Large-pipe-diameter flow metering device of high-level water tank

By introducing a float control valve and a differential pressure switch into the main water supply pipe of the high-level pool, the water supply bypass is used to achieve accurate measurement of water flow, which solves the problem of inaccurate measurement of large-diameter flowmeters when water demand is small and reduces costs. And improve the measurement accuracy.

CN221881171UActive Publication Date: 2024-10-22CHONGQING CHINA TOBACCO IND CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420337316.9
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-02-23
Publication Date
2024-10-22
Estimated Expiration
2034-02-23

AI Technical Summary

Technical Problem

In industrial production, the large-diameter flowmeter of the main water supply pipe of the high-level pool is inaccurate in measuring water consumption, especially when the water demand is small, resulting in inaccurate water flow monitoring.

Method used

A device including a main water supply pipe, a main pipeline flow meter, a float control valve, a differential pressure switch and a solenoid valve is designed. The differential pressure switch monitors the pressure difference on both sides of the float control valve and controls the opening of the float control valve. When water demand is low, small flow water supply is provided through the water supply bypass, and the bypass flow meter is used to monitor the water flow to ensure the accuracy of measurement.

Benefits of technology

It achieves accurate measurement of water flow when water demand is low, reduces costs, simplifies the structure and maintenance of the device, and improves measurement accuracy and practicality.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN221881171U_ABST
    Figure CN221881171U_ABST
Patent Text Reader

Abstract

The utility model relates to the technical field of flow metering, and particularly discloses a large-pipe-diameter flow metering device of a high-level water tank. Comprising a main water supply pipe, a main pipeline flowmeter and a main pipeline control valve, the main pipeline flowmeter and the main pipeline control valve are arranged on the main water supply pipe, the main water supply pipe is further communicated with a water supply bypass, the pipeline diameter of the water supply bypass is smaller than that of the main water supply pipe, and the water supply bypass is connected to the two sides of the main pipeline control valve in parallel. The two sides of the main pipeline control valve are further connected with differential pressure switches in series, and the differential pressure switches are used for controlling the opening degree of the main pipeline control valve. The utility model aims to solve the problem that the water consumption of a main water supply pipe cannot be accurately metered by a large-diameter flow meter in industrial production.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model belongs to the technical field of flow metering, and in particular relates to a large-diameter flow metering device for a high-level water tank. Background Art

[0002] A high-level water tank is a water storage structure built on high ground. Common forms include water towers, which are tall structures used for water storage and water distribution. They are used to maintain and regulate the amount of water and water pressure in the water supply network. They are mainly composed of a water tank, a foundation, and a support tube or bracket connecting the two. They are generally used for water storage in residential areas and water supply for production. In water supply environments with intermittent water use and low pressure requirements, high-level water tanks can be used. In this way, the water inlet pump does not need to be turned on all the time. When the water in the pool is low, the water inlet pump can be automatically started to replenish water, and the pump will stop when the water is replenished.

[0003] In the industrial production high-level water tank water supply system, the main water supply pipe usually has a larger diameter. When the water demand is small, the water flow in the main water supply pipe is low. The large-diameter flow meter used for main water supply pipe metering is not accurate enough, resulting in inaccurate flow meter measurement of the main water supply pipe water flow when the flow is small. Utility Model Content

[0004] The purpose of the utility model is to provide a large-diameter flow metering device for a high-level water tank, which is used to solve the problem of inaccurate water consumption measurement of a main water supply pipe by a large-diameter flow meter in industrial production.

[0005] In order to achieve the above technical purpose, the technical solution adopted by the utility model is as follows:

[0006] A large-diameter flow metering device for a high-level water tank comprises a main water supply pipe, a main pipeline flow meter and a main pipeline control valve, wherein the main pipeline flow meter and the main pipeline control valve are arranged on the main water supply pipe, and the main water supply pipe is also connected to a water supply bypass, the pipe diameter of the water supply bypass is smaller than the main water supply pipe, the water supply bypass is connected in parallel on both sides of the main pipeline control valve, a bypass flow meter is arranged on the water supply bypass, and pressure differential switches are also connected in series on both sides of the main pipeline control valve, and the pressure differential switch is used to control the opening of the main pipeline control valve.

[0007] In this technical solution, the water stored in the high-level water tank is supplied to the production line through the main water supply pipe. The main pipeline control valve is used to control the water flow of the main water supply pipe through the opening of the control valve. The main pipeline flowmeter is used to monitor the water flow of the main water supply pipe. In actual applications, when the water consumption of the main water supply pipe is small, the water flow is low. The detection accuracy of the main pipeline flowmeter set on the main water supply pipe is insufficient, which leads to inaccurate water flow monitoring. Therefore, when the water demand is small, the opening and closing of the main pipeline control valve is controlled by the pressure difference switch connected in series on both sides of the control valve, so that when the water flow in the main water supply pipe is small, a small flow of water is provided through the water supply bypass connected to the main water supply pipe and connected on both sides of the main pipeline control valve, and a bypass flowmeter is set on the water supply bypass to monitor the water flow of the water supply bypass. In this way, accurate measurement of the water flow of the high-level water tank is achieved.

[0008] It is further defined that the main pipeline control valve is a float control valve, and a control valve pressure relief pipe connected to the main water supply pipe is also provided on one side of the float control valve, and a solenoid valve is provided on the control valve pressure relief pipe, and the solenoid valve is electrically connected to the pressure difference switch. In the present technical scheme, if the float control valve adopts traditional float hydraulic control or a single control motor, there are disadvantages of high cost and complex process. Therefore, the pressure in the float control valve is adjusted by cooperating with the control valve pressure relief pipe and the solenoid valve to achieve the purpose of controlling the valve opening of the float control valve. At the same time, the solenoid valve is electrically connected to the pressure differential switch, and the pressure difference on both sides of the float control valve is monitored by the pressure differential switch. When the pressure difference on both sides is too large, it is determined that the water flow in the main water supply pipe is small, and the main pipeline flowmeter cannot accurately measure the water flow in the main water supply pipe. The pressure differential switch sends a level signal indicating that the water pressure is too low to the solenoid valve. The solenoid valve controls the valve closure of the float control valve according to the level signal, so that the water flow in the main water supply pipe is supplied to the production line through the water supply bypass. Such a design has a simple structure, low cost, and strong practicality.

[0009] It is further defined that the main water supply pipe is also provided with a first gate valve, and the first gate valve is located between the main pipeline flow meter and the main pipeline control valve. It is understandable that the main pipeline control valve in actual application will inevitably fail due to the limitation of service life or wear and tear caused by high-pressure water flow. In order to facilitate the disassembly, maintenance, replacement and installation of the main pipeline control valve, the water flow from the high-level water tank is cut off by the first gate valve. Such a design structure is simple and has strong practicality.

[0010] It is further defined that a second gate valve is also provided on the water supply bypass. In this technical solution, the cooperation between the second gate valve and the first gate valve prevents the water flow in the main water supply pipe from flowing to the water supply bypass, which facilitates the disassembly, maintenance, replacement, and installation of the bypass flowmeter. Such a design structure is simple and has strong practicality.

[0011] It is further defined that there are two second gate valves, and the two second gate valves are respectively arranged on both sides of the bypass flowmeter. In this technical solution, the second gate valves are respectively arranged on both sides of the bypass flowmeter, so that the water flow from the main water supply pipe can be cut off without the cooperation of the first gate valve, and the bypass flowmeter can be disassembled, repaired, etc. without affecting the water supply of the production line. Such a design structure is simple and has strong practicality.

[0012] It is further defined that the end of the main water supply pipe is also connected to multiple production water supply pipelines, and each of the production water supply pipelines is provided with a third gate valve. In actual applications, the water supply of the production line often has multiple demands and the demand and demand time of each part of the production line are different. Therefore, by providing multiple water supply pipes and providing each water supply pipe with a third gate valve, accurate water supply can be achieved at each part of the production line. Such a design structure is simple and has strong practicality.

[0013] The utility model adopting the above technical solution has the following advantages:

[0014] 1. In the utility model, when the water demand of the production line is small, the main pipeline control valve is opened and closed by the pressure difference switch connected in series on both sides of the main pipeline control valve, so that when the water flow in the main water supply pipe is small, a small flow water supply is provided through the water supply bypass connected to the main water supply pipe and connected on both sides of the main pipeline control valve, and a bypass flowmeter is set on the water supply bypass to monitor the water flow of the water supply bypass. In this way, the water flow of the high-level water tank can be accurately measured.

[0015] 2. In the utility model, the pressure in the float control valve is adjusted by the cooperation of the control valve pressure relief pipe and the solenoid valve, thereby achieving the purpose of controlling the valve opening of the float control valve. At the same time, the solenoid valve is electrically connected to the pressure differential switch, and the pressure difference on both sides of the float control valve is monitored by the pressure differential switch. When the pressure difference on both sides is too large, it is determined that the water flow in the main water supply pipe is small, and the main pipeline flow meter cannot accurately measure the water flow in the main water supply pipe. The pressure differential switch sends a level signal indicating that the water pressure is too low to the solenoid valve, and the solenoid valve controls the valve of the float control valve to close according to the level signal, so that the water flow in the main water supply pipe is supplied to the production line via the water supply bypass, saving a lot of costs. BRIEF DESCRIPTION OF THE DRAWINGS

[0016] The present invention can be further described by the non-limiting embodiments given in the accompanying drawings;

[0017] Figure 1 It is a structural schematic diagram of an embodiment of a large-diameter flow metering device for a high-level water tank of the utility model;

[0018] The main component symbols are described as follows:

[0019] Main water supply pipe 1, main pipeline flowmeter 2, float control valve 3, first gate valve 4, second gate valve 5, third gate valve 6, production water supply pipeline 7, water supply bypass 8, bypass flowmeter 9, differential pressure switch 10, control valve pressure relief pipe 11, solenoid valve 12. DETAILED DESCRIPTION

[0020] The present invention will be described in detail below in conjunction with the accompanying drawings and specific embodiments. It should be noted that in the drawings or in the specification, similar or identical parts use the same figure numbers, and the implementation methods not shown or described in the drawings are forms known to ordinary technicians in the relevant technical field. In addition, the directional terms mentioned in the embodiments, such as "upper", "lower", "top", "bottom", "left", "right", "front", "back", etc., are only referenced to the directions of the drawings and are not used to limit the scope of protection of the present invention.

[0021] like Figure 1 As shown, a large-diameter flow metering device for a high-level water tank of the utility model comprises a main water supply pipe 1, a main pipeline flow meter 2 and a float control valve 3, the main pipeline flow meter 2 and the float control valve 3 are arranged on the main water supply pipe 1, the main water supply pipe 1 is also provided with a first gate valve 4, the end of the main water supply pipe 1 is also connected to a plurality of production water supply pipelines 7, each production water supply pipeline 7 is provided with a third gate valve 6, the main water supply pipe 1 is also connected to a water supply bypass 8, the pipe diameter of the water supply bypass 8 is smaller than the main water supply pipe 1, and the water supply bypass 8 is connected in parallel On both sides of the float control valve 3, a bypass flowmeter 9 is arranged on the water supply bypass 8, and a second gate valve 5 is respectively arranged on both sides of the bypass flowmeter 9 on the water supply bypass 8. A pressure differential switch 10 is also connected in series on both sides of the float control valve 3. A control valve pressure relief pipe 11 connected to the main water supply pipe 1 is also arranged on one side of the float control valve 3. A solenoid valve 12 is arranged on the control valve pressure relief pipe 11, and the solenoid valve 12 is electrically connected to the pressure differential switch 10. In this way, the opening of the float control valve 3 is controlled by monitoring the pressure differential value of the pressure differential switch 10.

[0022] The method of using this embodiment is as follows:

[0023] In this embodiment, the water stored in the high-level water tank flows to each production line through the main water supply pipe 1. During this period, the water demand of the production line is sometimes small, and the main pipeline flowmeter 2 on the main water supply pipe 1 cannot accurately detect the water flow in the main water supply pipe 1 due to accuracy limitations. Therefore, when the water flow in the main water supply pipe 1 is small, the water in the main water supply pipe 1 passes through the float control valve 3. At this time, the water flow at the upper end of the float control valve 3 fills the entire pipeline under the action of gravity, while the water flow at the lower end of the float control valve 3 is small due to the valve opening of the float control valve 3. Correspondingly, the water pressure difference between the two ends of the float control valve 3 is also large.

[0024] Therefore, when the pressure differential switch 10 detects that the pressure difference at both ends of the float control valve 3 exceeds a preset pressure difference value, it is determined that the water demand of the production line is small at this time, and the main pipeline flowmeter 2 may have an inaccurate measurement problem. At this time, the pressure differential switch 10 sends a level signal to the solenoid valve 12. After the solenoid valve 12 receives the level signal, the solenoid valve 12 cooperates with the control valve pressure relief pipe 11 to adjust the pressure in the float control valve 3 to control the float control valve 3 to close, so that the water flow in the main water supply pipe 1 is forced to flow to the water supply bypass 8, and then the bypass flowmeter 9 with a smaller diameter arranged on the water supply bypass 8 realizes accurate detection of water consumption. After the water flows through the main water supply pipe 1 or the water supply bypass 8, it flows to various parts of the production line through multiple production water supply management lines. During this process, the water flow of the main water supply pipe 1 can be cut off by the first gate valve 4, which is convenient for the disassembly and maintenance of the float control valve 3, or the water flow of the water supply bypass 8 can be cut off by the two second gate valves 5, which is convenient for the disassembly and inspection of the bypass flow meter 9, and the precise control of each production water supply pipeline 7 can be achieved by the third gate valve 6, so as to control the final flow direction of the water to meet the specific water demand of the production line.

[0025] The above is a detailed introduction to a large-diameter flow metering device for a high-level water tank provided by the utility model. The description of the specific embodiment is only used to help understand the method and core idea of ​​the utility model. It should be pointed out that for ordinary technicians in this technical field, without departing from the principle of the utility model, the utility model can also be improved and modified, and these improvements and modifications also fall within the scope of protection of the claims of the utility model.

Claims

1. A large-diameter flow meter for a high-level water tank, comprising a main water supply pipe, a main pipeline flow meter and a main pipeline control valve, characterized in that: The main pipeline flowmeter and the main pipeline control valve are arranged on the main water supply pipe. The main water supply pipe is also connected to a water supply bypass. The pipe diameter of the water supply bypass is smaller than that of the main water supply pipe. The water supply bypass is connected in parallel on both sides of the main pipeline control valve. A bypass flowmeter is arranged on the water supply bypass. Pressure differential switches are also connected in series on both sides of the main pipeline control valve. The pressure differential switch is used to control the opening of the main pipeline control valve.

2. The large-diameter flow metering device for a high-level water tank according to claim 1 is characterized in that: The main pipeline control valve is a float control valve, and a control valve pressure relief pipe connected to the main water supply pipe is also provided on one side of the float control valve. A solenoid valve is provided on the control valve pressure relief pipe, and the solenoid valve is electrically connected to the pressure difference switch.

3. The large-diameter flow metering device for a high-level water tank according to claim 1 is characterized in that: The main water supply pipe is also provided with a first gate valve, and the first gate valve is located between the main pipeline flow meter and the main pipeline control valve.

4. The large-diameter flow metering device for a high-level water tank according to claim 3 is characterized in that: A second gate valve is also provided on the water supply bypass.

5. The large-diameter flow metering device for a high-level water tank according to claim 4 is characterized in that: There are two second gate valves in total, and the two second gate valves are respectively arranged on both sides of the bypass flowmeter.

6. The large-diameter flow metering device for a high-level water tank according to claim 1 is characterized in that: The end of the main water supply pipe is also connected to a plurality of production water supply pipelines, and each of the production water supply pipelines is provided with a third gate valve.