Temporary track dismantling device for shield tunnel construction
By designing the track loading system and the track transfer system, using components such as tongs, support columns and electric hoists, the difficulty and balance of temporary track removal devices in the existing technology is solved, and simple assembly and efficient track removal are achieved. transportation.
Patent Information
- Application Number
- CN202420630751.0
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-03-29
- Publication Date
- 2024-11-26
- Estimated Expiration
- 2034-03-29
AI Technical Summary
The installation of the existing temporary rail removal device for shield tunnels is difficult, and the parts processing requirements are special. The initial installation period is long, and balance problems and safety hazards are prone to occur when the rail lengths are different. Careless operation may lead to damage to the device.
A device including a track loading system and a track transfer system was designed. Using a tong, support column, walking beam, electric hoist and track holder, the lifting and transfer of the track is achieved through the sliding cooperation of the electric hoist, and the bottom of the tong The sliding of the shaft wheel and undeleted tracks realizes the transport of the tracks, and the splicing of the top frame and support columns simplifies assembly, reducing the complexity of the parts and the construction process.
The installation process of the device is simplified, the preliminary preparation time is shortened, the replacement and stability of parts are improved, the balance problems and safety hazards of rails are avoided, and the efficiency and safety of track removal and transportation are improved.
Smart Images

Figure CN222065051U_ABST
Abstract
Description
Technical Field
[0001] The utility model belongs to the technical field of track removal, and in particular relates to a temporary track removal device used for shield tunnel construction. Background Art
[0002] At present, shield tunnel construction and material transportation in underground projects all use tram transport in the tunnel. The shield tunnel is connected to the track synchronously during excavation. After the tunnel is through, the temporary track needs to be removed and transported to the outside of the tunnel for subsequent processes. At present, the temporary track removal and transportation of shield tunnels is carried out by manual removal from the terminal to the beginning, and then transported to the transport vehicle by the transport vehicle via the unremoved track to the designated place.
[0003] A Chinese patent document discloses a temporary track remover (Announcement No.: CN 206337470 U; Application No.: 201621400635.1). This technology uses a rail trolley for transportation. The track is removed and lifted by setting up a support frame, a cantilever beam, a moving platform and a lifting mechanism on a hopper chassis fixed on the rail trolley. The specific implementation process is: the rail trolley moves to the track to be removed, removes the track fixing parts, lowers the track clamp through an electric guide chain, rotates the operating shaft to make the track clamp tighten the track, then raises the guide chain to a certain height and turns on the motor to drive the roller to roll to a suitable position in the direction of the vehicle head, then drives the guide chain to lower the track to the hopper chassis, and finally rotates the operating shaft to loosen the track, and repeats this process. After the hopper chassis is filled with the track, the trolley drives to the wellhead, and cooperates with the gantry crane above the wellhead to lift the track out in two times using a sling.
[0004] Although the existing technology can dismantle and transport temporary tracks in shield tunnels, the device is difficult to set up and some parts need special processing to meet the use requirements. The motor of the mobile platform and the four small drive motors in the lifting mechanism are particularly difficult to set up, and the initial construction period is relatively long. When the lengths of the rails on both sides of the temporary track are different, if four rail clamps are used to clamp the rails on both sides at the same time, the balance of the rails cannot be guaranteed, and the rails are prone to fall to one side. If only two rail clamps on one side of the mobile platform are used to clamp the rails, the rollers of the mobile platform are unbalanced and the force is easily unbalanced, which may cause the rollers to be out of the groove and the rails to fall. There are no limiters at both ends of the cantilever beam on the support frame, which poses a safety hazard of over-limit of the mobile platform. The bottom of the support column of the device is flat and cannot fit with the circular pipe segment. After the rails stacked on the hopper chassis are tied up with a sling, the trolley needs to be moved to pull out and lift the rails. If the operation is not careful, the device may be damaged. Utility Model Content
[0005] In order to solve the above problems existing in the prior art, the utility model aims to provide a temporary track removal device for shield tunnel construction.
[0006] The technical solution adopted by the utility model is as follows: it includes a track loading system and a track transfer system installed on the track loading system, the track loading system includes a carrier, the bottom of the carrier is rotatably provided with an axle wheel, the top of the carrier is installed with a support column, the end of the support column away from the carrier is connected with a top frame, a walking beam is fixed between the top frames, an electric hoist is provided on the walking beam, the electric hoist is slidably connected to the walking beam, and a track clamp is hoisted on the electric hoist.
[0007] As a preferred embodiment of the utility model, a track placement space is formed between the support card and the top frame, and base frame rods are symmetrically provided at both ends of the top of the support card. The base frame rods are fixedly connected to the support card, and the support columns are welded at both ends of each of the base frame rods, and the axes of the support columns are perpendicular to the axes of the base frame rods.
[0008] As a preferred embodiment of the utility model, the support column is fixedly connected to the support card through a fixing rod, a U-shaped rod is provided at one end of the support column away from the base frame rod, the U-shaped rod is spliced with the support column, a pin hole is provided on the U-shaped rod, the pin hole passes through the U-shaped rod and the support column, a pin is provided in the pin hole, and the U-shaped rod and the support column are fixedly connected through the cooperation of the pin hole and the pin.
[0009] As a preferred embodiment of the present invention, a connecting rod is provided between the two U-shaped rods, both ends of the connecting rod are welded to the U-shaped rod, and the top frame is formed by splicing the two connecting rods and the two U-shaped rods.
[0010] As a preferred embodiment of the utility model, the walking beam is fixedly connected to the two U-shaped rods through fixed iron blocks, forming a sliding space on the walking beam, and the sliding space is located on the side of the U-shaped rod close to the support card. Lifting ears are respectively provided on both sides of the walking beam, and the two lifting ears are fixedly connected by bolts. A walking wheel compatible with the sliding space is rotatably provided between the two lifting ears.
[0011] As a preferred embodiment of the present invention, the top of the electric hoist is connected to the lifting eye, and the bottom of the electric hoist is connected to the track clamp.
[0012] As a preferred embodiment of the utility model, both ends of the walking beam are provided with walking wheel limit blocks, the walking wheel limit blocks are fixedly connected to the walking beam, and the walking wheel limit blocks are used to limit the maximum sliding stroke of the walking wheels.
[0013] As a preferred embodiment of the utility model, it further comprises an electric locomotive, wherein the electric locomotive is used to provide traction for the rail loading system and provide working voltage for the electric hoist.
[0014] The beneficial effects of the utility model are:
[0015] 1. The utility model is a temporary track removal device for shield tunnel construction. A track transfer system is installed on a track loading system. The track is hoisted by an electric hoist in the track transfer system. After the track is hoisted, the track can be slid in the track loading system through the sliding cooperation on the top of the electric hoist, so that the removed track can be transferred to a tray for storage. The removed track is finally slid with the unremoved track through the shaft wheel installed on the bottom of the tray, so that the removed track can be transferred to a desired place. The loading space for the removed track is spliced with a top frame, a support column and a tray. The raw materials of the track loading system are easy to obtain and easy to process. The frame components only need to be welded or cut. The track transfer and lifting mechanism can be directly purchased as finished products. The device has few construction steps, short preparatory work time, and high parts interchangeability and device stability.
[0016] 2. There are pockets inside the carrier to hold a large number of track connecting plates cut off during track removal.
[0017] 3. The top of the device is a detachable frame. After unplugging the pin and removing the top frame, the track can be lifted at one time.
[0018] 4. The device can be dismantled by simple cutting and re-welded when needed. The device has a high reuse rate and is more economical. BRIEF DESCRIPTION OF THE DRAWINGS
[0019] The utility model is further described in detail below with reference to the accompanying drawings and specific implementation methods.
[0020] Figure 1 It is a schematic diagram of the overall structure of the utility model;
[0021] Figure 2 This utility model Figure 1 A schematic diagram of the enlarged structure at point A;
[0022] Figure 3 This utility model Figure 1 Schematic diagram of the enlarged structure at B.
[0023] In the figure: 1. track loading system; 2. track transfer system; 11. support card; 12. support column; 13. top frame; 14. axle wheel; 21. walking beam; 22. electric hoist; 23. track clamp; 111. base frame rod; 112. fixing rod; 113. track placement space; 131. connecting rod; 132. U-shaped rod; 133. pin hole; 134. pin; 211. sliding space; 212. lifting ear; 213. running wheel; 214. fixing iron block; 215. running wheel limit block; 216. fixing bolt. DETAILED DESCRIPTION
[0024] In order to make the purpose, technical solution and advantages of the utility model more clear, the utility model is further described in detail below in conjunction with the accompanying drawings and embodiments. It should be understood that the specific embodiments described herein are only used to explain the utility model and are not used to limit the utility model, that is, the described embodiments are only part of the embodiments of the utility model, not all of the embodiments. The components of the embodiments of the utility model described and shown in the drawings here can be arranged and designed in various different configurations.
[0025] Therefore, the following detailed description of the embodiments of the utility model provided in the accompanying drawings is not intended to limit the scope of the utility model claimed for protection, but merely represents selected embodiments of the utility model. Based on the embodiments of the utility model, all other embodiments obtained by those skilled in the art without creative work are within the scope of protection of the utility model.
[0026] Combine the following Figure 1-3 The specific implementation mode of the utility model is described, a temporary track removal device for shield tunnel construction, comprising a track loading system 1 and a track transfer system 2 installed on the track loading system 1, the track loading system 1 comprising a toggle 11, a shaft wheel 14 is rotatably provided at the bottom of the toggle 11, a support column 12 is installed on the top of the toggle 11, a top frame 13 is connected to the end of the support column 12 away from the toggle 11, a walking beam 21 is fixed between the top frames 13, an electric hoist 22 is provided on the walking beam 21, the electric hoist 22 is slidably connected to the walking beam 21, and a track clamp 23 is hoisted on the electric hoist 22.
[0027] In this embodiment, please refer to Figure 1 and 2 A track placement space 113 is formed between the toggle switch 11 and the top frame 13, and the track placement space 113 is used to carry and store the dismantled tracks, and multiple dismantled tracks can be stacked and stored. The top two ends of the toggle switch 11 are symmetrically provided with bottom frame rods 111, and the bottom frame rods 111 are fixedly connected to the toggle switch 11, and the support columns 12 are welded at both ends of each bottom frame rod 111, and the axis of the support column 12 is perpendicular to the axis of the bottom frame rod 111. A bottom frame rod 111 is fixedly connected to the two ends of the toggle switch 11 in the length direction, and the bottom of the bottom frame rod 111 is welded to the top of the toggle switch 11, and the top of the bottom frame rod 111 is used to weld the support column 12. In this embodiment, the number of the support columns 12 is four, which correspond to the four corners of the top surface of the shaft wheel 14, and the bottom of the support column 12 is also reinforced and fixed by a fixing rod 112 to improve the strength of the connection between the support column 12 and the toggle switch 11.
[0028] For further details of this embodiment, please refer to Figure 1 and 2 The support column 12 is fixedly connected to the support card 11 through a fixing rod 112, and the support column 12 is provided with a U-shaped rod 132 at one end away from the base rod 111, and the U-shaped rod 132 is spliced with the support column 12, and a latch hole 133 is provided on the U-shaped rod 132, and the latch hole 133 passes through the U-shaped rod 132 and the support column 12, and a latch 134 is provided in the latch hole 133. The U-shaped rod 132 and the support column 12 are fixedly connected through the latch hole 133 and the latch 134. The top of the support column 12 is inserted into the U-shaped rod 132, and the U-shaped rod 132 is installed and connected to the support column 12 through the cooperation of the latch 134 and the latch hole 133, so that a detachable connection is formed between the U-shaped rod 132 and the support column 12, so as to facilitate the storage of the disassembled rail to be hoisted out of the rail loading system 1.
[0029] For details of this embodiment, please refer to Figure 1 and 2 A connecting rod 131 is provided between the two U-shaped rods 132, and both ends of the connecting rod 131 are welded to the U-shaped rod 132. The top frame 13 is formed by splicing the two connecting rods 131 and the two U-shaped rods 132. The top frame 13 is spliced by two connecting rods 131 and two U-shaped rods 132. The U-shaped rod 132 and the connecting rod 131 are welded, and the top frame 13 is detachably connected to multiple support columns 12.
[0030] In this embodiment, please refer to Figure 1-3The walking beam 21 is fixedly connected to the two U-shaped rods 132 through a fixed iron block 214, and a sliding space 211 is formed on the walking beam 21. The sliding space 211 is located on the side of the U-shaped rod 132 close to the tocar 11. Lifting ears 212 are respectively provided on both sides of the walking beam 21. The two lifting ears 212 are fixedly connected by bolts. A running wheel 213 adapted to the sliding space 211 is rotatably provided between the two lifting ears 212. The walking beam 21 is overlapped and fixed on the two U-shaped rods 132 through a fixed iron block 214 to achieve a fixed connection between the U-shaped rod 132 and the walking beam 21. A sliding space 211 is formed in the middle of the walking beam 21. The sliding space 211 is used for the electric hoist The back-and-forth sliding of the reed 22 allows the demolition track hoisted by the electric hoist 22 to slide into the track placement space 113 through the walking beam 21, so as to avoid manual handling and improve the transfer speed of the track. Specifically, the sliding of the electric hoist 22 is achieved by the lifting ears 212 clamped on both sides of the sliding space 211. The two lifting ears 212 are respectively located on the opposite sides of the sliding space 211 and are fixedly connected to each other by fixing bolts 216, which effectively limit the lateral position of the running wheel 213 to avoid derailment. A running wheel 213 is rotatably provided between the two lifting ears 212. Through the sliding connection between the running wheel 213 and the sliding space 211, the electric hoist 22 can finally slide back and forth along the length direction of the walking beam 21 to realize the handling of the demolished track.
[0031] The top of the electric hoist 22 is connected to the lifting ear 212, and the bottom of the electric hoist 22 is connected to the track clamp 23. The electric hoist 22 is driven by an electric power station, and is first lowered onto the track, the track clamp 23 is connected to the track, and finally the height of the track clamp 23 is raised to realize the lifting of the track, and finally slides into the track placement space 113.
[0032] Wheel limit blocks 215 are provided at both ends of the walking beam 21 , and the wheel limit blocks 215 are fixedly connected to the walking beam 21 . The wheel limit blocks 215 are used to limit the maximum sliding stroke of the wheels 213 to prevent the wheels 213 from sliding off the track.
[0033] It also includes an electric locomotive (not shown), which is a commonly used vehicle in track maintenance. It provides traction for the track loading system 1 and provides electrical energy to the electric hoist 22 to ensure its normal operation. The electric locomotive pulls the track loading system 1 to slide on the unremoved track, so that the removed track can be transferred to the required position. The electric locomotive is used to provide traction for the track loading system 1 and provide working voltage for the electric hoist 22.
[0034] Working principle of this utility model:
[0035] First, the track is removed, and the track clamp 23 is slid between the top of the electric hoist 22 and the walking beam 21 to slide the track clamp 23 onto the removed track, and the electric hoist 22 is controlled to lower the height of the track clamp 23 so that it can be limitedly connected with the removed track, and the track clamp 23 is connected to the removed track, and the hoisted track is raised by the electric hoist 22 to make it off the ground;
[0036] The sliding of the electric hoist 22 is achieved by the cooperation between the running wheel 213 on the top of the electric hoist 22 and the sliding space 211. The running wheel 213 rotates between the two lifting ears 212. The lifting ears 212 can limit the lateral position of the running wheel 213 to prevent the running wheel 213 from leaving the track. The sliding of the running wheel 213 in the sliding space 211 is manually pushed. After the removed track is hoisted, the running wheel 213 and the sliding space 211 are pushed to slide, so that the track finally slides to the track placement space 113 in the track loading system 1 for storage.
[0037] After the rail enters the rail placement space 113, the electric hoist 22 is controlled to descend so that it falls into the carrier 11, and the rail clamp 23 is released from clamping the clamped rail, so that the rail is transferred from the ground to the rail loading system 1, and multiple rails are transferred back and forth until the rails are fully stacked in the rail placement space 113. Finally, the rail loading system 1 is pulled by the electric locomotive to slide on the unremoved rail to realize the transfer of the removed rail.
[0038] Among them, the assembly of the track loading system 1 is composed of a top frame 13 and multiple support columns 12. The top frame 13 is detachably connected to the multiple support columns 12 through the pin holes 133 and the pins 134 on the U-shaped rod 132. The detachable connection can facilitate the unloading of the track in the track placement space 113, and the track can be lifted at one time, thereby improving the unloading efficiency.
[0039] In the description of the present invention, it should be noted that, unless otherwise clearly specified and limited, the terms "installed", "connected", "connected", etc. should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection, or an indirect connection through an intermediate medium, or it can be the internal communication of two components. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.
[0040] The above contents are merely examples and explanations of the structure of the utility model. The technicians in this technical field may make various modifications or additions to the specific embodiments described or replace them in a similar manner. As long as they do not deviate from the structure of the utility model or exceed the scope defined in the claims, they should all fall within the protection scope of the utility model.
Claims
1. A temporary track removal device for shield tunnel construction, characterized in that: It includes a track loading system and a track transfer system installed on the track loading system. The track loading system includes a carrier. The bottom of the carrier is rotatably provided with an axle wheel. The top of the carrier is installed with a support column. The end of the support column away from the carrier is connected with a top frame. A walking beam is fixed between the top frames. An electric hoist is provided on the walking beam. The electric hoist is slidably connected to the walking beam. A track clamp is hoisted on the electric hoist.
2. A temporary track removal device for shield tunnel construction according to claim 1, characterized in that: A track placement space is formed between the support card and the top frame, and base rods are symmetrically provided at both ends of the top of the support card. The base rods are fixedly connected to the support card, and the support columns are welded at both ends of each base rod, and the axes of the support columns are perpendicular to the axes of the base rods.
3. A temporary track removal device for shield tunnel construction according to claim 2, characterized in that: The support column is fixedly connected to the support card through a fixing rod, and a U-shaped rod is provided at one end of the support column away from the base rod, and the U-shaped rod is spliced with the support column. A latch hole is provided on the U-shaped rod, and the latch hole passes through the U-shaped rod and the support column. A latch is provided in the latch hole, and the U-shaped rod and the support column are fixedly connected through the cooperation of the latch hole and the latch.
4. A temporary track removal device for shield tunnel construction according to claim 3, characterized in that: A connecting rod is arranged between the two U-shaped rods, and both ends of the connecting rod are welded to the U-shaped rods. The top frame is formed by splicing the two connecting rods and the two U-shaped rods.
5. The temporary track removal device for shield tunnel construction according to claim 3, characterized in that: The walking beam is fixedly connected to the two U-shaped rods through fixed iron blocks, and a sliding space is formed on the walking beam. The sliding space is located on the side of the U-shaped rod close to the toca. Lifting ears are respectively provided on both sides of the walking beam, and the two lifting ears are fixedly connected by bolts. A walking wheel adapted to the sliding space is rotatably provided between the two lifting ears.
6. The temporary track removal device for shield tunnel construction according to claim 5, characterized in that: The top of the electric hoist is connected to the lifting lug, and the bottom of the electric hoist is connected to the track clamp.
7. A temporary track removal device for shield tunnel construction according to claim 6, characterized in that: Wheel limit blocks are provided at both ends of the walking beam, the wheel limit blocks are fixedly connected to the walking beam, and the wheel limit blocks are used to limit the maximum sliding stroke of the walking wheel.
8. The temporary track removal device for shield tunnel construction according to claim 1, characterized in that: It also includes an electric locomotive, which is used to provide traction for the rail loading system and provide working voltage for the electric hoist.