Lifting frame for upper module of ultra-large booster station

By designing the upper block hoisting rack of the super-large booster station with a combined structure, the problem that the existing technology cannot meet the lifting needs of offshore wind power projects is solved, and flexible adjustment and efficient lifting of the hoisting rack are realized to adapt to lifting of different sizes and angles The demand for the station has improved the lifting capacity and adaptability.

CN222042357UActive Publication Date: 2024-11-22华能(浙江岱山)海上风电有限公司 +1
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420898506.8
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-04-27
Publication Date
2024-11-22
Estimated Expiration
2034-04-27

AI Technical Summary

Technical Problem

Existing super-large cranes are difficult to meet the lifting needs of the upper blocks of the boost station in offshore wind power projects. The lifting racks need to have greater lifting weight and span capabilities, and can adapt to the requirements of boost stations of different sizes and angles.

Method used

A super-large booster station upper block hoist is designed, adopting a combined structure of upper beam and lower beam. Through the connecting frame and retractable balance beam and support beam, the driving parts realize flexible adjustment of the hoisting frame to adapt to different The lifting requirements of size and angle are connected to the crane through a second suspender to meet the lifting requirements.

Benefits of technology

The lifting capacity of single-hook and multi-hook super-large lifting ships has been realized, the practicality and adaptability of the lifting racks have been improved, labor costs have been reduced, and stable lifting of the booster station has been ensured.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222042357U_ABST
    Figure CN222042357U_ABST
Patent Text Reader

Abstract

The utility model discloses an ultra-large booster station upper module lifting frame which comprises a pair of upper cross beams and a pair of lower cross beams, one end of one upper cross beam is connected to one end of one lower cross beam, and the other end of the upper cross beam is connected to one end of the other lower cross beam; the two ends of the other upper cross beam are connected to the two lower cross beams respectively; a connecting frame is arranged between the upper cross beam and the lower cross beam, the upper cross beam is fixedly connected to one end of the connecting frame, and the lower cross beam is rotationally connected to the other end of the connecting frame; each upper cross beam is provided with a first lifting belt, and one end, far away from the upper cross beam, of each first lifting belt is used for being connected with a crane ship matched with the lifting frame for use; a second lifting belt is arranged at the end part of each lower cross beam; and one end, far away from each lower cross beam, of each second lifting belt is connected to a booster station used for being matched with the lifting frame for use. The hoisting device has the effect of meeting the hoisting requirement of the booster station upper module.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the field of offshore engineering construction, and in particular to an upper assembly hoisting frame for a super-large booster station. Background Art

[0002] Against the backdrop of the depletion of fossil energy and the severe climate change situation, wind energy has become a renewable, clean energy with little environmental impact, and its strategic value is increasingly prominent. All countries attach great importance to wind energy. Moreover, large offshore power plants are a new market industry, and there is very little experience in similar engineering construction that can be used as a reference. As the scale of offshore wind power projects becomes larger and larger, the capacity, size, and weight of the upper modules of the booster station are also increasing. At present, most of the single hooks and multiple hooks of super-large cranes cannot meet the lifting needs of the upper modules of the booster station. It is urgent to develop a super-large booster station upper module lifting frame. Summary of the invention

[0003] In order to meet the lifting requirements of the upper assembly of the booster station and stably lift the booster station to an offshore installation platform, the present application provides an ultra-large upper assembly lifting frame for the booster station.

[0004] The present application provides a super-large booster station upper assembly hoisting frame adopts the following technical solution:

[0005] A super-large booster station upper assembly lifting frame, comprising a pair of upper crossbeams and a pair of lower crossbeams, wherein one end of one of the upper crossbeams is connected to one end of one of the lower crossbeams, and the other end is connected to one end of the other lower crossbeam, and the two ends of the other upper crossbeam are respectively connected to the two lower crossbeams; a connecting frame is arranged between the upper crossbeams and the lower crossbeams, the upper crossbeam is fixedly connected to one end of the connecting frame, and the lower crossbeam is rotatably connected to the other end of the connecting frame; a first sling is arranged at the end of each of the upper crossbeams, and the end of the first sling away from the upper crossbeam is used to connect to a lifting ship used in conjunction with the lifting frame; a second sling is arranged at the end of each of the lower crossbeams, and the end of each of the second slings away from the lower crossbeam is connected to a booster station used in conjunction with the lifting frame.

[0006] By adopting the above technical solution, after the lifting frame is installed as a whole on the crane ship, the super-large crane ships with single hooks or multiple hooks can use the second lifting belt on the lifting frame to lift the booster station as long as the lifting weight and span meet the lifting requirements; at the same time, according to different sizes of booster stations, the lifting angle requirements of the booster station can be met by adjusting the connection between the upper beam and the lower beam, thereby improving the practicality of the lifting frame.

[0007] Preferably, a balance beam is provided between the two first slings on the same upper cross beam.

[0008] By adopting the above technical solution, after the first sling is connected to the balance beam, the part of the first sling located on the side of the balance beam away from the upper cross beam is perpendicular to the horizontal plane, which is convenient for connecting the crane ship and the lifting frame.

[0009] Preferably, the balance beam includes a fixed section and a telescopic section, and a pair of fixed sections are provided, and the ends of the two fixed sections that are away from each other are respectively fixedly connected to the two first slings on the same upper cross beam, and the two ends of the telescopic section are respectively slidably inserted into the two fixed sections.

[0010] By adopting the above technical solution and setting a retractable balance beam, workers can adjust the length of the balance beam according to the lifting points set on the crane ship, thereby adjusting the two first slings on the same upper beam, so that the two first slings on the same upper beam are always balanced on the balance beam and away from the upper beam, which is convenient for lifting.

[0011] Preferably, a support beam is provided between the two lower cross beams.

[0012] By adopting the above technical solution, the supporting beam connects the two lower cross beams, thereby enhancing the overall structural stability of the hanging frame.

[0013] Preferably, the upper cross beam is telescopically arranged; the support beam includes a sleeve and a threaded section, the sleeve is provided with an internal thread, and the threaded section is threadedly connected to the sleeve; one end of the sleeve is connected to one of the lower cross beams, and the end of the threaded section away from the sleeve is rotatably installed on the other lower cross beam.

[0014] By adopting the above technical solution, when it is necessary to hoist booster stations of different sizes, the rotating threaded section drives the two lower beams to move away from or towards each other, thereby changing the overall volume of the hoisting frame to adapt to booster stations of different sizes; thereby improving the adaptability of the hoisting frame in hoisting booster stations of different sizes.

[0015] Preferably, the hanging frame also includes a driving member for driving the threaded section to rotate on the lower cross beam.

[0016] By adopting the above technical solution, workers only need to start the driving member to realize the rotation of the threaded segment, thereby reducing the manpower cost consumed by workers when driving the threaded segment of the large hoisting frame to rotate.

[0017] Preferably, the driving member includes a driving motor and a driving block, and the driving block is fixed on the output shaft of the driving motor; the lower cross beam on which the threaded segment is rotatably mounted is provided with a driving port, and the end of the threaded segment away from the sleeve is provided with a driving groove and the end of the threaded segment is located in the driving port, the driving block is connected to the threaded segment through the driving port, and the driving block is inserted into the threaded segment through the driving groove.

[0018] By adopting the above technical solution, after the worker starts the driving motor, the driving motor drives the threaded segment to rotate in the sleeve through the driving block, thereby driving the lower beam to move away from or close to each other, thereby changing the overall size of the lifting frame and reducing the labor cost of the worker rotating the threaded segment.

[0019] Preferably, a shackle is provided at one end of the second sling away from the lower cross beam.

[0020] By adopting the above technical solution, the booster station can be connected to the lifting frame only by fixing the lifting lug of the booster station to the shackle on the second lifting belt.

[0021] In summary, the present application includes at least one of the following beneficial technical effects:

[0022] 1. After the hoisting frame is installed on the crane ship as a whole, the super-large crane ships with single hooks or multiple hooks can use the second lifting belt on the hoisting frame to hoist the booster station as long as the lifting weight and span meet the hoisting requirements; at the same time, according to the different sizes of booster stations, the hoisting angle requirements of the booster station can be met by adjusting the connection frame between the upper beam and the lower beam, thereby improving the practicality of the hoisting frame;

[0023] 2. A retractable balance beam is set up, and workers can adjust the length of the balance beam according to the lifting points set on the crane ship, so as to adjust the two first slings on the same upper beam, so that the two first slings on the same upper beam are always balanced on the balance beam and away from the upper beam, which is convenient for lifting. BRIEF DESCRIPTION OF THE DRAWINGS

[0024] Figure 1 It is a schematic diagram of the overall structure of the hanging frame according to the embodiment of the present application.

[0025] Figure 2 It is a front view of the hanging frame of the embodiment of the present application.

[0026] Figure 3 It is a side view of the hanging frame of the embodiment of the present application.

[0027] Figure 4 It is a cross-sectional view of a driving component on a hanging frame according to an embodiment of the present application.

[0028] Description of reference numerals:

[0029] 1. Upper crossbeam; 11. First sling; 2. Lower crossbeam; 21. Second sling; 22. Shackle; 3. Connecting frame; 4. Balance beam; 41. Fixed section; 42. Telescopic section; 5. Support beam; 51. Sleeve; 52. Threaded section; 6. Driving member; 61. Driving motor; 62. Driving block; 63. Driving port; 64. Driving slot. DETAILED DESCRIPTION

[0030] The following is combined with Figure 1-4 This application is described in further detail.

[0031] The present application embodiment discloses a super-large booster station upper assembly hoisting frame. Figure 1 The upper assembly lifting frame of the super-large booster station includes a pair of upper beams 1 and a pair of lower beams 2, wherein one end of an upper beam 1 is connected to one end of a lower beam 2, and the other end is connected to one end of another lower beam 2; the two ends of the other upper beam 1 are respectively connected to the two lower beams 2, and each upper beam 1 and the lower beam 2 form a frame with a rectangular cross section; a connecting frame 3 is arranged between adjacent upper beams 1 and lower beams 2, the upper beam 1 is fixedly connected to one end of the adjacent connecting frame 3, and the lower beam 2 is rotatably connected to the other end of the adjacent connecting frame 3; a first sling 11 is arranged at the end of each upper beam 1, and the end of the first sling 11 away from the upper beam 1 is used to connect to a transfer ship used in conjunction with the lifting frame; a second sling 21 is arranged at the end of each lower beam 2, and the end of each second sling 21 away from the lower beam 2 is connected to a booster station used in conjunction with the lifting frame.

[0032] A shackle 22 is provided at one end of the second lifting belt 21 away from the lower cross beam 2; predetermined lifting points are provided on the booster station, and each lifting point is provided with a lifting lug, and the booster station is stably connected to the lifting frame through the connection between the lifting lug and the shackle 22; when lifting the booster station, the booster station is first connected to the lifting frame through the lifting lug and the shackle 22, and then the lifting frame is connected to the corresponding lifting equipment such as a crane or a super-large gantry crane using the first lifting belt 11, and then the booster station is lifted; by using the lifting frame, no matter it is a single-hook or multi-hook lifting equipment, as long as the lifting weight and span meet the lifting requirements, it can be lifted, which is convenient for offshore construction.

[0033] Reference Figure 2A balance beam 4 is arranged between the two first slings 11 on the same upper crossbeam 1; the balance beam 4 includes a fixed section 41 and a telescopic section 42. A pair of fixed sections 41 are arranged. The ends of the two fixed sections 41 away from each other are respectively fixedly connected to the two first slings 11 on the same upper crossbeam 1. The two ends of the telescopic section 42 are respectively slidably inserted into the two fixed sections 41. In this embodiment, the telescopic section 42 is a bidirectional threaded rod. The two ends of the telescopic section 42 are both threadedly connected to the two fixed sections 41. The worker only needs to twist the telescopic section 42 to adjust the balance beam 4.

[0034] Reference Figure 3 A support beam 5 is arranged between the two lower beams 2; the upper beam 1 is telescopically arranged; the support beam 5 includes a sleeve 51 and a threaded section 52, the sleeve 51 is provided with an internal thread, and the threaded section 52 is threadedly connected to the sleeve 51; one end of the sleeve 51 is connected to one of the lower beams 2, and the end of the threaded section 52 away from the sleeve 51 is rotatably installed on the other lower beam 2, and after rotating the threaded section 52, the lower beams 2 on both sides can be driven to move, thereby adjusting the size of the entire hanging frame, so that the hanging frame is suitable for booster stations of different sizes.

[0035] Reference Figure 4 The lifting frame also includes a driving member 6 for driving the threaded segment 52 to rotate on the lower cross beam 2, the driving member 6 includes a driving motor 61 and a driving block 62, the driving block 62 is fixedly mounted on the output shaft of the driving motor 61; the lower cross beam 2 on which the threaded segment 52 is rotatably mounted is provided with a driving port 63, the end of the threaded segment 52 away from the sleeve 51 is provided with a driving groove 64 and the crane is located in the driving port 63, the driving block 62 is connected to the threaded segment 52 through the driving port 63, and the driving block 62 is inserted into the threaded segment 52 through the driving groove 64. In this embodiment, the driving motor 61 is detachably mounted on the lower cross beam 2. When the driving motor 61 is removed, the accident caused by the driving motor 61 falling from a high altitude is reduced.

[0036] The implementation principle of the upper assembly lifting frame of a super-large booster station in an embodiment of the present application is as follows: when the booster station needs to be lifted to an installation platform at sea, the driving member 6 is first started to drive the threaded section 52 to rotate so that the size of the lifting frame is adapted to the booster station, and then the shackle 22 of the lifting frame is used to connect with the lifting lug on the booster station. The worker then adjusts the length of the balance beam 4 according to the position of the lifting point on the crane ship, so that the end of the first lifting belt 11 away from the upper cross beam 1 remains vertical, and the first lifting belt 11 is connected to the crane ship, so that the booster station can be lifted and transported to the installation platform at sea.

[0037] The above are all preferred embodiments of the present application, and the protection scope of the present application is not limited thereto. Therefore, any equivalent changes made according to the structure, shape, and principle of the present application should be included in the protection scope of the present application.

Claims

1. A super-large booster station upper assembly hoisting frame, characterized in that: The invention comprises a pair of upper cross beams (1) and a pair of lower cross beams (2), wherein one end of one of the upper cross beams (1) is connected to one end of one of the lower cross beams (2), and the other end is connected to one end of the other lower cross beam (2); the two ends of the other upper cross beam (1) are respectively connected to the two lower cross beams (2); a connecting frame (3) is arranged between the upper cross beam (1) and the lower cross beam (2), and the upper cross beam (1) is fixedly connected to one end of the connecting frame (3). The lower crossbeam (2) is rotatably connected to the other end of the connecting frame (3); a first sling (11) is provided at the end of each upper crossbeam (1), and the end of the first sling (11) away from the upper crossbeam (1) is used to connect to a crane ship used in conjunction with the lifting frame; a second sling (21) is provided at the end of each lower crossbeam (2), and the end of each second sling (21) away from the lower crossbeam (2) is connected to a booster station used in conjunction with the lifting frame.

2. The super-large booster station upper assembly hoisting frame according to claim 1 is characterized in that: A balance beam (4) is arranged between the two first slings (11) on the same upper cross beam (1).

3. The super-large booster station upper assembly hoisting frame according to claim 2 is characterized in that: The balance beam (4) comprises a fixed section (41) and a telescopic section (42), wherein a pair of the fixed sections (41) are provided, and ends of the two fixed sections (41) which are away from each other are respectively fixedly connected to the two first slings (11) on the same upper cross beam (1), and the two ends of the telescopic section (42) are respectively slidably inserted into the two fixed sections (41).

4. The super-large booster station upper assembly hoisting frame according to claim 1 is characterized in that: A support beam (5) is arranged between the two lower cross beams (2).

5. The super-large booster station upper assembly hoisting frame according to claim 4 is characterized in that: The upper cross beam (1) is telescopically arranged; the support beam (5) comprises a sleeve (51) and a threaded section (52), the sleeve (51) is provided with an internal thread, and the threaded section (52) is threadedly connected to the sleeve (51); one end of the sleeve (51) is connected to one of the lower cross beams (2), and one end of the threaded section (52) away from the sleeve (51) is rotatably mounted on the other lower cross beam (2).

6. The super-large booster station upper assembly hoisting frame according to claim 5, characterized in that: The hanging frame also includes a driving member (6) for driving the threaded section (52) to rotate on the lower crossbeam (2).

7. The super-large booster station upper assembly hoisting frame according to claim 6, characterized in that: The driving member (6) comprises a driving motor (61) and a driving block (62), wherein the driving block (62) is fixedly mounted on the output shaft of the driving motor (61); the lower cross beam (2) on which the threaded section (52) is rotatably mounted is provided with a driving opening (63), an end of the threaded section (52) away from the sleeve (51) is provided with a driving groove (64), and an end of the threaded section (52) is located in the driving opening (63), the driving block (62) is connected to the threaded section (52) via the driving opening (63), and the driving block (62) is inserted into the threaded section (52) via the driving groove (64).

8. The super-large booster station upper assembly hoisting frame according to claim 1, characterized in that: A shackle (22) is provided at one end of the second sling (21) away from the lower cross beam (2).