Lifting appliance device of long-piled wharf beam and slab erecting machine

By introducing steel cables, circular gears and hydraulic position adjustment mechanisms into the beam and plate erection machine slings in the high pile dock, the problem of difficult positioning during the lifting process of prefabricated beam and plate components is solved, and rapid and stable lifting and installation are achieved , improves safety and efficiency.

CN222099399UActive Publication Date: 2024-12-03CCCC SECOND HARBOR ENGINEERING CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420447561.5
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-03-08
Publication Date
2024-12-03
Estimated Expiration
2034-03-08

AI Technical Summary

Technical Problem

During the lifting of prefabricated beam slab components at high pile docks, the prior art is difficult to control the position of the components, resulting in skews and position deviations during the installation process, especially in the case of heavy sea breezes.

Method used

A high pile dock beam plate mounting machine sling device was designed, using steel cables, circular gears, oil cylinders and hydraulic position adjustment mechanisms. The circular gear is driven by the motor and the oil cylinder is adjusted to adjust the position of the cross beams and longitudinal beams to realize the prefabricated beams. Quick leveling and posture adjustment of the plate members.

Benefits of technology

It realizes rapid and stable lifting and automatic leveling of prefabricated beam and slab components, reduces external manual traction needs, improves the safety and efficiency of the lifting process, can be lifted under 360-degree rotation, and adapts to component installation in different postures .

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222099399U_ABST
    Figure CN222099399U_ABST
Patent Text Reader

Abstract

The utility model discloses a long piled wharf beam plate erecting machine lifting appliance device which comprises a circular gear, a motor is installed on the upper surface of the circular gear, the upper end of a circular gear rotating shaft is connected with a transmission shaft of the motor, the lower end of the circular gear rotating shaft is connected with the top end of a stand column, and the motor works to drive the circular gear to rotate. The bottom end of the stand column is movably connected with the middle of the cross beam. The first oil cylinder is arranged between the stand column and the cross beam, the second oil cylinder is arranged between the stand column and the longitudinal beam, when the first oil cylinder extends or shortens, the heights of the left end and the right end of the cross beam are increased or decreased, and when the second oil cylinder extends or shortens, the heights of the front end and the rear end of the cross beam are increased or decreased; according to the lifting appliance device, the posture of the precast beam and slab component in the horizontal direction can be rapidly leveled, the top of the lifting appliance device is of a disc-shaped structure, the disc-shaped structure can rotate by 360 degrees, the posture of the precast beam and slab component can be rapidly adjusted, and the precast beam and slab component can be conveniently and rapidly installed.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the field of prefabricated component hoisting of high-pile docks, in particular to a hoisting device for a beam and slab erecting machine of a high-pile dock. Background Art

[0002] The construction of high-pile docks is often located in offshore areas. The high-pile docks are assembled and installed using prefabricated components. Specifically, the high-pile docks are assembled using multiple prefabricated beams and slabs. The high-pile docks include multiple beams and slabs arranged horizontally and vertically. The multiple prefabricated beams and slabs are placed horizontally or vertically to form a tic-tac-toe shape to form a high-pile dock.

[0003] Affected by the sea breeze and waves in the high-pile wharf construction area, many domestic projects have adopted erection machines to install prefabricated beam and slab components. Its structure is similar to that of a bridge erection machine. The prefabricated beam and slab components are lifted by an overhead crane on a double-truss structure track. The prefabricated beam and slab components are connected to the hoisting equipment, and the installation of the prefabricated beam and slab components is completed by lifting, translating, and lowering. During the installation process, the prefabricated beams and slabs are placed horizontally or vertically, and multiple prefabricated beams and slabs are placed horizontally or vertically to form a tic-tac-toe shape.

[0004] In the prior art, the lifting device of prefabricated beam and slab components usually includes a crossbeam, with a steel wire rope connected to each end of the crossbeam, the upper end of the steel wire rope is fixed to the two ends of the crossbeam, and the lower end of each steel wire rope can be connected to a pre-buried annular lifting ring on the top surface of the beam and slab to lift the prefabricated beam and slab components. Since the center of gravity of the prefabricated beam and slab components is not necessarily in a straight line with the center of the lifting device, the position of the lifting ring on the top surface of the prefabricated beam and slab components will also affect the posture of the beam and slab during the lifting process. For example, the steel wire ropes at both ends of the crossbeam are each connected to a lifting ring on the top surface of the prefabricated beam and slab components. When the two lifting rings connected by the steel wire ropes are asymmetrically designed with the center of gravity of the prefabricated beam and slab components, the prefabricated beam and slab components will tilt during the lifting process.

[0005] During the installation of prefabricated beam and slab components, due to the heavy weight of the beam and slab and the uneven distribution of the weight, the traditional hoisting equipment needs to consider the position of the lifting point when hoisting, and cooperate with external traction when moving to complete the hoisting. During the hoisting process, the posture of the prefabricated beam and slab components is difficult to control, and it is easy to deflect when the sea breeze is strong, resulting in position deviation of the prefabricated beam and slab components during the installation process. Therefore, it is necessary to develop a high-pile dock erection machine hoist to solve the problem of difficult control of the posture during component installation. Utility Model Content

[0006] The utility model aims to provide a lifting device for a beam and slab erecting machine of a high-pile wharf, so as to quickly and stably complete the lifting operation and solve the problem that the posture of prefabricated beam and slab components of the high-pile wharf is difficult to control during the lifting process.

[0007] In order to achieve the above objectives, the technical solution of the utility model is:

[0008] A lifting device for a beam and slab erecting machine for a high-pile wharf comprises a connecting structure, the connecting structure comprises a steel cable, the top end of the steel cable is connected to a crane, the crane moves along a track of a double-truss structure to lift prefabricated beam and slab components, the bottom end of the steel cable is connected to a lifting device, the connecting device also comprises a circular gear, the bottom end of the steel cable is connected to a hook arranged on the circular gear, a motor is arranged on the upper surface of the circular gear through a mounting base, the upper end of a rotating shaft of the circular gear is connected to a transmission shaft of the motor, and the operation of the motor drives the circular gear to rotate; the lower end of the rotating shaft of the circular gear is connected to the top end of a column, the bottom end of the column is movably connected to the middle part of a beam, a longitudinal beam is arranged on one side of the beam, and the longitudinal beam forms a certain angle with the beam; the positioning mechanism comprises a first oil cylinder and a second oil cylinder, the first oil cylinder is arranged between the column and the beam, the second oil cylinder is arranged between the column and the longitudinal beam, when the piston cylinder of the first oil cylinder is extended or shortened, the height of the left and right ends of the beam is increased or decreased, and when the piston rod of the second oil cylinder is extended or shortened, the height of the front and rear ends of the beam is increased or decreased.

[0009] Furthermore, the crossbeam is in the shape of a rectangular parallelepiped, and a rectangular groove is provided in the middle of the upper surface of the crossbeam. A plurality of horizontal axes are arranged on the groove at laterally intervals, and the horizontal axes include a first horizontal axis and a second horizontal axis. The two ends of the first horizontal axis and the second horizontal axis are respectively connected to the opposite side surfaces of the rectangular groove, and the setting direction of the first horizontal axis and the second horizontal axis is the same as the setting direction of the crossbeam.

[0010] Furthermore, the bottom end of the column is a rectangular frame structure, the bottom of the rectangular frame structure is a longitudinal axis, the first horizontal axis and the second horizontal axis are sleeved on the longitudinal axis, the first horizontal axis and the second horizontal axis are located above the longitudinal axis, when no external force is applied to the cross beam or the longitudinal beam, the first horizontal axis and the second horizontal axis are in contact with the longitudinal axis and the first horizontal axis and the second horizontal axis are perpendicular to the longitudinal axis; the length of the longitudinal axis is less than the length of the square groove.

[0011] Furthermore, the longitudinal beam is in a rectangular parallelepiped shape, the longitudinal beam is located on one side of the cross beam, and one end of the longitudinal beam is fixed to the side surface of the cross beam.

[0012] Furthermore, the sling device also includes a positioning mechanism, which includes a first oil cylinder, a second oil cylinder, a pump station and an arc structure; the first oil cylinder and the pump station are located on both sides of the column, the first oil cylinder is located on the right side of the column, and the pump station is arranged on the upper surface of the left end of the beam; the pump station is connected to the first oil cylinder through a hydraulic hose, and the pump station is connected to the second oil cylinder through a hydraulic hose, the arc structure is located on the right side of the column, and the left end of the arc structure is movably connected to the column.

[0013] Furthermore, the connection point between the left end of the arc structure and the column is lower than the first lug arranged on the column, the bottom surface of the right end of the arc structure is arranged on the upper surface of the right end of the beam, and the bottom surface of the left end of the arc structure can gradually move away from the upper surface of the right end of the beam.

[0014] Furthermore, the upper end of the first oil cylinder is hingedly connected to the column, a first lug is arranged on the left side of the column, a hinge shaft is arranged on the first lug, and the upper end of the first oil cylinder is connected to the hinge shaft;

[0015] The lower end of the first oil cylinder is hingedly connected to the right end of the arc structure. A hinge shaft is arranged at the right end of the arc structure. The lower end of the first oil cylinder is hingedly connected to the right end of the arc structure through the hinge shaft.

[0016] Furthermore, a second lug is arranged on the surface of the column adjacent to the surface where the first lug is located, and the second lug is at the same height as the first lug; a hinge shaft is arranged on the second lug, and the upper end of the second oil cylinder is hingedly connected to the hinge shaft on the second lug; a third lug is arranged on the upper surface of the end of the longitudinal beam away from the cross beam, and a hinge shaft is arranged on the third lug, and the lower end of the second oil cylinder is hingedly connected to the hinge shaft on the third lug.

[0017] Furthermore, a through hole is provided at the top of the column, and a through hole is also provided at the lower end of the circular gear rotating shaft. The through hole and the through hole at the lower end of the circular gear rotating shaft are connected by bolts, so as to realize the connection between the circular gear rotating shaft and the top of the column.

[0018] Furthermore, a hook is provided at each end of the beam, the hook is ring-shaped, and the hook is provided at both ends of the bottom surface of the beam. Each hook is connected to the top end of a steel wire rope, and the bottom end of each steel wire rope is connected to a ring-shaped lifting ring embedded on the top surface of the beam plate.

[0019] The beneficial effects of the utility model are:

[0020] 1. The utility model automatic lifting device can realize the rapid leveling of the prefabricated beam and slab components in the horizontal direction through the oil cylinders arranged horizontally and longitudinally, without the need for external manual traction, thus ensuring the safety of personnel and realizing the rapid installation of prefabricated beam and slab components.

[0021] 2. The oil cylinder provided in the utility model can realize the adjustment of the horizontal posture of the left and right ends and the front and rear ends of the prefabricated beam and slab components. The hoisting device of the utility model can control the posture of the prefabricated beam and slab components during the hoisting process, and is easy to use.

[0022] 3. The top of the utility model hoist adopts a disc-shaped structure, which can be rotated 360 degrees. The initial lifting position of the prefabricated beam and slab components is not restricted. The prefabricated beam and slab components can enter the lifting area longitudinally or transversely by rotating the disc.

[0023] 4. The load-bearing structure of the sling adopts a combination of crossbeams and longitudinal beams, which has a better load-bearing effect. BRIEF DESCRIPTION OF THE DRAWINGS

[0024] Figure 1 This is the front view of the utility model sling device

[0025] Figure 2 It is a side view of the sling device of the utility model.

[0026] Figure 3 It is a schematic diagram of a column of the utility model.

[0027] Figure 4 It is a schematic diagram of the crossbeam of the utility model.

[0028] Figure 5 It is a plan view of the sling device of the utility model.

[0029] Among them: connecting structure 1; circular gear 11; column 12; frame structure 121; through hole 122; longitudinal axis 1211; adjustment mechanism 2; first oil cylinder 21; second oil cylinder 22; pump station 23; arc structure 24; first lug 25; second lug 26; third lug 27; crossbeam 3; groove 31; first horizontal axis 311; second horizontal axis 312; hook 32; longitudinal beam 4; hydraulic hose 5. DETAILED DESCRIPTION

[0030] In order to make the purpose, technical solution and advantages of the utility model clearer, the utility model is further described below with reference to the accompanying drawings.

[0031] like Figure 1 and Figure 2 As shown, the sling device of the utility model comprises a connecting structure 1, a positioning mechanism 2, a cross beam 3 and a longitudinal beam 4.

[0032] The connecting structure 1 includes a circular turntable, which can be a circular gear 11. A motor and a plurality of raised annular hooks are arranged on the upper surface of the circular turntable. The motor can be installed on the upper surface of the circular turntable through a motor base. The upper end of the rotating shaft of the circular gear 11 is connected to the transmission shaft of the motor, and the lower end of the rotating shaft of the circular gear 11 is connected to the top of the column 12. The bottom end of the column 12 is movably connected to the middle part of the crossbeam 3. The motor can drive the circular gear 11 to rotate 360°, and the rotation of the circular gear 11 drives the column 12 to rotate. A through hole 122 is arranged at the top of the column 12, and a through hole is also arranged at the lower end of the rotating shaft of the circular gear 11. The through hole 122 is connected to the through hole at the lower end of the rotating shaft of the circular gear 11 by bolts or pins, so as to realize the connection between the rotating shaft of the circular gear and the top of the column 12.

[0033] like Figure 4As shown, the crossbeam 3 is in the shape of a rectangular parallelepiped. Regarding the movable connection between the bottom end of the column 12 and the middle part of the upper surface of the crossbeam structure 3, a square groove 31 can be set in the middle part of the upper surface of the crossbeam 3. A plurality of horizontal axes are arranged horizontally at intervals on the rectangular groove 31. Specifically, two horizontal axes are arranged, namely a first horizontal axis 311 and a second horizontal axis 312. The two ends of the first horizontal axis 311 and the second horizontal axis 312 are respectively connected to the opposite side surfaces of the rectangular groove 31. The setting direction of the first horizontal axis 311 and the second horizontal axis 312 is the same as the setting direction of the crossbeam 3.

[0034] like Figure 3 As shown, the bottom end of the column 12 is a rectangular frame structure 121, and the bottom of the rectangular frame structure is a longitudinal axis 1211. The first horizontal axis 311 and the second horizontal axis 312 are sleeved on the longitudinal axis 1211 at the bottom of the rectangular frame structure 121 at the bottom end of the column 12. The first horizontal axis 311 and the second horizontal axis 312 are located above the longitudinal axis 1211. When no external force is applied to the cross beam 3 or the longitudinal beam 4, the first horizontal axis 311 and the second horizontal axis 312 are both in contact with the longitudinal axis 1211 and are perpendicular to the longitudinal axis 1211; the length of the longitudinal axis 1211 is less than the length of the square groove 31.

[0035] The longitudinal beam 4 is in a rectangular parallelepiped shape. The longitudinal beam 4 is located on one side of the cross beam 3 . One end of the longitudinal beam 4 is fixed to the side of the cross beam 3 . The longitudinal beam 4 can be vertically arranged with the cross beam 3 . The longitudinal beam 4 can be welded to the cross beam 3 .

[0036] The positioning mechanism 2 includes a first oil cylinder 21, a second oil cylinder 22, a pump station 23 and an arc structure 24; the first oil cylinder 21 and the pump station 23 are located on both sides of the column 12, such as Figure 1 , Figure 2 and Figure 5 As shown, the pump station 23 is located on the left side of the column 12 , and the pump station 23 is arranged on the upper surface of the left end of the beam 3 .

[0037] The pump station 23 is connected to the first oil cylinder 21 through a hydraulic hose 5 , and the pump station 23 is connected to the second oil cylinder 22 through a hydraulic hose 5 . The pump station 23 is used to control the operation of the first oil cylinder 21 and the second oil cylinder 22 .

[0038] The arc structure 24 is located on the right side of the column 12, and the left end of the arc structure 24 is connected to the column 12. The connection point between the left end of the arc structure 24 and the column 12 is lower than the first lug 25. The left end of the arc structure 24 is movably connected to the column 12. Specifically, a pin passes through the left end of the arc structure 24 and the column 12, and the left end of the arc structure 24 is hingedly connected to the column 12 through the pin. When external force is applied to the arc structure 24, the left end of the arc structure 24 can rotate around the pin; the bottom surface of the right end of the arc structure 24 can be partially welded to the upper surface of the right end of the beam 3, and the bottom surface of the left end of the arc structure 24 can gradually move away from the upper surface of the right end of the beam 3.

[0039] The upper end of the first oil cylinder 21 is hingedly connected to the column 12. A first lug 25 is arranged on the left side of the column 12. A hinge shaft is arranged on the first lug 25. The upper end of the first oil cylinder 21 is connected to the hinge shaft. The upper end of the first oil cylinder 21 is hingedly connected to the hinge shaft.

[0040] The lower end of the first oil cylinder 21 is hingedly connected to the right end of the arc structure 24 . A hinge shaft is provided at the right end of the arc structure 24 . The lower end of the first oil cylinder 21 is hingedly connected to the right end of the arc structure 24 via the hinge shaft.

[0041] A second lug 26 is provided on the surface of the column 12 adjacent to the surface where the first lug 25 is located, and the second lug 26 is at the same height as the first lug 25; a hinge shaft is provided on the second lug 26, and the upper end of the second oil cylinder 22 is hingedly connected to the hinge shaft on the second lug 26; a third lug 27 is provided on the upper surface of the end of the longitudinal beam 4 away from the cross beam 3, and a hinge shaft is provided on the third lug 27, and the lower end of the second oil cylinder 22 is hingedly connected to the hinge shaft on the third lug 27.

[0042] The method for hoisting prefabricated beam and slab components by using the utility model hoisting device is:

[0043] A hook 32 is provided at each end of the cross beam 3. The hook 32 is annular and is provided at both ends of the bottom surface of the cross beam 3. Each hook 32 is connected to the top end of a steel wire rope. The bottom end of each steel wire rope is connected to a pre-buried annular lifting ring on the top surface of the beam plate to facilitate the lifting of the prefabricated beam plate components. When the two lifting rings connected by the two steels are asymmetrically designed with the center of gravity of the prefabricated beam plate components, the prefabricated beam plate components will tilt during the lifting process.

[0044] The prefabricated beam and slab component includes four surfaces: front, rear, left and right. When the prefabricated beam and slab component is hoisted, the left end of the prefabricated beam and slab component tilts downward, that is, the left end of the prefabricated beam and slab component is lower than the right end of the prefabricated beam and slab component during the hoisting process. The pump station 23 is controlled by the remote control to extend the first cylinder 21, and the left end of the arc structure 24 is hinged to the column 12. The bottom surface of the right end of the arc structure 24 is connected to the upper surface of the right end of the beam 3. The first cylinder 21 is extended, and the right end of the beam 3 is subjected to downward pressure. The left ends of the first horizontal axis 311 and the second horizontal axis 312 are tilted upward, and at the same time, the right end of the beam 3 is subjected to pressure and moves downward, thereby causing the right end of the prefabricated beam and slab component hoisted by the beam 3 to tilt downward, thereby realizing the horizontal leveling of the left and right ends during the hoisting of the prefabricated beam and slab.

[0045] When the precast beam and slab component is being hoisted, the left end of the precast beam and slab component is tilted upward, that is, the left end of the precast beam and slab component is higher than the right end of the precast beam and slab component during the hoisting process. The pump station 23 is controlled by the remote controller to shorten the first cylinder 21, and the left end of the arc structure 24 is hingedly connected to the column 12. The bottom surface of the right end of the arc structure 24 is connected to the upper surface of the right end of the beam 3. The first cylinder 21 is shortened, and the right end of the beam 3 is subjected to an upward pulling force. The right ends of the first horizontal axis 311 and the second horizontal axis 312 are tilted upward, and at the same time, the right end of the beam 3 is pulled upward, so that the right end of the precast beam and slab component hoisted by the beam 3 is tilted upward, thereby realizing the horizontal leveling of the left and right ends during the hoisting of the precast beam and slab.

[0046] When the front end of the precast beam and slab component is higher than the rear end during the process of hoisting the precast beam and slab component, the pump station 23 is controlled by the remote control to extend the second oil cylinder 22. When the second oil cylinder 22 extends, the end of the longitudinal beam 4 away from the cross beam 3 is subjected to downward pressure, and the end of the longitudinal beam 4 away from the cross beam 3 moves downward, so that the cross beam 3 moves downward synchronously. When the front end of the cross beam 3 moves downward, the first horizontal axis 311 can gradually separate from the longitudinal axis 1211; the downward movement of the front end of the cross beam 3 causes the front end of the hoisted precast beam and slab component to move downward, thereby realizing the horizontal leveling of the front and rear ends during the hoisting of the precast beam and slab.

[0047] When the front end of the precast beam and slab component is lower than the rear end during the process of hoisting the precast beam and slab component, the pump station 23 is controlled by the remote control to shorten the second oil cylinder 22. When the second oil cylinder 22 is shortened, the end of the longitudinal beam 4 away from the cross beam 3 is subjected to an upward pulling force, and the end of the longitudinal beam 4 away from the cross beam 3 moves upward, so that the front end of the cross beam 3 moves upward synchronously. When the front end of the cross beam 3 moves upward, the second horizontal axis 312 can gradually separate from the longitudinal axis 1211; the upward movement of the front end of the cross beam 3 causes the front end of the hoisted precast beam and slab component to move upward, thereby realizing the horizontal leveling of the front and rear ends during the hoisting of the precast beam and slab.

[0048] In the utility model, the front end of the cross beam 3 refers to the side of the cross beam 3 facing the longitudinal beam 4. The first cylinder 21 and the second cylinder 22 use hydraulic means to control the level and height of the sling by adjusting the height of one end of the cross beam and the longitudinal beam to meet different on-site lifting requirements.

[0049] In the process of hoisting the prefabricated beam and slab by the hoisting device of the utility model, the prefabricated beam and slab components are hoisted by the crane on the double-truss structure. The double-truss structure and the crane are prior arts. The crane is connected to the top end of the steel cable, and the bottom end of the steel cable connected to the crane is connected to the hoisting device, specifically, the bottom end of the steel cable is connected to the annular hook on the circular turntable included in the hoisting device. The hoisting device hoists the prefabricated beam and slab components, and the crane moves on the double-truss structure to transport the prefabricated beam and slab components to the installation position; when the prefabricated beam and slab components reach the installation position, the direction of the prefabricated beam and slab components can be adjusted for the convenience of installation, specifically, the motor on the circular turntable is controlled by a remote controller to work, the motor drives the circular gear to rotate, and the rotation of the circular gear drives the column 12 to rotate, and the 360° rotation of the circular gear realizes the 360° rotation of the prefabricated beam and slab components, so as to facilitate the adjustment of the hoisting posture of the prefabricated beam and slab components, so as to facilitate the installation of the prefabricated beam and slab components.

[0050] In the description of the present invention, it should be understood that the terms "up", "down", "left", "right", etc., indicating directions or positional relationships are based on the directions or positional relationships shown in the accompanying drawings, and are only for the convenience of describing the present invention and simplifying the description, rather than indicating or implying that the device or element referred to must have a specific direction, be constructed and operated in a specific direction, and therefore cannot be understood as a limitation on the present invention.

[0051] Finally, it should be noted that the contents not described in detail in this specification belong to the prior art known to professional and technical personnel in this field. The above description is only the preferred embodiment of the utility model and is not used to limit the utility model. Although the utility model is described in detail with reference to the above embodiments, for those skilled in the art, they can still modify the technical solutions recorded in the above embodiments, or replace some of the technical features therein with equivalents. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the utility model shall be included in the protection scope of the utility model.

Claims

1. A lifting device for a beam and slab erection machine for a high-pile wharf, comprising a connection structure (1), the connection structure (1) comprising a steel cable, the top end of the steel cable being connected to a crane, the crane moving along a track of a double truss structure to lift prefabricated beam and slab components, the bottom end of the steel cable being connected to a lifting device, characterized in that: The connecting device also includes a circular gear (11), the bottom end of the steel cable is connected to a hook arranged on the circular gear (11), the motor is arranged on the upper surface of the circular gear (11) through a mounting base, the upper end of the rotating shaft of the circular gear (11) is connected to the transmission shaft of the motor, and the lower end of the rotating shaft of the circular gear (11) is connected to the top of the column (12), the operation of the motor drives the circular gear (11) to rotate, and the rotation of the circular gear (11) drives the column (12) to rotate; the bottom end of the column (12) is connected to the crossbeam ( The middle part of the cross beam (3) is movably connected, a longitudinal beam (4) is arranged on one side of the cross beam (3), and the longitudinal beam (4) and the cross beam (3) form a certain angle; the first oil cylinder (21) is arranged between the column (12) and the cross beam (3), and the second oil cylinder (22) is arranged between the column (12) and the longitudinal beam (4); when the first oil cylinder (21) is extended or shortened, the height of the left and right ends of the cross beam (3) increases or decreases, and when the second oil cylinder (22) is extended or shortened, the height of the front and rear ends of the cross beam (3) increases or decreases.

2. A sling device for a high-pile wharf beam and slab erection machine according to claim 1, characterized in that: The crossbeam (3) is in the shape of a rectangular parallelepiped, and a rectangular groove (31) is arranged in the middle of the upper surface of the crossbeam (3). A plurality of horizontal axes are arranged on the groove (31) at intervals in the horizontal direction, and the horizontal axes include a first horizontal axis (311) and a second horizontal axis (312). The two ends of the first horizontal axis (311) and the second horizontal axis (312) are respectively connected to two opposite side surfaces of the rectangular groove (31), and the arrangement direction of the first horizontal axis (311) and the second horizontal axis (312) is the same as the arrangement direction of the crossbeam (3).

3. A sling device for a high-pile wharf beam and slab erection machine according to claim 1, characterized in that: The bottom end of the column (12) is a rectangular frame structure (121), the bottom of the rectangular frame structure is a longitudinal axis (1211), the first horizontal axis (311) and the second horizontal axis (312) are sleeved on the longitudinal axis (1211), the first horizontal axis (311) and the second horizontal axis (312) are located above the longitudinal axis (1211), and when no external force is applied to the cross beam (3) or the longitudinal beam (4), the first horizontal axis (311) and the second horizontal axis (312) are in contact with the longitudinal axis (1211) and are perpendicular to the longitudinal axis (1211); the length of the longitudinal axis (1211) is less than the length of the square groove (31).

4. The sling device for the beam and slab erection machine of a high-pile wharf according to claim 1, characterized in that: The longitudinal beam (4) is in the shape of a rectangular parallelepiped. The longitudinal beam (4) is located on one side of the cross beam (3). One end of the longitudinal beam (4) is fixed to the side of the cross beam (3).

5. The sling device for the beam and slab erection machine of a high-pile wharf according to claim 1, characterized in that: The sling device also includes a positioning mechanism (2), which includes a first oil cylinder (21), a second oil cylinder (22), a pump station (23) and an arc structure (24); the first oil cylinder (21) and the pump station (23) are located on both sides of the column (12), the first oil cylinder (21) is located on the right side of the column (12), and the pump station (23) is arranged on the upper surface of the left end of the crossbeam (3); the pump station (23) and the first oil cylinder (21) are connected through a hydraulic hose (5), and the pump station (23) and the second oil cylinder (22) are connected through a hydraulic hose (5); the arc structure (24) is located on the right side of the column (12), and the left end of the arc structure (24) is movably connected to the column (12).

6. A lifting device for a beam and slab erection machine for a high-pile wharf according to claim 5, characterized in that: The connection point between the left end of the arc structure (24) and the column (12) is lower than the first lug (25) provided on the column (12), the bottom surface of the right end of the arc structure (24) is provided on the upper surface of the right end of the cross beam (3), and the bottom surface of the left end of the arc structure (24) can gradually move away from the upper surface of the right end of the cross beam (3).

7. The sling device for the beam and slab erection machine of a high-pile wharf according to claim 5, characterized in that: The upper end of the first oil cylinder (21) is hingedly connected to the column (12), a first lug (25) is arranged on the left side of the column (12), a hinge shaft is arranged on the first lug (25), and the upper end of the first oil cylinder (21) is connected to the hinge shaft; The lower end of the first oil cylinder (21) is hingedly connected to the right end of the arc structure (24), and a hinge shaft is provided at the right end of the arc structure (24). The lower end of the first oil cylinder (21) is hingedly connected to the right end of the arc structure (24) via the hinge shaft.

8. The sling device for the beam and slab erection machine of a high-pile wharf according to claim 5, characterized in that: A second lug (26) is arranged on a surface of the column (12) adjacent to the surface where the first lug (25) is located, and the second lug (26) is at the same height as the first lug (25); a hinge shaft is arranged on the second lug (26), and the upper end of the second oil cylinder (22) is hingedly connected to the hinge shaft on the second lug (26); a third lug (27) is arranged on the upper surface of the end of the longitudinal beam (4) away from the cross beam (3), and the third lug (27) is arranged with a hinge shaft, and the lower end of the second oil cylinder (22) is hingedly connected to the hinge shaft on the third lug (27).

9. The sling device for the beam and slab erection machine of a high-pile wharf according to claim 1, characterized in that: A through hole (122) is provided at the top end of the column (12), and a through hole is also provided at the lower end of the rotating shaft of the circular gear (11). The through hole (122) and the through hole at the lower end of the rotating shaft of the circular gear (11) are connected by bolts, so that the rotating shaft of the circular gear can be connected to the top end of the column (12).

10. The sling device for the beam and slab erection machine of a high-pile wharf according to claim 1, characterized in that: A hook (32) is provided at each end of the cross beam (3), and the hook (32) is annular. The hook (32) is provided at both ends of the bottom surface of the cross beam (3), and each hook (32) is connected to the top end of a steel wire rope, and the bottom end of each steel wire rope is connected to a pre-buried annular lifting ring on the top surface of the beam plate.