Turnover type PC component supporting rod pulling joint
By designing a turnaroundable PC component strut pulling point, the bent and welded anchor bars are combined with steel bars to achieve the rotation turnover of the tie rod, solving the high material and cost problems caused by disposable products, and reducing the Consumption of construction materials.
Patent Information
- Application Number
- CN202323449214.0
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2023-12-18
- Publication Date
- 2024-11-08
- Estimated Expiration
- 2033-12-18
AI Technical Summary
The existing PC component strut junction points are disposable products and cannot be used in turnover, resulting in high material consumption and high cost.
A rotatable PC component strut joint point including connecting rod, support rod, tie rod, sleeve and anchoring rib is designed. The anchoring rod can be bent and welded with the main structure steel bar, and the tie rod and sleeve are Threaded connection, can be screwed out for turnover after use.
Through bending and welding of anchor ribs, the stability of the sleeve is improved, and the turnover use of the pull-up rod is achieved through threaded connections, reducing material consumption and cost.
Smart Images

Figure CN221972681U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to a PC component support rod tie point, in particular to a rotatable PC component support rod tie point. Background Art
[0002] PC component brace tie points are a construction technology widely used in the field of construction, especially in prefabricated buildings. With the continuous development of building industrialization and standardization, PC component brace tie point technology has been more and more widely used. In traditional construction methods, the supporting structure of the building is usually composed of a reinforced concrete frame. The disadvantages of this method are long construction period, high construction difficulty, and high material consumption. In contrast, PC component brace tie points have the advantages of short construction period, material saving, and cost reduction. In China, with the promotion and popularization of building industrialization, PC component brace tie points have also been widely used. At present, PC component brace tie points are mainly embedded, that is, the pre-processed tie points are welded to the main structure steel bars before concrete pouring. After the concrete pouring is completed, the tie points are fixed by the strength of the concrete itself to form a tie force. After the brace is removed, the tie points are cut off to expose the part above the concrete surface. Therefore, this type of PC component brace tie points are disposable products and cannot be used in a turnover manner, which is not conducive to saving materials and costs. Utility Model Content
[0003] The main purpose of the utility model is to provide a rotatable PC component support rod tie point to solve the problem that the PC component support rod tie point proposed in the related art cannot be rotatably used, which is not conducive to saving materials and costs.
[0004] In order to achieve the above-mentioned object, according to one aspect of the utility model, a rotatable PC component support rod tie point is provided, comprising a connecting rod, one end of which is fixedly mounted with a support rod, and the other end of which is fixedly mounted with a connecting ring, and further comprising:
[0005] A tie rod, wherein a connecting ring is fixedly installed on the upper end of the tie rod, and the connecting ring is slidably installed on the connecting ring. A sleeve is provided at the other end of the tie rod, and anchor bars are fixedly installed on the side wall of the sleeve. The anchor bars are welded to the steel bars of the main structure, and the other end of the tie rod is threadedly connected to the sleeve, so that the tie rod can be easily removed after use, so as to be used in a turnover manner.
[0006] Furthermore, the anchoring bar can be bent, and a fixing bar is fixedly installed on the other end of the anchoring bar.
[0007] Furthermore, a separation groove is provided on the upper surface of the sleeve, and a clamping groove is provided in the separation groove.
[0008] Furthermore, a baffle is fixedly mounted on the side wall of the tie rod, a baffle cover is plugged and mounted on the tie rod, and the baffle cover is arranged between the baffle and the tie ring.
[0009] Furthermore, a clamping ring is fixedly installed at the edge of the shield.
[0010] Compared with the prior art, the utility model has the following beneficial effects:
[0011] In the rotatable PC component support rod tie point, anchor bars are fixedly installed on the side wall of the sleeve, the anchor bars are bent according to the needs of use, and then the bent anchor bars are welded to the main structure steel bars, and then the tie rod is screwed into the sleeve. After use, the tie rod can be screwed out for turnover use, which reduces the consumption of materials and further saves costs. BRIEF DESCRIPTION OF THE DRAWINGS
[0012] Figure 1 It is a schematic diagram of the overall structure of the tie-joint point of the rotatable PC component support rod;
[0013] Figure 2 It is a structural schematic diagram of a half-section view of the tie-joint point of the turnable PC component support rod;
[0014] Figure 3 for Figure 2 Schematic diagram of the structure enlarged at point A in the middle.
[0015] Illustrations: 1. Connecting rod; 101. Support rod; 102. Connecting ring; 2. Pull-connecting ring; 201. Tie rod; 202. Baffle; 203. Baffle; 204. Clamp; 3. Sleeve; 301. Anchor rib; 302. Fixing rib; 303. Partition groove; 304. Clamp groove. DETAILED DESCRIPTION
[0016] In order to further explain the technical means and effects adopted by the present invention to achieve the predetermined purpose of the utility model, the specific implementation method, structure, characteristics and effects of the present invention are described in detail below in combination with the accompanying drawings and preferred embodiments.
[0017] See also Figure 1-Figure 3 As shown, the purpose of this embodiment is to provide a rotatable PC component support rod tie point, including a connecting rod 1, a support rod 101 is fixedly installed at one end of the connecting rod 1, and a connecting ring 102 is fixedly installed at the other end of the support rod 101, and also includes:
[0018] A tie rod 201, a tie ring 2 is fixedly installed on the upper end of the tie rod 201, a connecting ring 102 is slidably installed on the tie ring 2, a sleeve 3 is provided at the other end of the tie rod 201, an anchor bar 301 is fixedly installed on the side wall of the sleeve 3, the anchor bar 301 is welded to the main structure steel bar, and the other end of the tie rod 201 is threadedly connected to the sleeve 3, so that the tie rod 201 is easy to remove after use, so as to be used in a turnover manner.
[0019] The anchoring rib 301 can be bent, and a fixing rib 302 is fixedly installed at the other end of the anchoring rib 301. By bending the anchoring rib 301, the angle between the anchoring rib and the horizontal direction is adjusted to improve the stability of the sleeve 3. By fixing the fixing rib 302 at the other end of the anchoring rib 301, the stability of the sleeve 3 is further improved.
[0020] A dividing groove 303 is provided on the upper surface of the sleeve 3, and a clamping groove 304 is provided in the dividing groove 303. A baffle 203 is fixedly installed on the side wall of the tie rod 201, and a blocking cover 202 is plugged and installed on the tie rod 201. The blocking cover 202 is arranged between the baffle 203 and the connecting ring 2, and a clamping ring 204 is fixedly installed on the edge of the blocking cover 202. In order to prevent concrete from entering the interior of the sleeve, which makes it difficult to separate the tie rod 201 and the sleeve 3, the blocking cover 202 is provided and connected to the upper end of the sleeve 3. At this time, the clamping ring 204 will be clamped in the clamping groove 304 to block the concrete and prevent the concrete from entering the interior of the sleeve 3.
[0021] When the utility model is used in practice, the fixing rib 302 is welded to one end of the anchor rib 301, and then the other ends of at least three anchor ribs 301 are fixedly welded to the side wall of the sleeve 3. Then, the anchor rib 301 is bent according to the thickness of the concrete to be laid on the construction site, and the anchor rib 301 is welded to the main structure steel bar. Then, the top of the sleeve 3 is kept level with the laid concrete surface. Then, one end of the tie rod 201 is threadedly connected to the sleeve 3, and at the same time, the baffle 202 is fitted with the upper surface of the sleeve 3, and the clamping ring 204 is clamped in the clamping groove 304 to block the concrete. At this time, the connecting ring 102 is connected to the connecting ring 2, and the connecting ring 102 can be supported at this time. After use, the tie rod 201 can be separated from the sleeve 3 by rotating the tie rod 201, and then it can be used in a turnover manner.
[0022] The above description is only a preferred embodiment of the present invention and does not constitute any form of limitation to the present invention. Although the present invention has been disclosed as a preferred embodiment as above, it is not intended to limit the present invention. Any technical personnel in this field can make some changes or modify the technical contents disclosed above into equivalent embodiments without departing from the scope of the technical solution of the present invention. However, any brief modifications, equivalent changes and modifications made to the above embodiments based on the technical essence of the present invention without departing from the content of the technical solution of the present invention are still within the scope of the technical solution of the present invention.
Claims
1. A rotatable PC component support rod tie point, comprising a connecting rod (1), one end of which is fixedly mounted with a support rod (101), characterized in that: The support rod (101) has a connecting ring (102) fixedly mounted on the other end thereof, and further comprises: A tie rod (201), wherein a tie ring (2) is fixedly installed on the upper end of the tie rod (201), and the connecting ring (102) is slidably installed on the tie ring (2). A sleeve (3) is provided at the other end of the tie rod (201), and an anchor bar (301) is fixedly installed on the side wall of the sleeve (3). The anchor bar (301) is welded to the main structural steel bar. The other end of the tie rod (201) is threadedly connected to the sleeve (3), so that the tie rod (201) is easy to remove after use.
2. The rotatable PC component support rod tie point according to claim 1 is characterized in that: The anchoring rib (301) can be bent, and a fixing rib (302) is fixedly mounted on the other end of the anchoring rib (301).
3. The rotatable PC component support rod tie point according to claim 1, characterized in that: A separation groove (303) is provided on the upper surface of the sleeve (3), and a clamping groove (304) is provided in the separation groove (303).
4. The rotatable PC component support rod tie point according to claim 1, characterized in that: A baffle (203) is fixedly mounted on the side wall of the tie rod (201), a baffle cover (202) is plugged and mounted on the tie rod (201), and the baffle cover (202) is arranged between the baffle plate (203) and the tie ring (2).
5. The rotatable PC component support rod tie point according to claim 4, characterized in that: A clamping ring (204) is fixedly mounted on the edge of the baffle (202).