Automatic pouring and curing production line for large aerial bombs
By designing an automated casting and curing production line, the safety and efficiency issues caused by manual operation of large aerial bombs were solved, achieving full automation and improving safety and production efficiency.
Patent Information
- Application Number
- CN202323662046.3
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2023-12-28
- Publication Date
- 2024-11-01
- Estimated Expiration
- 2033-12-28
AI Technical Summary
The casting and curing of existing large aerial bombs mainly rely on manual operation, which is unsafe, risky, and inefficient, and cannot meet the requirements of fixed personnel for safe production.
An automated casting and curing production line for large aerial bombs was designed, including a tiered heat preservation device, a vacuum casting device, and a tail screw assembly device. The aerial bombs are automatically transported by a conveying system and preheated and cast in the tiered heat preservation device and the vacuum casting device. The tail screw assembly device automatically installs the tail screws, realizing full automation of the process.
The process of casting and curing aerial bombs has been fully automated, improving safety and production efficiency and meeting the requirements for safe production.
Smart Images

Figure CN221945043U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of pyrotechnic production, in particular to an automatic pouring and curing production line for large-scale aerial bombs. Background Art
[0002] In recent years, with the rapid development of industrial automation production technology, the field of pyrotechnics has also gradually transitioned from a manual production model to an automated one. At present, the casting and curing of large domestic bombs are mainly completed by manual operations, which has poor safety, high risks, and low production efficiency. It does not meet the requirements of safe production quotas and personnel, and urgently needs a casting and curing production line with a higher degree of automation. Utility Model Content
[0003] Based on the above description, the utility model provides an automatic pouring and curing production line for large-scale aerial bombs to solve the problems of too many people involved in the charging process and low degree of automation.
[0004] The utility model solves the above technical problems with the following technical solutions: an automatic pouring and curing production line for large bombs, comprising:
[0005] Step-by-step thermal care device, including a thermal jacket to keep the bomb warm before pouring;
[0006] A vacuum pouring device including a multi-stage hopper for storing explosive slurry;
[0007] A tail screw assembly device, comprising a grasping and tightening mechanism for mounting the tail screw on the bomb;
[0008] The conveying system and the tail screw assembly device share a set of tracks. The conveying system conveys the bomb to move along a first track. The first track is connected to the cascade thermal insulation care device, the vacuum casting device, and the tail screw assembly device through the conveying system.
[0009] On the basis of the above technical solution, the present invention can also be improved as follows.
[0010] Furthermore, the conveying system includes a plate chain conveying device, a turning device, and a first transport rail vehicle, and the plate chain conveying device and the turning device are arranged on one side of the track, the plate chain conveying device and the turning device are close to the regional space, and the plate chain conveying device transfers the bomb to the work station of the turning device.
[0011] Furthermore, the step-by-step thermal insulation care device and the vacuum pouring device are also respectively connected to auxiliary power devices, and the auxiliary power device, the step-by-step thermal insulation care device, and the vacuum pouring device are arranged on the other side of the track.
[0012] Furthermore, the auxiliary power device includes a vacuum extraction device and a hot water circulation device for providing a heat source, and the cascade thermal insulation care device and the vacuum pouring device can be provided in multiple sets.
[0013] Furthermore, the flipping device includes a manipulator and a flipping mechanism. The manipulator is arranged at one end of the plate chain conveyor. When the bomb is located at the first position, the manipulator is connected to the bomb and transferred to the flipping mechanism. The flipping mechanism is connected to the bomb. At this time, the bomb is in a vertical state.
[0014] Furthermore, the first transport railcar includes a railcar and a grabbing and rotating mechanism. When the bomb is located at the second position, the grabbing and rotating mechanism is connected to the bomb, the bomb is in a horizontal state, and is transported to the tiered thermal insulation care device station by the railcar.
[0015] Furthermore, the step-by-step thermal insulation care device also includes a positioning seat, the thermal jacket is arranged on the positioning seat, the thermal jacket includes a plurality of independent compartments, and the plurality of compartments are independently connected to the hot water circulation device.
[0016] Furthermore, the vacuum casting device also includes a movable bracket, the multi-stage hoppers are connected to the explosives paddle, the movable bracket includes a first bracket and a second bracket, which are respectively arranged between the multi-stage hoppers; the multi-stage hoppers are a sandwich structure, and the hoppers include a degassing structure.
[0017] Furthermore, a slide rail is provided at the bottom of the vacuum pouring device, the vacuum pouring device is slidably connected to the slide rail, and the step-by-step thermal insulation care device is provided at the lower part of the slide rail.
[0018] Furthermore, the tail screw assembly device also includes a second transport rail car and a temporary storage rack for placing the tail screws. The temporary storage rack is arranged on a side close to the vacuum casting device, and the grabbing and tightening mechanism and the temporary storage rack are both arranged on the upper part of the second transport rail car.
[0019] Compared with the prior art, the technical solution of this application has the following beneficial technical effects:
[0020] This production line is equipped with a conveying system, a step-by-step thermal insulation and care device, a vacuum pouring device, and a tail screw assembly device. It can automatically transport the bomb to the designated position and adjust the bomb placement posture, preheat the bomb, and automatically pour the bomb. Finally, the bomb is assembled. The whole process has a high level of automation, the various devices are well coordinated, the design is reasonable, the safety level is high, and the entire process of pouring and curing of large bombs can be automated, with high production efficiency. BRIEF DESCRIPTION OF THE DRAWINGS
[0021] Figure 1A schematic diagram of the structure of an automatic pouring and curing production line for large-scale bombs provided by an embodiment of the utility model;
[0022] Figure 2 A schematic diagram of the plan layout of an automatic pouring and curing production line for large-scale bombs provided in an embodiment of the utility model;
[0023] Figure 3 for Figure 2 A is a partial enlarged schematic diagram;
[0024] Figure 4 for Figure 2 A partial enlarged schematic diagram of B in the middle;
[0025] Figure 5 for Figure 2 A partial enlarged schematic diagram of C in the middle;
[0026] Figure 6 This is a schematic diagram of the structure of the first transport rail vehicle in the utility model;
[0027] Figure 7 It is a structural schematic diagram of the turning device in the utility model;
[0028] Figure 8 It is a schematic diagram of the position structure of the tiered heat preservation and care device and the vacuum pouring device in the utility model;
[0029] Fig. 9 This is a schematic diagram of the structure of the tiered thermal insulation nursing device in the utility model from a first perspective;
[0030] Fig.10 for Fig. 9 Schematic diagram of the cross section along DD;
[0031] Fig.11 It is a second perspective structural diagram of the tiered thermal insulation care device in the present invention;
[0032] Fig.12 It is a schematic structural diagram of the vacuum casting device in the implementation of the utility model from the first perspective;
[0033] Fig.13 It is a second perspective structural schematic diagram of the vacuum casting device in the implementation of the utility model;
[0034] In the accompanying drawings, the components represented by the reference numerals are listed as follows:
[0035] 1. Plate chain conveyor; 11. Conveyor line; 2. Turning device; 21. Manipulator; 22. Turning mechanism; 3. First transport rail car; 31. Rail car; 32. Grasping and rotating mechanism; 4. Step-by-step thermal insulation and care device; 41. Heat jacket; 42. Positioning seat; 5. Vacuum casting device; 51. Hopper; 52. First bracket; 53. Second bracket; 54. Slide rail; 6. Tail screw assembly device; 61. Grasping and tightening mechanism; 62. Second transport rail car; 63. Temporary storage rack; 7. Bombs. DETAILED DESCRIPTION
[0036] In order to facilitate understanding of the present application, the present application will be described more fully below with reference to the relevant drawings. Embodiments of the present application are provided in the drawings. However, the present application can be implemented in many different forms and is not limited to the embodiments described herein. On the contrary, the purpose of providing these embodiments is to make the disclosure of the present application more thorough and comprehensive.
[0037] Unless otherwise defined, all technical and scientific terms used herein have the same meaning as those commonly understood by those skilled in the art to which this application belongs. The terms used herein in the specification of this application are only for the purpose of describing specific embodiments and are not intended to limit this application.
[0038] When used herein, the singular forms "a", "an" and "said / the" may also include plural forms, unless the context clearly indicates otherwise. It should also be understood that the terms "include / comprise" or "have" etc. specify the presence of stated features, wholes, steps, operations, components, parts or combinations thereof, but do not exclude the possibility of the presence or addition of one or more other features, wholes, steps, operations, components, parts or combinations thereof.
[0039] See also Figure 1-13 The utility model provides a technical solution: an automatic pouring and curing production line for large-scale bombs, including:
[0040] The stepwise heat preservation and care device 4 includes a heat jacket 41 for heat preservation of the bomb 7 before pouring;
[0041] The vacuum pouring device 5 includes a multi-stage hopper 51 for storing explosive slurry;
[0042] The tail screw assembly device 6 comprises a gripping and tightening mechanism 61 for mounting the tail screw on the bomb 7;
[0043] The conveying system and the tail screw assembly device 6 share a set of tracks. The conveying system conveys the bomb 7 to move along a first trajectory. The first trajectory is connected to the cascade thermal insulation care device 4, the vacuum casting device 5, and the tail screw assembly device 6 respectively through the conveying system.
[0044] It should be noted that the conveying system here can be used to automatically convey the bomb 7 to a designated position and adjust the placement posture of the bomb 7 relative to the conveying system; the step-by-step thermal insulation care device 4 can be used to preheat the bomb 7 before pouring to facilitate subsequent pouring, and perform step-by-step temperature control care on the bomb 7 in the overall pouring process; the vacuum pouring device 5 is used for automatically receiving, transporting, and vacuuming the explosive slurry and pouring it into the bomb 7.
[0045] Please refer to the attached Figure 2 In a specific embodiment, the conveying system includes a plate chain conveying device 1, a turning device 2, and a first transport rail vehicle 3, and the plate chain conveying device 1 and the turning device 2 are arranged on one side of the track, and the plate chain conveying device 1 and the turning device 2 are close to the regional space, and the plate chain conveying device 1 transfers the bomb 7 to the work station of the turning device 2.
[0046] It should be noted that the area close to the entrance of the workshop is referred to as the space close to the entrance of the workshop. The plate chain conveyor 1 and the flipping device 2 are arranged close to the entrance of the workshop to facilitate the transportation of the bomb 7 to the workshop to be put on line faster. The plate chain conveyor 1 is used to complete the putting on line of the bomb 7 and to transfer it. Specifically, the plate chain conveyor 1 includes a conveyor line 11. The bomb 7 is placed horizontally on the plate chain conveyor 1. That is, after the bomb 7 is put on line manually, the automatic program is started. The plate chain conveyor 1 automatically transports the bomb 7 to the flipping device 2 station through the conveyor line 11. The plate chain conveyor 1, the flipping device 2, and the first transport rail car 3 cooperate with each other to automatically transport the bomb 7 to the designated position, and flip the bomb 7 from the horizontal posture by 90° to the vertical posture, so as to make preliminary preparations for pouring. The plate chain conveyor 1 is used to complete the putting on line of the bomb 7, and can automatically run the bomb 7 to the station where the flipping device 2 is located. The plate chain conveyor device 1 can temporarily store the usage of the shift, and all the aerial bombs 7 can be manually hoisted to the conveying line 11 of the plate chain conveyor device 1 and then evacuated, and subsequent work can be completed automatically.
[0047] Furthermore, the step-by-step thermal insulation care device 4 and the vacuum pouring device 5 are also respectively connected to auxiliary power devices, and the auxiliary power device, the step-by-step thermal insulation care device 4 and the vacuum pouring device 5 are arranged on the other side of the track.
[0048] The auxiliary power device includes a vacuum device and an auxiliary power device for providing a heat source, and the step-by-step heat preservation care device 4 and the vacuum pouring device 5 can be provided with multiple sets. It should be noted that multiple sets can be provided to simultaneously perform care and pouring of the bomb 7, so as to increase the output.
[0049] Specifically, the hot water circulation device here mainly provides a heat source for the cascade temperature control care device and the vacuum pouring device 5, and the vacuum pumping device is used to vacuum the vacuum pouring device 5. The cascade heat preservation care device 4 and the vacuum pouring device 5 can be provided with multiple sets according to actual needs, and arranged in sequence on one side of the track, and can simultaneously preheat and pour the bomb 7 to increase production.
[0050] Please refer to the attached Figure 4 In a specific embodiment, the flipping device 2 includes a manipulator 21 and a flipping mechanism 22. The manipulator 21 is arranged at one end of the plate chain conveyor 11. When the bomb 7 is located at the first position, the manipulator 21 is connected to the bomb 7 and transferred to the flipping mechanism 22. The flipping mechanism 22 is connected to the bomb 7. At this time, the bomb 7 is in a vertical state.
[0051] It should be noted that the first position mentioned here refers to when the flip device 2 can detect the range of the bomb 7, the manipulator 21 automatically grabs the bomb 7 and transfers it to the flip mechanism 22, and the flip mechanism 22 flips the bomb 7 from the horizontal position by 90° to the vertical position, waiting for the first transport rail vehicle 3 to grab it. In other words, the manipulator 21 is arranged at the tail end of the plate chain conveyor 1, and when it detects that the bomb 7 is in place, it automatically grabs the bomb 7 and transfers it to the flip mechanism 22, and the flip mechanism 22 flips the bomb 7 from the horizontal position by 90° to the vertical position, waiting for the first transport rail vehicle 3 to grab it.
[0052] Please refer to the attached Figure 6 In a specific embodiment, the first transport rail vehicle 3 includes a rail vehicle 31 and a grabbing and rotating mechanism 32. When the bomb 7 is located at the second position, the grabbing and rotating mechanism 32 is connected to the bomb 7. The bomb 7 is in a horizontal state and is transported to the station of the tiered thermal insulation care device 4 by the rail vehicle 31.
[0053] It should be noted that the second position here refers to the bomb 7 being transported to the first transport rail car 3, the grabbing and rotating mechanism 32 automatically grabs the bomb 7, and transports it to the designated position through the rail car 31, and the grabbing and rotating mechanism 32 rotates the angle to transfer the bomb 7 to the station of the step-by-step thermal insulation and care device 4. In other words, the first transport rail car 3 runs to the station of the flipping device 2 to automatically grab the bomb 7 in a vertical posture, rotate it to the other side of the track, and then runs to the designated position, and rotates 180° to transfer the bomb 7 to the care station for preheating. It should be explained that the first trajectory includes multiple points, that is, multiple positions, including the first position and the second position mentioned here. And the bomb 7 is in contact with the step-by-step thermal insulation and care device, the vacuum casting device, and the tail screw assembly device at multiple positions.
[0054] Please refer to the attached Fig.11 In a specific embodiment, the cascade thermal insulation care device 4 also includes a positioning seat 42, the heat jacket 41 is arranged on the positioning seat 42, and the heat jacket 41 includes a plurality of independent compartments, and the plurality of compartments are independently connected to the hot water circulation device.
[0055] By controlling the hot water temperature of each section of the cabin, the preheating of the bomb 7 and the post-casting care are completed. The first transport rail vehicle 3 transfers the bomb 7 to the positioning seat 42, and the thermal jacket 41 is closed for preheating and care.
[0056] Please refer to the attached Fig.12 In a specific embodiment, the vacuum casting device 5 also includes a movable bracket, the multi-stage hopper 51 is connected to the explosive powder paddle, and the movable bracket includes a first bracket 52 and a second bracket 53, which are respectively arranged between the multi-stage hoppers 51; the multi-stage hoppers are a sandwich structure, and the hoppers include a degassing structure.
[0057] It should be noted that the explosive slurry is automatically transported to the multi-stage hopper 51 through a hanging chain, and the explosive slurry is automatically poured into the bomb 7 after being vacuumed twice.
[0058] Please refer to the attached Figure 8Specifically, the vacuum pouring device 5 is connected to the vacuum pumping device and the hot water circulation device, and cooperates to complete the automatic material receiving, transportation, and vacuum pumping of the explosive slurry, and pours the explosive slurry into the bomb 7. The multi-stage hopper 51 mentioned here can include multi-layer graded hoppers such as a primary hopper and a secondary hopper. In this embodiment, the multi-stage hopper 51 includes two hoppers arranged up and down, and the movable bracket includes a first bracket 52 and a second bracket 53, which are respectively arranged between and at the bottom of the two hoppers 51; the two hoppers 51 are sandwich structures, and are connected to the auxiliary power unit for heat flow circulation. The hopper 51 includes a degassing structure, and the lower part of the vacuum pouring device 5 is provided with the step-by-step thermal insulation care device 4. The gunpowder slurry flows down from the two hoppers 51 in sequence, and after degassing, it flows into the bomb 7 built into the step-by-step thermal insulation care device 4. That is to say, the explosive slurry can be automatically transported to the top of the vacuum pouring device 5, the first-level hopper cover is automatically opened, and then the explosive slurry is automatically introduced into the first-level hopper and flows into the second-level hopper. The movable bracket drives the first and second-level hoppers to be transported to the pouring station, sealed and docked with the bomb 7, and then the vacuum pumping device is started to vacuum the multi-level hopper 51. After two vacuum pumpings, the explosive slurry is automatically poured into the bomb 7 to complete the vacuum pouring.
[0059] Furthermore, by changing the temperature of each section of the cabin, the cast bomb 7 solidifies step by step from bottom to top, thereby completing the care of the bomb 7.
[0060] Furthermore, a slide rail 54 is provided at the bottom of the vacuum pouring device 5 , the vacuum pouring device 5 is slidably connected to the slide rail 54 , and the step-by-step thermal insulation care device 4 is provided at the lower part of the slide rail 54 .
[0061] That is to say, the vacuum pouring device 5 can slide along the slide rail 54 to the top of the step-by-step thermal insulation care device 4 and align with the bomb 7 in the heat jacket 41. It should be noted that the slide rail 51 is arranged at the lower part of the second bracket 53. After the step-by-step thermal insulation care device 4 detects that the bomb 7 is in place, the heat jacket 41 automatically closes and starts preheating the bomb 7. The first transport rail vehicle 3 releases the bomb 7 and then transports the next bomb 7. The step-by-step thermal insulation care device 4 completes the preheating of all the bombs 7 in sequence. And while the bomb 7 is preheating, the heat source also starts preheating the vacuum pouring device 5 to prepare for pouring. The step-by-step thermal insulation care device 4 can not only complete the preheating of the bomb 7 before pouring, but also complete the step-by-step temperature control care function of the bomb 7 according to the pouring process.
[0062] In a specific embodiment, the tail screw assembly device 6 also includes a second transport rail car 62 and a temporary storage rack 63 for placing the tail screw, the temporary storage rack 63 is arranged on a side close to the vacuum casting device 5, and the grabbing and tightening mechanism 61 and the temporary storage rack 63 are both arranged on the upper part of the second transport rail car 62. The grabbing and tightening mechanism 61 grabs the tail screw on the temporary storage rack 63, and the second transport rail car 62 runs to the top of the bomb 7, and the grabbing and tightening mechanism 61 tightens the tail screw onto the bomb 7. It should be noted that the grabbing and tightening mechanism 61 here can tighten the tail screw to a set torque value. The assembled bomb 7 is automatically transported to the next workstation by the first transport rail car 3.
[0063] Please refer to the attached Figure 2 It should be noted that the conveying system and the tail screw assembly device 6 share a set of tracks; the tail screw assembly device 6 can automatically complete the capture and transportation of the tail screw and install it on the bomb 7. The temporary storage rack 63 is placed next to the pouring station, so that the capture and tightening mechanism 61 can capture the tail screw on the temporary storage rack 63, and then move it to the top of the bomb 7 through the second transport rail car 62, and then tighten the tail screw onto the bomb 7.
[0064] Working principle: In the specific production process, the bomb 7 is manually transferred horizontally to the plate chain conveyor 1, and then the automatic program is started. The plate chain conveyor 1 automatically transports the bomb 7 to the turning device 2 station. After the turning device 2 detects that the bomb 7 is in place, the grabbing manipulator 21 of the turning device 2 transfers the bomb 7 to the turning mechanism 22. The turning mechanism 22 turns the bomb 7 in the horizontal posture 90° to the vertical posture, waiting for the first transport rail vehicle 3 to grab it. The first transport rail vehicle 3 runs to the turning station to grab the bomb 7 in the vertical posture, rotates it to the other side of the track, and transfers the bomb 7 to the corresponding nursing station. After the cascade heat preservation nursing device 4 detects that the bomb 7 is in place, the heat jacket 41 automatically closes and starts to preheat the bomb 7. The first transport rail vehicle 3 releases the bomb 7 and then transfers the next bomb 7, completing the preheating of all the bombs 7 in sequence. While the bomb 7 is preheated, the vacuum pouring device 5 is also preheated to prepare for pouring. The pre-prepared explosive slurry is automatically transported to the top of the vacuum pouring device 5 by a hanging chain or other automatic means, the first-level hopper cover is automatically opened, and then the slurry is automatically introduced into the first-level hopper. The vacuum pouring device 5 then automatically runs to the pouring station, seals and docks with the bomb 7, starts the vacuum pumping device, and the slurry automatically falls into the bomb 7 after two exhausts to complete the vacuum pouring. After pouring, the bomb 7 is solidified from bottom to top by changing the temperature of each layer of the cabin of the thermal jacket 41 of the step-by-step thermal insulation care device 4, thereby completing the care of the bomb 7. The tail screw assembly device 6 automatically grabs the tail screw on the temporary storage rack 63, then transports it to the top of the bomb 7, and then tightens the tail screw to the set torque value. The assembled bomb 7 is automatically transported to the next station by the first transport rail car 3.
[0065] By arranging the conveying system, the step-by-step heat preservation and care device 4, the vacuum pouring device 5, and the tail screw assembly device 6, the production line can automatically convey the bomb 7 to the specified position and adjust the placement posture of the bomb 7, preheat the bomb 7, and automatically pour it, and finally assemble the bomb 7. The whole process has a high level of automation, the various devices are well coordinated, the design is reasonable, the safety level is high, and the whole process of pouring and curing of large-scale bombs 7 can be automated, and the production efficiency is high.
[0066] The above description is only a preferred embodiment of the present invention and is not intended to limit the present invention. Any modifications, equivalent substitutions, improvements, etc. made within the spirit and principles of the present invention shall be included in the protection scope of the present invention.
Claims
1. An automatic pouring and curing production line for large bombs, characterized in that: include: Step-by-step thermal care device, including a thermal jacket to keep the bomb warm before pouring; A vacuum pouring device including a multi-stage hopper for storing explosive slurry; A tail screw assembly device, comprising a grasping and tightening mechanism for mounting the tail screw on the bomb; The conveying system and the tail screw assembly device share a set of tracks. The conveying system conveys the bomb to move along a first track. The first track is connected to the cascade thermal insulation care device, the vacuum casting device, and the tail screw assembly device through the conveying system.
2. The automatic pouring and curing production line for large bombs according to claim 1 is characterized in that: The conveying system includes a plate chain conveying device, a turning device, and a first transport rail vehicle, and the plate chain conveying device and the turning device are arranged on one side of the track. The plate chain conveying device and the turning device are close to the regional space, and the plate chain conveying device transfers the bomb to the work station of the turning device.
3. The automatic pouring and curing production line for large bombs according to claim 2 is characterized in that: The step-by-step thermal insulation care device and the vacuum pouring device are also respectively connected to auxiliary power devices, and the auxiliary power device, the step-by-step thermal insulation care device, and the vacuum pouring device are arranged on the other side of the track.
4. The automatic pouring and curing production line for large bombs according to claim 3 is characterized in that: The auxiliary power device comprises a vacuum pumping device and a hot water circulation device for providing a heat source, and the stepwise heat preservation and care device and the vacuum pouring device are provided in multiple sets.
5. The automatic pouring and curing production line for large bombs according to claim 2 is characterized in that: The flipping device includes a manipulator and a flipping mechanism. The manipulator is arranged at one end of the plate chain conveyor. When the bomb is located at the first position, the manipulator is connected to the bomb and transferred to the flipping mechanism. The flipping mechanism is connected to the bomb. At this time, the bomb is in a vertical state.
6. The automatic pouring and curing production line for large bombs according to claim 2 is characterized in that: The first transport railcar comprises a railcar and a grabbing and rotating mechanism. When the bomb is located at the second position, the grabbing and rotating mechanism is connected to the bomb. The bomb is in a horizontal state and is transported to the tiered thermal insulation and care device station by the railcar.
7. The automatic pouring and curing production line for large bombs according to claim 4 is characterized in that: The step-by-step thermal insulation nursing device also includes a positioning seat, the thermal jacket is arranged on the positioning seat, the thermal jacket includes multiple sections of independent cabins, and the multiple sections of the cabins are independently connected to the hot water circulation device.
8. The automatic pouring and curing production line for large bombs according to claim 1 is characterized in that: The vacuum casting device also includes a movable bracket, the multi-stage hoppers are connected to the explosives paddle, the movable bracket includes a first bracket and a second bracket, which are respectively arranged between the multi-stage hoppers; the multi-stage hoppers are sandwich structures, and the hoppers include a degassing structure.
9. The automatic pouring and curing production line for large bombs according to claim 7, characterized in that: A slide rail is arranged at the bottom of the vacuum pouring device, the vacuum pouring device is slidably connected to the slide rail, and the step-by-step heat preservation and care device is arranged at the lower part of the slide rail.
10. The automatic pouring and curing production line for large bombs according to claim 1, characterized in that: The tail screw assembly device also includes a second transport rail car and a temporary storage rack for placing the tail screws. The temporary storage rack is arranged on a side close to the vacuum casting device. The grabbing and tightening mechanism and the temporary storage rack are both arranged on the upper part of the second transport rail car.
Citation Information
Cited By
Automatic pouring and curing production line for large aerial bombs
CN117704904A