Large-diameter non-soil-squeezing high-bearing-capacity low-carbon energy pile

By using solid waste materials to prepare high-performance gelling materials and drilling-drinkage tube-grouting processes, large-diameter non-extruded soil with high bearing capacity and low carbon energy piles are manufactured, which solves the problems of low bearing capacity and poor thermal performance in the prior art. , achieving the effect of low carbon high strength and efficient heat exchange.

CN222044168UActive Publication Date: 2024-11-22CHINA POWER ENG CONSULTING GRP CORP EAST CHINA ELECTRIC POWER DESIGN INST +2
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202323214449.1
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2023-11-28
Publication Date
2024-11-22
Estimated Expiration
2033-11-28

AI Technical Summary

Technical Problem

There is a contradiction between the structural load and thermal performance of existing energy piles, resulting in low bearing capacity and poor thermal resistance. In order to improve strength, high-performance concrete needs to be added, which violates the goal of low-carbon environmental protection.

Method used

High-performance gelling materials are prepared using solid waste materials, and large-diameter non-extruded soil, high-load capacity, low-carbon energy piles are manufactured through drilling-dip pipe-grouting process. Combining special pile boots and thermally conductive reinforced grouting bodies, low-carbon energy piles are formed The high-strength pipe pile structure can be embedded in soft and hard soil layers and heat exchanged.

Benefits of technology

It realizes low-carbon high-strength and efficient heat conduction, coordinates the contradiction between bearing capacity and thermal performance, has economical and low-carbon emission reduction advantages, and can have strong adaptability and high load capacity in different soil layers.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222044168U_ABST
    Figure CN222044168U_ABST
Patent Text Reader

Abstract

The utility model discloses a large-diameter non-soil-squeezing high-bearing-capacity low-carbon energy pile. The device comprises a tubular pile, a pile shoe, a bottom sealing body, a cover plate, an end plate, a grouting guide pipe and a heat exchange unit, wherein the number of the tubular piles is one or more, and the multiple tubular piles are connected end to end; the grouting guide pipe is arranged in the side wall of the pipe pile; the pile shoe is arranged at the bottom end of the bottommost section of the tubular pile; the cover plate is arranged at the top end of the topmost section of the tubular pile, and a hole is formed in the cover plate. Compared with the prior art, the solid-waste-based phase-change material embedded with the microbial capsules serves as a main material to form a large-diameter, low-carbon and high-strength pipe pile body, the side friction force of the pipe pile and the heat exchange performance between the pipe pile and surrounding soil are controlled through the specific drilling-pile sinking and side wall grouting technology, and the specially-made pile shoe is further adopted; the energy pile has high adaptability to the underground rock-soil body and can fully exchange heat with the surrounding rock-soil body.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the field of integration of architecture and energy, and in particular to a large-diameter non-soil-squeezing high-bearing-capacity low-carbon energy pile. Background Art

[0002] Energy piles are an innovative technology that combines geothermal energy technology with deep foundations. They not only support traditional pile foundations, but also act as geothermal heat exchangers to absorb or release heat from the soil. Energy piles provide an effective and sustainable technical solution for the construction industry, which not only helps achieve the goals of carbon peak and carbon neutrality, but also improves the economic and environmental benefits of buildings.

[0003] At present, the main technical problem of energy piles in practice is the contradiction between structural load and thermal performance. For example, in traditional PHC (diameter 300-600mm) pipe piles, heat exchange tubes are buried and backfilled with filling materials. This technology is easy to install, fast in construction, and not easy to damage the heat exchange tubes. However, there are also problems such as short pile diameter and low bearing capacity, which easily lead to thermal short circuit and poor heat resistance. In order to improve the strength and heat resistance of pipe piles, it is often necessary to add a variety of reagents and configure high-performance concrete, which is contrary to the original intention of low-carbon and environmental protection.

[0004] Therefore, on the one hand, the utility model uses solid waste materials as the main raw materials, reduces the amount of cement, obtains high-performance cementitious materials through a variety of excitation methods, and adds special microcapsules for the main material of the pipe piles, so that the pipe piles are low-carbon, high-strength and heat-storing; on the other hand, the diameter of the pipe piles is enlarged, special pile shoes are added, and the drilling-pipe sinking-grouting process is adopted, so that the overall structure of the pipe piles can be embedded in soft soil areas, adapt to hard soil layers, and can be closely integrated with the surrounding soil (including mechanical properties and thermal conductivity properties). Utility Model Content

[0005] The purpose of the present application is to provide a large-diameter non-soil-extruding, high-bearing-capacity, low-carbon energy pile. The energy pile of the present application adopts a drilling-pipe sinking-grouting process so that the overall structure of the pipe pile can be embedded in soft soil areas and adapt to hard soil layers, and is low-carbon, high-strength, and heat-storing.

[0006] The present application discloses a large-diameter non-squeezed soil high-bearing-capacity low-carbon energy pile, comprising: a pipe pile, a pile shoe, a bottom sealing body, a cover plate, an end plate, a grouting conduit, a grouting outlet, a heat-conducting enhanced grouting body, a heat transfer medium delivery pipeline, a circulating pump and a heat exchange unit; wherein:

[0007] The pipe piles include one or more, and the plurality of pipe piles are connected end to end;

[0008] The grouting conduit is arranged in the side wall of the pipe pile and the bottom of the pipe pile is provided with a grouting outlet in coordination with the grouting conduit;

[0009] The pile shoe is arranged at the bottom end of the bottommost section of the pipe pile, and the pile shoe further comprises: a pile tip body, one end of the pile tip body is provided with a plurality of crushing tips, and the other end is provided with a pile head end plate, the crushing tip comprises a first sharp corner and a second sharp corner connected to each other, the first sharp corner and the second sharp corner are respectively arranged at the ends of the pile tip body and the longitudinal rib plate, the longitudinal rib plate is arranged on the outside of the pile tip body, and a plurality of cutting sector ring steel sheets are spaced apart between the other end thereof and the pile head end plate;

[0010] The cover plate is arranged on the top of the topmost section of the pipe pile, and a hole is provided on the cover plate, and the grouting conduit passes through the hole;

[0011] The main part of the heat transfer medium delivery pipeline can be arranged in the inner cavity of the (1) pipe pile, or can be pre-buried in its side wall, or can be arranged along the outer wall of the pipe pile;

[0012] The two ends of the heat transfer medium delivery pipeline are respectively connected to the two sides of the heat exchange unit through the circulation pump.

[0013] In a preferred embodiment, the main part of the heat transfer medium delivery pipeline is arranged at a position selected from the following group: arranged in the inner cavity of the pipe pile, pre-buried in the side wall of the pipe pile, or arranged along the pipe wall outside the pipe pile;

[0014] In a preferred example, the pipe pile is made of solid waste materials as the main material, has a diameter of 600-1000 mm, and a bearing capacity of 500-2000 tons.

[0015] In a preferred example, the grouting conduit is a tube with an inner diameter of 15-25 mm and a wall thickness of 2-8 mm, and its materials include: aluminum-plastic tube.

[0016] In a preferred example, the thermally conductive enhanced grouting body is prepared by the following steps: firstly, a phase change material is mixed with an emulsifier to form a microemulsion, and then the microemulsion is mixed with a urease-producing microbial culture, a mixed solution containing a calcium source and urea.

[0017] In a preferred example, the valve system is selected from the following group: a four-way valve, an electronic expansion valve or a reversible cycle system.

[0018] In a preferred example, the heat exchange unit is composed of a compressor, an evaporator, a condenser, an expansion valve and a piping system.

[0019] In a preferred example, the main body of the heat transfer medium delivery pipeline is arranged in a spiral shape and fixed by a joint.

[0020] In a preferred example, the pipe pile further includes a heat-conducting strengthening structure, which is a structure formed by injecting the heat-conducting enhanced grouting body around the pipe pile through the grouting conduit and combining the pipe pile and soil into one after cooling.

[0021] The present application also discloses a method for installing a large-diameter non-squeezed soil high-bearing-capacity low-carbon energy pile, the method comprising the following steps:

[0022] S1. Drilling-pile driving;

[0023] S2. Connect the pile;

[0024] S3. Repeat S2 and S3 until the pile length reaches the designed length or the pile end is effectively embedded in the designed stratum;

[0025] S4. Grouting the pile side through the grouting pipe pre-buried in the pipe wall of the pile;

[0026] S5. After cleaning the bottom of the hole, pour concrete into the bottom of the hole through the tube cavity to form a bottom seal to complete the construction;

[0027] S6. Pile inspection;

[0028] S7 connects the heat transfer medium delivery pipeline to the circulation pump and the valve system, and then connects it to the heat exchange unit;

[0029] S8. Install the cover.

[0030] In a preferred example, the step between steps S7 and S8 further includes: injecting heat storage liquid into the cavity of the pipe pile.

[0031] In a preferred example, step S2 further includes: connecting the expandable and retractable drill bit to the long spiral drill rod and entering the stratum to be sunk through the inner cavity of the large-diameter pipe pile; driving the drill rod to drill, and the drill bit expands under the action of soil pressure to cause the diameter of the drilled hole to be larger than the outer diameter of the pipe pile, ensuring that the pipe pile sinks synchronously with the drill bit under the action of zero pile sinking resistance or a smaller pile sinking resistance; the residual soil generated by the drilling is brought out to the ground through the spiral blades on the long spiral drill rod in the inner cavity of the pipe pile.

[0032] In a preferred example, the step S3 further comprises: connecting the upper and lower sections of the pipe piles by welding and performing airtight treatment; and connecting the grouting conduits between the upper and lower sections of the pipe piles by a high-strength aluminum-plastic pipe.

[0033] In a preferred embodiment, the step S8 comprises: placing the cover plate on the top of the pipe pile and sealing the contact portion between the cover plate and the pipe pile; passing the pipe arranged in the pile through the reserved hole of the cover plate (4) and sealing the reserved hole.

[0034] On the other hand, the present application also discloses a method for preparing high-performance concrete, characterized in that the high-performance concrete is made of solid waste materials as the main materials, including: industrial materials containing active silicon and aluminum are first treated by one or more of alkali activation, thermal activation, mechanical activation, microbial activation, electrochemical activation and wet heat treatment methods to prepare high-performance cementitious materials, and then high-performance concrete is configured based on the cementitious materials.

[0035] In a preferred example, the method further comprises: adding microcapsule material to the high-performance gelling material, wherein the microcapsule material is prepared by first mixing a phase change material with an emulsifier to form a microemulsion, and then mixing the microemulsion with a urease-producing microbial culture, a mixed solution containing a calcium source and urea.

[0036] The advantages of the utility model include:

[0037] (1) Solid waste materials are used as the main materials. Through stimulation and adding special microcapsule materials, a low-carbon and high-strength pipe pile body is formed. This can effectively coordinate the contradiction between the heat conduction and high bearing capacity of the pipe pile, and has the advantages of being economical and low-carbon and reducing emissions.

[0038] (2) The use of special pile shoes and the drilling-pipe sinking-grouting process makes the energy pile of the utility model highly adaptable to underground rock and soil. It can fully utilize the strength of the surrounding rock and soil to improve the bearing capacity of the pile, and can fully exchange heat with the surrounding rock and soil.

[0039] (3) By forming a heat-conducting reinforcement structure around the pipe pile, on the one hand, the heat is transferred from the soil to the pile and then to the heat transfer system through the heat-conducting reinforcement structure. On the other hand, the entire pipe pile and the soil are strongly combined together, thereby improving the bearing capacity of the entire pile.

[0040] A large number of technical features are recorded in the specification of this application, which are distributed in various technical solutions. If all possible combinations of technical features of this application (i.e., technical solutions) are to be listed, the specification will be too long. In order to avoid this problem, the various technical features disclosed in the above-mentioned utility model content of this application, the various technical features disclosed in the various embodiments and examples below, and the various technical features disclosed in the accompanying drawings can be freely combined with each other to form various new technical solutions (these technical solutions should all be regarded as having been recorded in this specification), unless the combination of such technical features is technically infeasible. For example, in one example, feature A+B+C is disclosed, and in another example, feature A+B+D+E is disclosed, and features C and D are equivalent technical means that play the same role. Technically, only one can be used, and it is impossible to use them at the same time. Feature E can be combined with feature C technically. Then, the solution of A+B+C+D should not be regarded as having been recorded because it is technically infeasible, and the solution of A+B+C+E should be regarded as having been recorded. BRIEF DESCRIPTION OF THE DRAWINGS

[0041] Figure 1 It is a structural schematic diagram of a large-diameter non-squeezed soil high-bearing-capacity low-carbon energy pile according to the utility model;

[0042] Figure 2 It is a schematic diagram of the cross section of the pile foundation of the large-diameter non-squeezed soil high-bearing-capacity low-carbon energy pile according to the utility model;

[0043] Figure 3 It is a schematic diagram of the pile shoe of the large-diameter non-soil squeezing high-bearing-capacity low-carbon energy pile according to the utility model.

[0044] Description of reference numerals:

[0045] 1- pipe pile; 2- pile shoe; 3- bottom sealing body; 4- cover plate; 5- end plate; 6- grouting conduit; 7- sealing end; 8- slurry outlet; 9- heat conductivity enhanced grouting body; 10- heat transfer medium delivery pipeline; 11- circulation pump; 12- valve system; 13- heat exchange unit; 14- pile tip body; 15- crushing tip; 16- pile head end plate; 17- longitudinal rib plate; 18- cut fan ring steel sheet; 19- cut steel ring; 20- crushing shoe head; 21 special joint. DETAILED DESCRIPTION

[0046] After in-depth research and extensive screening, the inventor of the utility model has developed a large-diameter non-soil-extruding, high-bearing-capacity, low-carbon energy pile. Compared with the prior art, the present application uses solid waste materials as the main material, and through stimulation and the addition of special microcapsule materials, a low-carbon and high-strength pipe pile body is formed, which can effectively coordinate the contradiction between the heat conduction and high bearing capacity of the pipe pile, and has the advantages of economy, applicability, and low-carbon emission reduction. Not only that, the utility model also adopts a special pile shoe and a drilling-sinking-grouting process, so that the energy pile of the utility model has strong adaptability to underground rock and soil, which can fully utilize the strength of the surrounding rock and soil to improve the bearing capacity of the pile, and can fully exchange heat with the surrounding rock and soil.

[0047] In order to make the objectives, technical solutions and advantages of the present application clearer, the implementation methods of the present application will be further described in detail below in conjunction with the accompanying drawings.

[0048] Example

[0049] The large diameter non-squeezed soil high bearing capacity low carbon energy pile described in this embodiment is as follows Figures 1 to 3 As shown, it includes:

[0050] Pipe pile 1, pile shoe 2, bottom sealing body 3, cover plate 4, end plate 5, grouting conduit 6, grouting outlet 8, thermal conductivity enhanced grouting body 9, heat transfer medium delivery pipeline 10, circulation pump 11 and heat exchange unit 13; wherein:

[0051] The pipe pile 1 includes one or more, and the multiple pipe piles 1 are connected end to end. Optionally, in one embodiment, the pipe pile 1 is made of solid waste material as the main material, and the diameter is 600-2000mm. Optionally, in another embodiment, the multiple pipe piles 1 are connected by welding through the end plate 5.

[0052] The grouting conduit 6 is arranged in the side wall of the pipe pile 1 and a grouting outlet 8 is arranged at the bottom of the pipe pile 1 to cooperate with the grouting conduit 6;

[0053] The main part of the heat transfer medium delivery pipeline 10 can be arranged in the inner cavity of the pipe pile 1, or can be pre-buried in the side wall thereof, or can be arranged along the outer wall thereof;

[0054] The pile shoe 2 is arranged at the bottom end of the bottommost section of the pipe pile 1. Optionally, in one embodiment, the pile shoe 2 further comprises: a pile tip body 14, one end of the pile tip body 14 is provided with a plurality of crushing tips 15, and the other end is provided with a pile head end plate 16, the crushing tips 15 include a first sharp corner and a second sharp corner connected to each other, the first sharp corner and the second sharp corner are respectively arranged at the ends of the pile tip body and a longitudinal rib plate 17, the longitudinal rib plate 17 is arranged on the outside of the pile tip body 14, and a plurality of cutting sector ring steel sheets 18 are spaced between the other end thereof and the pile head end plate 16.

[0055] The cover plate 4 is arranged at the top of the pipe pile at the top section, and a hole is provided on the cover plate 4, through which the grouting conduit 6 passes. Optionally, in one embodiment, the grouting conduit 6 is a tube with an inner diameter of 15-25 mm and a wall thickness of 2-8 mm, and its material includes: aluminum-plastic tube.

[0056] Both ends of the heat transfer medium delivery pipeline 10 are connected to both sides of the heat exchange unit 13 through the circulation pump 11 .

[0057] Optionally, in one embodiment, the heat exchange unit is equipped with a valve system 12, and the valve system 12 includes: a four-way valve. Optionally, in another embodiment, the heat exchange unit 13 is composed of a compressor, an evaporator, a condenser, an expansion valve and a pipeline system.

[0058] Optionally, in one embodiment, the main body of the heat transfer medium delivery pipeline 10 is arranged in a spiral shape and fixed by a joint.

[0059] This embodiment also discloses a method for installing a large-diameter non-squeezed soil high-bearing-capacity low-carbon energy pile, the method comprising the following steps:

[0060] S1. Drilling-pile driving;

[0061] S2. Connect the pile;

[0062] S3. Repeat S2 and S3 until the pile length reaches the designed length or the pile end is effectively embedded in the designed stratum;

[0063] S4. Grouting the pile side through the grouting pipe pre-buried in the pipe wall of the pile;

[0064] S5. After cleaning the bottom of the hole, pour concrete into the bottom of the hole through the tube cavity to form a bottom seal to complete the construction;

[0065] S6. Pile inspection;

[0066] S7 connects the heat transfer medium delivery pipeline to the circulation pump and the valve system, and then connects it to the heat exchange unit;

[0067] S8. Install the cover.

[0068] Optionally, in one embodiment, the steps S7 and S8 further include: injecting thermal storage liquid into the cavity of the pipe pile, reserving a pipe hole on the cover plate for adding thermal storage liquid, and reserving monitoring equipment in the cavity. When the thermal storage liquid drops, the thermal storage liquid can be replenished through the reserved pipe hole, which is convenient for later maintenance.

[0069] Optionally, in one embodiment, step S2 further includes: connecting the expandable and retractable drill bit to the long spiral drill rod and entering the stratum to be sunk through the inner cavity of the large-diameter pipe pile; driving the drill rod to drill, and the drill bit expands under the action of soil pressure to cause the diameter of the drilled hole to be larger than the outer diameter of the pipe pile, thereby ensuring that the pipe pile sinks synchronously with the drill bit under the action of zero pile sinking resistance or a relatively small pile sinking resistance; the residual soil generated by the drilling is brought out to the ground through the spiral blades on the long spiral drill rod in the inner cavity of the pipe pile.

[0070] Optionally, in one embodiment, step S3 further comprises: the upper and lower sections of the pipe piles are connected by welding and sealed; the grouting conduits between the upper and lower sections of the pipe piles are connected by a high-strength aluminum-plastic pipe.

[0071] In a preferred embodiment, the step S8 further comprises: placing the cover plate 4 on the top of the pipe pile, and sealing the contact portion between the cover plate 4 and the pipe pile 1; passing the pipe arranged in the pile through the reserved hole of the cover plate 4, and sealing the reserved hole.

[0072] On the other hand, an embodiment further discloses a method for preparing high-performance concrete, characterized in that the high-performance concrete is made of solid waste materials as the main materials, including: industrial materials containing active silicon and aluminum are first treated by one or more of alkali activation, thermal activation, mechanical activation, microbial activation, electrochemical activation and wet heat treatment methods to prepare high-performance cementitious materials, and then high-performance concrete is configured based on the cementitious materials.

[0073] Optionally, in one embodiment, the method further comprises: adding a microcapsule material to the high-performance gelling material, wherein the microcapsule material is prepared by first mixing a phase change material with an emulsifier to form a microemulsion, and then mixing the microemulsion with a urease-producing microbial culture, a mixed solution containing a calcium source and urea.

[0074] It should be noted that in the application documents of this patent, relational terms such as first and second are only used to distinguish one entity or operation from another entity or operation, and do not necessarily require or imply any such actual relationship or order between these entities or operations. Moreover, the terms "include", "comprise" or any other variants thereof are intended to cover non-exclusive inclusion, so that the process, method, article or device including a series of elements includes not only those elements, but also other elements not explicitly listed, or also includes elements inherent to such process, method, article or device. In the absence of further restrictions, the elements defined by the sentence "including one" do not exclude the existence of other identical elements in the process, method, article or device including the elements. In the application documents of this patent, if it is mentioned that an action is performed according to an element, it means that the action is performed at least according to the element, which includes two situations: performing the action only according to the element, and performing the action according to the element and other elements. Expressions such as multiple, multiple, and multiple include 2, 2 times, 2 kinds, and more than 2, more than 2 times, and more than 2 kinds.

[0075] This specification includes combinations of the various embodiments described herein. Individual references to "one embodiment" or a particular embodiment, etc., do not necessarily refer to the same embodiment; however, these embodiments are not mutually exclusive unless indicated as mutually exclusive or clear to those skilled in the art. It should be noted that the word "or" is used in this specification in a non-exclusive sense unless the context clearly indicates or requires otherwise.

[0076] All documents mentioned in this application are considered to be included in the disclosure of this application as a whole, so that they can be used as the basis for modification when necessary. In addition, it should be understood that after reading the above disclosure of this application, those skilled in the art can make various changes or modifications to this application, and these equivalent forms also fall within the scope of protection claimed in this application.

Claims

1. A large diameter non-squeezed soil high bearing capacity low carbon energy pile, It is characterized in that include: Pipe piles, pile shoes, cover plates, end plates, grouting conduits, slurry outlets, heat transfer medium delivery pipelines, circulation pumps and heat exchange units; among which: The pipe piles include one or more, the plurality of pipe piles are connected end to end via end plates and the pipe piles are provided with inner cavities; The grouting conduit is arranged in the side wall of the pipe pile and the bottom of the pipe pile is provided with a grouting outlet in coordination with the grouting conduit; The pile shoe is arranged at the bottom end of the bottommost section of the pipe pile; the pile shoe comprises: a pile tip body, one end of the pile tip body is provided with a plurality of crushing tips, and the other end is provided with a pile head end plate, the crushing tip comprises a first sharp corner and a second sharp corner connected to each other, the first sharp corner and the second sharp corner are respectively arranged at the ends of the pile tip body and the longitudinal rib plate, the longitudinal rib plate is arranged on the outside of the pile tip body, and a plurality of cutting sector ring steel sheets are spaced between the other end thereof and the pile head end plate; The cover plate is arranged on the top of the topmost section of the pipe pile, and a hole is provided on the cover plate, and the grouting conduit passes through the hole; The main part of the heat transfer medium delivery pipeline is arranged at a position selected from the following group: arranged in the inner cavity of the pipe pile, pre-buried in the side wall of the pipe pile, or arranged along the pipe wall outside the pipe pile; The two ends of the heat transfer medium delivery pipeline are respectively connected to the two sides of the heat exchange unit through the circulation pump.

2. According to claim 1, a large-diameter non-squeezed soil high-bearing capacity low-carbon energy pile, It is characterized in that The diameter of the pipe pile is 600-2000mm, and the bearing capacity is 500-2000 tons.

3. According to claim 1, a large-diameter non-squeezed soil high-bearing-capacity low-carbon energy pile, It is characterized in that The plurality of pipe piles are connected by welding through end plates and are subjected to airtightness treatment, so that the leakage rate of the pipe piles under a pressure of 0.5 MPa is less than 1%.

4. According to claim 1, a large-diameter non-squeezed soil high-bearing-capacity low-carbon energy pile, It is characterized in that The pipeline of the pipe pile is connected to the heat exchange unit through a valve system, and the valve system is selected from the following group: a four-way valve, an electronic expansion valve or a reversible circulation system.

5. According to claim 1, a large-diameter non-squeezed soil high-bearing-capacity low-carbon energy pile, It is characterized in that The heat exchange unit is composed of a compressor, an evaporator, a condenser, an expansion valve and a pipeline system.

6. A large-diameter non-squeezed soil high-bearing-capacity low-carbon energy pile according to claim 1, It is characterized in that The main body of the heat transfer medium delivery pipeline is arranged in a spiral shape and fixed by a joint.