Boiler flue gas desulfurization device
By adopting improved filter plate and nozzle assembly design in boiler flue gas desulfurization system, the desulfurization efficiency and flow area are improved, and the problems of low desulfurization efficiency and high NOX generation in existing systems are solved, and the filter and The service life of the circulation pump.
Patent Information
- Application Number
- CN202420224068.7
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-01-30
- Publication Date
- 2024-11-12
- Estimated Expiration
- 2034-01-30
AI Technical Summary
The desulfurization efficiency of the existing boiler flue gas desulfurization system is low, resulting in excessive consumption of limestone powder, increasing NOX production, increasing ash slag volume, insufficient flow area of the filter screen leads to reduced desulfurization efficiency and damage to the circulation pump.
Adopt a design including an absorption tower, a filter plate and a nozzle assembly. The filter plate has a 25mm aperture on the top of the filter plate. The nozzle assembly includes a single-head bidirectional, one-way bidirectional and one-way solid nozzles. By improving the flow area of the filter screen and spray coverage improve desulfurization efficiency.
It improves the desulfurization efficiency, reduces the consumption of limestone powder and NOX generation, extends the service life of the filter, and avoids damage to the circulation pump.
Smart Images

Figure CN221982013U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of desulfurization and purification, in particular to a boiler flue gas desulfurization device. Background Art
[0002] The desulfurization efficiency of the post-furnace desulfurization system is low, resulting in a large output of the in-furnace desulfurization system, excessive consumption of limestone powder, and a high amount of compressed air consumed for conveying limestone powder, which leads to increased power consumption of the air compressor. In addition, with the increase in limestone powder consumption, the amount of NOX generated in the furnace also increases, thereby increasing urea consumption. The increase in the use of limestone powder in the furnace also leads to a continuous increase in the amount of ash, which further increases the output of the boiler's slag and ash removal systems.
[0003] The filter size of the desulfurization absorption tower is 1716*1296*R648*4mm, the filter aperture is 20, the hole spacing is 25, the effective flow area is 2.355㎡, the DN1000 cross-sectional area is 0.785㎡, and the flow multiple is about 3 times, which does not meet the basic design requirement of the filter by more than 3.3 times. It can no longer meet the diversified and complex slurry in the absorption tower at this stage. Due to the small aperture, it is very easy to be blocked by impurities, lining rubber, detached scales and other debris, causing the filter to pass The flow area is not enough, which affects the desulfurization efficiency. At the same time, when the circulating pump is started and stopped, a large amount of slurry enters the pump body through the filter and hits the spray layer. Due to the insufficient flow area of the filter, it is easy to produce imbalance and uneven force, causing the filter to vibrate and cause the filter to fall off. When designing the inlet filter of the circulating pump, sufficient aperture and flow area should be considered. When the flow area of the filter is too small, the inlet resistance of the circulating pump will be too high, which will easily cause cavitation in the circulating pump, thereby causing damage to the circulating pump casing and impeller. Utility Model Content
[0004] The purpose of the utility model is to provide a boiler flue gas desulfurization device to solve the problems raised in the above background technology.
[0005] In order to achieve the above-mentioned purpose, the utility model provides the following technical solutions: a boiler flue gas desulfurization device, comprising an absorption tower body;
[0006] A filter plate is symmetrically installed at the bottom of the inner cavity of the absorption tower body, a nozzle assembly is arranged on the top of the filter plate, and a liquid supply assembly for installing and supplying liquid to the nozzle assembly is arranged on the absorption tower body, and the nozzle assembly includes:
[0007] A single-head bidirectional nozzle, wherein the single-head bidirectional nozzle is arranged in the middle of the inner cavity of the absorption tower;
[0008] A one-way double-ended nozzle, wherein the one-way double-ended nozzle is arranged on the side of the inner cavity of the absorption tower body;
[0009] A one-way solid nozzle is arranged on the side of the bottom of the inner cavity of the absorption tower body.
[0010] Preferably, the filter plate is in a semi-cylindrical shape as a whole, and a vertical downward sieve hole is opened on the top of the filter plate, the sieve hole has a pore diameter of 25 mm, and the sieve hole spacing is 30 mm.
[0011] Preferably, the liquid supply assembly comprises:
[0012] A liquid supply pipe, which is in a horizontal state and fixedly inserted and sleeved with the absorption tower body;
[0013] A delivery pipe, the delivery pipe is in a horizontal state and is fixedly connected to the liquid supply pipe in a vertical state;
[0014] A connecting assembly is arranged on the outer wall of the delivery pipe and is used for fixing and installing the nozzle assembly.
[0015] Preferably, the connection assembly comprises:
[0016] A connecting spiral tube, the end of which is fixedly inserted and sleeved with the outer wall of the conveying pipe;
[0017] A connecting sleeve and a connecting pipe, the nozzle assembly is communicated with the inner cavity of the connecting spiral tube through the connecting sleeve and the connecting pipe.
[0018] Preferably, an annular water storage cavity is provided inside the connecting sleeve, the connecting sleeve is slidably sleeved on the outer wall of the connecting spiral tube, the outer wall of the connecting spiral tube is provided with a through hole connected to the annular water storage cavity, and the inner wall of the annular water storage cavity is provided with a connecting hole connected to the connecting pipe.
[0019] Preferably, sealing gaskets are provided at the top and bottom of the connecting sleeve, and a sealing end cap for locking the connecting sleeve is threadedly sleeved on the outer wall of the connecting spiral tube, and the sealing end cap is used to seal the end of the connecting spiral tube.
[0020] Technical effects and advantages of the utility model:
[0021] The utility model utilizes the coordinated use of an absorption tower body, a filter plate, a nozzle assembly and a liquid supply assembly. The nozzle assembly includes a one-way double-head nozzle, a single-head two-way nozzle and a one-way solid nozzle. It can improve the slurry spray coverage in the absorption tower, thereby improving the desulfurization efficiency. By improving the filter plate, the flow area of the inlet filter is increased, thereby improving the desulfurization efficiency. BRIEF DESCRIPTION OF THE DRAWINGS
[0022] Figure 1 It is a schematic diagram of the top structure of the utility model.
[0023] Figure 2It is a schematic diagram of the internal structure of the front part of the connecting spiral tube of the utility model.
[0024] Figure 3 It is a schematic diagram of the overall structure of the one-way double-ended nozzle of the utility model.
[0025] Figure 4 It is a schematic diagram of the top structure of the single-head bidirectional nozzle of the utility model.
[0026] Figure 5 It is a schematic diagram of the top structure of the one-way solid nozzle of the utility model.
[0027] In the figure: 1. absorption tower body; 2. filter plate; 3. one-way double-head nozzle; 4. single-head two-way nozzle; 5. one-way solid nozzle; 6. liquid supply assembly; 61. liquid supply pipe; 62. delivery pipe; 63. connection assembly; 631. connecting spiral tube; 632. connecting sleeve; 633. connecting pipe; 634. annular water storage chamber; 635. through hole; 636. connecting hole; 637. sealing end cover. DETAILED DESCRIPTION
[0028] The following will be combined with the drawings in the embodiments of the utility model to clearly and completely describe the technical solutions in the embodiments of the utility model. Obviously, the described embodiments are only part of the embodiments of the utility model, not all of the embodiments. Based on the embodiments in the utility model, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the utility model.
[0029] The utility model provides Figure 1-5The boiler flue gas desulfurization device shown in the figure includes an absorption tower body 1. In order to avoid scaling inside the oxidation air duct in the absorption tower due to the high outlet temperature of the oxidation fan, which affects the slurry oxidation effect and reduces the desulfurization efficiency, cooling water is added to the eight oxidation air branches on the absorption tower body 1, that is, a cooling water system is added to the oxidation air inlet pipe of the absorption tower to prevent scaling in the oxidation air duct and reduce the flow area in the oxidation air duct, ensure that the oxidation air volume meets the design requirements, prevent the desulfurization efficiency of the absorption tower from being reduced, and effectively solve the scaling problem of the oxidation air duct. A filter plate 2 is symmetrically installed at the bottom of the inner cavity of the absorption tower body 1. The filter plate 2 is as a whole. It has a semi-cylindrical shape, and a vertical downward sieve hole is provided on the top of the filter plate 2. The sieve hole has an aperture of 25 mm and a hole spacing of 30 mm. The new filter ensures that the flow area is ≥ 330% of the inlet pipe of the circulation pump, thereby solving the problem of reduced desulfurization efficiency caused by reduced slurry circulation volume due to filter blockage, and the flow area of the filter plate 2 is increased to 3.9 times the area of the inlet pipe of the slurry circulation pump. A nozzle assembly is arranged on the top of the filter plate 2, and a liquid supply assembly 6 for installing and supplying liquid to the nozzle assembly is arranged on the absorption tower body 1, and the number of liquid supply assemblies 6 is four, so that the nozzle assembly inside the absorption tower body 1 is divided into four layers.
[0030] In particular, the nozzle assembly includes a single-head bidirectional nozzle 4, a unidirectional double-head nozzle 3 and a unidirectional solid nozzle 5. The ends of the single-head bidirectional nozzle 4, the unidirectional double-head nozzle 3 and the unidirectional solid nozzle 5 are respectively fixedly connected to different connecting pipes 633. The single-head bidirectional nozzle 4 is arranged in the middle of the inner cavity of the absorption tower body 1, the unidirectional double-head nozzle 3 is arranged on the side of the inner cavity of the absorption tower body 1, and the unidirectional solid nozzle 5 is arranged on the side of the bottom of the inner cavity of the absorption tower body 1. The number of original single-layer nozzles is increased from 117 to 160, and 6 nozzles are added to each spray layer according to the distribution of flue gas flow direction. The angles of all nozzles are installed strictly as required. During the installation process, The angle of the nozzle is adjusted according to the actual situation on site to prevent scouring and leakage on the tower wall and beam. The single-head two-way nozzle 4 has strong atomization and desulfurization performance. Therefore, it is designed that all single-head two-way nozzles 4, 116 in number, are arranged in the middle position of the spray layer of the absorption tower. The peripheral spray is close to the tower wall. In order to prevent the nozzle from scouring the tower wall, the nozzle adopts one-way double-head nozzle 3, 44 in number. Since the fourth spray layer is close to the demister, in order to prevent the demister from being blocked, the middle area of the fourth spray layer adopts single-head two-way nozzle 4, 116 in number, and the peripheral area of the absorption tower adopts one-way solid nozzle 5, 44 in number.
[0031] Furthermore, the liquid supply assembly 6 includes a liquid supply pipe 61, a delivery pipe 62 and a connecting assembly 63. The liquid supply pipe 61 is in a horizontal state and is fixedly inserted and sleeved with the absorption tower body 1. The delivery pipe 62 is in a horizontal state and is fixedly connected to the liquid supply pipe 61 in a vertical state. The connecting assembly 63 is arranged on the outer wall of the delivery pipe 62. The connecting assembly 63 is used to fix the nozzle assembly. The liquid supply pipe 61 can supply liquid to the nozzle assembly through multiple delivery pipes 62 and connecting assemblies 63.
[0032] Furthermore, the connecting assembly 63 includes a connecting coil 631, a connecting sleeve 632 and a connecting pipe 633. The end of the connecting coil 631 is fixedly inserted and sleeved with the outer wall of the delivery pipe 62. The nozzle assembly is communicated with the inner cavity of the connecting coil 631 through the connecting sleeve 632 and the connecting pipe 633, and the ends of the connecting pipe 633 are respectively fixedly connected to the nozzle assembly and the connecting sleeve 632. An annular water storage cavity 634 is provided inside the connecting sleeve 632. The connecting sleeve 632 is slidably sleeved on the outer wall of the connecting coil 631. The outer wall of the connecting coil 631 is provided with a through hole 635 that is communicated with the annular water storage cavity 634. The inner wall of the annular water storage cavity 634 is provided with a through hole 635 that is communicated with the annular water storage cavity 634. A connecting hole 636 connected to the connecting pipe 633 is provided, that is, the connecting spiral tube 631, the through hole 635, the annular water storage chamber 634, the connecting hole 636 and the connecting tube 633 form a liquid supply circulation pipeline for the nozzle assembly, and sealing gaskets are provided on the top and bottom of the connecting sleeve 632. The outer wall of the connecting spiral tube 631 is threadedly sleeved with a sealing end cover 637 that locks the connecting sleeve 632, and the sealing end cover 637 is used to seal the end of the connecting spiral tube 631. The sealing end cover 637 can fix the connecting sleeve 632. Loosening the sealing end cover 637 can make the connecting sleeve 632 rotate relative to the connecting spiral tube 631, thereby adjusting the angle of the nozzle assembly.
[0033] Finally, it should be noted that the above is only a preferred embodiment of the present invention and is not intended to limit the present invention. Although the present invention has been described in detail with reference to the aforementioned embodiments, those skilled in the art can still modify the technical solutions described in the aforementioned embodiments or make equivalent substitutions for some of the technical features therein. Any modifications, equivalent substitutions, improvements, etc. made within the spirit and principles of the present invention should be included in the protection scope of the present invention.
Claims
1. A boiler flue gas desulfurization device, comprising an absorption tower body (1); It is characterized in that A filter plate (2) is symmetrically mounted at the bottom of the inner cavity of the absorption tower body (1), a nozzle assembly is arranged on the top of the filter plate (2), and a liquid supply assembly (6) for mounting the nozzle assembly and supplying liquid is arranged on the absorption tower body (1), the nozzle assembly comprising: A single-head bidirectional nozzle (4), wherein the single-head bidirectional nozzle (4) is arranged in the middle of the inner cavity of the absorption tower body (1); A one-way double-ended nozzle (3), wherein the one-way double-ended nozzle (3) is arranged on the side of the inner cavity of the absorption tower body (1); A one-way solid nozzle (5), wherein the one-way solid nozzle (5) is arranged on the side of the bottom of the inner cavity of the absorption tower body (1).
2. A boiler flue gas desulfurization device according to claim 1, characterized in that: The filter plate (2) is in a semi-cylindrical shape as a whole, and a sieve hole is provided vertically downward on the top of the filter plate (2), the sieve hole has a hole diameter of 25 mm, and the hole spacing of the sieve hole is 30 mm.
3. A boiler flue gas desulfurization device according to claim 1, characterized in that: The liquid supply component (6) comprises: A liquid supply pipe (61), the liquid supply pipe (61) being in a horizontal state and fixedly inserted and sleeved with the absorption tower body (1); A delivery pipe (62), wherein the delivery pipe (62) is in a horizontal state and is fixedly connected to the liquid supply pipe (61) in a vertical state; A connecting assembly (63), wherein the connecting assembly (63) is arranged on the outer wall of the delivery pipe (62), and the connecting assembly (63) is used to fix the nozzle assembly.
4. A boiler flue gas desulfurization device according to claim 3, characterized in that: The connection component (63) comprises: A connecting spiral tube (631), the end of which is fixedly inserted and sleeved with the outer wall of the delivery tube (62); A connecting sleeve (632) and a connecting pipe (633), wherein the nozzle assembly is in communication with the inner cavity of the connecting spiral tube (631) via the connecting sleeve (632) and the connecting pipe (633).
5. A boiler flue gas desulfurization device according to claim 4, characterized in that: An annular water storage cavity (634) is provided inside the connecting sleeve (632), the connecting sleeve (632) is slidably sleeved on the outer wall of the connecting spiral tube (631), a through hole (635) communicating with the annular water storage cavity (634) is provided on the outer wall of the connecting spiral tube (631), and a connecting hole (636) communicating with the connecting tube (633) is provided on the inner wall of the annular water storage cavity (634).
6. A boiler flue gas desulfurization device according to claim 4, characterized in that: The top and bottom of the connecting sleeve (632) are both provided with sealing gaskets, and the outer wall of the connecting spiral tube (631) is threadedly sleeved with a sealing end cover (637) that locks the connecting sleeve (632), and the sealing end cover (637) is used to seal the end of the connecting spiral tube (631).