Municipal rain and sewage pipeline construction positioning device
By designing the supporting frame, positioning structure and pushing structure of the municipal rainwater and sewage pipeline construction positioning device, the complex positioning problem during construction is solved, the fast and accurate connection and support of the pipe docking is achieved, and the construction process is simplified.
Patent Information
- Application Number
- CN202420443138.8
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-03-07
- Publication Date
- 2024-10-22
- Estimated Expiration
- 2034-03-07
AI Technical Summary
During the construction of municipal rainwater and sewage pipelines, the positioning device needs to be frequently disassembled and assembled to determine the location of the pipe joints, resulting in complicated work and inconvenient structural installation.
Design a construction positioning device that includes a support frame, a positioning structure and a push structure. The position of the support plate is adjusted by rotating the threaded pipe sleeve and screw rod, and the positioning of the pipe mouth is achieved accurately by using the limit chute and slide plate, and through the splint and soft cushion. Increase friction and push the frame to achieve pipe docking.
It achieves fast and accurate positioning and connection of pipeline docking locations, simplifying the construction process. After completion, the device can be left in the pipeline as a support structure, simplifying the installation and burial process.
Smart Images

Figure CN221878298U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of pipeline laying, in particular to a municipal rainwater and sewage pipeline construction positioning device. Background Art
[0002] The sewage pipe system consists of pipes and their ancillary structures for collecting and transporting urban sewage. The sewage flows from the branch pipes into the trunk pipes, then into the main pipes, and finally into the sewage treatment plant. The pipes are distributed from small to large, similar to rivers and in a tree-like shape. This is completely different from the circulation and penetration of the water supply network. Sewage generally flows from high to low in the pipes due to the water level difference at both ends of the pipes. The inside of the pipes is not under pressure, that is, it flows by gravity.
[0003] During the construction of municipal rainwater and sewage pipes, a pipe construction positioning device is used to fix the position of the sewage pipe and facilitate the installation of the pipe. However, a positioning structure is required to determine the position of each two pipe joints for easy docking. The positioning device needs to be repeatedly disassembled and assembled to position the new joint, which is complicated. At the same time, a pipe installation bracket is required for the installation of the structural pipe. A positioning device that can replace part of the pipe installation bracket is proposed. Utility Model Content
[0004] The purpose of the utility model is to solve the problem that a pipeline construction positioning device is used in the construction process of municipal rainwater and sewage pipelines to fix the position of the sewage pipeline and facilitate the installation of the pipeline. However, a positioning structure is required to determine the position of each two pipe joints to facilitate the joint. The positioning device needs to be repeatedly disassembled and assembled to position the new joint, which makes the work complicated.
[0005] The purpose of the utility model can be achieved through the following technical solutions:
[0006] A municipal rainwater and sewage pipe construction positioning device comprises a support frame, a positioning structure is slidably installed on the front side of the support frame, and a pushing structure is clamped at the four corners of the rear side of the positioning structure. The support frame comprises a No. 1 frame, and a No. 1 threaded pipe sleeve is rotatably and interlacedly installed on the bottom side and the two side surfaces of the No. 1 frame, and a No. 1 screw is screwed in the No. 1 threaded pipe sleeve, and a base is fixedly installed on one end of the No. 1 screw, and one end of the base is fixedly connected to a support plate.
[0007] Furthermore, limiting sliding grooves are interspersed on the four side edges of the No. 1 frame, and a No. 1 angle plate is fixedly installed at the four inner corners of the No. 1 frame, and the No. 1 angle plate is interspersed with an adjusting screw hole.
[0008] Furthermore, the positioning structure includes a No. 2 frame, and No. 2 angle plates are fixedly installed at the four corners inside the No. 2 frame. A clamping block is rotatably embedded in the rear side of the No. 2 angle plate, and a limiting slide is fixedly installed at the edge of the rear surface of the No. 2 frame.
[0009] Furthermore, a No. 2 threaded sleeve is rotatably installed on the four side surfaces of the No. 2 frame, a No. 2 screw rod is screwed and inserted into the No. 2 threaded sleeve, a clamp is rotatably installed on one end of the No. 2 screw rod, and a soft pad is fixedly installed on one side surface of the clamp.
[0010] Furthermore, the pushing structure includes a No. 3 screw rod, a connecting plug-in is fixedly installed on one end of the No. 3 screw rod, and a rotating handle is fixedly installed on the other end of the No. 3 screw rod.
[0011] Furthermore, the limiting slide plate is slidably connected with the limiting slide groove.
[0012] Furthermore, the third screw rod passes through the adjusting screw hole, and the connecting plug-in and the clamping block are clamped with each other.
[0013] Beneficial effects of the utility model:
[0014] 1. By rotating the No. 1 threaded pipe sleeve and turning the No. 1 screw rod, the position of the support plate is adjusted, so that the support plates at the bottom and both sides of the No. 1 frame are pressed against the inner wall of the pipe channel where the pipe is buried, and the position of the sewage pipe mouth is limited. At the same time, by rotating the No. 1 threaded pipe sleeve at different directions of the No. 1 frame, the length of the No. 1 screw rod in different directions of the No. 1 frame is adjusted, and the position of the pipe mouth is adjusted and positioned, so that the two sewage pipes can be connected to each other at the interface. After the pipe connection is completed, the overall structure can be left in the pipe channel to serve as a pipe support structure and buried together with the pipe.
[0015] 2. By rotating the No. 2 threaded pipe sleeve, the No. 2 screw is controlled to move up and down, and then the pipe opening is clamped by the clamping plate, and the friction between the clamping plate and the side surface of the pipe is increased by the soft pad. The No. 3 screw is rotated by rotating the handle, and the thread inside the adjusting screw is used to control the movement of the No. 3 screw, thereby pushing the No. 2 frame away from the No. 1 frame, and using the clamping plate to clamp the pipe opening, the two pipe openings are driven close to each other to achieve the docking effect. BRIEF DESCRIPTION OF THE DRAWINGS
[0016] The utility model is further described below in conjunction with the accompanying drawings.
[0017] Figure 1 It is a schematic diagram of the overall structure of the utility model;
[0018] Figure 2 It is a schematic diagram of the support frame in the utility model;
[0019] Figure 3 It is a schematic diagram of the positioning structure in the utility model;
[0020] Figure 4 It is a schematic diagram of the propulsion structure in the utility model.
[0021] In the figure: 1. Support frame; 101. Frame No. 1; 102. Limiting slide; 103. Angle plate No. 1; 104. Adjusting screw; 105. Threaded sleeve No. 1; 106. Screw rod No. 1; 107. Base; 108. Support plate; 2. Positioning structure; 201. Frame No. 2; 202. Angle plate No. 2; 203. Block; 204. Limiting slide; 205. Threaded sleeve No. 2; 206. Screw rod No. 2; 207. Clamp; 208. Cushion; 3. Pushing structure; 301. Screw rod No. 3; 302. Connecting plug-in; 303. Rotating handle. DETAILED DESCRIPTION
[0022] The following will be combined with the embodiments of the utility model to clearly and completely describe the technical solutions in the embodiments of the utility model. Obviously, the described embodiments are only part of the embodiments of the utility model, not all of the embodiments. Based on the embodiments of the utility model, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the utility model.
[0023] See also Figure 1-4 As shown, a municipal rainwater and sewage pipe construction positioning device includes a support frame 1, a positioning structure 2 is slidably installed on the front side of the support frame 1, and a pushing structure 3 is clamped at the four corners of the rear side of the positioning structure 2. The support frame 1 includes a No. 1 frame 101, and a No. 1 threaded pipe sleeve 105 is rotatably interlaced and installed on the bottom side and the two side surfaces of the No. 1 frame 101. A No. 1 screw rod 106 is screwed and installed in the No. 1 threaded pipe sleeve 105. A base 107 is fixedly installed at one end of the No. 1 screw rod 106, and one end of the base 107 is fixedly connected to a support plate 108. When in use, the overall structure is sleeved on the butt joint of the sewage pipe, and the pipe mouth is clamped by the positioning structure 2, and the overall structure is relatively fixedly connected to the pipe. At the same time, by rotating the No. 1 threaded sleeve 105 and turning the No. 1 screw rod 106, the position of the support plate 108 is adjusted, so that the support plates 108 at the bottom and both sides of the No. 1 frame 101 are pressed against the inner wall of the pipe channel where the pipe is buried, and the position of the sewage pipe mouth is limited. At the same time, by rotating the No. 1 threaded sleeve 105 at different directions of the No. 1 frame 101, the length of the No. 1 screw rod 106 in different directions of the No. 1 frame 101 is adjusted, and then the position of the pipe mouth is adjusted and positioned, so that the two sewage pipes are connected to each other at the interface. After the pipe connection is completed, the overall structure can be left in the pipe channel to serve as a pipe support structure and buried together with the pipe.
[0024] A No. 2 threaded sleeve 205 is rotatably installed on the four side surfaces of the No. 2 frame 201, and a No. 2 screw rod 206 is screwed and inserted in the No. 2 threaded sleeve 205. A clamping plate 207 is rotatably installed on one end of the No. 2 screw rod 206, and a soft pad 208 is fixedly installed on one side surface of the clamping plate 207. By rotating the No. 2 threaded sleeve 205, the No. 2 screw rod 206 is controlled to move up and down, and then the clamping plate 207 is pressed against and clamped to clamp the pipe mouth, and the soft pad 208 increases the friction between the clamping plate 207 and the side surface of the pipe; limited sliding grooves 102 are inserted on the four side edges of the No. 1 frame 101, and a No. 1 angle plate 103 is fixedly installed at the four corners of the inner side of the No. 1 frame 101, and the No. 1 angle plate 103 is inserted with an adjusting screw hole 104; the positioning structure 2 includes a No. 2 frame 201, and a No. 2 angle plate 202 is fixedly installed at the four corners inside the No. 2 frame 201, and a card is rotatably embedded in the rear side of the No. 2 angle plate 202 Block 203, a limiting slide 204 is fixedly installed on the edge of the rear surface of frame No. 201, frame No. 101 and frame No. 201 are slidably connected with the limiting slide 102 through the limiting slide 204; the limiting slide 204 is slidably connected with the limiting slide 102; the pushing structure 3 includes a third screw rod 301, one end of the third screw rod 301 is fixedly installed with a connecting plug-in 302, and the other end of the third screw rod 301 is fixedly installed with a rotating handle 303, the third screw rod 301 is rotated by rotating the handle 303, and the thread inside the adjusting screw mouth 104 is used to control the movement of the third screw rod 301, thereby pushing the second frame 201 away from the first frame 101, and the clamping plate 207 is used to clamp the pipe mouth, thereby driving the two pipe mouths to approach each other to achieve the docking effect; the third screw rod 301 passes through the adjusting screw mouth 104, and the connecting plug-in 302 and the clamping block 203 are mutually clamped.
[0025] Working principle: When in use, the overall structure is sleeved on the joint of the sewage pipe, the pipe mouth is clamped by the positioning structure 2, and the overall structure is relatively fixedly connected to the pipe. At the same time, by rotating the No. 1 threaded pipe sleeve 105 and the No. 1 screw rod 106, the position of the support plate 108 is adjusted, so that the support plates 108 at the bottom and both sides of the No. 1 frame 101 are against the inner wall of the pipe channel where the pipe is buried, and the position of the sewage pipe mouth is limited. At the same time, by rotating the No. 1 threaded pipe sleeve 105 at different directions of the No. 1 frame 101, the length of the No. 1 screw rod 106 in different directions of the No. 1 frame 101 is adjusted, and the position of the pipe mouth is adjusted and positioned, which is convenient for the two sewage pipes. The pipeline interfaces are connected to each other. After the pipeline connection is completed, the overall structure can be left in the pipeline to serve as a pipeline support structure and buried together with the pipeline. By rotating the No. 2 threaded sleeve 205, the No. 2 screw rod 206 is controlled to move up and down, and then the pipe mouth is clamped by the clamping plate 207, and the friction between the clamping plate 207 and the side surface of the pipeline is increased by the soft pad 208. The No. 3 screw rod 301 is rotated by rotating the handle 303, and the thread inside the adjusting screw mouth 104 is used to control the movement of the No. 3 screw rod 301, thereby pushing the No. 2 frame 201 away from the No. 1 frame 101, and the clamping of the pipe mouth by the clamping plate 207 is used to drive the two pipe mouths close to each other to achieve the docking effect.
[0026] In the description of this specification, the description with reference to the terms "one embodiment", "example", "specific example", etc. means that the specific features, structures, materials or characteristics described in conjunction with the embodiment or example are included in at least one embodiment or example of the utility model. In this specification, the schematic representation of the above terms does not necessarily refer to the same embodiment or example. Moreover, the specific features, structures, materials or characteristics described can be combined in any one or more embodiments or examples in a suitable manner.
[0027] The above contents are merely examples and explanations of the present utility model. The technicians in this technical field may make various modifications or additions to the specific embodiments described or replace them in a similar manner. As long as they do not deviate from the utility model or exceed the scope defined in the claims, they should all fall within the protection scope of the present utility model.
Claims
1. A municipal rainwater and sewage pipe construction positioning device, comprising a support frame (1), characterized in that: A positioning structure (2) is slidably mounted on the front side of the support frame (1), and a pushing structure (3) is clamped at the four corners of the rear side of the positioning structure (2). The support frame (1) comprises a No. 1 frame (101), and a No. 1 threaded sleeve (105) is rotatably and interlacedly mounted on the bottom side and the two side surfaces of the No. 1 frame (101), and a No. 1 screw rod (106) is screwed and mounted inside the No. 1 threaded sleeve (105), and a base (107) is fixedly mounted on one end of the No. 1 screw rod (106), and one end of the base (107) is fixedly connected to a support plate (108).
2. A municipal rainwater and sewage pipe construction positioning device according to claim 1, characterized in that: The four side edges of the first frame (101) are interspersed with limit sliding grooves (102), and the four inner corners of the first frame (101) are fixedly installed with a first angle plate (103), and the first angle plate (103) is interspersed with an adjusting screw hole (104).
3. A municipal rainwater and sewage pipe construction positioning device according to claim 2, characterized in that: The positioning structure (2) comprises a second frame (201), wherein second angle plates (202) are fixedly mounted at the four corners inside the second frame (201), a clamping block (203) is rotatably embedded in the rear side of the second angle plate (202), and a limiting slide plate (204) is fixedly mounted at the edge of the rear surface of the second frame (201).
4. A municipal rainwater and sewage pipe construction positioning device according to claim 3, characterized in that: A No. 2 threaded pipe sleeve (205) is rotatably mounted on the four side surfaces of the No. 2 frame (201), a No. 2 screw rod (206) is screwed and inserted into the No. 2 threaded pipe sleeve (205), a clamping plate (207) is rotatably mounted on one end of the No. 2 screw rod (206), and a soft pad (208) is fixedly mounted on one side surface of the clamping plate (207).
5. A municipal rainwater and sewage pipe construction positioning device according to claim 4, characterized in that: The pushing structure (3) comprises a third screw rod (301), one end of which is fixedly mounted with a connecting plug-in (302), and the other end of which is fixedly mounted with a rotating handle (303).
6. A municipal rainwater and sewage pipe construction positioning device according to claim 5, characterized in that: The limiting slide plate (204) is interlaced and slidably connected with the limiting slide groove (102).
7. A municipal rainwater and sewage pipe construction positioning device according to claim 6, characterized in that: The third screw rod (301) passes through the adjusting screw hole (104), and the connecting plug-in (302) and the clamping block (203) are clamped with each other.
Citation Information
Cited By
Municipal rain and sewage pipeline construction positioning device
CN223907636U