Remote control device based on one-key sequential control
By designing a remote control device for substations, the working status and power supply incoming status of substation equipment are automatically controlled, and the problems of low manual operation efficiency and high error operation are solved, and more efficient and safe shutdown operation is achieved.
Patent Information
- Application Number
- CN202323570770.3
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2023-12-27
- Publication Date
- 2024-11-12
- Estimated Expiration
- 2033-12-27
AI Technical Summary
The switch-back operation of the substation mainly relies on on-site manual methods, resulting in low operating efficiency and high personnel operating pressure, which is prone to misoperation of equipment and affecting safety.
Design a remote control device based on one-click sequence control, including a host, a switch, a first control device, a second control device, a first line inlet cabinet, a bus connection cabinet, a second line inlet cabinet and a first switch cabinet, through The switch converts the control signal into an operating signal, automatically controls the working state of these devices or the power supply incoming state, and realizes automatic operation.
It improves work efficiency, reduces the probability of incorrect operation of the shutter operation, ensures operation safety, and has strong reliability.
Smart Images

Figure CN221995180U_ABST
Abstract
Description
Technical Field
[0001] The present application relates to the technical field of power equipment, and in particular to a remote control device based on one-button sequential control. Background Art
[0002] At present, substation switching operations are mainly carried out manually on-site, with low operating efficiency and multi-point operations that put operators under great operating pressure. In addition, with a sharp increase in workload, personnel fatigue is likely to occur, which can easily lead to equipment misoperation and pose a hidden danger to the safety of on-site operators and equipment. Utility Model Content
[0003] The present application aims to solve at least one of the technical problems existing in the prior art. To this end, the present application proposes a remote control device based on one-button sequential control, which can improve work efficiency, effectively reduce the probability of misoperation of switching operation, ensure safety, and have strong reliability.
[0004] The present application provides a remote control device based on one-button sequential control, comprising: a host, a switch, a first control device, a second control device, a first incoming line cabinet, a busbar cabinet, a second incoming line cabinet and a first switch cabinet;
[0005] The host is connected to the input end of the switch, the output end of the switch is respectively connected to the input ends of the first control device and the second control device, the output end of the first control device is respectively connected to the first incoming line cabinet, the bus coupling cabinet, and the second incoming line cabinet, the output end of the second control device is connected to the first switch cabinet, and the bus coupling cabinet is respectively connected to the first incoming line cabinet and the second incoming line cabinet;
[0006] The switch is used to convert a first control signal sent from the host into a first operation signal, and send the first operation signal to the first control device, and the first control device is used to control the first working state or the first power supply state of the first incoming cabinet, the busbar cabinet and the second incoming cabinet according to the first operation signal; the switch is also used to convert a second control signal sent from the host into a second operation signal, and send the second operation signal to the second control device, and the second control device is used to control the second working state or the second power supply state of the first switch cabinet according to the second operation signal.
[0007] According to the remote control device based on one-key sequential control of the embodiment of the present application, at least the following beneficial effects are achieved: the first control signal sent from the host is converted into a first operation signal through the switch, and the first operation signal is sent to the first control device, and the first control device is used to control the first working state or the first power supply incoming state of the first incoming line cabinet, the busbar cabinet and the second incoming line cabinet according to the first operation signal; the second control signal sent from the host is also converted into a second operation signal through the switch, and the second operation signal is sent to the second control device, and the second control device is used to control the second working state or the second power supply incoming state of the first switch cabinet according to the second operation signal; a large number of cumbersome manual switching operation steps are solidified on the dedicated background host, and as long as the required "operation task" is clicked on the host, the host can automatically complete the remote control operation of the first incoming line cabinet, the busbar cabinet, the second incoming line cabinet and the first switch cabinet through the converter and the first control device and the second control device. Through this setting, the present application can improve work efficiency, effectively reduce the probability of misoperation of switching operation, ensure safety, and have strong reliability.
[0008] According to some embodiments of the present application, the remote control device based on one-button sequential control also includes a first circuit breaker and a first shaking trolley respectively arranged corresponding to the first incoming line cabinet, the main coupling cabinet, and the second incoming line cabinet, each of the first shaking trolleys is respectively connected to the first control device and the corresponding first circuit breaker, and the first control device is also used to control the shaking in and out of each of the first shaking trolleys according to the first operation signal, and move the position of the corresponding first circuit breaker by shaking the first shaking trolley in and out to control the first working state of the corresponding first incoming line cabinet, or the main coupling cabinet, or the second incoming line cabinet.
[0009] According to some embodiments of the present application, the remote control device based on one-button sequential control also includes a second circuit breaker and a second shaking trolley arranged corresponding to the first switch cabinet, and the second shaking trolley is respectively connected to the second control device and the corresponding second circuit breaker. The second control device is also used to control the shaking in and out of the second shaking trolley according to the second operation signal, and move the position of the corresponding second circuit breaker by shaking the second shaking trolley in and out to control the second working state of the corresponding first switch cabinet.
[0010] Additional aspects and advantages of the present application will be given in part in the description below, and in part will become apparent from the description below, or will be learned through the practice of the present application. BRIEF DESCRIPTION OF THE DRAWINGS
[0011] Additional aspects and advantages of the present application will become apparent and easily understood from the description of the embodiments in conjunction with the following drawings, in which:
[0012] Figure 1 A schematic diagram of the structure of a remote control device based on one-button sequential control provided in an embodiment of the present application. DETAILED DESCRIPTION
[0013] The embodiments of the present application are described in detail below, and examples of the embodiments are shown in the accompanying drawings, wherein the same or similar reference numerals throughout represent the same or similar elements or elements having the same or similar functions. The embodiments described below with reference to the accompanying drawings are exemplary and are only used to explain the present application, and cannot be understood as limiting the present application.
[0014] In the description of the present application, it should be understood that descriptions involving orientation, such as up, down, front, back, left, right, etc., indicating orientations or positional relationships, are based on the orientations or positional relationships shown in the accompanying drawings, and are only for the convenience of describing the present application and simplifying the description, and do not indicate or imply that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore should not be understood as a limitation on the present application.
[0015] In the description of this application, if there is a description of first or second, it is only for the purpose of distinguishing technical features, and cannot be understood as indicating or implying relative importance or implicitly indicating the number of the indicated technical features or implicitly indicating the order of the indicated technical features.
[0016] In the description of this application, unless otherwise clearly defined, terms such as setting, installing, connecting, etc. should be understood in a broad sense, and technicians in the relevant technical field can reasonably determine the specific meanings of the above terms in this application based on the specific content of the technical solution.
[0017] At present, substation switching operations are mainly carried out manually on-site, with low operating efficiency and multi-point operations that put operators under great operating pressure. In addition, with a sharp increase in workload, personnel fatigue is likely to occur, which can easily lead to equipment misoperation and pose a hidden danger to the safety of on-site operators and equipment.
[0018] In order to solve the above problems, the present application proposes a remote control device based on one-button sequential control. The embodiments of the present application are further described below in conjunction with the accompanying drawings.
[0019] Reference Figure 1The present application provides a remote control device based on one-button sequential control, including: a host, a switch, a first control device, a second control device, a first incoming line cabinet, a bus coupling cabinet, a second incoming line cabinet and a first switch cabinet; the host is connected to the input end of the switch, the output end of the switch is respectively connected to the input end of the first control device and the second control device, the output end of the first control device is respectively connected to the first incoming line cabinet, the bus coupling cabinet and the second incoming line cabinet, the output end of the second control device is connected to the first switch cabinet, and the bus coupling cabinet is respectively connected to the first incoming line cabinet and the second incoming line cabinet; the switch is used to convert a first control signal sent from the host into a first operation signal, and send the first operation signal to the first control device, and the first control device is used to control the first incoming line cabinet, the bus coupling cabinet and the second incoming line cabinet according to the first operation signal. The first control device is used to control the first working state or the first power supply incoming line state of the first incoming line cabinet, the bus coupling cabinet and the second incoming line cabinet according to the first operation signal; the switch is also used to convert a second control signal sent from the host into a second operation signal, and send the second operation signal to the second control device, and the second control device is used to control the second working state or the second power supply incoming line state of the first switch cabinet according to the second operation signal.
[0020] It should be noted that the first incoming cabinet and the second incoming cabinet are the main power incoming equipment, and the first incoming cabinet and the second incoming cabinet are equipped with incoming lines from different sources. The busbar of the first incoming cabinet and the second incoming cabinet is connected when the system has the first incoming cabinet and the second incoming cabinet, and the first incoming cabinet and the second incoming cabinet are backup for each other. The switch cabinet connecting the two sections of the busbar is called the busbar. At the same time, the busbar is generally prohibited from being closed at the same time as the first incoming cabinet and the second incoming cabinet.
[0021] It should be noted that the working states of the first incoming cabinet, the second incoming cabinet and the bus coupling cabinet include the operating state, the hot standby state and the cold standby state, and the power incoming state of the first incoming cabinet, the second incoming cabinet and the bus coupling cabinet include: when the first incoming cabinet and the bus coupling cabinet are in the closed state, and the second incoming cabinet is in the open state, the first incoming cabinet is used for incoming line; when the second incoming cabinet and the bus coupling cabinet are in the closed state, and the first incoming cabinet is in the open state, the second incoming cabinet is used for incoming line; when the first incoming cabinet and the second incoming cabinet are in the closed state, and the bus coupling cabinet is in the closed state or the open state, the first incoming cabinet and the second incoming cabinet are used for incoming line at the same time.
[0022] Specifically, the operation of the substation is compiled into operation module buttons on the monitoring background of the smart substation according to a certain five-defense logic. The operator does not need to compile a complex operation ticket during operation. He only needs to call the operation ticket corresponding to the one-key sequence button according to the name of the operation task to complete the closing and opening of the first incoming line cabinet, the second incoming line cabinet and the main coupling cabinet.
[0023] In some embodiments, when the first incoming cabinet and the bus coupling cabinet are in the closed state and the second incoming cabinet is in the open state, the second incoming cabinet can only be in the hot standby state; when the second incoming cabinet and the bus coupling cabinet are in the closed state and the first incoming cabinet is in the open state, the first incoming cabinet can only be in the hot standby state.
[0024] It should be noted that the second working state of the first switch cabinet includes the operating state, hot standby state, cold standby state and maintenance state, and the second power supply line state of the first switch cabinet includes: power supply line and power supply line is not connected.
[0025] In the present application, the first control signal sent from the host is converted into a first operation signal through the switch, and the first operation signal is sent to the first control device, and the first control device is used to control the first working state or the first power supply line state of the first incoming line cabinet, the busbar cabinet and the second incoming line cabinet according to the first operation signal; the second control signal sent from the host is also converted into a second operation signal through the switch, and the second operation signal is sent to the second control device, and the second control device is used to control the second working state or the second power supply line state of the first switch cabinet according to the second operation signal; a large number of cumbersome manual switching operation steps are solidified on the dedicated background host, and as long as the required "operation task" is clicked on the host, the host can automatically complete the remote control operation of the first incoming line cabinet, the busbar cabinet, the second incoming line cabinet and the first switch cabinet through the converter and the first control device and the second control device, and can also automatically check whether the operation is in place to ensure the correct operation. Through this setting, the present application can improve work efficiency, effectively reduce the probability of misoperation of switching operation, ensure safety, and have strong reliability.
[0026] It can be understood that the remote control device based on one-button sequential control also includes a first circuit breaker and a first shaking trolley respectively arranged corresponding to the first incoming cabinet, the main coupling cabinet, and the second incoming cabinet. Each first shaking trolley is respectively connected to the first control device and the corresponding first circuit breaker. The first control device is also used to control the shaking in and out of each first shaking trolley according to the first operation signal, and move the position of the corresponding first circuit breaker by shaking the first shaking trolley in and out to control the first working state of the corresponding first incoming cabinet, or the main coupling cabinet, or the second incoming cabinet.
[0027] It should be noted that, for the first incoming cabinet, the second incoming cabinet and the main coupling cabinet: when the first shaking trolley is in the shaking-in state, the first circuit breaker is in the closed state, and the corresponding first incoming cabinet, or the main coupling cabinet, or the second incoming cabinet is in the running state; when the first shaking trolley is in the shaking-in state, the first circuit breaker is in the open state, and the corresponding first incoming cabinet, or the main coupling cabinet, or the second incoming cabinet is in the hot standby state; when the first shaking trolley is in the shaking-in state and shaken out, the first circuit breaker is in the open state, and the corresponding first incoming cabinet, or the main coupling cabinet, or the second incoming cabinet is in the cold standby state.
[0028] It should be noted that the first rocking trolley is a transfer trolley for the first circuit breaker, which is an important tool in the transportation and installation of power equipment. It can move the first circuit breaker in the power equipment from one position to another for inspection, maintenance or replacement. In the transportation and installation of power equipment, the first rocking trolley has the following functions: Improve work efficiency: The first rocking trolley can be used to quickly transfer the first circuit breaker from one position to another without disassembly or assembly, thereby greatly improving work efficiency;
[0029] Ensure safety: Using the first rocking trolley can reduce safety risks such as personal injury and equipment damage caused by moving and assembling the first circuit breaker; Strong reliability: The first rocking trolley can be made of heavy-duty tires and high-quality steel, can withstand a lot of weight and pressure, and has a high service life.
[0030] It can be understood that the remote control device based on one-button sequential control also includes a second circuit breaker and a second shaking trolley arranged corresponding to the first switch cabinet. The second shaking trolley is respectively connected to the second control device and the corresponding second circuit breaker. The second control device is also used to control the shaking in and out of the second shaking trolley according to the second operation signal, and move the position of the corresponding second circuit breaker by shaking the second shaking trolley in and out to control the second working state of the corresponding first switch cabinet.
[0031] In this embodiment, the remote control device based on one-button sequential control also includes an electric grounding knife arranged corresponding to the first switch cabinet. For the first switch cabinet: when the second rocking trolley is in the rocking-in state, the second circuit breaker is in the closed state, and the electric grounding knife is in the open state, the corresponding first switch cabinet is in the running state; when the second rocking trolley is in the rocking-in state, the second circuit breaker is in the open state, and the electric grounding knife is in the closed state, the corresponding first switch cabinet is in the hot standby state; when the second rocking trolley is in the rocking-out state, the second circuit breaker is in the open state, and the electric grounding knife is in the open state, the corresponding first switch cabinet is in the cold standby state; when the second rocking trolley is in the rocking-in state, the second circuit breaker is in the closed state, and the electric grounding knife is in the closed state, the corresponding first switch cabinet is in the maintenance state.
[0032] It should be noted that the second rocking trolley is the transfer trolley for the second circuit breaker, which is an important tool in the transportation and installation of power equipment. It can move the second circuit breaker in the power equipment from one location to another for inspection, maintenance or replacement. In the transportation and installation of power equipment, the second rocking trolley has the following functions: Improve work efficiency: The second rocking trolley can be used to quickly transfer the second circuit breaker from one location to another without disassembly or assembly, thereby greatly improving work efficiency;
[0033] Ensure safety: Use the second rocking trolley to reduce safety risks such as personal injury and equipment damage caused by moving and assembling the second circuit breaker; Strong reliability: The second rocking trolley can be made of heavy-duty tires and high-quality steel, can withstand a lot of weight and pressure, and has a long service life.
[0034] In the description of this specification, the description with reference to the terms "one embodiment", "some embodiments", "illustrative embodiments", "examples", "specific examples", or "some examples" means that the specific features, structures, materials, or characteristics described in conjunction with the embodiment or example are included in at least one embodiment or example of the present application. In this specification, the schematic representation of the above terms does not necessarily refer to the same embodiment or example. Moreover, the specific features, structures, materials, or characteristics described may be combined in any one or more embodiments or examples in a suitable manner.
[0035] The above is a preferred embodiment of the present application. It should be pointed out that for ordinary technicians in this technical field, several improvements and modifications can be made without departing from the principles of the present application. These improvements and modifications are also considered to be within the scope of protection of the present application.
[0036] Although the embodiments of the present application have been shown and described, those skilled in the art will appreciate that various changes, modifications, substitutions and variations may be made to the embodiments without departing from the principles and spirit of the present application, and that the scope of the present application is defined by the claims and their equivalents.
Claims
1. A remote control device based on one-button sequential control, characterized in that: include: Host, switch, first control device, second control device, first incoming line cabinet, busbar cabinet, second incoming line cabinet and first switch cabinet; The host is connected to the input end of the switch, the output end of the switch is respectively connected to the input ends of the first control device and the second control device, the output end of the first control device is respectively connected to the first incoming line cabinet, the bus coupling cabinet, and the second incoming line cabinet, the output end of the second control device is connected to the first switch cabinet, and the bus coupling cabinet is respectively connected to the first incoming line cabinet and the second incoming line cabinet; The switch is used to convert a first control signal sent from the host into a first operation signal, and send the first operation signal to the first control device, and the first control device is used to control the first working state or the first power supply state of the first incoming cabinet, the busbar cabinet and the second incoming cabinet according to the first operation signal; the switch is also used to convert a second control signal sent from the host into a second operation signal, and send the second operation signal to the second control device, and the second control device is used to control the second working state or the second power supply state of the first switch cabinet according to the second operation signal.
2. The remote control device based on one-button sequential control according to claim 1, characterized in that: The remote control device based on one-button sequential control also includes a first circuit breaker and a first shaking trolley respectively arranged corresponding to the first incoming line cabinet, the bus coupling cabinet, and the second incoming line cabinet. Each of the first shaking trolleys is respectively connected to the first control device and the corresponding first circuit breaker. The first control device is also used to control the shaking in and out of each of the first shaking trolleys according to the first operation signal, and move the position of the corresponding first circuit breaker by shaking the first shaking trolley in and out to control the first working state of the corresponding first incoming line cabinet, the bus coupling cabinet, or the second incoming line cabinet.
3. The remote control device based on one-button sequential control according to claim 1, characterized in that: The remote control device based on one-button sequential control also includes a second circuit breaker and a second shaking trolley arranged corresponding to the first switch cabinet. The second shaking trolley is respectively connected to the second control device and the corresponding second circuit breaker. The second control device is also used to control the shaking in and out of the second shaking trolley according to the second operation signal, and move the position of the corresponding second circuit breaker by shaking the second shaking trolley in and out to control the second working state of the corresponding first switch cabinet.