Plate surface reinforcing structure of platform plate
By setting reinforced steel plates and newly cast building surface layers between the cantilever plates of the platform plates, the problem of the loss of stress performance of the cantilever plates in the platform door renovation is solved, and the reinforcement and structural stability of the platform plates are achieved , reducing the impact on rail transit operations.
Patent Information
- Application Number
- CN202420816964.2
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-04-19
- Publication Date
- 2024-12-06
- Estimated Expiration
- 2034-04-19
AI Technical Summary
The existing platform panels are difficult to effectively reinforce during the platform door renovation process, which may lead to loss of stress performance of the cantilever plates and affect structural safety. The current specifications require structural inspection and reinforcement, resulting in a great impact on station operations.
By setting up reinforced steel plates between the cantilever plates and the building surface layer, and adding new poured building surface layers in the newly established platform door area, using structural glue to fix the reinforced steel plates, and threading holes and fixing holes are set to ensure the stability of the newly established platform door. Connect to reduce load changes to existing platform slabs.
The reinforcement of the platform plate is achieved, ensuring clear and reliable stress, simplifying the construction process, reducing the impact on rail transit operation, allowing for rotational closed construction, reducing the scope and cycle of operational impact.
Smart Images

Figure CN222119975U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of rail transit platform reconstruction, in particular to a platform plate surface reinforcement structure. Background Art
[0002] like Figure 1 As shown, the existing platform slab includes two parts: a structural side beam 1 and a cantilever slab 2. The cantilever slab 2 is a reinforced concrete load-bearing structure, on which is a non-load-bearing building surface layer 3. The load-bearing steel bars 4 of the cantilever slab 2 are upper skin cantilever steel bars. According to the actual situation, the cantilever length of the cantilever slab 2 extending from the structural side beam 1 is not fixed. The platform door may be fixed within the cantilever length range of the cantilever slab 2, or partly on the cantilever slab 2 and partly on the structural side beam 1.
[0003] Both the old and new platform doors are made by post-drilling process, and it is impossible to determine whether the stress-bearing steel bars 4 will be cut under the hole. If the stress-bearing steel bars 4 are cut during post-drilling, the stress-bearing performance of the cantilever plate 2 will be greatly affected, affecting the structural safety.
[0004] According to current regulations, if the update of equipment causes an increase in load or damages the original structure, structural inspection and identification and structural reinforcement must be carried out, which will have a significant impact on station operations. Therefore, how to design a special construction plan based on actual conditions to avoid large-scale structural reinforcement of the station is a technical problem that needs to be solved urgently. Summary of the invention
[0005] The purpose of the utility model is to provide a platform slab reinforcement structure based on the above-mentioned deficiencies of the prior art, which effectively realizes the reinforcement of the existing platform slab during the platform door renovation construction by adding new bonded steel reinforcement to compensate for the loss of stress-bearing steel bars in the cantilever slab caused by the opening of the rear hole.
[0006] The purpose of this utility model is achieved by the following technical solutions:
[0007] A platform slab surface reinforcement structure is used to reinforce an existing platform slab structure when a new platform door is installed, the existing platform slab structure includes a structural side beam, a cantilevered plate and a building surface layer, wherein the cantilevered plate is arranged on the structural side beam and one side plate end of the cantilevered plate is cantilevered out of the structural side beam, and the building surface layer is arranged above the cantilevered plate, characterized in that: the building surface layer is divided into an existing building surface layer and a newly poured building surface layer, the newly poured building surface layer corresponds to the range of the newly installed platform door and is located between the newly installed platform door and the cantilevered plate, a reinforcing steel plate is arranged between the newly poured building surface layer and the cantilevered plate, the reinforcing steel plate is fixed to the cantilevered plate by structural adhesive, and the cantilevered plate is provided with a mounting hole for connecting with the newly installed platform door.
[0008] The size range of the reinforced steel plate covers the newly installed platform door, the cantilever plate and the 1 / 4 inner plate span, and the newly poured building surface layer corresponds to the size range of the reinforced steel plate.
[0009] The mounting holes include a threading hole and a fixing hole. The threading hole is used for threading the newly installed platform door. The newly installed platform door is anchored to the cantilever plate by a rear anchor bolt arranged at the fixing hole.
[0010] The advantages of the utility model are: clear force, firm reinforcement, simple process, no need to measure and process components in advance, and no impact on the conditions under the platform slab; the construction can be carried out in a manner of closing the platform doors in turn to reduce the impact on the normal operation of rail transit. BRIEF DESCRIPTION OF THE DRAWINGS
[0011] Figure 1 It is a structural schematic diagram of an existing platform plate in the prior art;
[0012] Figure 2 It is a plan view of the utility model;
[0013] Figure 3 It is an elevation view of the utility model. DETAILED DESCRIPTION
[0014] The following is a further detailed description of the features of the present invention and other related features through embodiments in conjunction with the accompanying drawings to facilitate understanding by technicians in the same industry:
[0015] like Figure 1-3 As shown, the marks 1-11 in the figure respectively represent: structural side beam 1, cantilever plate 2, building surface layer 3, stress-bearing steel bar 4, old door fixing hole 5, new door threading hole 6, new door fixing hole 7, reinforcing steel plate 8, rear anchor bolt 9, existing building surface layer 10, and newly poured building surface layer 11.
[0016] Example: Figures 1 to 3 As shown, the platform slab reinforcement structure in this embodiment is used to reinforce the cantilever slab 2, especially the reinforcement of the stress-bearing steel bars 4 of the cantilever slab 2 after the performance loss due to the post-opening process of the new platform door. The cantilever slab 2 is provided with old door fixing holes 5 for connecting with the existing old platform door.
[0017] Combination Figure 2 and Figure 3 As shown, the slab reinforcement structure in this embodiment reinforces the cantilever slab 2 by adding a reinforcing steel plate 8 between the cantilever slab 2 and the building surface layer 3, so as to meet the requirements of the platform slab stress and structural reinforcement; for the platform slab and the structural side beam 1, there is no load change within this range (the platform door area is set and no pedestrians walk).
[0018] Specifically, part of the building surface layer 3 is chiseled out within the span of the newly-installed platform door, cantilever plate 2 and 1 / 4 inner plate to expose the structural concrete surface of the cantilever plate 2, and the entire reinforcing steel plate 8 is tightly connected to the cantilever plate 2 using structural adhesive, and then a new building surface layer 11 is poured on top of the reinforcing steel plate 8. The surface height of the new building surface layer 11 is consistent with the surface height of the existing building surface layer 10 that has not been chiseled out.
[0019] In this embodiment, if Figure 2 As shown, a new door threading hole 6 and a new door fixing hole 7 are provided on the cantilever plate 2, wherein the new door threading hole 6 is used for threading the new platform door, and the new door fixing hole 7 is used as a new door fixing force-bearing hole for installing a rear anchor bolt 9, and the rear anchor bolt 9 can anchor the new platform door to the cantilever plate 2 to ensure the structural stability of the new platform door.
[0020] During the specific implementation of this embodiment: the platform surface needs to remove the building surface layer 3 and restore it, and there is wet processing. Therefore, it is preferred to organize the construction to close the platform doors in turn. Although it will inevitably have a certain impact on the normal operation of rail transit, the impact range and impact period are small, and the normal operation of rail transit can still be maintained.
[0021] Although the above embodiments have described the concepts and embodiments of the purpose of the utility model in detail with reference to the accompanying drawings, ordinary technicians in this field can recognize that various improvements and modifications can still be made to the utility model without departing from the scope of the claims, so they are not described one by one here.
Claims
1. A platform slab reinforcement structure, used for reinforcing an existing platform slab structure when a new platform door is installed, wherein the existing platform slab structure comprises a structural side beam, a cantilevered slab and a building surface layer, wherein the cantilevered slab is arranged on the structural side beam and one side end of the cantilevered slab cantilevers out from the structural side beam, and the building surface layer is arranged above the cantilevered slab. Features: The building surface layer is divided into an existing building surface layer and a newly poured building surface layer. The newly poured building surface layer corresponds to the range of the newly installed platform door and is located between the newly installed platform door and the cantilever plate. A reinforcing steel plate is arranged between the newly poured building surface layer and the cantilever plate. The reinforcing steel plate is fixed to the cantilever plate by structural adhesive. The cantilever plate is provided with an installation hole for connecting with the newly installed platform door.
2. A platform slab reinforcement structure according to claim 1, Features: The size range of the reinforced steel plate covers the newly installed platform door, the cantilever plate and the 1 / 4 inner plate span, and the newly poured building surface layer corresponds to the size range of the reinforced steel plate.
3. A platform slab reinforcement structure according to claim 1, Features: The mounting holes include a threading hole and a fixing hole. The threading hole is used for threading the newly installed platform door. The newly installed platform door is anchored to the cantilever plate by a rear anchor bolt arranged at the fixing hole.