symmetrically arranged on both sides of the through-core steel rod and connected between the upper wing plate and the lower wing plate, so as to apply a pre-tensioning force between the upper wing plate and the lower wing plate; and A contact pad is filled between the contact surfaces of the upper wing plate, the lower wing plate, the column assembly and the outer wall of the pier.
2. A large cap beam support structure based on a small diameter through-steel rod as claimed in claim 1, characterized in that The lower wing assembly also includes a horizontal bubble tube arranged on the supporting platform.
3. A large cap beam support structure based on a small diameter through-steel rod as claimed in claim 1, characterized in that: The column embracing assembly includes a pier column embracing plate and a pier column tightening belt. One end of the pier column embracing plate is hinged to one side of the lower wing plate, and the other end is overlapped on the outer wall of the pier column. The pier column tightening belt is connected between the pier column embracing plates on both sides of the pier column, so as to embrace, tighten and fix the lower wing plate to both sides of the pier column through the cooperation between the pier column tightening belt and the pier column embracing plate.
4. A large cap beam support structure based on a small diameter through-steel rod as claimed in claim 1, characterized in that: The upper wing assembly also includes a plurality of upper wing plate stiffening ribs arranged at both ends of the back side of the upper wing plate, and the plurality of upper wing plate stiffening ribs cooperate with the upper wing plate to form a channel for clamping the contact pad.
5. A large cap beam support structure based on a small diameter through-steel rod as claimed in claim 1, characterized in that: The lower wing assembly also includes a plurality of sleeve stiffening ribs connected between the movable sleeve and the lower wing plate and uniformly arranged along the circumferential direction.
6. A large cap beam support structure based on a small diameter through-steel rod as claimed in claim 1, characterized in that: The pre-tensioning assembly includes an upper connecting rib connected to the upper wing plate, a lower connecting rib connected to the lower wing plate, and a steel bar-sleeve connecting mechanism connected between the upper connecting rib and the lower connecting rib; the steel bar-sleeve connecting mechanism includes a threaded sleeve and a threaded steel bar threadedly connected to the threaded sleeve.
7. A large cap beam support structure based on a small diameter through-steel rod as claimed in claim 1, characterized in that: The upper wing plate is directly fixed to the two sides of the pier below the support beam by tensioning screws; or, the upper wing plate is installed on the belly of the support beam, and the support beam is tightened and fixed to the pier by tensioning screws, so that the upper wing plate is indirectly fixed to the two sides of the pier.
8. A large cap beam support structure based on a small diameter through-core steel rod as claimed in claim 7, characterized in that: When the upper wing plate is indirectly fixed to both sides of the pier by tension, the upper wing plate is installed at the belly position below the center line of the support beam, and the support beam is tightened and fixed to the pier by tensioning screws at a position above its center line.