Tunnel lining construction joint anti-seepage device
By installing a seepage prevention device consisting of rubber waterstops and drainage pipes in the tunnel floor construction area, the problem of water seepage at the tunnel lining construction joints was solved, achieving a seepage prevention effect at the construction joints, ensuring construction quality and reducing costs.
Patent Information
- Application Number
- CN202420611641.X
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-03-27
- Publication Date
- 2024-11-29
- Estimated Expiration
- 2034-03-27
AI Technical Summary
During tunnel lining construction, water seepage at horizontal construction joints is difficult to control, leading to quality problems and making subsequent treatment difficult and costly.
Rubber waterstops and drainage pipes are installed in the tunnel floor construction area. The rubber waterstops are divided into lower and upper intercepting parts and are fixed by waterstop fixing devices. The drainage pipes are equipped with inlets and outlets to drain seepage water. The combination of the waterstop fixing devices and drainage pipes forms an effective seepage prevention device.
It effectively controls water seepage at construction joints, ensuring that the bonding between new and old concrete at construction joints is not affected by water seepage. It is easy to install, simple to operate, has good seepage prevention effect, and is low in cost.
Smart Images

Figure CN222084521U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of tunnel lining horizontal construction joint anti-seepage, in particular to a tunnel lining construction joint anti-seepage device. Background Art
[0002] During the tunnel lining concrete construction process, in order to ensure the safety of tunnel construction, it is necessary to carry out lining construction while excavating. To meet this condition, the tunnel bottom plate lining concrete needs to be poured separately from the side top arch lining concrete, forming a horizontal construction joint between the bottom plate lining concrete and the side top arch lining concrete. This horizontal construction joint is in the tunnel seepage tunnel section. If no anti-seepage measures are taken or quality control is not in place, it is very easy to cause construction joint seepage quality problems. If the construction joint seepage is not controlled in the early stage, it will be difficult to deal with in the later stage and the cost is high. Utility Model Content
[0003] The utility model aims to provide an anti-seepage device which can effectively control water seepage at construction joints.
[0004] To this end, the utility model adopts the following technical solutions:
[0005] A tunnel lining construction joint anti-seepage device, a rubber water stop is arranged on the top of the tunnel bottom plate construction area, the rubber water stop is divided into a lower blocking part extending into the bottom plate construction area and an upper blocking part that can extend into the side top arch construction area, a water stop fixing device limitedly connected to the lower blocking part is arranged in the bottom plate construction area; a drainage pipe that can discharge water seeping from the initial support surface is also arranged on the top of the bottom plate construction area, a water inlet and a water outlet are arranged at both ends of the drainage pipe, the water inlet is arranged in the area between the rubber water stop and the initial support surface, and the water inlet extends out of the bottom plate construction area, the water outlet is arranged below the rubber water stop, and the water outlet is connected to the flow surface and communicated with the flow surface.
[0006] Furthermore: both side ends of the water-stopping fixture are connected to the steel bars in the bottom plate construction area.
[0007] Furthermore: a downwardly recessed groove is provided on the water-stop fixing device, and the lower blocking portion of the rubber water-stop is hung in the groove.
[0008] Furthermore: the interval between the groove and the flow surface is smaller than the interval between the groove and the primary support surface.
[0009] Furthermore: a detachable protective piece is provided on the upper blocking portion of the rubber water stop and / or the water inlet of the drain pipe.
[0010] Compared with the prior art, the utility model has the following beneficial effects:
[0011] The utility model uses rubber water-stopping to block water seepage and pre-buried drainage pipes to drain water, creating good construction conditions, so that the combination of new and old concrete at the construction joint is not affected by water seepage, and effectively controls the quality of water seepage at the construction joint. It can ensure the construction quality of lining concrete at the construction joint and effectively control the overall water seepage at the construction joint. It has the advantages of easy installation, simple operation, good anti-seepage effect, and low cost. BRIEF DESCRIPTION OF THE DRAWINGS
[0012] Figure 1 It is a plan view of the utility model;
[0013] Figure 2 For the utility model Figure 1 An enlarged schematic diagram of
[0014] Figure 3 It is a cross-sectional schematic diagram of the utility model.
[0015] The markings in the attached drawings are: 1- rubber water stop; 11- water stop fixture; 111- groove; 2- drainage pipe; 201- water inlet; 202- water outlet; 21- drainage fixture; 3- initial support surface; 4- flow surface; 5- reinforcement bar. DETAILED DESCRIPTION
[0016] The present invention is further described below in conjunction with the accompanying drawings and embodiments, but they are not intended to limit the present invention.
[0017] like Figure 1-3 As shown, a tunnel lining construction joint anti-seepage device is provided, a rubber water stop 1 is arranged on the top of the tunnel bottom plate construction area, the rubber water stop 1 is divided into a lower blocking part extending into the bottom plate construction area and an upper blocking part which can extend into the side top arch construction area, a water stop fixing device 11 which is limit-connected with the lower blocking part is arranged in the bottom plate construction area, so that when pouring the bottom plate lining concrete, the rubber water stop 1 is fixed in advance at the position of the construction joint area through the water stop fixing device 11; a drainage pipe 2 is also arranged on the top of the bottom plate construction area, the drainage pipe 2 is bent in the middle so that the pipe sections on both sides are divided into a first pipe section and a second pipe section, and a water inlet 201 and a water outlet 202 are arranged at both ends of the drainage pipe 2, the first pipe section is arranged in the area between the rubber water stop 1 and the initial support surface 3, and the water inlet 201 on the first pipe section is extended out of the bottom plate construction area, the second pipe section is arranged below the rubber water stop 1, and the water outlet 202 on the second pipe section is connected to the flow surface 4 and communicated with the flow surface 4.
[0018] In this embodiment, when pouring the bottom plate lining concrete, the lower blocking portion of the rubber water stop 1 is poured into the bottom plate lining concrete, and when the side top arch lining concrete is poured, the upper blocking portion of the rubber water stop 1 is poured into the side top arch lining concrete, forming the water blocking effect of the rubber water stop 1 on the construction joint. At the same time, before pouring the bottom plate lining concrete, the drainage fixing device 21 is used to fix the first pipe section of the drainage pipe 2 on the primary support surface 3, and the end of the second pipe section of the drainage pipe 2 is fixed on the flow surface 4, so as to discharge the seepage of the primary support surface 3 to achieve the drainage effect.
[0019] The drainage fixing device 21 can use a U-shaped clamp to fix the drainage pipe 2. The water-stopping fixing device 11 is made of round steel.
[0020] In this embodiment, the water inlet 201 of the drainage pipe 2 is located 10 cm above the location of the construction joint, and the water outlet 202 is located 50 cm below the location of the construction joint.
[0021] In this embodiment, the ends of both sides of the water stop fixture 11 are fixed to the steel bars 5 in the bottom plate construction area by tying wires. A groove 111 concave downward is provided on the water stop fixture 11, and the lower blocking portion of the rubber water stop 1 is hung in the groove 111. Several water stop fixtures 11 are arranged at intervals of 1.5m in the direction of the steel bars 5, so that the lower blocking portion of the rubber water stop 1 can be stably arranged in the bottom plate construction area before the bottom plate lining concrete is poured.
[0022] The spacing between the groove 111 and the flow surface 4 is smaller than the spacing between the groove 111 and the primary support surface 3 . In this embodiment, the spacing between the rubber water stop 1 and the flow surface 4 is 20 cm.
[0023] In this embodiment, a detachable protective part (not shown in the figure) is provided on the upper blocking portion of the rubber water stop 1 and the water inlet 201 of the drain pipe 2, so that the construction joints can be roughened when pouring the side arch lining concrete. During the roughening process, care should be taken to avoid damaging the rubber water stop 1 or clogging the drain pipe.
[0024] In order to ensure the anti-seepage effect of the device, the following matters should be noted during the use of the device:
[0025] When pouring concrete at the construction joint, pay attention to vibrating the lining concrete around the rubber water stop 1 to make it dense.
[0026] The above embodiment is only a preferred technical solution of the present invention. Those skilled in the art should understand that the technical solutions or parameters in the embodiments can be modified or replaced without departing from the principle and essence of the present invention, and all should be included in the protection scope of the present invention.
Claims
1. A tunnel lining construction joint anti-seepage device, Features: A rubber water stop (1) is arranged at the top of the tunnel bottom plate construction area. The rubber water stop (1) is divided into a lower blocking portion extending into the bottom plate construction area and an upper blocking portion that can extend into the side arch construction area. A water stop fixing device (11) is arranged in the bottom plate construction area and is limitedly connected to the lower blocking portion. A drainage pipe (2) that can discharge water seeping from the primary support surface (3) is also arranged at the top of the bottom plate construction area. A water inlet (201) and a water outlet (202) are arranged at both ends of the drainage pipe (2). The water inlet (201) is arranged in the area between the rubber water stop (1) and the primary support surface (3), and the water inlet (201) extends out of the bottom plate construction area. The water outlet (202) is arranged below the rubber water stop (1), and the water outlet (202) is connected to the flow surface (4) and communicates with the flow surface (4).
2. A tunnel lining construction joint anti-seepage device according to claim 1, Features: Both end portions of the water-stopping fixing device (11) are connected to the steel bars (5) in the bottom plate construction area.
3. A tunnel lining construction joint anti-seepage device according to claim 1, Features: The water stop fixing device (11) is provided with a groove portion (111) which is recessed downwards, and the lower blocking portion of the rubber water stop (1) is hung in the groove portion (111).
4. A tunnel lining construction joint anti-seepage device according to claim 3, Features: The spacing between the groove portion (111) and the flow surface (4) is smaller than the spacing between the groove portion (111) and the primary support surface (3).
5. A tunnel lining construction joint anti-seepage device according to claim 1, Features: The upper blocking portion of the rubber water stop (1) and / or the water inlet (201) of the drainage pipe (2) are provided with a detachable protective piece.