Automatic argon butt joint device for ladle car of LF (ladle furnace)
By using sealing rings and guide plates in the automatic docking device of the argon gas chartered in the LF refining furnace, the air leakage problem caused by slag accumulation in the saddle is solved, the sealing and automatic docking function of argon gas docking is realized, and the steelmaking production is improved quality.
Patent Information
- Application Number
- CN202420699796.3
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-04-07
- Publication Date
- 2024-11-19
- Estimated Expiration
- Not applicable · inactive patent
AI Technical Summary
In the existing LF refining furnace ladle argon docking device, the saddle is prone to slag accumulation, resulting in misalignment of the interface and leakage, affecting the argon blowing effect of the molten steel.
An automatic argon gas docking device including the upper and lower part of the argon blowing device is designed. The sealing ring is used to ensure the docking seal is tight, and the docking is correct through the guide plate and the fixing device. The upper part of the argon blowing device is installed on the steel clamp and the lower part is installed. In the southeast corner of the ladle car body, the automatic docking of argon gas is achieved by using components such as filters, check valves and ball valves.
Through the design of the sealing ring and guide plate, the argon gas docking is ensured to be connected without leakage, and the automatic docking of the ladle is achieved, which improves the quality and efficiency of steelmaking production.
Smart Images

Figure CN222024415U_ABST
Abstract
Description
Technical Field
[0001] The utility model belongs to the technical field of LF refining furnace argon gas automatic docking equipment, and in particular relates to an LF refining furnace ladle car argon gas automatic docking device. Background Art
[0002] At present, the argon gas docking device of the ladle car of the LF refining furnace in each steel plant is to dock the saddle seats on both sides of the ladle car with the ladle trunnions, lift the ladle to the ladle car, and dock the ladle trunnions with the saddle seats of the ladle car to achieve automatic argon gas docking. This connection method mainly has the following problems: slag is easily accumulated at the saddle seats on both sides of the ladle car, resulting in misalignment and unevenness of the docking interface, resulting in gas leakage, affecting the argon blowing effect of molten steel, and having a great impact on the process quality. Summary of the invention
[0003] The utility model aims to provide an argon automatic docking device for a ladle car of an LF refining furnace, so as to solve the problem of gas leakage caused by slag accumulation on a saddle seat in the prior art.
[0004] The utility model solves the technical problem by adopting the following technical solution: an argon gas automatic docking device for a ladle car of an LF refining furnace, comprising an upper box of an argon blowing device, an upper part of the argon blowing device arranged in the upper box of the argon blowing device, a lower part of the argon blowing device connected to the lower part of the upper part of the argon blowing device, and a sealing ring is arranged between the upper part of the argon blowing device and the lower part of the argon blowing device;
[0005] The upper part of the argon blowing device includes a filter, a one-way valve, a ball valve and an upper pipe. The filter, the one-way valve, the ball valve and the upper pipe are provided in two sets. The upper end of each set of the upper pipe is used to connect to the position of the ladle air brick. Each set of the upper pipe is provided with a filter, a one-way valve and a ball valve in sequence along the forward direction of the gas source.
[0006] The lower part of the argon blowing device is provided with two sets, and the lower part of each set of the argon blowing device includes a lower connecting pipe, a rotating device, and a cover plate. The cover plate is fixedly installed on the top of the rotating device. The upper end of the lower connecting pipe passes through the rotating device and the cover plate in sequence and is connected with the lower end of the corresponding upper connecting pipe. The lower end of the lower connecting pipe is connected to the argon gas source. The bottom of the lower part of each set of the argon blowing device is fixedly connected with a base frame, and the base frame is fixedly installed on the base.
[0007] Specifically, the filter has a nominal diameter of 25 mm, is connected to the upper connecting pipe via a flange, and has a nominal pressure of 1.6 MPa.
[0008] Specifically, the one-way valve has a nominal diameter of 20 mm, a nominal pressure of 5.0 MPa, a main body material of 304, and hard-sealed joints at both ends to meet the requirement of unidirectional advancement of the gas source.
[0009] Specifically, the ball valve has a nominal diameter of 25 mm, a nominal pressure of 5 MPa, and an operating temperature of ≤350° C., so as to facilitate inspection and maintenance.
[0010] Specifically, the upper box of the argon blowing device is fixedly installed on the ladle hoop, and the lower part of the argon blowing device is installed at the southeast corner of the ladle car body.
[0011] Furthermore, guide plates are respectively provided at the southwest and northwest positions of the ladle car body, and the guide plates are used to support the ladle hoops.
[0012] Specifically, the cover plate is connected and fixed to the rotating device by bolts, matching nuts and washers, the lower part of the argon blowing device is connected and fixed to the base frame by bolts, matching nuts and washers, and the base frame is welded to the base.
[0013] The utility model has the following beneficial effects: the argon automatic docking device of the utility model ensures that the upper part of the ladle argon blowing device is aligned with the lower part of the argon blowing device through the guide plate, ensures that the upper part of the argon blowing device and the lower part of the argon blowing device are docked and sealed tightly without leakage through the O-ring, and protects the upper part of the argon blowing device through the upper box of the argon blowing device installed on the ladle hoop. The upper part of the automatic docking argon blowing device is installed on the ladle hoop, and the lower part of the automatic docking argon blowing device is installed at the southeast corner of the ladle car body. After the ladle is hoisted on the ladle car, the upper and lower parts of the argon blowing device are docked to realize automatic docking and argon blowing of the ladle, meeting the steelmaking production needs of the LF refining furnace. BRIEF DESCRIPTION OF THE DRAWINGS
[0014] Figure 1 The utility model is a schematic diagram of the overall installation structure of the argon gas automatic docking device of the ladle car of the LF refining furnace.
[0015] Figure 2 The utility model is a schematic diagram of the installation of the upper box and the steel ladle hoop of the argon blowing device.
[0016] Figure 3 It is a left view of the overall installation of the utility model LF refining furnace ladle car argon gas automatic docking device.
[0017] Figure 4 yes Figure 3 A magnified view of the structure in the middle.
[0018] Figure 5 It is a top view of the overall installation of the utility model LF refining furnace ladle car argon gas automatic docking device.
[0019] Figure 6 yes Figure 5 Middle BB section view.
[0020] Figure 7 This is the overall installation front view of the utility model LF refining furnace ladle car argon gas automatic docking device.
[0021] Figure 8 yes Figure 7 CC section view.
[0022] In the figure: 1, upper box of argon blowing device, 2, sealing ring, 3, upper part of argon blowing device, 4, lower part of argon blowing device, 5, filter, 6, one-way valve, 7, ball valve, 8, upper connecting pipe, 9, lower connecting pipe, 10, ladle hoop, 11, ladle car body, 12, rotating device, 13, cover plate, 14, base, 15, base frame, 16, bolts, 17, guide plate. DETAILED DESCRIPTION
[0023] The utility model will now be further described in detail with reference to the accompanying drawings.
[0024] like Figure 1-8 As shown, an argon automatic docking device for a LF refining furnace ladle car comprises an argon blowing device upper box 1, an argon blowing device upper part 3 arranged in the argon blowing device upper box 1, an argon blowing device lower part 4 connected to the argon blowing device upper part 3 below the argon blowing device upper part 3, and a sealing ring 2 is provided between the argon blowing device upper part 3 and the argon blowing device lower part 4; the sealing ring 2 is an O-type sealing ring, which ensures that the argon blowing device upper part 3 and the argon blowing device lower part 4 are tightly docked and sealed.
[0025] The upper part 3 of the argon blowing device includes a filter 5, a one-way valve 6, a ball valve 7 and an upper connecting pipe 8. The filter 5, the one-way valve 6, the ball valve 7 and the upper connecting pipe 8 are each provided with two sets. The upper end of each set of the upper connecting pipe 8 is used to be connected to the position of the ladle air brick. Each set of the upper connecting pipe 8 is provided with a filter 5, a one-way valve 6 and a ball valve 7 in sequence along the forward direction of the gas source.
[0026] The filter 5 has a nominal diameter of 25 mm and is connected to the upper pipe 8 through a flange. The nominal pressure of 1.6 MPa realizes two-position selection control to ensure that there are no impurities in the argon gas pipeline.
[0027] The one-way valve 6 has a nominal diameter of 20mm, a nominal pressure of 5.0MPa, a main body material of 304, and hard-sealed joints at both ends to meet the requirements of unidirectional air source movement.
[0028] The nominal diameter of ball valve 7 is 25mm, the nominal pressure is 5MPa, and the operating temperature is ≤350℃, which is convenient for inspection and maintenance.
[0029] The lower part 4 of the argon blowing device is provided with two sets, and each set of the lower part 4 of the argon blowing device includes a lower pipe 9, a rotating device 12, and a cover plate 13. The cover plate 13 is fixedly installed on the top of the rotating device 12, and the cover plate 13 is connected and fixed to the rotating device 12 by bolts 16 and matching nuts and washers. The upper end of the lower pipe 9 passes through the rotating device 12 and the cover plate 13 in sequence and is connected to the lower end of the corresponding upper pipe 8. The lower end of the lower pipe 9 is connected to the argon gas source. The bottom of each set of the lower part 4 of the argon blowing device is fixedly connected with a base frame 15 respectively. The lower part 4 of the argon blowing device and the base frame 15 are connected and fixed by bolts 16 and matching nuts and washers. The base frame 15 is welded to the base 14.
[0030] The upper box 1 of the argon blowing device is fixedly installed on the ladle hoop 10, and the lower part 4 of the argon blowing device is installed at the southeast corner of the ladle car body 11. Guide plates 17 are respectively provided at the southwest and northwest positions of the ladle car body 11. The guide plates 17 are used to support the ladle hoop 10, fix the ladle, and ensure that the ladle is automatically connected to the upper and lower parts for alignment and compaction.
[0031] The upper box 1 of the argon blowing device is installed at the position of the ladle hoop, the upper part 3 of the argon blowing device is fixed in the upper box 1 of the argon blowing device, and the lower part 4 of the argon blowing device is installed at the southeast corner of the ladle car. The upper part 3 of the argon blowing device is tightly fitted with the lower part 4 of the argon blowing device through the sealing ring 2. According to the rhythm of steelmaking production, the ladle is lifted to the ladle car by a metallurgical crane. The two guide plates 17 located in the southwest and northwest positions of the ladle car body 11 support the ladle hoop 10. The upper part of the automatic docking device ladle is aligned and fitted with the lower part of the ladle car. The personnel on duty can realize the automatic docking opening and closing of the argon gas by operating the argon gas automatic docking on-site operation box. The argon gas source is divided into two routes, and the two medium pipeline equipments are the same. The argon gas source passes through the lower part 4 of the argon blowing device, the sealing ring 2, the upper part 3 of the argon blowing device, the filter 5, the one-way valve 6, and the ball valve 7 in turn. Finally, the gas source reaches the position of the ladle air brick to realize the automatic docking function of the ladle argon gas.
[0032] The above-described embodiments are merely descriptions of preferred implementations of the present invention, and are not intended to limit the concept and scope of the present invention. Without departing from the design concept of the present invention, various modifications and improvements made by ordinary persons in the art to the technical solution of the present invention shall fall within the scope of protection of the present invention.
[0033] The technology, shape and structure parts not described in detail in the present invention are all known technologies.
Claims
1. An argon automatic docking device for a LF refining furnace ladle car, characterized in that: It comprises an upper box of an argon blowing device, an upper part of the argon blowing device arranged in the upper box of the argon blowing device, a lower part of the argon blowing device connected to the lower part of the argon blowing device, and a sealing ring is arranged between the upper part of the argon blowing device and the lower part of the argon blowing device; The upper part of the argon blowing device includes a filter, a one-way valve, a ball valve and an upper pipe. The filter, the one-way valve, the ball valve and the upper pipe are provided in two sets. The upper end of each set of the upper pipe is used to connect to the position of the ladle air brick. Each set of the upper pipe is provided with a filter, a one-way valve and a ball valve in sequence along the forward direction of the gas source. The lower part of the argon blowing device is provided with two sets, and the lower part of each set of the argon blowing device includes a lower connecting pipe, a rotating device, and a cover plate. The cover plate is fixedly installed on the top of the rotating device. The upper end of the lower connecting pipe passes through the rotating device and the cover plate in sequence and is connected with the lower end of the corresponding upper connecting pipe. The lower end of the lower connecting pipe is connected to the argon gas source. The bottom of the lower part of each set of the argon blowing device is fixedly connected with a base frame, and the base frame is fixedly installed on the base.
2. The argon automatic docking device for the LF refining furnace ladle car according to claim 1, characterized in that: The filter has a nominal diameter of 25 mm, is connected to the upper connecting pipe via a flange, and has a nominal pressure of 1.6 MPa.
3. The argon automatic docking device for the LF refining furnace ladle car according to claim 1, characterized in that: The one-way valve has a nominal diameter of 20 mm, a nominal pressure of 5.0 MPa, a main body material of 304, and hard-sealed joints at both ends to meet the requirement of unidirectional forward movement of the gas source.
4. The argon automatic docking device for the LF refining furnace ladle car according to claim 1, characterized in that: The ball valve has a nominal diameter of 25 mm, a nominal pressure of 5 MPa, and an operating temperature of ≤350°C, so it is easy to inspect and maintain.
5. The argon automatic docking device for the LF refining furnace ladle car according to claim 1, characterized in that: The upper box of the argon blowing device is fixedly installed on the ladle hoop, and the lower part of the argon blowing device is installed at the southeast corner of the ladle car body.
6. The argon automatic docking device for the LF refining furnace ladle car according to claim 5, characterized in that: Guide plates are respectively provided at the southwest and northwest positions of the ladle car body, and the guide plates are used to support the ladle hoops.
7. The argon automatic docking device for the LF refining furnace ladle car according to claim 1, characterized in that: The cover plate is connected and fixed to the rotating device by bolts, matching nuts and washers, the lower part of the argon blowing device is connected and fixed to the base frame by bolts, matching nuts and washers, and the base frame is welded to the base.