Water pipe supporting frame mounting mechanism for fire engineering
The water pipe support frame installation mechanism addresses inefficiencies and structural risks by enabling simultaneous multi-pipe installation and enhanced support through a rotating wheel and auxiliary device, improving efficiency and stability.
Patent Information
- Application Number
- CN202420764570.7
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-04-15
- Publication Date
- 2024-12-10
- Estimated Expiration
- 2034-04-15
AI Technical Summary
Existing water pipe support frame installation mechanisms in fire protection engineering require multiple steps and knobs to install water pipes, leading to reduced installation efficiency and increased risk of damage due to limited contact area and weight of the water pipes, resulting in potential frame failure.
A water pipe support frame installation mechanism with a rotating wheel, double-headed screw, threaded blocks, and sliding grooves that allow simultaneous installation of multiple water pipes, along with an auxiliary device to increase contact area and stability.
Enhances installation efficiency by reducing steps and time, while improving the structural integrity and use effect of the support frame through increased contact area and support.
Smart Images

Figure CN222142246U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of fire protection engineering, in particular to an installation mechanism for a water pipe support frame for fire protection engineering. Background Art
[0002] Fire protection engineering mainly studies the basic knowledge and skills of fire protection laws and regulations, fire prevention and fire fighting engineering technology, fire investigation, fire fighting and rescue, etc. Fire management, fire fighting and rescue, fire investigation, etc. are carried out in the fire department. In fire protection engineering, the water pipe needs to be installed into the support frame through the installation mechanism.
[0003] For example, a fire-fighting engineering water pipe support frame installation mechanism with the authorization announcement number CN220337647U includes a mounting plate fixed on the top of the wall, and two left-right symmetrical and vertical fixing rods are fixedly connected to the bottom of the mounting plate. Although the above document can realize that the height position of the support plate can be changed when the two adjustment rods move up and down under the action of the lifting mechanism, so as to adjust the height position according to the water pipe installation requirements, so as to be compatible with water pipes of different installation heights; however, when using, when the installation mechanism installs the water pipes for fire-fighting engineering into the support frame, the staff needs to turn multiple knobs in sequence to move the clamping blocks and install multiple water pipes into the support frame in sequence, resulting in more installation steps and a longer installation time, thereby reducing the installation efficiency of the installation mechanism for the water pipes; at the same time, when the installation mechanism installs the water pipes into the support frame, due to the small contact area between the support frame and the mounting plate, and the weight of the water pipes for fire-fighting engineering is also heavy, after long-term use, the support frame may fall down, causing damage to the water pipes, thereby reducing the use effect of the support frame. Summary of the invention
[0004] The utility model aims to solve the problems existing in the above-mentioned prior art and provides a water pipe support frame installation mechanism for fire protection engineering, which specifically improves the installation efficiency of the installation mechanism for water pipes and improves the use effect of the support frame.
[0005] The utility model adopts a technical solution to solve its technical problems: this water pipe support frame installation mechanism for fire protection engineering includes an outer wall of the support frame fixedly connected to the outer wall of the installation plate, a mounting hole is opened inside the installation plate, the interior of the support frame is fixedly connected to the outer wall of the hollow column, the interior of the hollow column is fixedly connected to the two ends of the slide rod, the outer wall of the support frame is fixedly connected to the outer wall of the second clamping plate, the interior of the support frame is processed with a slide groove, the interior of the hollow column is provided with an installation mechanism, and the outside of the support frame is provided with an auxiliary device.
[0006] For further improvement, the installation mechanism includes a rotating wheel, a double-headed screw and a threaded block. The rotating wheel is fixedly connected to the end of the double-headed screw, the double-headed screw is threadedly connected to the threaded block, and both of the threaded blocks are rotatably connected to the inclined column through a first pin shaft, and the inclined column is rotatably connected to the vertical block through a second pin shaft.
[0007] For further improvement, the two vertical blocks are both fixedly connected to the outer wall of the first clamping plate, and the two threaded blocks are both slidably connected to the sliding rod.
[0008] For further improvement, the hollow column is rotationally connected to the double-headed screw via a bearing, a sliding block is fixedly connected to the outer wall of the first clamping plate, and the sliding block is slidably connected to the sliding groove.
[0009] To be further improved, the auxiliary device includes a transverse plate and an inclined plate, the transverse plate is threadedly connected to the mounting plate by a first bolt, the outer wall of the transverse plate is fixedly connected to the inclined plate, and the end of the inclined plate is fixedly connected to the outer wall of the vertical plate.
[0010] For further improvement, the vertical plate is threadably connected to the support frame via a second bolt, and the horizontal plate is fitted to the outer wall of the mounting plate.
[0011] For further improvement, the outer wall of the support frame fits with the outer wall of the vertical plate.
[0012] The beneficial effects of the utility model are as follows: the utility model drives the double-headed screw to rotate through the rotating wheel in the installation mechanism, the double-headed screw drives the threaded block to move, the two threaded blocks slide in the sliding rod, the two threaded blocks drive the inclined column to rotate, the inclined columns on both sides drive the vertical blocks to move, the two vertical blocks drive the first clamping plates to move, the two first clamping plates drive the sliders to slide in the sliding grooves on both sides of the support frame, and the water pipes are installed in the support frame. When the installation mechanism is set to install the water pipes used for fire protection engineering in the support frame, multiple water pipes can be installed simultaneously through the installation device, the installation steps are reduced, the installation time is shortened, and the installation efficiency of the installation mechanism for the water pipes is improved.
[0013] The horizontal plate is fixed to the mounting plate by the first bolt in the auxiliary device, and the staff then turns the second bolt to fix the vertical plate to the support frame. The inclined plate connects the horizontal plate and the vertical plate together to support the support frame and the mounting plate. When the installation mechanism is set to install the water pipe into the support frame, the auxiliary device is used to increase the contact area between the support frame and the mounting plate, thereby improving the use effect of the support frame. BRIEF DESCRIPTION OF THE DRAWINGS
[0014] Figure 1 It is a schematic diagram of the structure of the utility model;
[0015] Figure 2 for Figure 1 A schematic diagram of the front view structure of
[0016] Figure 3 for Figure 2 A side view structural schematic diagram of;
[0017] Figure 4 for Figure 2 A schematic diagram of a top view structure;
[0018] Figure 5 for Figure 2 A schematic diagram of the structure of the installation mechanism;
[0019] Figure 6 for Figure 2 Schematic diagram of the structure of the auxiliary device.
[0020] Explanation of the reference numerals in the accompanying drawings: 1. support frame, 2. mounting plate, 3. mounting hole, 4. hollow column, 5. mounting mechanism, 501. rotating wheel, 502. double-headed screw, 503. threaded block, 504. inclined column, 505. vertical block, 5a1. rubber pad, 5a2. connecting plate, 6. first splint, 7. slider, 8. auxiliary device, 801. horizontal plate, 802. inclined plate, 803. vertical plate, 9. second splint, 10. sliding rod. DETAILED DESCRIPTION
[0021] The utility model is further described below in conjunction with the accompanying drawings: Embodiment 1:
[0022] See attached Figure 1-6 : In this embodiment, a fire-fighting engineering water pipe support frame installation mechanism includes an outer wall of a support frame 1 fixedly connected to the outer wall of a mounting plate 2, a mounting hole 3 is opened inside the mounting plate 2, the inside of the support frame 1 is fixedly connected to the outer wall of a hollow column 4, the inside of the hollow column 4 is fixedly connected to the two ends of a slide bar 10, the outer wall of the support frame 1 is fixedly connected to the outer wall of a second clamping plate 9, the water pipes used for fire-fighting engineering are placed on the two second clamping plates 9 in sequence, the staff rotates the installation mechanism 5, and simultaneously installs multiple water pipes into the support frame 1, the inside of the support frame 1 is processed with a slide groove, the inside of the hollow column 4 is provided with an installation mechanism 5, and the outside of the support frame 1 is provided with an auxiliary device 8;
[0023] See attached Figure 1-6: In this embodiment, the mounting mechanism 5 includes a rotating wheel 501, a double-headed screw 502 and a threaded block 503. The rotating wheel 501 is fixedly connected to the end of the double-headed screw 502, the rotating wheel 501 drives the double-headed screw 502 to rotate, the double-headed screw 502 is threadedly connected to the threaded block 503, the head screw 502 drives the threaded block 503 to move, the two threaded blocks 503 are rotatably connected to the inclined column 504 through the first pin shaft, the two threaded blocks 503 drive the inclined column 504 to rotate, the inclined column 504 is rotatably connected to the vertical block 505 through the second pin shaft, the inclined columns 504 on both sides drive the vertical block 505 to move, the two vertical blocks 505 are fixed to the outer wall of the first clamping plate 6, the two vertical blocks 505 drive the first clamping plate 6 to move, the two threaded blocks 503 are slidably connected to the sliding rod 10, and the two threaded blocks 503 slide in the sliding rod 10;
[0024] The rotating wheel 501 in the installation mechanism 5 drives the double-headed screw 502 to rotate, and the double-headed screw 502 drives the threaded block 503 to move. The two threaded blocks 503 slide in the slide rod 10, and the two threaded blocks 503 drive the inclined column 504 to rotate. The inclined columns 504 on both sides drive the vertical block 505 to move. The two vertical blocks 505 drive the first clamping plate 6 to move. The two first clamping plates 6 drive the slider 7 to slide in the slide grooves on both sides of the support frame 1 to install the water pipe into the support frame 1. When the installation mechanism is set to install the water pipe used for fire protection engineering into the support frame, multiple water pipes are installed simultaneously through the installation device 5, the installation steps are reduced, the installation time is shortened, and the installation efficiency of the installation mechanism for the water pipe is improved.
[0025] See attached Figure 1-6 : In this embodiment, the hollow column 4 is rotatably connected to the double-headed screw 502 through a bearing, and a slider 7 is fixedly connected to the outer wall of the first clamping plate 6. The two first clamping plates 6 drive the slider 7 to slide in the slide grooves on both sides of the support frame 1, and the slider 7 is slidably connected to the slide groove. The auxiliary device 8 includes a horizontal plate 801 and an inclined plate 802. The horizontal plate 801 is threadedly connected to the mounting plate 2 through a first bolt. The staff rotates the first bolt, and the first bolt fixes the horizontal plate 801 to the mounting plate 2. The outer wall of the horizontal plate 801 is fixedly connected to the inclined plate 802. The end of the inclined plate 802 is fixedly connected to the outer wall of the vertical plate 803. The vertical plate 803 is threadedly connected to the support frame 1 through a second bolt. The staff rotates the second bolt again to fix the vertical plate 803 to the support frame 1. The horizontal plate 801 fits with the outer wall of the mounting plate 2, and the outer wall of the support frame 1 fits with the outer wall of the vertical plate 803.
[0026] The horizontal plate 801 is fixed to the mounting plate 2 by the first bolt in the auxiliary device 8, and the staff then turns the second bolt to fix the vertical plate 803 to the support frame 1. The inclined plate 802 connects the horizontal plate 801 and the vertical plate 803 together to support the support frame 1 and the mounting plate 2. When the installation mechanism is set to install the water pipe into the support frame, the auxiliary device 8 is used to increase the contact area between the support frame 1 and the mounting plate 2, thereby improving the use effect of the support frame.
[0027] Working principle:
[0028] When the fire protection engineering work is being carried out, when the installation mechanism 5 installs the water pipes for the fire protection engineering into the support frame 1, the staff first installs the auxiliary device 8 onto the support frame 1 and the installation plate 2. After completion, the support frame 1 is installed on the wall through the installation plate 2 and the installation hole 3. Then the staff puts the water pipes for the fire protection engineering on the two second clamping plates 9 in sequence. The staff rotates the installation mechanism 5 and installs multiple water pipes into the support frame 1 at the same time. The specific installation process and auxiliary process are as follows:
[0029] Installation process:
[0030] The staff rotates the rotating wheel 501, and the rotating wheel 501 drives the double-headed screw 502 to rotate, and the double-headed screw 502 drives the threaded block 503 to move, and the two threaded blocks 503 slide in the slide rod 10, and the two threaded blocks 503 drive the inclined column 504 to rotate, and the inclined columns 504 on both sides drive the vertical block 505 to move, and the two vertical blocks 505 drive the first clamping plate 6 to move, and the two first clamping plates 6 drive the slider 7 to slide in the slide grooves on both sides of the support frame 1 to install the water pipe into the support frame 1. After completion, the staff stops rotating the rotating wheel 501;
[0031] Auxiliary process:
[0032] The staff rotates the first bolt to fix the horizontal plate 801 to the mounting plate 2, and then rotates the second bolt to fix the vertical plate 803 to the support frame 1. The inclined plate 802 connects the horizontal plate 801 and the vertical plate 803 together to support the support frame 1 and the mounting plate 2. Embodiment 2:
[0033] See attached Figure 1-6 : In this embodiment, the installation mechanism 5 also includes a rubber pad 5a1 and a connecting plate 5a2. The rubber pad 5a1 is fixedly connected to the outer wall of the first clamp plate 6 and the outer wall of the second clamp plate 9 respectively, and both ends of the connecting plate 5a2 are fixedly connected to the outer wall of the first clamp plate 6; when installing the water pipe used in fire protection engineering, the first clamp plate 6 drives the upper end rubber pad 5a1 to move, and installs the water pipe into the inside of the support frame 1. The rubber pad 5a1 protects the water pipe, and the connecting plate 5a2 connects the two first clamp plates 6, so that the two first clamp plates 6 move at the same time.
[0034] Working principle:
[0035] When installing the water pipe used in fire protection engineering, the first clamping plate 6 drives the upper rubber pad 5a1 to move, and the water pipe is installed inside the support frame 1. The rubber pad 5a1 protects the water pipe, and the connecting plate 5a2 connects the two first clamping plates 6 so that the two first clamping plates 6 move simultaneously.
[0036] Although the present invention has been shown and described with reference to the preferred embodiments, it will be understood by those skilled in the art that various changes in form and details may be made therein within the scope of the claims.
Claims
1. A water pipe support frame installation mechanism for fire engineering, comprising an outer wall of a support frame (1) and an outer wall of a mounting plate (2) fixedly connected, wherein: The mounting plate (2) is provided with a mounting hole (3), the interior of the support frame (1) is fixedly connected to the outer wall of the hollow column (4), the interior of the hollow column (4) is fixedly connected to the two ends of the slide rod (10), the outer wall of the support frame (1) is fixedly connected to the outer wall of the second clamping plate (9), the interior of the support frame (1) is processed with a slide groove, the interior of the hollow column (4) is provided with a mounting mechanism (5), and the exterior of the support frame (1) is provided with an auxiliary device (8).
2. The fire protection engineering water pipe support frame installation mechanism according to claim 1 is characterized by: The mounting mechanism (5) comprises a rotating wheel (501), a double-headed screw (502) and a threaded block (503); the rotating wheel (501) is fixedly connected to the end of the double-headed screw (502); the double-headed screw (502) is threadedly connected to the threaded block (503); both threaded blocks (503) are rotatably connected to an inclined column (504) via a first pin shaft; and the inclined column (504) is rotatably connected to a vertical block (505) via a second pin shaft.
3. The fire protection engineering water pipe support frame installation mechanism according to claim 2 is characterized by: The two upright blocks (505) are both fixedly connected to the outer wall of the first clamping plate (6), and the two threaded blocks (503) are both slidably connected to the sliding rod (10).
4. The fire protection engineering water pipe support frame installation mechanism according to claim 3 is characterized by: The hollow column (4) is rotatably connected to the double-headed screw (502) via a bearing, a sliding block (7) is fixedly connected to the outer wall of the first clamping plate (6), and the sliding block (7) is slidably connected to the sliding groove.
5. The fire protection engineering water pipe support frame installation mechanism according to claim 1 is characterized by: The auxiliary device (8) comprises a transverse plate (801) and an inclined plate (802); the transverse plate (801) is threadedly connected to the mounting plate (2) via a first bolt; the outer wall of the transverse plate (801) is fixedly connected to the inclined plate (802); and the end of the inclined plate (802) is fixedly connected to the outer wall of the vertical plate (803).
6. The fire protection engineering water pipe support frame installation mechanism according to claim 5 is characterized by: The vertical plate (803) is threadably connected to the support frame (1) via a second bolt, and the horizontal plate (801) is in contact with the outer wall of the mounting plate (2).
7. The fire protection engineering water pipe support frame installation mechanism according to claim 1 is characterized by: The outer wall of the support frame (1) fits the outer wall of the vertical plate (803).