Waterproof structure for construction joint of single-layer buried section of open-cut tunnel
By using combined technologies such as spraying fast-gel rubber asphalt waterproof coating, cement-based permeable crystal waterproof coating and water-expanded putty blocks in open-cut tunnels, the problem of water leakage in tunnel construction joints is solved, forming a continuous waterproof layer, and improving the tunnel's Lifespan and safety.
Patent Information
- Application Number
- CN202323320118.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2023-12-06
- Publication Date
- 2024-11-26
- Estimated Expiration
- 2033-12-06
AI Technical Summary
During the construction of the hidden buried section of the open-dig tunnel, the longitudinal construction joints and annular construction joints of the tunnel body are prone to leakage, affecting the service life and safety of the tunnel structure.
Adopt a waterproof structure including tunnel body, enclosure structure and medium buried steel edge rubber water stop. By spraying a combination of quick-coagulated rubber asphalt waterproof coating and cement-based permeable crystal waterproof coating, combining water expansion putty blocks and steel plate water stops Belts, forming a continuous integrated all-inclusive waterproofing system, sealing construction joints to prevent leakage.
It effectively alleviates the problem of poor waterproof performance in open-cut tunnels, forms a continuous and complete waterproof layer, prevents water leakage, and improves the service life and safety of the tunnel structure.
Smart Images

Figure CN222065575U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the field of building waterproof construction, in particular to a waterproof structure for construction joints of a single-layer concealed section of an open-cut tunnel. Background Art
[0002] The construction methods of tunnels under urban roads at home and abroad can be divided into open-cut method and dark-cut method. When the tunnel is shallow, the open-cut method is generally used, and when the tunnel is deep, the dark-cut method is generally used. According to the excavation depth of the foundation pit, engineering geology, hydrogeology and surrounding environmental conditions, the open-cut method can adopt slope excavation, combined with retaining structures such as soil nail walls, anchor retaining walls, and pile rows. When there are dense buildings around the foundation pit, pile row retaining structures are generally set up. The construction sequence of the open-cut tunnel is usually to construct the foundation pit retaining structure first, then excavate the rock and soil from top to bottom in layers, cast the tunnel lining structure after excavating to the bottom of the pit, and finally backfill the top of the tunnel to restore the surface.
[0003] For the construction of the buried section of the open-cut tunnel, the longitudinal construction joints and annular construction joints of the tunnel body are nodes that are prone to water seepage. If the sealing measures for the nodes are not perfect, the resulting water leakage will affect the service life and safety of the tunnel structure. Utility Model Content
[0004] The utility model aims to provide a waterproof structure for construction joints of a single-layer buried section of an open-cut tunnel, so as to solve the problem that longitudinal construction joints and annular construction joints of a tunnel body are prone to water leakage in the prior art.
[0005] Based on the above purpose, the present application provides a waterproof structure for construction joints of a single-layer buried section of an open-cut tunnel, comprising a tunnel body, a retaining structure and a centrally embedded steel-edge rubber waterstop;
[0006] The tunnel body comprises a bottom plate, a side wall and a top plate which are cast in sequence from bottom to top, and a first fine stone concrete protective layer, a first sprayed quick-setting rubber asphalt waterproof coating layer, a non-woven fabric layer and a concrete cushion layer are sequentially arranged below the bottom plate;
[0007] The enclosure structure is arranged on the outside of the side wall, and a second sprayed quick-setting rubber asphalt waterproof coating layer and a base surface leveling layer are sequentially arranged between the side wall and the enclosure structure;
[0008] Furthermore, the first sprayed quick-setting rubber asphalt waterproof coating layer and the second sprayed quick-setting rubber asphalt waterproof coating layer are formed by continuous spraying;
[0009] A third sprayed quick-setting rubber asphalt waterproof coating layer and a second fine stone concrete protective layer are sequentially arranged on the top of the top plate from bottom to top;
[0010] In addition, an embedded steel-edge rubber waterstop is arranged between each section of the circumferential construction joints along the extension direction of the tunnel body, wherein both side ends of the embedded steel-edge rubber waterstop are respectively wrapped with water-expandable putty blocks.
[0011] Furthermore, the embedded steel-edge rubber waterstop includes a rubber connecting belt and a steel belt, and the two ends of the rubber connecting belt are respectively connected to the steel belt; and the two sides of the center line of the rubber connecting belt in the length direction are respectively wrapped with water-expandable putty blocks.
[0012] Furthermore, a first grouting conduit is pre-buried in the annular construction joint of the side wall, and is used to fill the annular construction joint outside the embedded steel edge rubber water stop with cement-based penetrating crystallization waterproof coating;
[0013] Furthermore, the annular construction joint inside the embedded steel-edge rubber waterstop is filled with water-swellable waterstop glue.
[0014] Furthermore, a second grouting conduit is pre-buried in the annular construction joint of the base plate, and is used to fill the annular construction joint below the embedded steel edge rubber water stop with cement-based penetrating crystallization waterproof coating;
[0015] Furthermore, the annular construction joint above the embedded steel-edge rubber waterstop is filled with water-swellable waterstop glue.
[0016] Furthermore, the longitudinal construction joint between the base plate and the side wall is filled with a cement-based penetrating crystalline waterproof coating, and a steel plate waterstop is provided in a direction perpendicular to the construction joint, and a water-swellable waterproof glue is filled between the steel plate waterstop and the longitudinal construction joint; a third grouting conduit is embedded in the side wall for injecting a cement-based penetrating crystalline waterproof coating into the longitudinal construction joint.
[0017] Furthermore, the steel plate waterstop and the steel strip of the embedded steel-edge rubber waterstop are connected by rivets.
[0018] Furthermore, a fourth grouting conduit is pre-buried in the annular construction joint of the top plate, and is used to fill the annular construction joint above the embedded steel edge rubber water stop with a cement-based penetrating crystalline waterproof coating;
[0019] Furthermore, the annular construction joint below the embedded steel-edge rubber waterstop is filled with water-swellable waterstop glue.
[0020] Furthermore, a middle wall is cast between the top plate and the bottom plate, and the longitudinal construction joints between the middle wall and the top plate and the bottom plate are filled with cement-based penetrating crystallization waterproof coating;
[0021] The annular construction joint of the middle wall is filled with cement-based penetrating crystallization waterproof coating, and water-expanding water-stopping glue is filled on both sides of the annular construction joint.
[0022] Furthermore, the base leveling layer extends downward to the connection between the concrete cushion layer and the enclosure structure to form a cement mortar chamfer;
[0023] A first sprayed quick-setting rubber asphalt waterproof coating reinforcement layer is arranged between the cement mortar chamfer and the first sprayed quick-setting rubber asphalt waterproof coating layer and the second sprayed quick-setting rubber asphalt waterproof coating layer.
[0024] Further, a second sprayed quick-setting rubber asphalt waterproof coating reinforcement layer is sprayed again on the inner side of the second sprayed quick-setting rubber asphalt waterproof coating layer directly opposite to the circumferential construction joint on the side wall;
[0025] A third sprayed quick-setting rubber asphalt waterproof coating reinforcement layer is sprayed again on the inner side of the first sprayed quick-setting rubber asphalt waterproof coating layer directly opposite to the circumferential construction joint on the bottom plate;
[0026] A fourth spray quick-setting rubber asphalt waterproof coating reinforcement layer is sprayed again on the inner side of the third spray quick-setting rubber asphalt waterproof coating layer directly opposite to the circumferential construction joint on the top plate.
[0027] By adopting the above technical solution, the present application provides a waterproof structure for construction joints of a single-layer buried section of an open-cut tunnel. Compared with the prior art, the following technical effects are achieved:
[0028] In the technical solution of the present application, firstly, by spraying the first quick-setting rubber asphalt waterproof coating layer, the second quick-setting rubber asphalt waterproof coating layer and the third quick-setting rubber asphalt waterproof coating layer on the outer sides of the bottom plate, the side wall and the top plate, the waterproof coating is directly and fully adhered to the structural surface without peeling or water leakage, and the waterproof layer is continuous and complete, forming a continuous overall all-inclusive waterproof system for the entire tunnel structure; secondly, an embedded steel-edge rubber waterstop is arranged between each section of the circumferential construction joints along the extension direction of the tunnel body, wherein the two side ends of the embedded steel-edge rubber waterstop are respectively wrapped with water-expandable putty blocks. During construction, before pouring concrete on one side, the water-expandable putty is used to seal the waterstop. The sub-block wraps half of the cross-section of the end of the embedded steel-edge rubber waterstop, and the putty block exceeds the end of the rubber waterstop, and then concrete is poured; before pouring concrete on the other side, the same water-swelling putty block is used to wrap the remaining cross-section of the waterstop end, and then concrete is poured, so that the embedded steel-edge rubber waterstop is used in combination with the water-swelling putty block, and is fully integrated with the concrete on both sides of the circumferential construction joint. Combined with the first sprayed quick-setting rubber asphalt waterproof coating layer, the second sprayed quick-setting rubber asphalt waterproof coating layer and the third sprayed quick-setting rubber asphalt waterproof coating layer on the outside, it can effectively alleviate the problem of poor waterproof performance of open-cut tunnels and easy water leakage in the prior art. BRIEF DESCRIPTION OF THE DRAWINGS
[0029] In order to more clearly illustrate the specific implementation methods of the utility model or the technical solutions in the prior art, the drawings required for use in the specific implementation methods or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are some implementation methods of the utility model. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative work.
[0030] Figure 1 A schematic diagram of the structure of a waterproof structure for a construction joint of a single-layer buried section of an open-cut tunnel provided in an embodiment of the present application;
[0031] Figure 2 for Figure 1 Sectional view at AA in the middle;
[0032] Figure 3 for Figure 2 Schematic diagram of the structure of the embedded steel-edge rubber waterstop and concrete;
[0033] Figure 4 This is a structural diagram of the embedded steel-edge rubber waterstop;
[0034] Figure 5 for Figure 1 Sectional view at the middle BB;
[0035] Figure 6 for Figure 1 Sectional view at CC;
[0036] Figure 7 for Figure 1 Sectional view at DD in the middle;
[0037] Figure 8 for Figure 1 Schematic diagram of the structure at E in the middle;
[0038] Fig. 9 for Figure 1 The structural diagram of the F position in the middle;
[0039] Fig.10 This is a schematic diagram of the connection structure between the steel plate waterstop and the embedded steel-edge rubber waterstop.
[0040] Icons: 100-tunnel body; 110-side wall; 111-first grouting conduit; 120-bottom plate; 121-first fine stone concrete protective layer; 122-first sprayed quick-setting rubber asphalt waterproof coating layer; 123-non-woven fabric layer; 124-concrete cushion layer; 126-third grouting conduit; 128-water-expanding water-stop glue; 129-steel plate waterstop; 130-longitudinal construction joint; 140-circumferential construction joint; 141-second grouting conduit; 143-fourth grouting conduit; 150-top plate; 151-third sprayed quick-setting rubber asphalt waterproof coating layer; 152-second fine stone concrete protective layer; 160-middle wall; 200-enclosing structure; 210-second sprayed quick-setting rubber asphalt waterproof coating layer; 220-base leveling layer; 230-cement mortar chamfer; 240-first sprayed quick-setting rubber asphalt waterproof coating reinforcement layer; 250-first sprayed quick-setting rubber asphalt waterproof coating reinforcement layer; 260-third sprayed quick-setting rubber asphalt waterproof coating reinforcement layer; 270-butyl rubber putty sheet; 280-fourth sprayed quick-setting rubber asphalt waterproof coating reinforcement layer; 300-buried steel-edge rubber waterstop; 301-rubber connecting belt; 302-steel belt; 310-water-expanding putty block; 400-rivet. DETAILED DESCRIPTION
[0041] The technical solution of the utility model will be described clearly and completely below in conjunction with the accompanying drawings. Obviously, the described embodiments are part of the embodiments of the utility model, not all of the embodiments. Based on the embodiments of the utility model, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the utility model.
[0042] In the description of the present invention, it should be noted that the terms "center", "upper", "lower", "left", "right", "vertical", "horizontal", "inner", "outer", etc., indicating the orientation or positional relationship, are based on the orientation or positional relationship shown in the drawings, and are only for the convenience of describing the present invention and simplifying the description, rather than indicating or implying that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore cannot be understood as limiting the present invention. In addition, the terms "first", "second", and "third" are used for descriptive purposes only, and cannot be understood as indicating or implying relative importance.
[0043] In the description of the present invention, it should be noted that, unless otherwise clearly specified and limited, the terms "installation", "connection" and "connection" should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection, or it can be indirectly connected through an intermediate medium, or it can be the internal communication of two components. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.
[0044] like Figures 1 to 9 As shown, an embodiment of the present application provides a waterproof structure for construction joints of a single-layer buried section of an open-cut tunnel, comprising a tunnel body 100, a retaining structure 200 and a centrally embedded steel-edge rubber waterstop 300;
[0045] The tunnel body 100 includes a side wall 110, a bottom plate 120 and a top plate 150, and a first fine stone concrete protective layer 121, a first sprayed quick-setting rubber asphalt waterproof coating layer 122, a non-woven fabric layer 123 and a concrete cushion layer 124 are sequentially arranged below the bottom plate 120;
[0046] The enclosure structure 200 is arranged on the outside of the side wall 110, and the second sprayed quick-setting rubber asphalt waterproof coating layer 210 and the base surface leveling layer 220 are arranged in sequence between the side wall 110 and the enclosure structure 200; that is, the base surface leveling layer 220 is arranged on the inner side of the side wall 110, and the second sprayed quick-setting rubber asphalt waterproof coating layer 210 is sprayed on the inner side of the base surface leveling layer 220, and then the side wall 110 is cast;
[0047] Furthermore, the first sprayed quick-setting rubber asphalt waterproof coating layer 122 and the second sprayed quick-setting rubber asphalt waterproof coating layer 210 are formed by continuous spraying.
[0048] It should be noted that Figure 3 The second sprayed quick-setting rubber asphalt waterproof coating layer 210 is shown to have a certain gap with the base surface leveling layer 220. The main purpose is to facilitate the clear display of the structure of the second sprayed quick-setting rubber asphalt waterproof coating layer 210 and the base surface leveling layer 220. In fact, the second sprayed quick-setting rubber asphalt waterproof coating layer 210 should be sprayed on the base surface leveling layer 220.
[0049] A third sprayed quick-setting rubber asphalt waterproof coating layer 151 and a second fine stone concrete protective layer 152 are sequentially arranged on the top plate 150 from bottom to top;
[0050] In addition, an embedded steel-edged rubber waterstop 300 is arranged between each section of the annular construction joints 140 along the extension direction of the tunnel body 100, wherein the two side ends of the embedded steel-edged rubber waterstop 300 are respectively wrapped with water-expandable putty blocks 310, and the above-mentioned annular construction joints 140 include construction joints between each section of the bottom plate 120, construction joints between the side walls 110 and construction joints between the top plates 150, and the above-mentioned construction joints are surrounded to form an annular construction joint 140.
[0051] In the technical solution of the present application, by spraying the first spray quick-setting rubber asphalt waterproof coating layer 122, the second spray quick-setting rubber asphalt waterproof coating layer 210 and the third spray quick-setting rubber asphalt waterproof coating layer 151 on the outer sides of the bottom plate 120, the side wall 110 and the top plate 150, the waterproof coating is directly fully adhered to the structural surface, without peeling or water leakage, the waterproof layer is continuous and complete, and a continuous overall all-inclusive waterproof system can be formed for the entire tunnel structure;
[0052] Reference Figures 1 to 4 A buried steel-edge rubber waterstop 300 is arranged between each section of the circumferential construction joints 140 along the extension direction of the tunnel body 100, wherein the ends of the buried steel-edge rubber waterstop 300 are respectively wrapped with water-expandable putty blocks 310. During construction, before pouring concrete on one side, half of the end of the buried steel-edge rubber waterstop 300 is wrapped with the water-expandable putty block 310, and the putty block exceeds the end of the rubber waterstop, and then concrete is poured; before pouring concrete on the other side, the same water-expandable putty block is used to wrap the end of the end of the buried steel-edge rubber waterstop 300. 310 wraps the remaining waterstop end section, and then pours concrete, so that the embedded steel-edge rubber waterstop 300 is used in combination with the water-expandable putty block 310, and is fully integrated with the concrete on both sides of the circumferential construction joint 140, combined with the first sprayed quick-setting rubber asphalt waterproof coating layer 122, the second sprayed quick-setting rubber asphalt waterproof coating layer 210 and the third sprayed quick-setting rubber asphalt waterproof coating layer 151 on the outside, it can effectively alleviate the problem of poor waterproof performance of open-cut tunnels in the prior art, which is prone to water leakage.
[0053] In this embodiment, the first sprayed quick-setting rubber asphalt waterproof coating layer 122, the second sprayed quick-setting rubber asphalt waterproof coating layer 210 and the third sprayed quick-setting rubber asphalt waterproof coating layer 151 all adopt a sprayed quick-setting rubber asphalt waterproof coating provided in the publication number CN107964362A, including component A and component B; component A includes anionic hard emulsified asphalt and polymer latex, and the needle penetration of the anionic hard emulsified asphalt is 30-50; component B includes a coagulant; wherein the polymer latex is a modified polymer latex, and the modified polymer latex is obtained by reacting a polymer latex containing a carboxyl group and a cross-linking agent that can react with the carboxyl group, and the cross-linking agent includes a coupling agent. one or more of an agent, a metal oxide, sulfur, a peroxide, an amine crosslinking agent, an epoxy compound and an isocyanate; the crosslinking reaction temperature of the carboxyl-containing polymer latex and the crosslinking agent is 20-25°C; in the component A, the weight proportion of the anionic hard emulsified asphalt is 30-90, and the weight proportion of the polymer latex is 10-70; in the component B, the concentration of the coagulant is 3-20%; the weight proportion ratio of the component A to the component B is 2:1-15:1; the tensile strength of the spray-applied quick-setting rubber asphalt waterproof coating reaches above 1.2MPa, the heat resistance reaches above 160°C, and the low temperature temperature is as low as below -25°C.
[0054] Based on the addition of anionic hard emulsified asphalt in component A, the prepared spray-coated quick-setting rubber asphalt waterproof coating has the characteristics of high tensile strength, good heat resistance and low low-temperature sensitivity, and is suitable for use in high-temperature construction environments and low-temperature environments. Since the material of the spray-coated quick-setting rubber asphalt waterproof coating topcoat belongs to the prior art, its specific components are not described in detail in this embodiment.
[0055] The spray-applied quick-setting rubber asphalt waterproof coating has no overlaps, which solves the risk of water seepage caused by overlaps; it provides perfect coverage to solve the problem of waterproofing special-shaped structures; it can cope with harsh natural exposed environments and has ultra-wide resistance to high and low temperatures, as well as ozone aging; it has high tensile strength, good heat resistance and low low-temperature temperature, and multiple properties of the waterproof coating are improved.
[0056] Reference Figure 4 Preferably, the embedded steel-edge rubber waterstop 300 includes a rubber connecting belt 301 and a steel belt 302, and the two ends of the rubber connecting belt 301 are respectively connected to the steel belt 302; the two sides of the center line of the rubber connecting belt 301 in the length direction are respectively wrapped with water-swelling putty blocks 310; through the use of the water-swelling putty blocks 310, a better sealing and waterproofing effect is achieved between the rubber connecting belt 301 and the steel belt 302 and the poured concrete.
[0057] Preferably, the embedded steel-edged rubber waterstop 300 is adapted to the cross-sectional shape of the tunnel body, that is, the embedded steel-edged rubber waterstop 300 is arranged as a U-shape as a whole, matching the shape of the bottom plate 120 and the side wall 110 of the tunnel body 100, so as to play a sufficient waterproof role.
[0058] Reference Figure 2 Preferably, a first grouting conduit 111 is pre-buried in the annular construction joint 140 of the side wall 110, and is used to fill the annular construction joint 140 on the outer side of the embedded steel-edge rubber waterstop 300 with a cement-based penetrating crystalline waterproof coating; and the annular construction joint 140 on the inner side of the embedded steel-edge rubber waterstop 300 is filled with a water-swellable waterproofing glue 128; through the combined use of the cement-based penetrating crystalline waterproof coating and the water-swellable waterproofing glue 128, the annular construction joint 140 on both sides of the side wall is fully sealed.
[0059] Reference Figure 5 Preferably, a second grouting conduit 141 is embedded in the annular construction joint 140 of the base plate 120, and is used to fill the annular construction joint 140 below the embedded steel-edge rubber waterstop 300 with a cement-based penetrating crystalline waterproof coating; and the annular construction joint 140 above the embedded steel-edge rubber waterstop 300 is filled with a water-swellable waterproofing glue 128; by using the cement-based penetrating crystalline waterproof coating and the water-swellable waterproofing glue 128 in combination, the annular construction joint 140 on both sides of the base plate is fully sealed.
[0060] Reference Figure 8 In addition, during construction, the base plate 120 is cast first, and then the side wall 110 is cast. The third grouting conduit 126 is pre-buried in the side wall 110, and the longitudinal construction joint 130 between the base plate 120 and the side wall 110 is filled with cement-based penetrating crystalline waterproof coating, and a steel plate waterstop 129 is arranged in a direction perpendicular to the construction joint, and the steel plate waterstop 129 and the longitudinal construction joint 130 are filled with water-swelling waterproof glue 128 to play a role in sealing and waterproofing the construction joint.
[0061] During the construction process, the steel plate water stop 129 and the embedded steel edge rubber water stop 300 are connected. In order to improve the firmness of the two, Fig.10 As shown, the steel plate waterstop 129 and the embedded steel-edge rubber waterstop 300 are connected by rivets 400, and a butyl rubber putty sheet 270 is arranged between the steel plate waterstop 129 and the embedded steel-edge rubber waterstop 300.
[0062] Preferably, refer to Figure 6A fourth grouting conduit 143 is pre-buried in the annular construction joint 140 located on the top plate 150, and is used to fill the annular construction joint 140 above the embedded steel-edge rubber waterstop 300 with a cement-based penetrating crystalline waterproof coating; and, the annular construction joint 140 below the embedded steel-edge rubber waterstop 300 is filled with water-swellable waterproof glue 128, which fully seals the annular construction joint between the top plates 150.
[0063] Preferably, refer to Figure 1 and Figure 7 A middle wall 160 is cast between the top plate 150 and the bottom plate 120, and the longitudinal construction joints 130 between the middle wall 160 and the top plate 150 and the bottom plate 120 are filled with cement-based penetrating crystalline waterproof coating; the circumferential construction joints 140 of the middle wall 160 are filled with cement-based penetrating crystalline waterproof coating, and water-swellable waterproofing glue 128 is filled on both sides of the circumferential construction joints 140, which plays a sealing role for the longitudinal construction joints and circumferential construction joints of the middle wall 160.
[0064] Reference Figure 8 In order to improve the waterproof performance between the concrete cushion layer 124 and the enclosure structure 200, in this embodiment, the base leveling layer 220 extends downward to the connection (inner corner) between the concrete cushion layer 124 and the enclosure structure 200 to form a cement mortar chamfer 230. In addition, a first sprayed quick-setting rubber asphalt waterproof coating reinforcement layer 240 is provided between the cement mortar chamfer 230 and the first sprayed quick-setting rubber asphalt waterproof coating layer 122 and the second sprayed quick-setting rubber asphalt waterproof coating layer 210 to further improve the waterproof performance.
[0065] Reference Figure 2 In addition, a second sprayed quick-setting rubber asphalt waterproof coating reinforcement layer 250 is sprayed again on the inner side of the second sprayed quick-setting rubber asphalt waterproof coating layer 210 directly opposite to the annular construction joint 140 on the side wall 110 to improve the waterproof performance at the annular construction joint 140 of the side wall;
[0066] Similarly, refer to Figure 5 A third sprayed quick-setting rubber asphalt waterproof coating reinforcement layer 260 is sprayed again on the inner side of the first sprayed quick-setting rubber asphalt waterproof coating layer 122 opposite to the annular construction joint 140 on the base plate 120 to improve the waterproof performance of the annular construction joint 140 of the base plate 120.
[0067] Reference Figure 6 A fourth sprayed quick-setting rubber asphalt waterproof coating reinforcement layer 280 is sprayed again on the inner side of the third sprayed quick-setting rubber asphalt waterproof coating layer 151 opposite to the circumferential construction joint 140 on the top plate 150 to improve the waterproof performance of the circumferential construction joint 140 of the top plate 150.
[0068] In addition, refer to Figure 5 and Figure 6 For the circumferential construction joint 140 between the top plate 150 and the bottom plate 120, the rubber connecting belt 301 in the embedded steel-edge rubber waterstop 300 is concave in shape corresponding to the water side, and the steel belt 302 is bent upward to further prevent water seepage.
[0069] Finally, it should be noted that the above embodiments are only used to illustrate the technical solution of the utility model, rather than to limit it. Although the utility model has been described in detail with reference to the aforementioned embodiments, ordinary technicians in this field should understand that they can still modify the technical solutions recorded in the aforementioned embodiments, or replace some or all of the technical features therein with equivalents. However, these modifications or replacements do not make the essence of the corresponding technical solution deviate from the scope of the technical solution of the embodiments of the utility model.
[0070] Finally, it should be noted that the above embodiments are only used to illustrate the technical solution of the utility model, rather than to limit it. Although the utility model has been described in detail with reference to the aforementioned embodiments, ordinary technicians in this field should understand that they can still modify the technical solutions recorded in the aforementioned embodiments, or replace some or all of the technical features therein with equivalents. However, these modifications or replacements do not make the essence of the corresponding technical solution deviate from the scope of the technical solution of the embodiments of the utility model.
Claims
1. A waterproof structure for construction joints of a single-layer buried section of an open-cut tunnel, characterized in that: It includes the tunnel body, enclosure structure and embedded steel-edge rubber waterstop; The tunnel body comprises a bottom plate, a side wall and a top plate which are cast in sequence from bottom to top, and a first fine stone concrete protective layer, a first sprayed quick-setting rubber asphalt waterproof coating layer, a non-woven fabric layer and a concrete cushion layer are sequentially arranged below the bottom plate; The enclosure structure is arranged on the outside of the side wall, and a second sprayed quick-setting rubber asphalt waterproof coating layer and a base surface leveling layer are sequentially arranged between the side wall and the enclosure structure; Furthermore, the first sprayed quick-setting rubber asphalt waterproof coating layer and the second sprayed quick-setting rubber asphalt waterproof coating layer are formed by continuous spraying; A third sprayed quick-setting rubber asphalt waterproof coating layer and a second fine stone concrete protective layer are sequentially arranged on the top of the top plate from bottom to top; In addition, an embedded steel-edge rubber waterstop is arranged between each section of the circumferential construction joints along the extension direction of the tunnel body, wherein both side ends of the embedded steel-edge rubber waterstop are respectively wrapped with water-expandable putty blocks.
2. The waterproof structure for construction joints of a single-layer buried section of an open-cut tunnel according to claim 1 is characterized in that: The embedded steel-edge rubber waterstop comprises a rubber connecting belt and a steel belt, the two ends of the rubber connecting belt are respectively connected to the steel belt; the two sides of the center line of the rubber connecting belt in the length direction are respectively wrapped with water-expanding putty blocks.
3. The waterproof structure for construction joints of a single-layer buried section of an open-cut tunnel according to claim 1 is characterized in that: A first grouting conduit is pre-buried in the annular construction joint of the side wall, and is used to fill the annular construction joint outside the embedded steel edge rubber water stop with cement-based penetrating crystallization waterproof coating; Furthermore, the annular construction joint inside the embedded steel-edge rubber waterstop is filled with water-swellable waterstop glue.
4. The waterproof structure for construction joints of a single-layer buried section of an open-cut tunnel according to claim 1, characterized in that: A second grouting conduit is pre-buried in the annular construction joint of the base plate, and is used to fill the annular construction joint below the embedded steel edge rubber water stop with a cement-based penetrating crystallized waterproof coating; Furthermore, the annular construction joint above the embedded steel-edge rubber waterstop is filled with water-swellable waterstop glue.
5. The waterproof structure for construction joints of single-layer buried section of open-cut tunnel according to claim 1 is characterized in that: The longitudinal construction joint between the base plate and the side wall is filled with cement-based penetrating crystalline waterproof coating, and a steel plate waterstop is arranged in a direction perpendicular to the construction joint, and water-swellable waterstop glue is filled between the steel plate waterstop and the longitudinal construction joint; a third grouting conduit is embedded in the side wall for injecting cement-based penetrating crystalline waterproof coating into the longitudinal construction joint.
6. The waterproof structure for construction joints of a single-layer buried section of an open-cut tunnel according to claim 5, characterized in that: The steel plate waterstop and the steel strip of the embedded steel-edge rubber waterstop are connected by rivets.
7. The waterproof structure for construction joints of a single-layer buried section of an open-cut tunnel according to claim 1, characterized in that: A fourth grouting conduit is pre-buried in the annular construction joint of the top plate, and is used to fill the annular construction joint above the embedded steel edge rubber water stop with a cement-based penetrating crystallized waterproof coating; Furthermore, the annular construction joint below the embedded steel-edge rubber waterstop is filled with water-swellable waterstop glue.
8. The waterproof structure for construction joints of a single-layer buried section of an open-cut tunnel according to claim 1, characterized in that: A middle wall is cast between the top plate and the bottom plate, and the longitudinal construction joints between the middle wall and the top plate and the bottom plate are filled with cement-based penetrating crystallization waterproof coating; The annular construction joint of the middle wall is filled with cement-based penetrating crystallization waterproof coating, and water-expanding water-stopping glue is filled on both sides of the annular construction joint.
9. The waterproof structure for construction joints of a single-layer buried section of an open-cut tunnel according to claim 1, characterized in that: The base leveling layer extends downward to the connection between the concrete cushion layer and the enclosure structure to form a cement mortar chamfer; A first sprayed quick-setting rubber asphalt waterproof coating reinforcement layer is arranged between the cement mortar chamfer and the first sprayed quick-setting rubber asphalt waterproof coating layer and the second sprayed quick-setting rubber asphalt waterproof coating layer.
10. The waterproof structure for construction joints of a single-layer buried section of an open-cut tunnel according to claim 1, characterized in that: A second spray quick-setting rubber asphalt waterproof coating reinforcement layer is sprayed again on the inner side of the second spray quick-setting rubber asphalt waterproof coating layer directly opposite to the circumferential construction joint on the side wall; A third sprayed quick-setting rubber asphalt waterproof coating reinforcement layer is sprayed again on the inner side of the first sprayed quick-setting rubber asphalt waterproof coating layer directly opposite to the circumferential construction joint on the bottom plate; A fourth spray quick-setting rubber asphalt waterproof coating reinforcement layer is sprayed again on the inner side of the third spray quick-setting rubber asphalt waterproof coating layer directly opposite to the circumferential construction joint on the top plate.