Continuous segmented grouting device for long hole of coal mine

By setting up multiple sealing parts, connecting parts and grouting parts in the long hole of the coal mine, automatic sealing and continuous grouting are achieved in segments, which solves the problem of insufficient diffusion of grouting liquid in the existing technology, and significantly improves grouting Effect and efficiency.

CN222066772UActive Publication Date: 2024-11-26CCTEG COAL MINING RES INST +1
View PDF 0 Cites 1 Cited by

Patent Information

Application Number
CN202323662351.2
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2023-12-29
Publication Date
2024-11-26
Estimated Expiration
2033-12-29

AI Technical Summary

Technical Problem

In the existing long-hole grouting technology, a single sealing piece causes the grouting slurry to diffuse only at the broken coal rock mass at the orifice, and rarely diffuse to the bottom of the hole, and the grouting effect and efficiency are poor.

Method used

Design a coal mine long hole continuous segment grouting application device, by setting multiple spaced sealing parts, connecting parts and grouting parts in the drilling hole, using the pressure control of the connecting parts and the structure of the grouting parts, to realize the division of the Automatic sealing of sections and continuous grouting improve grouting effect and efficiency.

Benefits of technology

The automatic sealing and continuous grouting of long holes is realized, which significantly improves the grouting effect and efficiency, ensures that the grouting liquid can effectively diffuse to the bottom of the hole, and enhances the reinforcement effect of coal mine tunnels.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222066772U_ABST
    Figure CN222066772U_ABST
Patent Text Reader

Abstract

The utility model discloses a coal mine long hole continuous segmented grouting device, the coal mine long hole continuous segmented grouting device comprises a plurality of plugging pieces, a plurality of communicating pieces and a plurality of grouting pieces, the plurality of plugging pieces are arranged at intervals along the length direction of the plugging pieces, and the plurality of plugging pieces are all arranged in a drill hole, so that the plugging pieces can plug the drill hole, and the grouting pieces are arranged at intervals along the length direction of the plugging pieces. The at least one communicating piece is arranged between the two adjacent plugging pieces, the two ends of the at least one communicating piece are connected with the two adjacent plugging pieces correspondingly, the at least one grouting piece is arranged between the two adjacent plugging pieces, and the at least one grouting piece is connected with at least one of the two adjacent plugging pieces. And after the two adjacent plugging pieces plug the drill hole, the grouting piece is communicated with at least one of the two adjacent plugging pieces, so that the grouting piece performs grouting on the drill hole. The continuous segmented grouting device for the long hole of the coal mine has the advantages of being simple in structure, high in grouting efficiency and the like.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the field of long hole grouting reinforcement of coal mine tunnels and working faces, and in particular to a coal mine long hole continuous segmented grouting device. Background Art

[0002] When mine tunnels and working faces encounter geological structures such as faults, the surrounding rock is soft and broken, and the tunnel roof is prone to leakage and spalling, and the working face roof leakage, which seriously affects the tunnel excavation and normal mining of the working face. It is necessary to use long-distance drilling to grouting reinforce the broken coal rock mass, and the drilling length generally exceeds 100m.

[0003] In the related art, long hole grouting sealing methods mostly use a single plugging piece, which causes the grouting slurry to spread only in the broken coal and rock mass at the hole mouth, and rarely spread to the bottom of the hole, thereby improving the grouting effect and grouting efficiency. Utility Model Content

[0004] The utility model aims to solve one of the technical problems in the related art at least to a certain extent.

[0005] To this end, the embodiment of the utility model proposes a coal mine long hole continuous segmented grouting device with simple structure, good grouting effect and high grouting efficiency.

[0006] According to the embodiment of the utility model, the coal mine long hole continuous segmented grouting device comprises: a plurality of plugging members, the plurality of plugging members are arranged at intervals along the length direction thereof, and the plurality of plugging members are arranged in the borehole so that the plugging members can block the borehole; a plurality of connecting members, at least one of the connecting members is arranged between two adjacent plugging members and the two ends of at least one of the connecting members are respectively connected to the two adjacent plugging members, the connecting member has a connected state and a disconnected state, in the connected state, the slurry pressure in at least one of the two adjacent plugging members is greater than the pre-set pressure. Set a value, the connecting piece connects the two adjacent sealing pieces, in the disconnected state, the pressure of the slurry in the two adjacent sealing pieces is less than the preset value, and at least one of the two adjacent sealing pieces is disconnected from the connecting piece; a plurality of grouting pieces, at least one of the grouting pieces is arranged between the two adjacent sealing pieces and at least one of the grouting pieces is connected to at least one of the two adjacent sealing pieces, after the two adjacent sealing pieces block the borehole, the grouting piece is connected to at least one of the two adjacent sealing pieces so that the grouting piece can grout the borehole.

[0007] According to the coal mine long hole continuous segmented grouting device of the utility model embodiment, multiple sealing parts, multiple connecting parts and multiple grouting parts are set. Slurry is injected in sequence according to the distance between the area and the hole mouth of the drill hole, which can realize automatic segmented sealing and continuous grouting of the long hole, greatly improving the long hole grouting effect and grouting efficiency.

[0008] In some embodiments, the opening pressure of the connected state of the plurality of connecting pieces gradually increases along the length direction of the borehole.

[0009] In some embodiments, the connecting member includes a connecting pipe, a first valve and a second valve, the first valve being arranged between the connecting pipe and a section of the blocking member and being connected to the connecting pipe and one end of the blocking member, the second valve being arranged between the other end of the blocking member and the connecting pipe and being connected to the connecting pipe and the other end of the blocking member, in the connected state, the second valve in one of the two adjacent blocking members is opened and the pressure of the first valve in the other of the two adjacent blocking members is opened, and the pressure of the second valve in the other of the two adjacent blocking members is closed, and in the disconnected state, the first valve and the second valve of the two adjacent blocking members are both closed.

[0010] In some embodiments, the first valve and the second valve are both pressure valves, the opening pressure of the second valve in one of the two adjacent sealing parts is equal to the opening pressure of the first valve in the other of the two adjacent sealing parts, and the opening pressure of the first valve in the two adjacent sealing parts gradually increases along the length direction of the borehole.

[0011] In some embodiments, the grouting part includes a grouting pipe and a third valve. The grouting pipe is arranged between two adjacent sealing parts and is connected to at least one of the two adjacent sealing parts. The third valve is arranged in the grouting pipe. After the two adjacent sealing parts block the drill hole, the third valve is opened so that the grouting pipe is arranged in at least one of the two adjacent sealing parts and is connected through the third valve.

[0012] In some embodiments, the third valve is a pressure valve, and the opening pressure of the third valve is greater than the opening pressure of the first valve or the opening pressure of the second valve adjacent to the third valve.

[0013] In some embodiments, the grouting part includes a tube body, and the outer circumferential surface of the tube body is provided with a plurality of grouting holes penetrating the tube body along the inward and outward directions. The plurality of grouting holes are arranged in multiple circles along the axial direction of the tube body, and each circle includes a plurality of grouting holes arranged at intervals along the circumference of the tube body.

[0014] In some embodiments, the distance between two adjacent blocking members is 5m-20m.

[0015] In some embodiments, the grouting pressure of the plurality of grouting members gradually increases along the length direction of the borehole.

[0016] In some embodiments, the sealing parts are all grouting sealing parts. BRIEF DESCRIPTION OF THE DRAWINGS

[0017] Figure 1 The utility model is a schematic structural diagram of a coal mine long hole continuous segmented grouting device according to an embodiment of the utility model.

[0018] Figure 2 The utility model is a schematic diagram of the working of the coal mine long hole continuous segmented grouting device according to the embodiment of the utility model.

[0019] Figure 3 It is a structural schematic diagram of a coal mine long hole continuous segmented grouting device for completing grouting according to an embodiment of the utility model.

[0020] Coal mine long hole continuous segmented grouting device 100;

[0021] Blocking piece 1; first blocking piece 11; second blocking piece 12; third blocking piece 13; nth blocking piece 14

[0022] Connecting piece 2; connecting pipe 21; first valve 22; second valve 23;

[0023] Grouting part 3; Grouting pipe 31; Third valve 32;

[0024] Drill hole 4. DETAILED DESCRIPTION

[0025] The embodiments of the present invention are described in detail below, and examples of the embodiments are shown in the accompanying drawings. The embodiments described below with reference to the accompanying drawings are exemplary and intended to be used to explain the present invention, but cannot be understood as limiting the present invention.

[0026] The following describes a coal mine long hole continuous segmented grouting device 100 according to an embodiment of the utility model with reference to the accompanying drawings.

[0027] like Figure 1-3 As shown, the coal mine long hole continuous segmented grouting device 100 according to the embodiment of the utility model includes a plurality of blocking members 1, a plurality of connecting members 2 and a plurality of grouting members 3.

[0028] A plurality of blocking members 1 are arranged at intervals along the length direction thereof, and a plurality of blocking members 1 are arranged in the borehole 4 so that the blocking members 1 can block the borehole 4. Specifically, as Figure 1-3 As shown, a plurality of plugging members 1 are arranged relative to each other at intervals along the left-right direction. A plurality of plugging members 1 can be installed in the borehole 4 and slurry can be introduced therein, and the plugging members 1 can expand with the slurry to plug the borehole 4.

[0029] At least one connecting piece 2 is disposed between two adjacent plugging pieces 1 and both ends of at least one connecting piece 2 are respectively connected to the two adjacent plugging pieces 1. The connecting piece 2 has a connected state and a disconnected state. In the connected state, the pressure of the slurry in at least one of the two adjacent plugging pieces 1 is greater than a preset value, and the connecting piece 2 connects the two adjacent plugging pieces 1. In the disconnected state, the pressure of the slurry in the two adjacent plugging pieces 1 is less than a preset value, and at least one of the two adjacent plugging pieces 1 is disconnected from the connecting piece 2. Specifically, as Figure 1-3 As shown, the connecting piece 2 is arranged between two adjacent blocking pieces 1 and the left and right ends of the connecting piece are respectively connected to the two adjacent blocking pieces 1. The connecting piece 2 can connect or disconnect the two adjacent blocking pieces 1 according to the pressure of the slurry between the two adjacent blocking pieces 1.

[0030] At least one grouting member 3 is disposed between two adjacent plugging members 1 and is connected to at least one of the two adjacent plugging members 1. After the two adjacent plugging members 1 plug the borehole 4, the grouting member 3 is connected to at least one of the two adjacent plugging members 1 so that the grouting member 3 grouts the borehole 4. Specifically, Figure 1-3 As shown, the grouting member 3 is arranged between the two sealing members 1 and can be connected with the two adjacent sealing members 1, for example: the left end of the grouting member 3 can be connected with the sealing member 1 at the left end, or the right end of the grouting member 3 can be connected with the sealing member 1 at the right end, or the left and right ends of the grouting member 3 are respectively connected with the left and right end sealing members 1, so that the slurry of the grouting member 3 can be injected into between the two adjacent sealing members 1 through the grouting member 3.

[0031] According to the coal mine long hole continuous segmented grouting device 100 of the utility model embodiment, a plurality of plugging parts 1, a plurality of connecting parts 2 and a plurality of grouting parts 3 are arranged, and the borehole 4 is divided into a plurality of areas along its length direction according to the actual situation of the borehole 4, and grouting is performed in sequence according to the distance between the area and the orifice of the borehole 4, which effectively solves the problem that the grouting slurry only spreads in the broken coal rock mass at the orifice, and can realize segmented automatic sealing and continuous grouting of the long hole, greatly improving the long hole grouting effect and grouting efficiency.

[0032] In some embodiments, the opening pressure of the connection state of the plurality of connecting pieces 2 is increased along the length direction of the borehole 4 (eg Figure 1 Specifically, as shown in the left and right directions, Figure 1-3 As shown, the opening pressure of the multiple connecting pieces 2 gradually increases from right to left, thereby causing the multiple grouting pieces 3 to expand and seal in the borehole 4 in turn, thereby grouting the borehole 4 from the hole mouth to the hole bottom in turn, thereby ensuring the grouting efficiency.

[0033] In some embodiments, the connecting member 2 includes a connecting pipe 21, a first valve 22, and a second valve 23. The first valve 22 is disposed between the connecting pipe 21 and a section of the plugging member 1 and is connected to the connecting pipe 21 and one end of the plugging member 1. The second valve 23 is disposed between the other end of the plugging member 1 and the connecting pipe 21 and is connected to the other end of the plugging member 1. In a connected state, the second valve 23 in one of the plugging members 1 of two adjacent plugging members 1 is opened and the pressure of the first valve 22 in the other of the two adjacent plugging members 1 is opened, and the pressure of the second valve 23 in the other of the two adjacent plugging members 1 is closed. In a disconnected state, the first valve 22 and the second valve 23 of the two adjacent plugging members 1 are both closed. Specifically, as Figure 1-3 As shown, the connecting pipe 21 is arranged between two adjacent blocking members 1 and the left and right ends of the connecting pipe 21 are respectively connected with the two adjacent blocking members 1. A first valve 22 and a second valve 23 are arranged in each blocking member 1. The first valve 22 is arranged at the left end of the blocking member 1 and is connected with the connecting pipe 21 at the left end of the blocking member 1. The second valve 23 is arranged at the right end of the blocking member 1 and is connected with the connecting pipe 21 at the right end of the blocking member 1. Thus, a plurality of blocking members 1 are connected into a whole through the connecting pipe 21, and the connection between the two adjacent blocking members 1 is controlled by the first valve 22 and the second valve 23. In the connected state, the second valve 23 in the blocking member 1 at the left end is opened and the pressure of the first valve 22 in the blocking member 1 at the right end is opened, and the pressure of the second valve 23 in the blocking member 1 at the right end is closed. In the disconnected state, the first valve 22 and the second valve 23 of the two adjacent blocking members 1 are both closed.

[0034] In some embodiments, the first valve 22 and the second valve 23 are both pressure valves, the opening pressure of the second valve 23 in one of the two adjacent sealing parts 1 is equal to the opening pressure of the first valve 22 in the other of the two adjacent sealing parts 1, and the opening pressure of the first valve 22 in the two adjacent sealing parts 1 gradually increases along the length direction of the borehole 4.

[0035] Specifically, Figure 2As shown, two adjacent blocking members 1 are respectively a first blocking member 1 and a second blocking member 1 (the first blocking member 1 is located at the right end of the second blocking member 1), the first blocking member 1 is located at the left end of the second blocking member 1 and the first blocking member 1 is arranged adjacent to the orifice of the borehole 4, the opening pressure of the second valve 23 of the first blocking member 1 is equal to the opening pressure of the first valve 22 of the second blocking member 1, and the opening pressure of the first valve 22 in the first blocking member 1 is less than the opening pressure of the second valve 23 in the first blocking member 1, and the opening pressure of the second valve 23 in the second blocking member 1 is greater than the opening pressure of the first valve 22 of the second blocking member 1. Therefore, when the first blocking member 1 is opened, the second valve 23 in the second blocking member 1 is opened. When grouting is performed, after the first valve 22 of the first blocking member 1 is opened, the first blocking member 1 expands, and grouting is continued on the first blocking member 1. When the pressure in the first blocking member 1 is greater than the opening pressure of the second valve 23 of the first blocking member 1, the second valve 23 of the first blocking member 1 will be opened. Since the opening pressure of the second valve 23 of the first blocking member 1 is equal to the opening pressure of the first valve 22 of the second blocking member 1, the first valve 22 of the second blocking member 1 is also opened synchronously, so that the slurry flows into the second blocking member 1 through the connecting pipe 21 to expand the second blocking member 1, so that the first blocking member 1 and the second blocking member 1 block the borehole 4.

[0036] In some embodiments, the grouting member 3 includes a grouting pipe 31 and a third valve 32. The grouting pipe 31 is disposed between two adjacent plugging members 1 and communicates with at least one of the two adjacent plugging members 1. The third valve 32 is disposed in the grouting pipe 31. After the two adjacent plugging members 1 block the borehole 4, the third valve 32 is opened so that the grouting pipe 31 disposed in at least one of the two adjacent plugging members 1 is communicated through the third valve 32. Specifically, as Figure 1-3 As shown, the grouting pipe 31 can be connected to two adjacent plugging members 1 (the first plugging device and the second plugging device) according to actual conditions. For example, the left end of the grouting pipe 31 can be connected to the first plugging device, or the right end of the grouting pipe 31 can be connected to the second plugging device, or the left and right ends of the grouting pipe 31 are respectively connected to the first plugging device and the second plugging device, so that the slurry in the grouting pipe 31 can be injected into the grouting area through the grouting pipe 31. The third valve 32 is arranged in the grouting pipe 31. The third valve 32 can be set according to actual conditions. For example, when the left end of the grouting pipe 31 is connected to the third valve 32, the third valve 32 can be set according to actual conditions. When one hole sealer is connected, the third valve 32 is arranged at the left end of the grouting pipe 31, or when the right end of the grouting pipe 31 is connected to the second hole sealer, the third valve 32 is arranged at the right end of the grouting pipe 31, or when the left end and the right end of the grouting pipe 31 are respectively connected to the first hole sealer and the second hole sealer, the number of the third valves 32 is two and they are respectively arranged at the left and right ends of the grouting pipe 31. Thus, the opening and closing of the grouting pipe 31 and the sealing member 1 are controlled by the third valve 32, ensuring that the borehole 4 is grouted after the two adjacent sealing members 1 expand and seal the borehole 4, thereby ensuring the grouting efficiency.

[0037] In some embodiments, the third valve 32 is a pressure valve, and the opening pressure of the third valve 32 is greater than the opening pressure of the first valve 22 or the opening pressure of the second valve 23 adjacent thereto. Figure 1-3 As shown, the opening pressure of the third valve 32 is greater than the opening pressure of the second valve 23 of the first sealer and less than the opening pressure of the second valve 23 of the second sealer. Therefore, after the first sealer and the second sealer seal the borehole 4, slurry is continuously injected into the first sealer, and the pressure of the first sealer increases. When the pressure in the first sealer is less than the opening pressure of the second valve 23 of the second sealer and greater than the opening pressure of the third valve 32, the third valve 32 will open, so that the slurry will be filled in the borehole 4.

[0038] In some embodiments, the grouting member 3 includes a pipe body, and the outer peripheral surface of the pipe body is provided with a plurality of grouting holes (not shown in the figure) penetrating the pipe body in the inner and outer directions, and the plurality of grouting holes are arranged in a plurality of circles along the axial direction of the pipe body, and each circle includes a plurality of grouting holes arranged at intervals along the circumference of the pipe body. Thus, the slurry in the grouting pipe 31 is injected into the borehole 4 through the grouting holes.

[0039] In some embodiments, the distance between two adjacent plugging members 1 is 5m-20m. Specifically, the length of two adjacent plugging members 1 in the left-right direction can be any one of 5m, 7m, 9m, 11m, 13m, 15m, 17m, 19m and 20m. When the distance between two adjacent plugging members 1 is less than 5m, the distance between the two adjacent plugging members 1 is too short, which leads to an increase in the number of grouting times, and then an increase in the workload of workers. When the distance between two adjacent plugging members 1 is greater than 20m, the distance between the two adjacent plugging members 1 is too long, which reduces the grouting effect and grouting efficiency of the grouting device 100. Therefore, the length of the distance between two adjacent plugging members 1 is 5m-20m, which makes the grouting device 100 more reasonably set, and reduces the number of grouting times while ensuring the grouting effect and grouting efficiency.

[0040] In some embodiments, the grouting pressure of the plurality of grouting parts 3 gradually increases along the length direction of the borehole 4. Since the pressure in the borehole 4 increases as the length of the borehole 4 increases, the grouting pressure of the plurality of grouting parts 3 gradually increases along the length direction of the borehole 4, and the grouting efficiency of the grouting parts 3 can be ensured.

[0041] In some embodiments, the plugging members 1 are all grouting plugging members 1. Thus, the borehole 4 can be plugged by the plugging members 1, making the setting of the plugging members 1 more reasonable.

[0042] According to the following Figure 1-3 The working process of the coal mine long hole continuous segmented grouting device 100 of the utility model is specifically described as follows:

[0043] a. A first valve 22 and a second valve 23 are installed inside the plugging member 1. The first valve 22 and the second valve 23 are set with different opening pressures. Two adjacent plugging members 1 are connected in series through a connecting pipe 21. According to the length of the grouting area 11, multiple grouting plugging members 1 are selected to be connected in series;

[0044] b. The pressure design basis of the first valve 22 and the second valve 23 of the grouting plugging member 1 is as follows: first, a digital drilling system is used to drill a borehole 4 of length L in the coal rock mass to be grouted. The digital drilling system includes an ultra-high-resolution panoramic camera and an in-situ strength test probe to obtain the development and strength of cracks at different depths of the borehole 4;

[0045] c. Based on the test results, a fractured coal-rock model was established using numerical simulation software, and a grouting simulation test was carried out to obtain the grouting opening pressure of the coal-rock mass at different depths from the borehole to the bottom of borehole 4;

[0046] d. According to the simulation results, first determine the segment length (5-20m), determine the number of plugging parts 1, count the grouting pressure levels of the segmented coal rock mass, set the opening pressures P1, P2, P3, P4, P5, Pn, etc. of the first valve 22 and the second valve 23 in the plugging part 1, and the corresponding sizes are P1<P2<P3<P4<P5……Pn. According to the order of the plugging parts 1 from the hole mouth to the hole bottom, the second valve 23 of the first plugging part 111 has the same opening pressure as the first valve 22 of the second plugging part 12, and the second valve 23 of the second plugging part 12 has the same opening pressure as the first valve 22 of the third plugging part 13, and so on. Among them, the first plugging part 111, which is the outermost from the grouting hole, has only one pressure valve;

[0047] e. After the borehole 4 is drilled, it is connected in series with the multi-stage pressure plugging piece 1 according to the set segment length to form a sealing system and plugged into the grouting hole at a distance of 5-10m from the bottom of the hole;

[0048] f. The hole sealing system is connected to the high-pressure grouting pump through the grouting pipe 31, and the grouting pump is started. The slurry enters the first plugging piece 111, and the slurry pressure reaches P1. At this time, the pressure valve in the plugging piece 1 opens, the plugging piece 1 expands, and enters the second plugging piece 12. The first valve 22 of the second plugging piece 12 opens, and the second plugging piece 12 expands to seal the hole. However, the second valve 23 is not opened, and the slurry begins to be injected into the surrounding rock between the second plugging piece 12 and the hole mouth. Similarly, when the pressure P2 is reached, the second valve 23 of the second plugging piece 12 opens, the first valve 22 of the third plugging piece 13 opens, and the second valve 23 of the third plugging piece 13 is not opened. The slurry enters the coal rock body behind the third plugging piece 13, and so on, until the entire hole grouting is completed;

[0049] g. The entire grouting process is carried out in multiple stages and sections according to the grouting pressure, which greatly improves the grouting effect and construction efficiency of the coal rock mass.

[0050] In the description of the present invention, it should be understood that the terms "center", "longitudinal", "lateral", "length", "width", "thickness", "up", "down", "front", "back", "left", "right", "vertical", "horizontal", "top", "bottom", "inside", "outside", "clockwise", "counterclockwise", "axial", "radial", "circumferential" and the like indicate orientations or positional relationships based on the orientations or positional relationships shown in the accompanying drawings, and are only for the convenience of describing the present invention and simplifying the description, and do not indicate or imply that the referred device or element must have a specific orientation, be constructed and operated in a specific orientation, and therefore should not be understood as a limitation on the present invention.

[0051] In addition, the terms "first" and "second" are used for descriptive purposes only and should not be understood as indicating or implying relative importance or implicitly indicating the number of the indicated technical features. Therefore, the features defined as "first" and "second" may explicitly or implicitly include at least one of the features. In the description of the present utility model, the meaning of "plurality" is at least two, such as two, three, etc., unless otherwise clearly and specifically defined.

[0052] In the present invention, unless otherwise clearly specified and limited, the terms "installed", "connected", "connected", "fixed" and the like should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral one; it can be a mechanical connection, an electrical connection, or communication with each other; it can be a direct connection, or an indirect connection through an intermediate medium, it can be the internal connection of two elements or the interaction relationship between two elements, unless otherwise clearly defined. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.

[0053] In the present utility model, unless otherwise clearly specified and limited, a first feature being "above" or "below" a second feature may mean that the first and second features are in direct contact, or the first and second features are in indirect contact through an intermediate medium. Moreover, a first feature being "above", "above" or "above" a second feature may mean that the first feature is directly above or obliquely above the second feature, or simply means that the first feature is higher in level than the second feature. A first feature being "below", "below" or "below" a second feature may mean that the first feature is directly below or obliquely below the second feature, or simply means that the first feature is lower in level than the second feature.

[0054] In the present utility model, the terms "one embodiment", "some embodiments", "examples", "specific examples", or "some examples" etc. mean that the specific features, structures, materials or characteristics described in conjunction with the embodiment or example are included in at least one embodiment or example of the present utility model. In this specification, the schematic representations of the above terms do not necessarily refer to the same embodiment or example. Moreover, the described specific features, structures, materials or characteristics may be combined in any one or more embodiments or examples in a suitable manner. In addition, those skilled in the art may combine and combine the different embodiments or examples described in this specification and the features of the different embodiments or examples, without contradiction.

[0055] Although the embodiments of the present invention have been shown and described above, it can be understood that the above embodiments are exemplary and cannot be understood as limitations of the present invention. Ordinary technicians in the field can change, modify, replace and modify the above embodiments within the scope of the present invention.

Claims

1. A coal mine long hole continuous segmented grouting device, It is characterized in that include: A plurality of blocking members, wherein the blocking members are arranged at intervals along the length direction thereof, and the blocking members are all arranged in the drilled hole so that the blocking members can block the drilled hole; A plurality of connecting pieces, at least one of which is disposed between two adjacent blocking pieces and both ends of at least one of which are respectively connected to the two adjacent blocking pieces, the connecting piece having a connecting state and a disconnecting state, in which the pressure of the slurry in at least one of the two adjacent blocking pieces is greater than a preset value, and the connecting piece connects the two adjacent blocking pieces, and in which the pressure of the slurry in both of the two adjacent blocking pieces is less than a preset value, and at least one of the two adjacent blocking pieces is disconnected from the connecting piece; A plurality of grouting pieces, at least one of which is arranged between two adjacent sealing pieces and is connected to at least one of the two adjacent sealing pieces; after the two adjacent sealing pieces seal the borehole, the grouting piece is connected to at least one of the two adjacent sealing pieces so that the grouting piece can grout the borehole.

2. The coal mine long hole continuous segmented grouting device according to claim 1, It is characterized in that The opening pressure of the connecting state of the plurality of connecting pieces gradually increases along the length direction of the borehole.

3. The coal mine long hole continuous segmented grouting device according to claim 1, It is characterized in that The connecting member includes a connecting pipe, a first valve and a second valve, wherein the first valve is arranged between the connecting pipe and a section of the blocking member and is connected to the connecting pipe and one end of the blocking member, and the second valve is arranged between the other end of the blocking member and the connecting pipe and is connected to the other end of the blocking member. In the connected state, the second valve in one of the two adjacent sealing parts is opened and the pressure of the first valve in the other of the two adjacent sealing parts is opened, and the pressure of the second valve in the other of the two adjacent sealing parts is closed. In the disconnected state, the first valve and the second valve of the two adjacent sealing parts are both closed.

4. The coal mine long hole continuous segmented grouting device according to claim 3, It is characterized in that The first valve and the second valve are both pressure valves, the opening pressure of the second valve in one of the two adjacent sealing parts is equal to the opening pressure of the first valve in the other of the two adjacent sealing parts, and the opening pressure of the first valve in the two adjacent sealing parts gradually increases along the length direction of the borehole.

5. The coal mine long hole continuous segmented grouting device according to claim 3, It is characterized in that The grouting part includes a grouting pipe and a third valve. The grouting pipe is arranged between two adjacent sealing parts and is connected to at least one of the two adjacent sealing parts. The third valve is arranged in the grouting pipe. After the two adjacent sealing parts block the drill hole, the third valve is opened so that the grouting pipe is arranged in at least one of the two adjacent sealing parts and is connected through the third valve.

6. The coal mine long hole continuous segmented grouting device according to claim 5, It is characterized in that The third valve is a pressure valve, and the opening pressure of the third valve is greater than the opening pressure of the first valve or the opening pressure of the second valve adjacent to the third valve.

7. The coal mine long hole continuous segmented grouting device according to claim 5, It is characterized in that The grouting part includes a tube body, and the outer peripheral surface of the tube body is provided with a plurality of grouting holes penetrating the tube body in the inner and outer directions. The plurality of grouting holes are arranged in a plurality of circles along the axial direction of the tube body, and each circle includes a plurality of grouting holes arranged at intervals along the circumference of the tube body.

8. The coal mine long hole continuous segmented grouting device according to claim 1, It is characterized in that The distance between two adjacent blocking members is 5m-20m.

9. The coal mine long hole continuous segmented grouting device according to claim 1, It is characterized in that The grouting pressure of the plurality of grouting pieces gradually increases along the length direction of the borehole.

10. The coal mine long hole continuous segmented grouting device according to claim 1, It is characterized in that The sealing parts are all grouting sealing parts.

Citation Information

Cited By

  • Continuous segmented grouting construction method for long hole of coal mine

    CN117780389A