Connecting structure for assembly of superposed beams
By arranging structures such as joint pouring troughs, pouring inner grooves and fixed blocks on the precast beams on both sides of the load-bearing wall, the problem of poor integrity of precast beams in the existing technology is solved, achieving stronger integrity and seismic performance, and simplifying installation process.
Patent Information
- Application Number
- CN202422338270.5
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-09-25
- Publication Date
- 2024-10-29
- Estimated Expiration
- 2034-09-25
AI Technical Summary
In the existing technology, the threaded connection between the prefabricated beams on both sides through threaded sleeves and strip steel bars results in troublesome installation and poor integrity, which cannot effectively improve the seismic performance.
Prefabricated beams on both sides are symmetrically distributed on both sides of the load-bearing wall, and structures such as joint pouring troughs, pouring inner grooves, fixed blocks, positioning steel bars, and pouring bulges are set up. Through the connection of the pouring inner grooves and the insertion of the fixed blocks, the structure increases Rebar perforations and through-grooves, expansion slots and inclined holes achieve a stronger overall connection.
The integrity and seismic performance of the precast beams on both sides are improved, the installation process is simplified, and the connectivity and stability of the beam structure are enhanced through concrete filling and solidification.
Smart Images

Figure CN221920004U_ABST
Abstract
Description
Technical Field
[0001] The utility model belongs to the technical field of composite beam assembly connection, in particular to an assembly connection structure of composite beams. Background Art
[0002] Prefabricated components are widely used in modern construction projects as a means to effectively improve construction efficiency. The use of composite components can reduce the weight of assembled components and make them easier to hoist. At the same time, due to the existence of post-poured concrete, the integrity of the structure is relatively good. Composite beams are reinforced concrete structural beams that are poured with concrete twice. The first time is made into a prefabricated beam in the prefabrication yard; the second time is carried out at the construction site. After the prefabricated beam is hoisted and placed, the upper concrete is poured to make it a whole.
[0003] In the actual construction process of a building project, it is sometimes necessary to set a beam structure on the top of the building's load-bearing wall to meet the building's support span requirements and load-bearing requirements. In the prior art, when a composite beam needs to be set on the top of a load-bearing wall, the composite beams on both sides of the wall are usually connected to the wall respectively.
[0004] For example, Chinese utility model patent CN211200709U discloses a composite beam connection structure in an assembled building, including two precast beams and a load-bearing wall located on the same straight line, the two precast beams are located above the load-bearing wall and are in contact with the top surface of the load-bearing wall, both ends of the precast beams in the length direction are provided with joint casting grooves, the joint casting grooves extend to the upper surface of the precast beams, the ends of the two precast beams close to each other are in contact, and when the end faces of the two precast beams are in contact, the joint casting grooves on the two precast beams are merged into a whole. The utility model has the effect of casting the composite beams on both sides of the load-bearing wall into a whole on the load-bearing wall by arranging the joint casting grooves, thereby improving the integrity of the beam structure and thus improving the seismic performance.
[0005] Although the above-mentioned existing technology can improve the earthquake resistance effect, the prefabricated beams on both sides are fixed by threading the threaded sleeves and the threaded ends of the strip steel bars together with the casting method. However, the above-mentioned connection and casting method through the threaded sleeves of the strip steel bars makes the prefabricated beams on both sides cast as a whole, and the integrity is poor. Utility Model Content
[0006] The purpose of this section is to summarize some aspects of the embodiments of the utility model and briefly introduce some preferred embodiments. Some simplifications or omissions may be made in this section and the abstract of the specification and the name of the utility model of this application to avoid blurring the purpose of this section, the abstract of the specification and the name of the utility model, and such simplifications or omissions cannot be used to limit the scope of the utility model.
[0007] In order to solve the problem proposed in the above background technology that the threaded connection between the prefabricated beams on both sides through the threaded sleeve and the threaded end of the bar steel bar combined with the casting method will make the installation of the prefabricated beams on both sides extremely troublesome, and the prefabricated beams on both sides are cast with poor integrity only through the connection and casting method of the bar steel bar threaded sleeve, the utility model adopts the following technical solution.
[0008] The two precast beams are symmetrically distributed on both sides of the load-bearing wall. An overlap groove is arranged on the upper end of the load-bearing wall. The bottom of the overlap groove is flush with the upper end surface of the support horns on both sides. A joint casting groove is arranged on the precast beams on both sides. A plurality of frame-shaped steel bars and a plurality of strip steel bars are arranged on the precast beams on both sides. A casting inner groove is arranged at the inner bottom of the joint casting groove where the precast beams on both sides are opposite to each other. The casting inner groove extends to the end of the precast beam. After the precast beams on both sides are butt-jointed at the position of the overlap groove, the casting inner grooves on both sides are connected to form a cavity. A fixed block is inserted in the cavity. A vertical casting protrusion is arranged in the casting inner groove. An inserting groove corresponding to the casting protrusion is opened at the bottom of the fixed block. After the fixed block is inserted, the casting protrusion extends into the inserting groove.
[0009] Preferably, a plurality of second positioning steel bars are passed through the inner bottom of the lap groove, a plurality of through holes are arranged inside the cast inner grooves on both sides, the second positioning steel bars pass through the through holes, and a plurality of plug-in holes corresponding to the second positioning steel bars are also arranged at the bottom of the fixed block, and the second positioning steel bars are inserted into the corresponding plug-in holes.
[0010] Preferably, the fixing block is provided with a penetrating communication groove, and the plug-in groove is communicated with the communication groove.
[0011] Preferably, a plurality of casting through grooves connected to the connecting groove are provided on the fixing block.
[0012] Preferably, one side of the cast inner groove on both sides is provided with an outwardly extending expansion slot, and the expansion slot allows a gap to exist between the fixed block and the expansion slot after the fixed block is inserted.
[0013] Preferably, the expansion slot is provided with a plurality of inclined casting holes which are inclined downward away from the inner casting groove.
[0014] Preferably, each casting inclined hole penetrates the precast beam.
[0015] Preferably, a plurality of first positioning steel bars extend through the upper ends of the supporting horns on both sides, and the plurality of first positioning steel bars pass upward from the bottom of the precast beam and reach the interior of the joint casting trough.
[0016] Preferably, a thread groove is processed at the end of each first positioning steel bar, and after the prefabricated beam is hoisted, the end of each first positioning steel bar is threadedly connected with a hexagonal nut.
[0017] Compared with the prior art, the beneficial effects of the utility model are:
[0018] 1. The inner grooves cast on both sides are connected after the precast beams on both sides are butted, so that during pouring, the concrete will fill the inner grooves and cooperate with the casting protrusions to make the integrity between the precast beams on both sides stronger.
[0019] 2. The setting of the fixed block allows the outer wall of the casting protrusion to be clamped by the plug-in grooves on both sides of the bottom of the fixed block during casting, thereby further increasing the integrity of the precast beams on both sides after casting.
[0020] 3. The second positioning steel bar is provided to pass through the multiple through holes and the fixing blocks inside the inner groove of the casting, so that the integrity between the precast beams on both sides and the load-bearing walls can be made stronger after casting.
[0021] 4. By setting the pouring through groove and the connecting groove, the concrete can enter the pouring through groove and the connecting groove during pouring, so that the integrity of the precast beams on both sides after pouring can be strengthened.
[0022] 5. The height of the fixed block is set to the height after the precast beams on both sides are poured. When pouring, the concrete only needs to exceed the upper end surface of the fixed block, which makes the pouring height easier to control and makes pouring more convenient.
[0023] 6. By setting up the expansion groove, during pouring, the concrete enters the expansion groove and then enters the inclined pouring hole, thereby further increasing the integrity of the precast beams on both sides after pouring. The inclined pouring hole penetrates the precast beams and connects with the outside, so that the concrete can better flow into the inclined pouring hole.
[0024] 7. By setting the first positioning steel bar, the lifting position of the precast beams on both sides can be positioned respectively. By connecting the hexagonal nut with the end of the first positioning steel bar through threads, the precast beams on both sides can be auxiliary fixed before pouring. During pouring, the first positioning steel bar and the hexagonal nut can make the integrity of the precast beams on both sides and the supporting horns on both sides stronger. BRIEF DESCRIPTION OF THE DRAWINGS
[0025] Figure 1 It is a schematic diagram of the connection structure of the assembly of a composite beam in the utility model;
[0026] Figure 2 This is a schematic diagram of the installation structure of the supporting horn and the prefabricated beam in the utility model;
[0027] Figure 3 For the utility model Figure 2 The enlarged structural diagram at A in the middle;
[0028] Figure 4This is a schematic diagram of the butt joint structure of prefabricated beams on both sides of the utility model;
[0029] Figure 5 This is a schematic diagram of the structure of the fixed block in the utility model;
[0030] Figure 6 It is a schematic diagram of the structure after the prefabricated beams on both sides of the utility model are cast.
[0031] The corresponding relationship between the illustrations and component names in the figure is as follows:
[0032] 100, load-bearing wall; 101, supporting horn; 102, first positioning steel bar; 103, hexagonal nut; 104, lap groove;
[0033] 200, precast beam; 201, frame-type steel bar; 202, cast inner groove; 203, cast protrusion; 204, cast inclined hole; 205, expansion slot; 206, through hole; 207, fixed block; 208, plug-in slot; 209, plug-in hole; 210, cast through slot; 211, connecting slot; 212, second positioning steel bar; 213, strip steel bar; 214, joint casting slot. DETAILED DESCRIPTION
[0034] In order to make the above-mentioned purposes, features and advantages of the present invention more obvious and easy to understand, the specific implementation methods of the present invention are described in detail below in conjunction with the accompanying drawings.
[0035] In the following description, many specific details are set forth to facilitate a full understanding of the present invention, but the present invention may also be implemented in other ways different from those described herein, and those skilled in the art may make similar generalizations without violating the connotation of the present invention. Therefore, the present invention is not limited to the specific embodiments disclosed below.
[0036] Secondly, the term "one embodiment" or "embodiment" as used herein refers to a specific feature, structure or characteristic that may be included in at least one implementation of the present invention. The term "in one embodiment" that appears in different places in this specification does not refer to the same embodiment, nor is it a separate or selective embodiment that is mutually exclusive with other embodiments. The present invention provides the following embodiments.
[0037] like Figure 1As shown, it is a schematic diagram of a connection structure of an assembled composite beam in a preferred embodiment of the utility model. The assembled connection structure of the composite beam in this embodiment includes two precast beams 200 and supporting horns 101 fixed on both sides of the load-bearing wall 100. The two precast beams 200 are symmetrically distributed on both sides of the load-bearing wall 100, and one end of the two precast beams 200 is respectively placed on the supporting horns 101 on both sides. A plurality of frame-shaped steel bars 201 and a plurality of strip steel bars 213 are arranged on the precast beams 200. A joint casting trough 214 is arranged on the precast beams 200. In this embodiment, the precast beams 200 on both sides are relatively placed on the upper ends of the supporting horns 101 on both sides by hoisting, and the precast beams 200 on both sides are cast into a whole by casting the inside of the joint casting trough 214. Figure 6 shown.
[0038] like Figure 2 As shown, a lap groove 104 is provided at the upper end of the load-bearing wall 100, and the bottom of the lap groove 104 is flush with the upper end surface of the supporting horns 101 on both sides. A plurality of first positioning steel bars 102 pass through the upper ends of the supporting horns 101 on both sides, and a threaded groove is processed at the end of each first positioning steel bar 102. The plurality of first positioning steel bars 102 pass upward from the bottom of the precast beam 200 and reach the interior of the joint casting groove 214. After the precast beam 200 is hoisted, the end of each first positioning steel bar 102 is threadedly connected with a hexagonal nut 103. In this embodiment, the hoisting position of the precast beam 200 can be positioned by setting a plurality of first positioning steel bars 102. The precast beam 200 can be auxiliary fixed before casting by threading the hexagonal nut 103 with the end of the first positioning steel bar 102. During casting, the first positioning steel bars 102 and the hexagonal nuts 103 can make the integrity of the precast beams 200 on both sides and the supporting horns 101 on both sides stronger.
[0039] like Figure 3-5As shown, the inner bottom of the joint casting groove 214 at the opposite side of the precast beams 200 on both sides is provided with a casting inner groove 202, and the casting inner groove 202 extends to the end of the precast beam 200, and the inner sides of the casting inner groove 202 are provided with vertical casting protrusions 203 upward; the precast beams 200 on both sides are butt-jointed at the position of the lap groove 104 so that the casting inner grooves 202 on both sides are connected to form a cavity, and a fixing block 207 is inserted in the cavity, and a 0.1-0. A gap of 3mm facilitates the smooth insertion of the fixing block 207 into the cavity. A plug-in groove 208 corresponding to the casting protrusion 203 is provided at the bottom of the fixing block 207. When the fixing block 207 is inserted into the cavity, the casting protrusion 203 extends into the plug-in groove 208. During casting, the plug-in groove 208 at the bottom of the fixing block 207 is stuck on the outer wall of the corresponding casting protrusion 203. The fixing block 207 is used to fix and connect the precast beams 200 on both sides, and the strength of the connection of the precast beams 200 is improved in conjunction with the later concrete pouring.
[0040] like Figure 3-5 As shown, a plurality of second positioning steel bars 212 pass through the inner bottom of the lap groove 104, and a plurality of through holes 206 are arranged inside the cast inner grooves 202 on both sides, and the second positioning steel bars 212 pass through the through holes 206. A plurality of plug-in holes 209 corresponding to the second positioning steel bars 212 are also arranged at the bottom of the fixed block 207. The second positioning steel bars 212 are inserted into the corresponding plug-in holes 209, and the second positioning steel bars 212 pass through the precast beams 200 and the fixed blocks 207 at the same time, so that the precast beams 200, the fixed blocks 207, and the load-bearing walls 100 on both sides are fixedly connected.
[0041] like Figure 5 As shown, the fixed block 207 is provided with a through connecting groove 211, and the plug-in groove 208 is connected with the connecting groove 211, so that the casting protrusion 203 extends into the plug-in groove 208 and then enters into the connecting groove 211, so that the casting protrusion 203 contacts the concrete entering into the connecting groove 211; the fixed block 207 is provided with a plurality of casting through grooves 210 connected with the connecting groove 211, so that the concrete can quickly enter into the connecting groove 211 from the casting through grooves 210, and the concrete entering into the fixed block 207 will prevent the fixed block 207 from shaking after solidification, and can also make the casting protrusion 203 in the fixed block 207 contact with the concrete and be bonded and fixed.
[0042] like Figure 5 As shown, the height of the fixed block 207 is set to the height of the precast beams 200 on both sides after pouring. When pouring, the concrete only needs to exceed the upper end surface of the fixed block 207, so that the pouring height is easier to control and pouring is more convenient.
[0043] like Figure 3As shown, an expansion slot 205 extending outward is provided on one side of the casting inner groove 202, and the expansion slot 205 allows a gap to exist between the fixed block 207 and the expansion slot 205 after being inserted, and a plurality of casting inclined holes 204 inclined downward away from the casting inner groove 202 are provided on the expansion slot 205, each casting inclined hole 204 penetrates the precast beam 200, and concrete enters the expansion slot 205, and then enters the interior of the casting inclined hole 204, and the concrete solidifies in the casting inclined hole 204, so that the cast precast beam 200 is fixed and supported from the inside, thereby improving the integrity after casting; the casting inclined hole 204 penetrates the precast beam 200 and is connected to the outside, so that the concrete can discharge the air inside the casting inclined hole 204 to the outside during casting, and can also discharge excess concrete, so that the concrete can flow into the interior of the casting inclined hole 204 better.
[0044] The above content is a further detailed description of the utility model in combination with specific implementation methods. It cannot be determined that the specific implementation of the utility model is limited to these descriptions. For ordinary technicians in the technical field to which the utility model belongs, without departing from the concept of the utility model, they can also make several simple deductions or substitutions, which should be regarded as belonging to the scope of protection determined by the claims submitted for the utility model.
Claims
1. A composite beam assembly connection structure, comprising two prefabricated beams (200) and supporting horns (101) fixed on both sides of a load-bearing wall (100), the two prefabricated beams (200) being symmetrically distributed on both sides of the load-bearing wall (100), a lap groove (104) being provided at the upper end of the load-bearing wall (100), the bottom of the lap groove (104) being flush with the upper end surfaces of the supporting horns (101) on both sides, a joint casting groove (214) being provided on the prefabricated beams (200) on both sides, a plurality of frame-shaped steel bars (201) and a plurality of strip steel bars (213) being provided on the prefabricated beams (200) on both sides, characterized in that: A vertical upward casting protrusion (203) is relatively arranged at the joint of the two side joint casting grooves (214), a fixed block (207) is arranged between the two side precast beams (200), a plug-in groove (208) corresponding to the casting protrusion (203) is opened at the bottom of the fixed block (207), and when the fixed block (207) is inserted into the cavity, the casting protrusion (203) extends into the plug-in groove (208), a plurality of second positioning steel bars (212) pass through the inner bottom of the lap groove (104), a plurality of through holes (206) are arranged inside the casting inner grooves (202) on both sides, and the second positioning steel bars (212) pass through the through holes (206), and a plurality of corresponding second positioning steel bars (212) are also arranged at the bottom of the fixed block (207). The second positioning steel bar (212) is inserted into the corresponding plug-in hole (209), and the inner bottom of the joint casting groove (214) at the opposite position of the precast beams (200) on both sides is provided with a casting inner groove (202), and the casting inner groove (202) extends to the end of the precast beam (200), and the casting protrusion (203) is located inside the casting inner groove (202). After the precast beams (200) on both sides are butt-jointed at the position of the lap groove (104), the casting inner grooves (202) on both sides are connected to form a cavity, and a gap is left between the outer wall of the fixed block (207) and the inner wall of the cavity. The fixed block (207) is provided with a penetrating connecting groove (211), and the plug-in groove (208) is connected with the connecting groove (211).
2. The composite beam assembly connection structure according to claim 1, characterized in that: The fixed block (207) is provided with a plurality of casting through grooves (210) which are connected to the connecting grooves (211).
3. The composite beam assembly connection structure according to claim 2, characterized in that: An extension groove (205) extending outward is provided on one inner wall of the cast inner groove (202) on both sides, and the extension groove (205) allows a gap to exist between the fixed block (207) and the extension groove (205) after being inserted.
4. The composite beam assembly connection structure according to claim 3, characterized in that: The expansion slot (205) is provided with a plurality of inclined casting holes (204) inclined downward away from the inner casting groove (202).
5. The composite beam assembly connection structure according to claim 4, characterized in that: Each casting inclined hole (204) penetrates the precast beam (200).
6. The composite beam assembly connection structure according to claim 5, characterized in that: A plurality of first positioning steel bars (102) pass through the upper ends of the supporting horns (101) on both sides, and the plurality of first positioning steel bars (102) pass upward from the bottom of the precast beam (200) and reach the interior of the joint casting trough (214).
7. The composite beam assembly connection structure according to claim 6, characterized in that: A threaded groove is processed at the end of each first positioning steel bar (102), and after the prefabricated beam (200) is hoisted, the end of each first positioning steel bar (102) is threadedly connected with a hexagonal nut (103).