Pipeline structure suitable for CIPP ultraviolet light curing full lining repairing method
By installing a knitted flexible hose layer and a resin layer inside the drainage pipe and using ultraviolet light curing technology, the problem of repairing structural defects in urban drainage pipes has been solved, achieving efficient and low-cost pipe reinforcement.
Patent Information
- Application Number
- CN202420384700.4
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-02-29
- Publication Date
- 2024-11-26
- Estimated Expiration
- 2034-02-28
AI Technical Summary
The structural defects of existing urban drainage pipes are difficult to repair efficiently, and replacement is costly and inconvenient.
The CIPP ultraviolet light curing full lining repair method is adopted. By setting a knitted hose layer, a resin layer and a low-density polyethylene coating inside the pipe, and using ultraviolet light curing technology to cure the hose to form an inner lining pipe, the pipe structure is reinforced.
It enables simple construction and efficient repair of pipeline structures, reduces maintenance costs, and improves the service life and strength of pipelines.
Smart Images

Figure CN222067953U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to an urban pipe network system, in particular to a pipe structure suitable for a CIPP ultraviolet light curing full lining repair method. Background Art
[0002] In order to prevent urban waterlogging, a large number of drainage pipes are distributed underground in cities, including rainwater pipes and sewage pipes. In the long-term drainage process, rainwater pipes and sewage pipes will have defects of varying degrees due to the scouring of rainwater or sewage, the deposition of impurities, etc., which can be mainly divided into two categories: functional defects and structural defects.
[0003] Functional defects refer to those that affect drainage functions (such as mud accumulation, tree roots, etc.). Functional defects can be improved by dredging and cleaning. Structural defects affect structural strength and service life (such as cracks, corrosion, etc.). Structural defects can only be improved by repair or replacement. However, the replacement cost is high and the construction is inconvenient. Therefore, repair methods are often used for local defects in pipelines. Utility Model Content
[0004] The purpose of the utility model is to overcome the shortcomings of the above-mentioned background technology and provide a pipeline structure suitable for the CIPP ultraviolet light curing full lining repair method, so that it has the advantages of simple structure, convenient construction and good maintenance effect.
[0005] The utility model provides a pipeline structure suitable for a CIPP ultraviolet light-curing full lining repair method, comprising a pipeline body, wherein a knitted hose layer coaxially arranged with the pipeline body is bonded to the inner wall of the pipeline body.
[0006] In the above technical solution, a coaxially arranged resin layer is provided between the knitted hose layer and the pipe body.
[0007] In the above technical solution, the inner wall of the knitted hose layer is provided with a low-density polyethylene coating coaxially arranged therewith.
[0008] In the above technical solution, a cushion membrane layer is provided between the bottom inner wall of the pipe body and the knitted hose layer.
[0009] The utility model is applicable to the pipeline structure of the CIPP ultraviolet light curing full lining repair method, and has the following beneficial effects:
[0010] The CIPP UV-curing lining repair process is a type of in-situ curing method, which involves pulling a glass fiber reinforced hose into the pipe section to be repaired, inflating it, and then curing the hose under the action of ultraviolet light to form a liner pipe with a certain strength, so as to achieve the purpose of reinforcing and repairing the original pipeline structure. BRIEF DESCRIPTION OF THE DRAWINGS
[0011] Figure 1 It is a schematic diagram of the structure of the pipeline structure applicable to the CIPP ultraviolet light curing full lining repair method of the utility model;
[0012] Figure 2 This is an on-site construction drawing of a pipeline structure suitable for the CIPP ultraviolet light-curing full-lining repair method of the utility model. DETAILED DESCRIPTION
[0013] The present invention will be further described in detail below in conjunction with the accompanying drawings and embodiments, but the embodiments should not be construed as limiting the present invention.
[0014] See also Figure 1 The utility model is applicable to a pipeline structure of a CIPP ultraviolet light curing full lining repair method, comprising a pipeline body 1, wherein a knitted hose layer 2 coaxially arranged therewith is bonded to the inner wall of the pipeline body 1.
[0015] A coaxially arranged resin layer 3 is provided between the knitted hose layer 2 and the pipe body 1. A coaxially arranged low-density polyethylene coating 4 is provided on the inner wall of the knitted hose layer 2.
[0016] A cushion membrane layer 5 is provided between the bottom inner wall of the pipe body 1 and the knitted hose layer 2 .
[0017] The CIPP UV-curing lining repair process is a type of in-situ curing method, which involves pulling a glass fiber reinforced knitted hose 6 into the pipe body 1 of the pipe section to be repaired, inflating it, and then curing the knitted hose 6 under the action of ultraviolet light to form a knitted hose layer 2 with a certain strength, so as to achieve the purpose of reinforcing and repairing the original pipe body 1 structure.
[0018] See also Figure 2 , CIPP UV light curing full lining repair process:
[0019] (1) The upstream and downstream adjacent pipe openings of the pipeline body 1 to be repaired and the pipe opening of the previous section of the drainage pipe are blocked with water-blocking airbags 7 (i.e., the upstream and downstream water-blocking airbags), and then the pipeline body 1 is cleared.
[0020] (2) A cushioning film layer 5 is laid on the inner wall of the pipeline body 1 to be repaired. The coverage of the cushioning film layer 5 should be greater than 1 / 3 of the cross-sectional circumference of the pipeline body 1. The knitted hose 6 is pulled into the pipeline body 1 to be repaired by a trolley (not shown in the figure). When the knitted hose 6 is pulled in, the resin-impregnated knitted hose 6 should be pulled smoothly, evenly and slowly along the cushioning film layer 5 inside the pipe into the pipeline body 1 to be repaired. The pulling speed shall not be greater than 5m / min, and the pulling force shall not be greater than 122KN.
[0021] (3) After the knitted hose 6 is pulled in, the hose is fully expanded and expanded by compressed air to fit tightly against the inner wall of the original pipe body 1. The pressure is uniformly increased to 100 mbar at a rate of 10 mbar / min, and then increased to 150 mbar at a maximum rate of 50 mbar / min to allow the hose to fully expand. The pressure is then slowly increased to a working pressure of 450 mbar and maintained for at least 10 minutes. The inflation is stopped, the tying head 8 is opened, and the 8x1000W ultraviolet double lamp holder is quickly placed into the tying head 8. The ultraviolet lamp 9 on the first lamp holder is turned on first, and then the ultraviolet lamp 9 on the second lamp holder is turned on after a period of time. In one or more embodiments, the interval between turning on the lamps is 10 seconds. Pull the lamp chain 10 connected to the curing equipment 11 parked on the road surface 12 into the knitted hose 6. The pulling-in speed of the UV lamp 9 lamp holder is determined comprehensively according to the pipe diameter, wall thickness and lamp holder combination. The moving speed of the UV lamp 9 lamp holder should be controlled at half of the predetermined speed within 0.5m at the starting end of curing, and then increased to the predetermined speed. When it reaches 1.0m at the end of curing, it will be reduced to half of the predetermined speed until the end.
[0022] (4) After the knitted hose layer 2 is cured, the pressure in the knitted hose layer 2 is slowly reduced to atmospheric pressure. After curing, the tying head 8 is removed, the cushion film layer 5 is pulled out, and the end of the knitted hose layer 2 is cut flat.
[0023] Obviously, those skilled in the art can make various changes and modifications to the present invention without departing from the spirit and scope of the present invention. Thus, if these modifications and variations of the present invention fall within the scope of the claims of the present invention and their equivalents, the present invention is also intended to include these modifications and variations.
[0024] The contents not described in detail in this specification belong to the prior art known to professional and technical personnel in this field.
Claims
1. A pipeline structure suitable for a CIPP ultraviolet light curing full lining repair method, comprising a pipeline body (1), characterized in that: A knitted hose layer (2) coaxially arranged therewith is bonded to the inner wall of the pipeline body (1).
2. The pipeline structure suitable for the CIPP ultraviolet light curing full lining repair method according to claim 1 is characterized in that: A coaxially arranged resin layer (3) is provided between the knitted hose layer (2) and the pipe body (1).