Road and bridge construction change monitoring structure
By improving the monitoring structure for road and bridge construction, and replacing infrared measurement with connecting rods and support plates, combined with adjustment and protection measures, the problem of infrared measurement being susceptible to environmental influences has been solved, achieving higher monitoring accuracy and stability.
Patent Information
- Application Number
- CN202420336606.1
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-02-22
- Publication Date
- 2024-11-12
- Estimated Expiration
- 2034-02-22
AI Technical Summary
Existing settlement monitoring devices mainly use infrared measurement for detection. The infrared rays emitted by the devices are easily affected by the environment, resulting in detection errors and affecting the accuracy of settlement detection.
The monitor uses a connecting rod and support plate structure at the bottom of the instrument body. Signal transmission is achieved through a push-button switch, replacing the infrared measurement method. The support plate height is adjusted by a bidirectional screw, screw sleeve, crank, and wheel. Guide bars and damping plates are set to limit the connection and provide protection, thereby enhancing connection stability and elastic reset effect.
It improves monitoring accuracy, prevents detection errors caused by environmental influences, features an adjustable support plate height, enhances connection stability, reduces vibration impact, and has an elastic reset function.
Smart Images

Figure CN221992671U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of road and bridge construction, in particular to a road and bridge construction change monitoring structure. Background Art
[0002] Road and bridge construction is a complex project involving multiple links and factors, so it requires careful organization and execution. Before construction, the construction site needs to be cleaned and leveled to ensure smooth construction. At the same time, construction materials need to be inspected and accepted to ensure that they meet design requirements and relevant standards. Before construction, the construction site needs to be cleaned and leveled to ensure smooth construction. Construction materials need to be inspected and accepted.
[0003] In order to ensure compliance with design requirements and relevant standards, it is necessary to determine the settlement effect during road and bridge construction. For example, the patent number disclosed on the China Patent Network is: 202223009341.4, and the patent name is: A bridge settlement monitoring device, including a monitoring device, an information nameplate is connected to the upper end of the monitoring device, a wire body is connected to the upper end of the monitoring device, and a connecting structure is connected to one side of the monitoring device. The connecting structure includes a protective plate, a protective plate is connected to one side of the monitoring device, and a support frame is connected to the upper end of the protective plate. A connecting sleeve is connected to one side of the monitoring device, and a connecting sleeve is embedded in the interior of the connecting sleeve and connected with a connecting tube, and a metal conductor is embedded in the interior of the connecting tube and connected with a positioning sleeve. The end of the metal conductor is connected to a connecting block. The utility model provides a bridge settlement monitoring device, which makes the connection more firm, wherein after the connection, pulling can be avoided to cause the wire body to break. After pulling, the sliding between the connecting block and the slide bar is adjusted to have a certain degree of buffering effect, which can better protect the wire body and avoid excessive pulling of the wire body and cause breakage.
[0004] However, the existing settlement monitoring devices mainly perform detection through infrared measurement. The infrared rays emitted by the equipment to the outside are easily affected by the environment and may cause detection errors, which may easily affect the accuracy of settlement detection.
[0005] Therefore, it is necessary to design and transform the monitoring structure of road and bridge construction changes. Utility Model Content
[0006] In order to solve the problems raised in the above-mentioned background technology, the purpose of the utility model is to provide a road and bridge construction change monitoring structure, which has the advantage of improving monitoring accuracy and solves the problem that the existing settlement monitoring device mainly performs detection through infrared measurement, and the infrared rays emitted by the equipment to the outside are easily affected by the environment and cause detection errors, which makes the settlement detection accuracy easily affected.
[0007] To achieve the above-mentioned purpose, the utility model provides the following technical solutions: a road and bridge construction change monitoring structure, including a monitoring instrument body;
[0008] A measuring structure is provided at the bottom of the monitoring instrument body;
[0009] The bottom of the monitoring instrument body is provided with an adjustment structure for connecting the measurement structure;
[0010] The measuring structure includes a push switch electrically connected to the bottom of the monitor body, a pressure plate is provided at the bottom of the monitor body, the pressure plate is located at the bottom of the push switch, a connecting rod is fixedly connected to the bottom of the pressure plate, a support plate is provided on the side of the connecting rod away from the pressure plate, a support frame is fixedly connected to the bottom of the monitor body, the support frame is sleeved on the surface of the connecting rod, the connecting rod and the support frame are slidably connected, and the connecting rod and the support plate are connected by an adjustment structure.
[0011] As a preferred embodiment of the utility model, the adjustment structure includes a connecting frame fixedly connected to the bottom end of the connecting rod, a bidirectional screw is movably connected to the interior of the connecting frame via a bearing, the left and right sides of the surface of the bidirectional screw are threadedly connected with screw sleeves, the front and back sides of the screw sleeve are movably connected with cranks via a pin, the side of the crank away from the screw sleeve is movably connected to the surface of the support plate via a pin, the left end of the bidirectional screw passes through the connecting frame and extends to the left side of the connecting frame, a rotating wheel is provided on the left side of the connecting frame, and the left end of the bidirectional screw is fixedly connected to the right side of the rotating wheel.
[0012] As a preferred embodiment of the utility model, a guide bar is fixedly connected to the interior of the connecting frame, and the guide bar extends to the interior of the screw sleeve from a side away from the connecting frame, and the screw sleeve and the guide bar are slidably connected.
[0013] As a preferred embodiment of the present invention, a damping plate is fixedly connected to the bottom of the support plate, and the interior of the damping plate is configured to be hollow.
[0014] As a preferred embodiment of the present invention, the left side and the right side of the connecting rod are fixedly connected with reinforcing ribs, and the side of the reinforcing rib away from the connecting rod is fixedly connected to the top of the connecting frame.
[0015] As a preferred embodiment of the utility model, the surface of the connecting rod is fixedly connected to an extension ring located inside the support frame, the top of the extension ring is fixedly connected to a compression spring sleeved on the surface of the connecting rod, and the top of the compression spring contacts the bottom of the monitoring instrument body.
[0016] Compared with the prior art, the beneficial effects of the utility model are as follows:
[0017] 1. The utility model transmits the downward force through the connecting rod and uses the pressure plate to squeeze the press switch. The press switch sends an alarm signal to the monitor body and warns. The utility model can improve the measurement method of the existing settlement monitoring device, replace the detection by infrared measurement, prevent the infrared rays emitted by the equipment to the outside from being affected by the environment and causing detection errors, and avoid affecting the accuracy of settlement detection.
[0018] 2. The utility model provides a bidirectional screw, a screw sleeve, a crank and a rotating wheel, so that the user can flexibly adjust the height of the support plate and the support plate can be in contact with the ground.
[0019] 3. The utility model can limit the screw sleeve by setting the guide strip, so as to avoid the screw sleeve from tilting during the movement.
[0020] 4. The utility model can protect the support plate and reduce the impact of external vibration on it by arranging the damping plate.
[0021] 5. The utility model can improve the connection stability between the connecting rod and the connecting frame by arranging reinforcing ribs, and prevent the connection between the two from becoming loose.
[0022] 6. The utility model can support the connecting rod by providing an extension ring and a compression spring, so that the connecting rod has an elastic reset effect. BRIEF DESCRIPTION OF THE DRAWINGS
[0023] Figure 1 It is a schematic diagram of the structure of the utility model;
[0024] Figure 2 This is a schematic diagram of the main structure of the utility model;
[0025] Figure 3 It is a three-dimensional schematic diagram of the local structure of the utility model.
[0026] In the figure: 1. Monitor body; 2. Measuring structure; 3. Adjusting structure; 4. Push switch; 5. Pressing plate; 6. Connecting rod; 7. Support plate; 8. Support frame; 9. Connecting frame; 10. Bidirectional screw; 11. Screw sleeve; 12. Crank; 13. Rotating wheel; 14. Guide strip; 15. Damping plate; 16. Reinforcing rib; 17. Extension ring; 18. Compression spring. DETAILED DESCRIPTION
[0027] The following will be combined with the drawings in the embodiments of the utility model to clearly and completely describe the technical solutions in the embodiments of the utility model. Obviously, the described embodiments are only part of the embodiments of the utility model, not all of the embodiments. Based on the embodiments in the utility model, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the utility model.
[0028] like Figures 1 to 3 As shown, the utility model provides a road and bridge construction change monitoring structure, including a monitoring instrument body 1;
[0029] A measuring structure 2 is provided at the bottom of the monitoring instrument body 1;
[0030] The bottom of the monitoring instrument body 1 is provided with an adjustment structure 3 for connecting the measurement structure 2;
[0031] The measuring structure 2 includes a push switch 4 electrically connected to the bottom of the monitoring instrument body 1, a pressure plate 5 is arranged at the bottom of the monitoring instrument body 1, the pressure plate 5 is located at the bottom of the push switch 4, a connecting rod 6 is fixedly connected to the bottom of the pressure plate 5, a support plate 7 is arranged on the side of the connecting rod 6 away from the pressure plate 5, a support frame 8 is fixedly connected to the bottom of the monitoring instrument body 1, the support frame 8 is sleeved on the surface of the connecting rod 6, the connecting rod 6 and the support frame 8 are slidably connected, and the connecting rod 6 and the support plate 7 are connected through the adjustment structure 3.
[0032] refer to Figure 3 The adjusting structure 3 includes a connecting frame 9 fixedly connected to the bottom end of the connecting rod 6, a bidirectional screw 10 is movably connected to the interior of the connecting frame 9 through a bearing, a screw sleeve 11 is threadedly connected to the left and right sides of the surface of the bidirectional screw 10, a crank 12 is movably connected to the front and back sides of the screw sleeve 11 through a pin, and the side of the crank 12 away from the screw sleeve 11 is movably connected to the surface of the support plate 7 through a pin, the left end of the bidirectional screw 10 passes through the connecting frame 9 and extends to the left side of the connecting frame 9, a rotating wheel 13 is arranged on the left side of the connecting frame 9, and the left end of the bidirectional screw 10 is fixedly connected to the right side of the rotating wheel 13.
[0033] As a technical optimization solution of the utility model, by providing a bidirectional screw 10, a screw sleeve 11, a crank 12 and a rotating wheel 13, it is convenient for the user to flexibly adjust the height of the support plate 7, so that the support plate 7 can contact the ground.
[0034] refer to Figure 3 A guide bar 14 is fixedly connected to the interior of the connecting frame 9 , and the guide bar 14 extends to the interior of the screw sleeve 11 from a side away from the connecting frame 9 , and the screw sleeve 11 and the guide bar 14 are slidably connected.
[0035] As a technical optimization solution of the present invention, by providing the guide strip 14, the screw sleeve 11 can be limited to avoid the screw sleeve 11 from tilting during the movement.
[0036] refer to Figure 3 A damping plate 15 is fixedly connected to the bottom of the support plate 7, and the interior of the damping plate 15 is configured to be hollow.
[0037] As a technical optimization solution of the present invention, by providing a damping plate 15, the support plate 7 can be protected to reduce the impact of external vibrations thereon.
[0038] refer to Figure 2 The left and right sides of the connecting rod 6 are fixedly connected with reinforcing ribs 16 , and the side of the reinforcing rib 16 away from the connecting rod 6 is fixedly connected to the top of the connecting frame 9 .
[0039] As a technical optimization solution of the present invention, by providing the reinforcing ribs 16, the connection stability between the connecting rod 6 and the connecting frame 9 can be improved to prevent the connection between the two from becoming loose.
[0040] refer to Figure 2 The surface of the connecting rod 6 is fixedly connected with an extension ring 17 located inside the support frame 8, and the top of the extension ring 17 is fixedly connected with a compression spring 18 sleeved on the surface of the connecting rod 6, and the top of the compression spring 18 contacts the bottom of the monitoring instrument body 1.
[0041] As a technical optimization solution of the present invention, by providing the extension ring 17 and the compression spring 18, the connecting rod 6 can be supported so that the connecting rod 6 has an elastic reset effect.
[0042] The working principle and use process of the utility model are as follows: when in use, the monitoring instrument body 1 is first fixedly connected to the surface of the bridge pier, and then the user rotates the rotating wheel 13, the rotating wheel 13 drives the bidirectional screw 10 to rotate, and the bidirectional screw 10 uses the thread to push the screw sleeve 11 to move toward each other. During the movement of the screw sleeve 11, the crank 12 is used to squeeze the support plate 7, and the support plate 7 is squeezed and moves to the side away from the connecting frame 9. When the bottom of the support plate 7 contacts the ground, the support plate 7 can use the reverse supporting force to push the connecting rod 6 to rise. When the pressing plate 5 at the top of the connecting rod 6 contacts the bottom of the push switch 4, the installation of the monitoring instrument body 1 is completed. When settlement occurs, the connecting rod 6 can transmit the downward force and use the pressing plate 5 to squeeze the push switch 4. The push switch 4 sends an alarm signal to the monitoring instrument body 1 and warns.
[0043] To sum up: the road and bridge construction change monitoring structure transmits the downward force through the connecting rod 6 and uses the pressure plate 5 to squeeze the press switch 4. The press switch 4 sends an alarm signal to the monitoring instrument body 1 and warns. The utility model can improve the measurement method of the existing settlement monitoring device, instead of detecting by infrared measurement, to prevent the infrared rays emitted by the equipment to the outside from being affected by the environment and causing detection errors, thereby avoiding affecting the accuracy of settlement detection.
[0044] It should be noted that, in this article, relational terms such as first and second, etc. are only used to distinguish one entity or operation from another entity or operation, and do not necessarily require or imply any such actual relationship or order between these entities or operations. Moreover, the terms "include", "comprise" or any other variants thereof are intended to cover non-exclusive inclusion, so that a process, method, article or device including a series of elements includes not only those elements, but also other elements not explicitly listed, or also includes elements inherent to such process, method, article or device.
[0045] Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that various changes, modifications, substitutions and variations may be made to the embodiments without departing from the principles and spirit of the present invention, and that the scope of the present invention is defined by the appended claims and their equivalents.
Claims
1. A road and bridge construction change monitoring structure, comprising a monitoring device body (1); Features: A measuring structure (2) is provided at the bottom of the monitoring instrument body (1); The bottom of the monitoring instrument body (1) is provided with an adjustment structure (3) for connecting to the measurement structure (2); The measuring structure (2) comprises a push switch (4) electrically connected to the bottom of the monitoring instrument body (1); a pressure plate (5) is arranged at the bottom of the monitoring instrument body (1); the pressure plate (5) is located at the bottom of the push switch (4); a connecting rod (6) is fixedly connected to the bottom of the pressure plate (5); a support plate (7) is arranged on the side of the connecting rod (6) away from the pressure plate (5); a support frame (8) is fixedly connected to the bottom of the monitoring instrument body (1); the support frame (8) is sleeved on the surface of the connecting rod (6); the connecting rod (6) and the support frame (8) are slidably connected; and the connecting rod (6) and the support plate (7) are connected via an adjustment structure (3).
2. A road and bridge construction change monitoring structure according to claim 1, characterized in that: The adjustment structure (3) comprises a connection frame (9) fixedly connected to the bottom end of the connection rod (6); a bidirectional screw (10) is movably connected to the interior of the connection frame (9) via a bearing; a screw sleeve (11) is threadedly connected to the left and right sides of the surface of the bidirectional screw (10); a crank (12) is movably connected to the front and back sides of the screw sleeve (11) via a pin; a side of the crank (12) away from the screw sleeve (11) is movably connected to the surface of the support plate (7) via a pin; the left end of the bidirectional screw (10) passes through the connection frame (9) and extends to the left side of the connection frame (9); a rotating wheel (13) is arranged on the left side of the connection frame (9); and the left end of the bidirectional screw (10) is fixedly connected to the right side of the rotating wheel (13).
3. A road and bridge construction change monitoring structure according to claim 2, characterized in that: A guide bar (14) is fixedly connected to the interior of the connection frame (9), and the guide bar (14) extends to the interior of the screw sleeve (11) from a side away from the connection frame (9). The screw sleeve (11) and the guide bar (14) are slidably connected.
4. A road and bridge construction change monitoring structure according to claim 1, characterized in that: A damping plate (15) is fixedly connected to the bottom of the support plate (7), and the interior of the damping plate (15) is arranged to be hollow.
5. A road and bridge construction change monitoring structure according to claim 2, characterized in that: The left and right sides of the connecting rod (6) are fixedly connected with reinforcing ribs (16), and the side of the reinforcing rib (16) away from the connecting rod (6) is fixedly connected to the top of the connecting frame (9).
6. A road and bridge construction change monitoring structure according to claim 1, characterized in that: The surface of the connecting rod (6) is fixedly connected to an extension ring (17) located inside the support frame (8), and the top of the extension ring (17) is fixedly connected to a compression spring (18) sleeved on the surface of the connecting rod (6), and the top of the compression spring (18) contacts the bottom of the monitoring instrument body (1).