By using a combination design of structural steel beams and several-shaped steel hooks in the steel bar truss bearing plate, suspension support is realized, and construction problems in super-self-support span construction is solved, construction efficiency and safety are improved, and materials are simplified. use.

CN222227941UActive Publication Date: 2024-12-24CHINA CONSTR 4TH ENG BUREAU 6TH +2
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420721929.2
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-04-09
Publication Date
2024-12-24
Estimated Expiration
2034-04-09

AI Technical Summary

Technical Problem

In the construction of steel bar truss bearing plates, the conventional temporary support method consumes time, is heavy in materials and is dangerous to disassemble when the span is over self-supported, making it difficult to meet construction needs.

Method used

Design a hanging installation device for steel bar truss floor bearing plates, using structural steel beams and a few-shaped steel hooks, and change them to upper suspension support, cancel the temporary support system below, and optimize the bearing by combining a few-shaped steel hooks and I-shaped steel. Reduce material use and speed up construction progress.

Benefits of technology

The rapid installation and safe disassembly of steel bar truss bearing plates is realized, the force transmission path is simplified, material investment is reduced, and construction efficiency and safety is improved.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222227941U_ABST
    Figure CN222227941U_ABST
Patent Text Reader

Abstract

The utility model discloses a steel bar truss floor support plate suspension installation device which comprises a corner connector, a steel bar truss floor support plate and I-shaped steel, studs penetrate through holes in the bottom of the corner connector to be welded to a structural steel beam, the side face of the corner connector is fixed to an upper flange and a lower flange of the I-shaped steel through bolts, and the I-shaped steel is supported. And a stable temporary suspension mounting system is formed. The installation stress mode of the steel bar truss floor support plate is optimized, a traditional lower portion supporting mode is changed into an upper portion suspension mode, and rapid installation of the large-span steel bar truss floor support plate is achieved. And after floor concrete pouring is completed and the design strength is achieved, the corner connectors and the n-shaped steel bar hooks higher than the floor are cut off, the temporary suspension mounting device can be detached, operation is easy, and safety and high efficiency are achieved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model belongs to the technical field of steel structure building construction, and in particular relates to a steel bar truss floor deck suspension installation device. Background Art

[0002] According to the design and specification requirements, when the floor span is large and exceeds the self-supporting span of the reinforced truss floor deck, temporary support must be added to ensure that the span is within the specified self-supporting range.

[0003] The conventional support method is to set up scaffolding or a temporary steel secondary beam under the steel truss floor deck. This method takes a long time to install and dismantle. The steel secondary beam is heavy and is difficult to dismantle and has a high risk factor when fixed under the steel truss floor deck. Utility Model Content

[0004] The utility model provides a steel truss floor deck suspension installation device to solve the temporary support construction problem of the steel truss floor deck with a super self-supporting span, so as to overcome the shortcomings of the prior art.

[0005] The purpose of the utility model can be achieved through the following technical solutions:

[0006] A steel bar truss floor deck suspension installation device, comprising:

[0007] The steel truss floor deck includes a bottom formwork steel plate and web reinforcements, wherein the upper end of the web reinforcement is welded with an upper chord reinforcement, and the lower end of the web reinforcement is welded with a lower chord reinforcement; and further includes:

[0008] A structural steel beam, wherein an angle bracket is arranged on the structural steel beam, the angle brackets are arranged symmetrically, an I-beam is arranged on the symmetrically arranged angle brackets, and a bottom formwork steel plate is arranged between the angle brackets and the structural steel beam;

[0009] The "J"-shaped steel bar hooks are evenly distributed along the length direction of the I-beam and placed on the upper end surface of the I-beam, and the upper chord steel bars are arranged on the hooking ends of the "J"-shaped steel bar hooks.

[0010] As a further solution of the utility model: a bolt is connected between the angle bracket and the structural steel beam, and the bolt passes through the bottom opening of the angle bracket and is welded and fixed to the bottom mold steel plate and the structural steel beam.

[0011] As a further solution of the utility model: bolts are connected between the angle bracket and the I-beam.

[0012] As a further solution of the utility model: the angle bracket is connected to the flange of the I-beam by bolts.

[0013] Due to the adoption of the above technical solution, the utility model has the following advantages:

[0014] 1. By evenly distributing the "J"-shaped steel hooks along the length of the I-beam and placing them on the upper end surface of the I-beam, the upper chord steel bars are set on the hook ends of the "J"-shaped steel hooks, thereby optimizing the force-bearing mode of the steel truss floor deck installation. The structural steel beam is used as a support and a temporary gantry hanger is added above it. The lower support is changed to an upper suspension, and the force transmission path is simple and reasonable.

[0015] 2. Cancel the temporary support system under the large-span steel truss floor slab to reduce material input and speed up construction progress. BRIEF DESCRIPTION OF THE DRAWINGS

[0016] The utility model is further described below in conjunction with the accompanying drawings.

[0017] Figure 1 It is a plan view of the utility model.

[0018] Figure 2 A cross-sectional schematic diagram of the utility model

[0019] Figure 3 This is an enlarged view of the node where the angle bracket supports the I-beam.

[0020] Figure 4 Schematic diagram of the hanging installation device.

[0021] Figure 5 This is an enlarged view of the node of the I-shaped steel bar hook.

[0022] Figure 6 Schematic diagram of the removal of the temporary suspension installation device after the floor slab concrete pouring is completed.

[0023] In the figure: 1. Angle code; 2. Studs; 3. Bolts; 4. Steel truss floor deck; 5. I-beam; 6. I-shaped steel hook; 7. Structural steel beam; 8. Floor slab; 41. Bottom formwork steel plate; 42. Web bar steel bar; 43. Upper chord steel bar; 44. Lower chord steel bar. DETAILED DESCRIPTION

[0024] The following will be combined with the drawings in the embodiments of the utility model to clearly and completely describe the technical solutions in the embodiments of the utility model. Obviously, the described embodiments are only part of the embodiments of the utility model, not all of the embodiments. Based on the embodiments of the utility model, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the utility model.

[0025] like Figure 1-5 As shown, a steel bar truss floor deck suspension installation device comprises:

[0026] A structural steel beam 7, on which an angle code 1 is arranged, the angle code 1 is symmetrically arranged, and an I-beam 5 is arranged on the symmetrically arranged angle code 1;

[0027] The "I"-shaped steel bar hooks 6 are evenly distributed along the length direction of the I-beam 5 and are placed on the upper end surface of the I-beam 5;

[0028] The steel truss floor deck 4 includes a bottom formwork steel plate 41 and web reinforcement bars 42. The bottom formwork steel plate 41 is arranged between the angle code 1 and the structural steel beam 7. The upper end of the web reinforcement bars 42 is welded with an upper chord reinforcement bar 43, and the lower end of the web reinforcement bars 42 is welded with a lower chord reinforcement bar 44. The upper chord reinforcement bar 43 is arranged on the hooking end of the "X"-shaped reinforcement hook 6.

[0029] A bolt 2 is connected between the angle bracket 1 and the structural steel beam 7. The bolt 2 passes through the bottom opening of the angle bracket 1 and the bottom mold steel plate 41 is welded and fixed to the structural steel beam 7. A bolt 3 is connected between the angle bracket 1 and the I-beam 5. The flanges of the angle bracket 1 and the I-beam 5 are connected by the bolt 3.

[0030] like Figure 6 As shown, after the concrete pouring of the floor slab 8 is completed and reaches the designed strength, the bolts 3 are removed, the I-beams 5 are removed, and the angle brackets 1 and the I-shaped steel bar hooks 6 that are higher than the floor slab are cut off.

[0031] The utility model optimizes the force-bearing mode of installation of steel truss floor decking, utilizes structural steel beams as supports and adds temporary portal hangers above them, changes the lower support to upper suspension, and makes the force transmission path simple and reasonable; at the same time, the temporary support system below the large-span steel truss floor decking is eliminated, thus reducing material input and accelerating construction progress.

[0032] A steel bar truss floor deck suspension installation device, the construction method of the steel bar truss floor deck suspension temporary suspension installation device has the following steps:

[0033] Step 1: When the span of the steel truss floor deck is larger than the maximum unsupported span during the construction phase, the length of the angle code 1, the length of the I-beam 5, and the number and length of the "X"-shaped steel hooks 6 in the hanging installation device are designed according to the span of the steel truss floor deck 4 and the thickness of the floor slab 8;

[0034] Step 2: After the steel truss floor deck 4 is laid, the bolts 2 pass through the bottom opening of the angle bracket 1 and are welded to the structural steel beams 7 at both ends of the plate span parallel to the steel truss floor deck 4;

[0035] Step 3: The angle bracket 1 is fixed to the flange of the I-beam 5 by bolts 3;

[0036] Step 4: The I-shaped steel hook 6 is placed on the I-beam 5, and the bottom is hooked on the upper chord steel bar 43 of the steel truss floor deck.

[0037] Step 5: After the concrete pouring of the floor slab 8 is completed and the dismantling conditions are met, the bolts 3 are removed and the I-beam 5 is removed. The bolts 3 and the I-beam 5 can be reused.

[0038] Step 6: Cut off the angle code 1 and the "J"-shaped steel bar hook 6 that are higher than the floor 8.

[0039] In the description of the present invention, it should be understood that the terms "up", "down", "left", "right", "front", "back", etc. indicating directions or positional relationships are based on the directions or positional relationships shown in the accompanying drawings, and are only for the convenience of describing the present invention and simplifying the description, rather than indicating or implying that the device or element referred to must have a specific direction, and a specific direction structure and operation. Therefore, it should not be understood as a limitation on the present invention.

[0040] In addition, unless otherwise clearly specified and limited, the terms "installed", "connected", "connected", etc. should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection or an indirect connection through an intermediate medium, or it can be the internal communication of two components. For ordinary technicians in this field, the specific meanings of the above terms in this utility model can be understood according to specific circumstances.

[0041] The above detailed description of the preferred embodiments of the utility model should not be considered to limit the scope of implementation of the utility model. All equivalent changes and improvements made within the scope of application of the utility model should still fall within the scope of the patent coverage of the utility model.

Claims

1. A steel bar truss floor deck suspension installation device, comprising: The steel bar truss floor deck (4) comprises a bottom formwork steel plate (41) and a web steel bar (42), wherein an upper chord steel bar (43) is welded to the upper end of the web steel bar (42), and a lower chord steel bar (44) is welded to the lower end of the web steel bar (42); the steel bar further comprises: A structural steel beam (7), wherein an angle bracket (1) is arranged on the structural steel beam (7), the angle brackets (1) are symmetrically arranged, an I-beam (5) is arranged on the symmetrically arranged angle brackets (1), and a bottom mold steel plate (41) is arranged between the angle brackets (1) and the structural steel beam (7); The ""-shaped" steel bar hooks (6) are evenly distributed along the length direction of the I-beam (5) and are placed on the upper end surface of the I-beam (5); the upper chord steel bar (43) is arranged on the hook connection end of the ""-shaped" steel bar hooks (6).

2. A steel bar truss floor deck suspension installation device according to claim 1, characterized in that: A bolt (2) is connected between the angle bracket (1) and the structural steel beam (7), and the bolt (2) penetrates through the bottom opening of the angle bracket (1) and the bottom mold steel plate (41) and the structural steel beam (7) and is welded and fixed.

3. The steel bar truss floor deck suspension installation device according to claim 1, characterized in that: A bolt (3) is connected between the angle bracket (1) and the I-beam (5).

4. A steel bar truss floor deck suspension installation device according to claim 3, characterized in that: The angle bracket (1) is connected to the flange of the I-beam (5) by means of bolts (3).