Prestress anchoring slope surface reinforcing structure
By opening cross-distributed grouting holes on the slope surface and setting up anchors and reinforcement ribs, an inverted spinous structure is formed, the problem of insufficient friction resistance between the anchor rod and the slope rock and soil body is solved, and the anchoring force and structural stability are improved , reducing costs and grouting volume.
Patent Information
- Application Number
- CN202420129208.2
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-01-18
- Publication Date
- 2024-11-01
- Estimated Expiration
- 2034-01-18
AI Technical Summary
During slope reinforcement, the friction resistance between the anchors of anchors and anchor cables and the drilling holes of the slope rock and soil bodies is insufficient, resulting in limited tension resistance. When the strength of the slope rock and soil bodies becomes worse, the anchoring force is Gradually insufficient, existing solutions such as increasing the drilling diameter will increase costs and grouting volume.
Design a prestressed anchor slope reinforcement structure. By opening three sets of cross-distributed grouting holes on the surface of the slope, installing anchors and reinforcement ribs. The anchor rods and reinforcement ribs are coordinated to form an inverted spinous structure, which increases the anchoring force and Reduce the impact of soil loosening.
It effectively increases the reinforcement protection force of the anchor rod in the slope, reduces the drilling cost and grouting amount, improves the structural strength and stability, and solves the problem of insufficient anchoring force.
Smart Images

Figure CN221941385U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of slope reinforcement, in particular to a prestressed anchor slope reinforcement structure. Background Art
[0002] Anchor rods and anchor cable frame beams are widely used in slope reinforcement and protection projects. They are light reinforcement and protection structures with easy construction and generally good reinforcement and protection effects. However, when the soil slope or soft rock slope has poor rock mass and the slope reinforcement and protection is subjected to large forces, the tensile strength provided by the anchor rods and anchor cable reinforcement and protection becomes limited. It is generally manifested as insufficient friction resistance between the anchor body of the anchor rod or anchor cable and the drilled hole in the slope rock mass.
[0003] At present, the method of increasing the diameter of the drill hole is usually used to solve this problem. The main adverse effects are increased drilling costs, large grouting volume, and when the strength of the slope rock and soil gradually deteriorates, the anchoring force provided will gradually become insufficient.
[0004] Therefore, it is necessary to invent a prestressed anchor slope reinforcement structure to solve the above problems. Utility Model Content
[0005] The utility model aims to provide a prestressed anchor slope reinforcement structure to solve the problems of increased drilling cost, large grouting volume, and the anchoring force gradually becoming insufficient when the strength of the slope rock and soil gradually deteriorates.
[0006] In order to achieve the above-mentioned purpose, the utility model provides the following technical solutions: a prestressed anchor slope reinforcement structure, including a slope body, wherein a first grouting hole, a second grouting hole and a third grouting hole are opened on the surface of the slope body, and a first anchor body, a second anchor body and a third anchor body are respectively arranged inside the first grouting hole, the second grouting hole and the third grouting hole, two groups of reinforced anchor bodies are arranged on the surface of the first anchor body, an anchor rod is fixedly connected to the inside of the first anchor body, and an anchor head is fixedly connected to the upper end of the anchor rod.
[0007] By adopting the above technical solution, three groups of grouting holes are opened. The first grouting hole is the main grouting hole, and the interior of the hole is used to fix the anchor rod. The second and third grouting holes are auxiliary holes. Concrete is injected into the holes, and after the concrete solidifies, the first anchor body, the second anchor body, and the third anchor body are formed. The first anchor body, the second anchor body, and the third anchor body are cross-fixed inside the slope, thereby increasing the reinforcing and protective anchoring force of the anchor rod in the slope.
[0008] Optionally, the first grouting hole is opened in a direction perpendicular to the slope.
[0009] Optionally, the second grouting hole is opened along the upper left position of the first grouting hole, and the second grouting hole intersects with the bottom of the first grouting hole.
[0010] Optionally, the third grouting hole is opened along the upper right position of the first grouting hole, and the third grouting hole intersects with the middle of the first grouting hole.
[0011] By adopting the above technical solution, three groups of grouting holes are cross-distributed, the anchor bodies inside them are cross-fixed, and the second anchor body and the third anchor body form inverted thorns on the surface of the first anchor body, reducing the impact of soil loosening on the anchor body.
[0012] Optionally, a first reinforcing rib is fixedly connected to the interior of the second anchor body, and a second reinforcing rib is fixedly connected to the interior of the third anchor body.
[0013] By adopting the above technical solution, the slope body is reinforced by utilizing the tension of the anchor rod in cooperation with the first reinforcing rib and the second reinforcing rib.
[0014] Optionally, the lower ends of the first reinforcing rib and the second reinforcing rib are fixedly connected with sleeve rings.
[0015] By adopting the above technical solution, the anchor rod is inserted into the interior of the sleeve ring, which is more conducive to improving the connection strength between the three groups of anchor bodies.
[0016] Optionally, the sleeve ring is located at the intersection of the first grouting holes, and the sleeve ring is sleeved on the outside of the anchor rod.
[0017] Optionally, two groups of reinforcement blocks are fixedly connected to the surface of the anchor rod.
[0018] By adopting the above technical solution, the reinforcement block is located inside the reinforced anchor body, which effectively solves the problem of poor soil mass and insufficient anchoring force of the slope rock soil.
[0019] In the above technical solution, the technical effects and advantages provided by the utility model are:
[0020] 1. The utility model is provided with a first grouting hole, a second grouting hole and a third grouting hole on the surface of the slope, wherein the first grouting hole, the second grouting hole and the third grouting hole are respectively provided with a first anchoring body, a second anchoring body and a third anchoring body, wherein the first anchoring body is fixedly connected with an anchor rod inside, and the three groups of grouting holes are cross-distributed, wherein the anchoring bodies inside the first anchoring body are cross-fixed, and the second anchoring body and the third anchoring body form inverted thorns on the surface of the first anchoring body, and the first anchoring body, the second anchoring body and the third anchoring body are cross-fixed inside the slope, thereby increasing the reinforcing and protective anchoring force of the anchoring body in the slope, reducing the influence of soil loosening on the anchoring body, and solving the problems of increased drilling cost, large grouting amount, and the anchoring force provided gradually becoming insufficient when the strength of the rock and soil body of the slope gradually deteriorates;
[0021] 2. The utility model has an anchor rod fixedly connected inside the first anchor body, a first reinforcing rib fixedly connected inside the second anchor body, and a second reinforcing rib fixedly connected inside the third anchor body. The two groups of reinforcing ribs cooperate with the anchor rod to reinforce the three groups of anchor bodies, thereby improving the structural strength of the three groups of anchor bodies, and at the same time further improving the structural strength of the anchor rod, making the structure more stable. BRIEF DESCRIPTION OF THE DRAWINGS
[0022] Figure 1 It is a schematic diagram of the overall structure of the utility model;
[0023] Figure 2 It is a schematic diagram of the grouting hole structure of the utility model;
[0024] Figure 3 It is a schematic diagram of the anchor structure of the utility model;
[0025] Figure 4 This is a schematic diagram of the anchor rod structure of the utility model.
[0026] Description of reference numerals:
[0027] 1. Slope; 11. First grouting hole; 12. Second grouting hole; 13. Third grouting hole; 14. First anchoring body; 15. Second anchoring body; 16. Third anchoring body; 17. Reinforced anchoring body; 18. Anchor rod; 19. Reinforcement block; 110. First reinforcing rib; 111. Second reinforcing rib; 112. Sleeve ring; 113. Anchor head. DETAILED DESCRIPTION
[0028] In order to enable those skilled in the art to better understand the technical solution of the present invention, the present invention will be further described in detail below in conjunction with the accompanying drawings.
[0029] The utility model provides Figures 1 to 4A prestressed anchor slope reinforcement structure shown includes a slope body 1, a first grouting hole 11, a second grouting hole 12 and a third grouting hole 13 are opened on the surface of the slope body 1, a first anchor body 14, a second anchor body 15 and a third anchor body 16 are respectively arranged inside the first grouting hole 11, the second grouting hole 12 and the third grouting hole 13, two groups of reinforcing anchor bodies 17 are arranged on the surface of the first anchor body 14, an anchor rod 18 is fixedly connected inside the first anchor body 14, an anchor head 113 is fixedly connected to the upper end of the anchor rod 18, and two groups of reinforcing blocks 19 are fixedly connected to the surface of the anchor rod 18.
[0030] Among them, the second anchor body 15 and the third anchor body 16 extend obliquely to both sides around the first anchor body 14, increasing the pressure of the soil on the three groups of anchor bodies. During the upward pulling of the anchor rod 18, the surrounding soil will provide resistance to the second anchor body 15 and the third anchor body 16 to maintain the stability of the anchor rod 18. At the same time, the three groups of anchor bodies cooperate to improve the structural strength of the surrounding soil and reinforce the slope 1.
[0031] See also Figure 3 The first grouting hole 11 is opened along the vertical direction of the slope 1, the second grouting hole 12 is opened along the upper left position of the first grouting hole 11, and the second grouting hole 12 intersects with the bottom of the first grouting hole 11. The third grouting hole 13 is opened along the upper right position of the first grouting hole 11, and the third grouting hole 13 intersects with the middle of the first grouting hole 11.
[0032] Specifically, the three groups of grouting holes are cross-distributed, and the anchor bodies inside them are cross-fixed. The second anchor body 15 and the third anchor body 16 form inverted thorns on the surface of the first anchor body 14 to reduce the influence of soil loosening on the anchor bodies.
[0033] See also Figure 4 The interior of the second anchor body 15 is fixedly connected with the first reinforcement rib 110, and the interior of the third anchor body 16 is fixedly connected with the second reinforcement rib 111. The lower ends of the first reinforcement rib 110 and the second reinforcement rib 111 are fixedly connected with a sleeve ring 112. The sleeve ring 112 is located at the intersection of the first grouting hole 11, and the sleeve ring 112 is sleeved on the outside of the anchor rod 18.
[0034] At the same time, during the construction process, the main hole position is determined and the first grouting hole 11 is opened. Next, according to the position of the first grouting hole 11, a certain distance is moved to the upper left to open a second grouting hole 12. The second grouting hole 12 is inclined to one side of the first grouting hole 11, so that the lower end of the second grouting hole 12 is connected with the lower end of the first grouting hole 11. Then a third grouting hole 13 is opened in the upper right corner of the first grouting hole 11, and the lower end of the third grouting hole 13 is connected with the middle position of the first grouting hole 11. Then, the first reinforcing rib 110 and the second reinforcing rib 111 are laid in the second grouting hole 12 and the third grouting hole 13 respectively. Then, the anchor rod 18 is inserted into the first grouting hole 11, and the anchor rod 18 is inserted into the inner side of the two groups of sleeve rings 112. Finally, concrete is injected into the three groups of grouting holes. After the concrete solidifies, three groups of anchor bodies are formed to fix the anchor rod 18 and reinforce the slope 1 at the same time.
[0035] Working principle of the utility model: in order to increase the reinforcing and protective anchoring force of the anchor rod 18 in the slope body 1 and reduce the influence of soil loosening on the anchor body, three groups of grouting holes are opened on the surface of the slope body 1, and the anchor rod 18, the first reinforcing rib 110 and the second reinforcing rib 111 are respectively inserted into the three groups of grouting holes. After pouring concrete, three groups of anchor bodies are formed, and the three groups of anchor bodies are cross-fixed. The second anchor body 15 and the third anchor body 16 form barbs on the surface of the first anchor body 14, thereby increasing the reinforcing and protective anchoring force of the anchor rod 18 in the slope body 1 and reducing the influence of soil loosening on the anchor body.
[0036] The above shows and describes the basic principle, main features and advantages of the utility model. Those skilled in the art should understand that the utility model is not limited by the above embodiments, and the above embodiments and descriptions are only preferred examples of the utility model, and are not used to limit the utility model. Without departing from the spirit and scope of the utility model, the utility model may have various changes and improvements, and these changes and improvements fall within the scope of the utility model to be protected.
Claims
1. A prestressed anchor slope reinforcement structure, comprising a slope body (1), characterized in that: The surface of the slope body (1) is provided with a first grouting hole (11), a second grouting hole (12) and a third grouting hole (13); the first grouting hole (11), the second grouting hole (12) and the third grouting hole (13) are respectively provided with a first anchor body (14), a second anchor body (15) and a third anchor body (16); the surface of the first anchor body (14) is provided with two groups of reinforcing anchor bodies (17); the interior of the first anchor body (14) is fixedly connected with an anchor rod (18); the upper end of the anchor rod (18) is fixedly connected with an anchor head (113).
2. A prestressed anchor slope reinforcement structure according to claim 1, characterized in that: The first grouting hole (11) is opened in a direction perpendicular to the slope (1).
3. A prestressed anchor slope reinforcement structure according to claim 2, characterized in that: The second grouting hole (12) is opened along the upper left position of the first grouting hole (11), and the second grouting hole (12) intersects with the bottom of the first grouting hole (11).
4. A prestressed anchor slope reinforcement structure according to claim 3, characterized in that: The third grouting hole (13) is opened along the upper right position of the first grouting hole (11), and the third grouting hole (13) intersects with the middle of the first grouting hole (11).
5. The prestressed anchor slope reinforcement structure according to claim 1, characterized in that: The interior of the second anchor body (15) is fixedly connected to a first reinforcing rib (110), and the interior of the third anchor body (16) is fixedly connected to a second reinforcing rib (111).
6. A prestressed anchor slope reinforcement structure according to claim 5, characterized in that: The lower ends of the first reinforcing rib (110) and the second reinforcing rib (111) are both fixedly connected with a sleeve ring (112).
7. A prestressed anchor slope reinforcement structure according to claim 6, characterized in that: The sleeve ring (112) is located at the intersection of the first grouting holes (11), and the sleeve ring (112) is sleeved on the outside of the anchor rod (18).
8. The prestressed anchor slope reinforcement structure according to claim 1, characterized in that: Two groups of reinforcement blocks (19) are fixedly connected to the surface of the anchor rod (18).