Hillside strip mine drainage system under weak surrounding rock geological condition

By designing a zigzag drainage connection channel and flood control ditch system in open-pit mines on hillsides with weak surrounding rock geological conditions, and combining it with geomembrane seepage prevention, the problems of drainage system blockage and misalignment were solved, achieving efficient and low-cost drainage effect.

CN222065690UActive Publication Date: 2024-11-26YUNNAN HUALIAN ZINC & INDIUM
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420101510.7
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-01-16
Publication Date
2024-11-26
Estimated Expiration
2034-01-16

AI Technical Summary

Technical Problem

Existing technologies for drainage systems in open-pit mines on slopes with weak surrounding rock geological conditions are prone to blockage and misalignment, resulting in ineffective water discharge. Furthermore, repeated construction costs are high, making it difficult to meet the needs of cost-saving mines.

Method used

The design incorporates a zigzag drainage connection channel combined with platform drainage ditches and flood control ditches, and uses geomembranes for seepage prevention to ensure that the system is not easily blocked or misaligned. The rectangular or trapezoidal cross-section drainage ditches adapt to different rock hardness and achieve smooth water flow guidance.

Benefits of technology

It improves construction efficiency, reduces production costs, reduces repeated investment in personnel and equipment, and achieves safe and efficient drainage, making it suitable for drainage in open-pit mines on hillsides under complex geological conditions.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222065690U_ABST
    Figure CN222065690U_ABST
Patent Text Reader

Abstract

The utility model discloses a hillside strip mine drainage system under the weak surrounding rock geological condition, and belongs to the technical field of mining, the hillside strip mine drainage system comprises platform drainage ditches, drainage connection ways and flood control ditches, and the platform drainage ditches are arranged on the lower portions of platform slope base lines on the two sides of a weak surrounding rock area; a plurality of platform drainage ditches are evenly distributed from top to bottom, water catchment ports are located in the weak surrounding rock area corresponding to the middle, a drainage connection channel is arranged in the weak surrounding rock area and is of a zigzag structure, and the water catchment ports of the platform drainage ditches on the two sides are communicated with the drainage connection channel. A flood control ditch is arranged at the bottom of the drainage connection channel and communicated with the drainage connection channel, and the flood control ditch is communicated with a stope main flood control system. According to the system, the conventional drainage ditch parameters of the mountain slope surface mine are combined with the zigzag drainage connection way, and the built drainage ditch system has the advantages of being not prone to blockage and dislocation and long in service cycle and conforms to the production concepts of cost saving, safety and high efficiency.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present application belongs to the field of mining technology and is mainly used for temporary drainage of mines, specifically a hillside open-pit mine drainage system under soft surrounding rock geological conditions. Background Art

[0002] According to the burial conditions of the ore deposit and the terrain conditions, open-pit mines are divided into hillside open-pit mines and sunken open-pit mines. The current drainage method for hillside open-pit mines is to dig an inner drainage ditch along the bottom line of the slope close to the foot of the slope on the inner side of the platform that has been excavated in place, and form a certain drainage longitudinal slope according to the terrain, and then introduce the water flow into the water collection points of each platform and then merge it into the main flood control ditch to discharge the mining area. The above conventional method is suitable for mines with relatively stable geological conditions, that is, mines with complete and stable rock mass. For weak surrounding rock or broken rock mass, it lacks stability in itself and is prone to landslides under the action of rock stress release. In addition, water erodes the weak surrounding rock. The drainage ditch excavated at the foot of the slope is prone to blockage due to soil and rock sliding or displacement and disconnection due to stress, resulting in the inability to discharge water and causing safety problems. At the same time, repeated construction is required to ensure smooth water flow, and a large number of personnel and equipment are invested, which does not conform to the current development concept of cost-saving mines. Utility Model Content

[0003] In view of the above problems existing in the prior art, the present invention provides a hillside open-pit mine drainage system under soft surrounding rock geological conditions, which is equipped with a zigzag drainage connecting channel on the basis of conventional drainage ditch technology to construct a drainage system that is not easy to be blocked or dislocated.

[0004] To achieve the above-mentioned purpose, the present application adopts the following technical scheme: a hillside open-pit mine drainage system under soft surrounding rock geological conditions, including a platform drainage ditch, a drainage connecting channel, and a flood control ditch. A platform drainage ditch is arranged at the lower part of the bottom line of each platform slope on both sides of the soft surrounding rock area. The platform drainage ditches are evenly arranged from top to bottom and the water confluences are all located in the weak surrounding rock area corresponding to the middle part. A drainage connecting channel is arranged in the soft surrounding rock area. The drainage connecting channel is a zigzag structure. The water confluence of each platform drainage ditch on both sides is connected to the drainage connecting channel. A flood control ditch is arranged at the bottom of the drainage connecting channel and the drainage connecting channel is connected to the flood control ditch, and the flood control ditch is connected to the main flood control system of the mining site.

[0005] Furthermore, a geomembrane for anti-seepage operations is laid in the system.

[0006] Furthermore, the exposed rock mass is not solid rock, and the platform drainage ditch adopts a rectangular cross-section drainage ditch.

[0007] Furthermore, the exposed rock mass is medium-solid rock or above, and the platform drainage ditch adopts a trapezoidal cross-section drainage ditch.

[0008] Beneficial effects of this application:

[0009] The present application provides a drainage system for hillside open-pit mines under soft surrounding rock geological conditions. The system combines conventional drainage ditch parameters of hillside open-pit mines with zigzag drainage connecting channels. The constructed drainage ditch system has the advantages of not being easy to clog, not being easy to dislocate and having a long service life, which significantly improves the drainage effect of mines under soft surrounding rock geological conditions, improves construction efficiency and reduces production costs, and greatly reduces repeated investment in personnel and equipment, conforms to the production concept of cost saving, safety and efficiency, and has good practicality in hillside open-pit mines with complex geological conditions. BRIEF DESCRIPTION OF THE DRAWINGS

[0010] Figure 1 This is a schematic diagram of the structure of this application;

[0011] Figure 2 This is a longitudinal section view of this application;

[0012] Figure 3 This is a schematic diagram of the water flow direction for this application.

[0013] Figure 1-3 Among them, 1 is platform drainage ditch, 2 is drainage connecting channel, 3 is water flow direction, 4 is soft surrounding rock area, 5 is geomembrane, 6 is slope line, 7 is working platform, 8 is flood control ditch. DETAILED DESCRIPTION

[0014] In order to make the purpose, technical solutions and beneficial effects of the present application clearer, the preferred embodiments of the present application will be described in detail below in conjunction with the accompanying drawings to facilitate understanding by technical personnel.

[0015] The hillside open-pit mine drainage system under soft surrounding rock geological conditions includes a platform drainage ditch 1, a drainage liaison channel 2, and a flood control ditch 8. The specific layout process is as follows:

[0016] The first step is to prepare the operation platform 7 plan. According to the mine geological information, technical parameters, design institute planning and design, and relevant laws and regulations, the current mining and stripping operation plan is prepared, the mining and stripping design line is drawn on the construction drawing, and the drainage direction is planned in the designed excavation area. Then, the actual terrain measurement is carried out at the mine site to make the planned drainage direction consistent with the actual site to ensure the feasibility of the operation plan.

[0017] The second step is to set the parameters of platform drainage ditch 1. For the area designed to be excavated, the platform drainage ditch 1 needs to be planned synchronously. After the platform working surface advances a certain distance, the inner drainage ditch of the platform needs to be excavated and improved immediately, and the platform acceptance should be organized. If the exposed rock mass is medium-solid rock or above (Puerto hardness coefficient ≥ 4), the conventional method is used to excavate a trapezoidal cross-section drainage ditch close to the bottom line of the platform slope. The relevant parameters are upper width a = 1.2m, bottom width b = 0.8m, ditch depth d = 1m, and the drainage longitudinal slope is not less than 2‰; if the exposed rock mass is not solid rock (Puerto hardness coefficient <4), the method of excavating a rectangular cross-section drainage ditch 2m away from the bottom line of the platform slope is adopted. The relevant parameters are upper width a = 1m, bottom width b = 1m, ditch depth d = 0.8m, and the drainage longitudinal slope is not less than 2‰.

[0018] The third step is to advance the mining platform 7. According to the mining plan and design parameters, production and organization operations are carried out. First, large excavators or large electric shovels are arranged on the working platform 7 to advance along the mining plan to the area 3-5m away from the designed excavation line, and then the construction is suspended. Then, large excavators are arranged to carry out slope trimming operations in the adjacent slope area according to the designed step slope angle. The operation is carried out in sections by first repairing the slope and then loading the vehicle. Each 5m drop in the vertical elevation direction is a section, that is, a vehicle is sent to transport the excess waste rock generated by the slope trimming of the working surface until all the waste rock in the slope area is excavated in place as planned. Every 50m the working line advances forward, a small excavator is arranged to follow the platform to dig the drainage ditch 1.

[0019] The fourth step is to construct the platform drainage ditch 1 and drainage connecting channel 2. The construction premise is that the weather is not rainy or foggy, and the work is carried out in the mining area under the geological conditions of soft surrounding rock, and the multi-step continuous collapse body has become stable. First, the upper and lower adjacent working platforms 7 that have been pushed into place at the moment are constructed by referring to the method of excavating rectangular cross-section drainage ditches 2m away from the bottom line of the platform slope. The platform drainage ditch 1 is excavated into a channel with an upper width of a=1m, a bottom width of b=1m, a ditch depth of ditch d=0.8m, and a drainage longitudinal slope of not less than 2‰; the soft surrounding rock area 4 is used as the drainage outlet of each platform drainage ditch 1, and the platform drainage ditch 1 is excavated from both ends of the platform to the drainage outlet area in a head-on excavation manner, and the water flow is converged into the soft surrounding rock area 4 corresponding to the middle of each platform; then the construction is started by the "Z"-shaped rapid trenching method from top to bottom, and a small excavator is used to clear the surface area of ​​the soft surrounding rock from top to bottom to meet the condition of the minimum upper and lower connecting channel width of the excavator of 5m, that is, the rapid The tunnel is advanced downward in a return manner at a fast speed, and a drainage connection channel 2 is excavated along the center line of the simple connection channel at the same time. The drainage ditch parameters are upper width a=1m, bottom width b=1m, and ditch depth d=0.8m. Each time a drainage connection channel 2 is built from top to bottom, the next platform drainage connection channel 2 is built downward in a return manner to achieve synchronous construction of the drainage connection channel 2 and the platform drainage ditch 1 until the construction reaches the bottom platform. On the lower side of the bottom working platform 7 of the drainage connection channel 2, a flood control ditch 8 with an upper width of a=1.5m, a bottom width of b=1m, and a ditch depth of d=1m is excavated along the area 2m away from the bottom line of the platform slope. The flood control ditch 8 is reinforced with cement plastering. The drainage connection channel 2 is connected with the confluence of all platform drainage ditches 1. The water flow direction 3 is from the platform drainage ditches 1 on both sides to the middle drainage connection channel 2. The water flow is introduced into the flood control ditch 8 through the drainage connection channel 2, and the flood control ditch 8 then stably introduces the water flow into the main flood control system of the mining site.

[0020] (V) Anti-seepage work

[0021] After the construction of drainage ditches 1 and drainage connecting channels 2 on each platform is completed, anti-seepage operations must be carried out in a timely manner, and production operations within 60m below the lowest operating platform 7 must be suspended to prevent deformation of the upper slope and damage caused by the release of lower excavation stress. First, geomembrane 5 is laid on the topmost working platform 7. Polyester staple needle-punched geomembrane 5 is selected with a width of 6m and a length of 100m. Secondly, geomembrane 5 is laid along the platform drainage ditch 1 that has been excavated and formed in the soft surrounding rock geological condition area on the platform. The geomembrane 5 is laid to the soft surrounding rock geological condition area and extends 5m to both ends respectively, so that the geomembrane 5 has sufficient anti-seepage range and deformation margin. After the geomembrane 5 on the platform is laid, the ditch in the downward return drainage liaison channel 2 is laid immediately. At the fork of horizontal and vertical drainage, two layers of geomembrane 5 are laid as a transitional stabilization layer. Every two rolls of geomembrane 5 are overlapped by natural overlap. When encountering a fork or a soft surrounding rock geological condition area, nails are used to sew and reinforce the geomembrane 5. Referring to the above method, anti-seepage construction work is carried out in all drainage liaison channel 2 areas.

[0022] In the face of severe safety situations such as tight construction period, large displacement and deformation, and frequent rainfall in the large-scale slope management of a certain hillside open-pit mine in southeastern Yunnan, through the implementation and application of the above-mentioned application technology, only one small excavator was arranged to cooperate with 6 workers to lay the geomembrane. It took 7 days to complete the drainage system of 8 working platforms within the 120m elevation range in the soft surrounding rock geological conditions area, which was completed 3 weeks ahead of the expected schedule. This improved the previous problems of repeated investment in equipment to clean the platform drainage ditch but still had poor results, the drainage ditch was disconnected due to displacement and deformation and could not be drained, and repeated dredging still had poor results, and the long-term occupation of excavators and high personnel investment costs.

[0023] The present application provides a drainage system for hillside open-pit mines under soft surrounding rock geological conditions. The system combines conventional drainage ditch parameters of hillside open-pit mines with zigzag drainage connecting channels. The constructed drainage ditch system has the advantages of not being easy to clog, not being easy to dislocate and having a long service life, which significantly improves the drainage effect of mines under soft surrounding rock geological conditions, improves construction efficiency and reduces production costs, and greatly reduces repeated investment in personnel and equipment, conforms to the production concept of cost saving, safety and efficiency, and has good practicality in hillside open-pit mines with complex geological conditions.

[0024] Finally, it should be noted that the above preferred embodiments are only used to illustrate the technical solution of the present application rather than to limit it. Although the present application has been described in detail through the above preferred embodiments, those skilled in the art should understand that various changes can be made in form and details without departing from the scope defined by the claims of the present application.

Claims

1. A hillside open-pit mine drainage system under soft surrounding rock geological conditions, mainly used for temporary mine drainage, characterized by: It includes platform drainage ditches, drainage connecting channels and flood control ditches. Platform drainage ditches are arranged at the lower part of the bottom line of each working platform on both sides of the soft surrounding rock area. The platform drainage ditches are evenly distributed from top to bottom and the water confluences are all located in the soft surrounding rock area corresponding to the middle part. A drainage connecting channel is arranged in the soft surrounding rock area. The drainage connecting channel is a zigzag structure. The water confluence of each platform drainage ditch on both sides is connected with the drainage connecting channel. Flood control ditches are arranged at the bottom of the drainage connecting channel and the drainage connecting channel is connected with the flood control ditch. The flood control ditch is connected with the main flood control system of the mining site.

2. The hillside open-pit mine drainage system under soft surrounding rock geological conditions as claimed in claim 1, characterized in that: A geomembrane for anti-seepage operations is laid in the system.

3. The hillside open-pit mine drainage system under soft surrounding rock geological conditions as claimed in claim 1, characterized in that: The exposed rock mass is not solid rock, and the platform drainage ditch adopts a rectangular cross-section drainage ditch.

4. The hillside open-pit mine drainage system under soft surrounding rock geological conditions as claimed in claim 1, characterized in that: The exposed rock mass is medium solid rock or above, and the platform drainage ditch adopts a trapezoidal cross-section drainage ditch.