Flying dust treatment device for constructional engineering
By designing the adjustment mechanism and blower assembly in the dust treatment device, the problem of spraying droplets overflowing in windy days is solved, and the dust reduction effect in the construction area is improved.
Patent Information
- Application Number
- CN202421029680.5
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-05-13
- Publication Date
- 2025-01-03
- Estimated Expiration
- Not applicable · inactive patent
AI Technical Summary
In the windy days of existing dust treatment devices, the sprayed liquid droplets are easily carried out of the construction area by the airflow, affecting the dust reduction effect.
A dust treatment device for construction engineering is designed, including fences, connecting plates, columns, movable arms and blowing components. The spray height is adjusted through the adjustment mechanism and the blowing components are used to blow droplets to ensure that they are in the construction area. Hover to prevent overflow.
It improves the hovering time and dust reduction effect of water mist in the construction area, ensures that the droplets do not overflow from the upper direction of the fence, and enhances the dust reduction effect.
Smart Images

Figure CN222286798U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of building construction, in particular to a dust treatment device for building engineering. Background Art
[0002] Construction site dust refers to the dust raised at the construction site due to large-scale operations such as demolition of old buildings, foundation excavation, bulldozing, backfilling, building materials processing, personnel and vehicle activities during the construction process; construction site dust is mainly composed of inhalable particles such as PM2.5, PM10 and large solid particles with a diameter greater than 10 microns; therefore, if the dust generated at the construction site cannot be well handled, it will not only deteriorate the construction environment, but may also have a certain impact on the health of the construction workers.
[0003] Using a dust suppression spray system to treat construction sites is a relatively economical and applicable treatment method. Common dust suppression spray pipelines mainly consist of several atomizing nozzles and several diversion pipes. The diversion pipes are connected to groundwater or water reservoirs, and the atomizing nozzles are evenly arranged on the top of the construction site fence. When dust is generated, water flows out of the atomizing nozzles, and the atomized droplets formed can effectively reduce dust pollution in the construction site. In order to increase the spraying range, the nozzles are mostly installed on the top of the fence. Therefore, during use, if there is a strong wind, the droplets sprayed from the nozzles can easily be carried by the airflow and spread outside the construction area, affecting the dust suppression effect. Summary of the invention
[0004] In view of the above problems, the utility model proposes a dust treatment device for construction projects, which is used to solve the shortcomings of existing dust treatment devices. During use, for example, when encountering strong winds, the droplets sprayed from the nozzle are easily carried by the airflow and spread outside the construction area, affecting the dust reduction effect.
[0005] To achieve the purpose of the utility model, the utility model is implemented through the following technical solutions: a dust treatment device for construction engineering, including a plurality of enclosures surrounding a construction area, a connecting plate is provided between two adjacent enclosures, and an atomizing spray mechanism is provided on the connecting plate;
[0006] The atomizing spray mechanism includes a column, which is detachably connected to a connecting plate, and an upper area of the column away from the connecting plate is provided with a movable arm, the lower end of the movable arm is hinged to the column through a hinge seat, and an adjustment mechanism for adjusting the angle between the column and the movable arm is provided on the column;
[0007] The movable arm is provided with an atomizing nozzle and a guide pipe, the atomizing nozzle is fixedly connected to the upper end of the movable arm, the guide pipe is communicated with the atomizing nozzle, the upper end of the movable arm is provided with an air blowing assembly, and the air blowing assembly is placed between the atomizing nozzle and the column.
[0008] Further improvement lies in that: the adjustment mechanism includes a positioning plate, and two second positioning bolts are installed on the positioning plate, one of the second positioning bolts passes through a fourth positioning hole opened on the positioning plate and is threadedly connected to a second positioning hole opened on the outside of the movable arm, and the other second positioning bolt passes through the fourth positioning hole and is threadedly connected to a third positioning hole opened on the outside of the column, there are multiple fourth positioning holes on the outside of the positioning plate, multiple third positioning holes on the outside of the column, and multiple second positioning holes on the outside of the movable arm, and the second positioning holes are evenly arranged along the length direction of the movable arm.
[0009] A further improvement is that the air blowing assembly includes a cover plate arranged at the upper end of the movable arm, the cover plate is detachably connected to a side of the movable arm close to the column, a blower fan is arranged on the cover plate, and the cover plate is arranged on one side of the atomizing nozzle.
[0010] A further improvement is that: a plurality of first positioning bolts are mounted on the column, and the first positioning bolts pass through the column and are threadedly connected to first positioning holes formed on the outside of the connection plate.
[0011] A further improvement is that: a plurality of third positioning bolts are mounted on the cover plate, and the third positioning bolts pass through the cover plate and are threadedly connected to fifth positioning holes provided on the outer side of the movable arm.
[0012] A further improvement is that a groove seat is provided on one side of the cover plate close to the movable arm, and the groove seat is clamped on the outer side of the movable arm.
[0013] A further improvement is that the adjustment mechanism includes an electric push rod, which is placed between the movable arm and the column, the mounting end of the electric push rod is rotatably connected to the column, and the output end of the electric push rod is rotatably connected to the movable arm.
[0014] The beneficial effects of the utility model are:
[0015] The spraying height of the atomizing nozzle can be adjusted automatically according to the height of the fence, thereby reducing the impact of strong outdoor winds on the water mist and increasing the hovering time of the water mist in the construction area.
[0016] The atomized droplets sprayed from the atomizing nozzle will also be blown by the air blowing assembly and blown toward the center of the construction area, further ensuring that the droplets will not overflow from the top of the fence to the outside of the construction area, thereby improving the dust reduction effect. BRIEF DESCRIPTION OF THE DRAWINGS
[0017] In order to more clearly illustrate the technical solutions in the embodiments of the present application, the drawings required for use in the description of the embodiments will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the present application. For ordinary technicians in this field, other drawings can be obtained based on these drawings without creative work.
[0018] Figure 1It is a structural diagram of the enclosure in the utility model.
[0019] Figure 2 It is a structural diagram of the center column of the utility model.
[0020] Figure 3 It is a structural diagram of the cover plate in the utility model.
[0021] Figure 4 It is a structural diagram of the positioning plate in the utility model.
[0022] Figure 5 It is a structural diagram of the movable arm in the utility model.
[0023] Figure 6 It is a structural diagram of the electric push rod in the utility model.
[0024] Among them: 1. enclosure; 2. connecting plate; 3. first positioning hole; 4. column; 5. first positioning bolt; 6. movable arm; 7. atomizing nozzle; 8. guide pipe; 9. hinged seat; 10. cover plate; 11. blower fan; 12. groove seat; 13. second positioning hole; 14. third positioning hole; 15. positioning plate; 16. fourth positioning hole; 17. second positioning bolt; 18. third positioning bolt; 19. fifth positioning hole; 20. electric push rod. DETAILED DESCRIPTION
[0025] In order to make the purpose, technical solution and advantages of the embodiments of the present application clearer, the technical solution in the embodiments of the present application will be clearly and completely described below in conjunction with the drawings in the embodiments of the present application. Obviously, the described embodiments are part of the embodiments of the present application, not all of the embodiments. Based on the embodiments in the present application, all other embodiments obtained by ordinary technicians in this field without making creative work are within the scope of protection of this application.
[0026] according to Figure 1 , 2 As shown in , 3, 4, and 5, this embodiment proposes a dust treatment device for construction engineering, including a plurality of enclosures 1 surrounding a construction area, a connecting plate 2 is provided between two adjacent enclosures 1, and an atomizing spray mechanism is provided on the connecting plate 2;
[0027] Please refer to the following instructions for the atomizing spray mechanism.
[0028] The atomizing spray mechanism includes a column 4, which is detachably connected to the connecting plate 2. A movable arm 6 is provided in the upper half of the column 4 away from the connecting plate 2. The lower end of the movable arm 6 is hinged to the column 4 through a hinge seat 9. The column 4 is provided with an adjustment mechanism for adjusting the angle between the column 4 and the movable arm 6.
[0029] An atomizing nozzle 7 and a guide pipe 8 are provided on the movable arm 6. The atomizing nozzle 7 is fixedly connected to the upper end of the movable arm 6. The guide pipe 8 is connected to the atomizing nozzle 7. An air blowing assembly is provided on the upper end of the movable arm 6. The air blowing assembly is placed between the atomizing nozzle 7 and the column 4.
[0030] Next, the use of the dust treatment device and the advantages of the technical solution are explained.
[0031] The guide pipe 8 is connected to the pipeline system buried deep on the ground or underground, which is beneficial to the groundwater or water in the fire water pool to provide a water source for the atomizing nozzle 7. After the atomized droplets are sprayed out through the atomizing nozzle 7, they will cooperate with the enclosure 1 to increase the humidity of the air in the construction area and absorb dust particles and impurities in the air, thereby playing a role in dust reduction and dust removal.
[0032] The angle between the column 4 and the movable arm 6 is adjustable, and the spraying height of the atomizing nozzle 7 on the movable arm 6 can be adjusted according to the height of the enclosure 1, thereby reducing the impact of outdoor strong winds on the water mist and increasing the hovering time of the water mist in the construction area. At the same time, the atomized droplets sprayed from the atomizing nozzle 7 will also be blown by the blower assembly and blown toward the center of the construction area, further ensuring that the droplets will not overflow from the top of the enclosure 1 to the outside of the construction area, thereby improving the dust reduction effect.
[0033] In a better implementation.
[0034] The adjustment mechanism includes a positioning plate 15, on which are mounted two second positioning bolts 17, one of which passes through a fourth positioning hole 16 provided on the positioning plate 15 and is threadedly connected to a second positioning hole 13 provided on the outside of the movable arm 6, and the other second positioning bolt 17 passes through the fourth positioning hole 16 and is threadedly connected to a third positioning hole 14 provided on the outside of the column 4. The positioning plate 15 has a plurality of fourth positioning holes 16 on the outside, the column 4 has a plurality of third positioning holes 14 on the outside, and the movable arm 6 has a plurality of second positioning holes 13 on the outside, and the second positioning holes 13 are evenly arranged along the length direction of the movable arm 6.
[0035] comprehensive Figure 3 , Figure 4 and Figure 5 The specific working mode of the regulating mechanism is:
[0036] When adjusting the height of the movable arm 6, the second positioning bolt 17 is screwed out from the corresponding second positioning hole 13 to release the locking of the movable arm 6 by the second positioning bolt 17 on the positioning plate 15. After unlocking, the movable arm 6 is rotated and rotated around the hinge seat 9. When the upper end of the movable arm 6 approaches the upper end of the column 4, the atomizing nozzle 7 is lifted upward. On the contrary, when the upper end of the movable arm 6 is away from the upper end of the column 4, the atomizing nozzle 7 falls. When locking the adjusted movable arm 6 again, the second positioning bolt 17 is screwed into the corresponding second positioning hole 13.
[0037] For the specific structure of the air blowing assembly, please refer to the following description.
[0038] The air blowing assembly includes a cover plate 10 disposed at the upper end of the movable arm 6 . The cover plate 10 is detachably connected to a side of the movable arm 6 close to the column 4 . A blower fan 11 is disposed on the cover plate 10 . The cover plate 10 is arranged on one side of the atomizing nozzle 7 .
[0039] comprehensive Figure 3 and Figure 4 , the specific operation mode of the blast assembly is:
[0040] The motor in the cover plate 10 drives the fan blades to rotate. When the airflow passes through the atomizing nozzle 7, it will blow the droplets sprayed from the atomizing nozzle 7 toward the center of the construction area. In conjunction with the cover plate 10, the spraying range is increased while preventing the droplets from spilling outside the enclosure 1.
[0041] In a preferred embodiment, a plurality of first positioning bolts 5 are mounted on the column 4, and the first positioning bolts 5 pass through the column 4 and are threadedly connected to the first positioning holes 3 provided on the outside of the connecting plate 2. When the column 4 is removed from the connecting plate 2, the first positioning bolts 5 can be screwed out of the corresponding first positioning holes 3.
[0042] In another preferred embodiment, the cover plate 10 is equipped with a plurality of third positioning bolts 18, which pass through the cover plate 10 and are threadedly connected to the fifth positioning holes 19 provided on the outer side of the movable arm 6. When the cover plate 10 is removed from the movable arm 6, the third positioning bolts 18 can be screwed out of the corresponding fifth positioning holes 19.
[0043] Detachable connection mode makes replacement and maintenance of each component easy.
[0044] Based on the previous embodiment, further optimization can be made. Specifically, a groove seat 12 is provided on the side of the cover plate 10 close to the movable arm 6, and the groove seat 12 is clamped on the outer side of the movable arm 6. During assembly, the cover plate 10 can be pre-matched with the movable arm 6 through the groove seat 12, so as to facilitate the screwing in of the third positioning bolt 18 on the cover plate 10.
[0045] In another preferred embodiment, the adjustment mechanism includes an electric push rod 20, which is placed between the movable arm 6 and the column 4, the mounting end of the electric push rod 20 is rotatably connected to the column 4, and the output end of the electric push rod 20 is rotatably connected to the movable arm 6.
[0046] comprehensive Figure 6 The specific working mode of the regulating mechanism is:
[0047] The angle adjustment between the movable arm 6 and the column 4 is controlled by the electric push rod 20. When the electric push rod 20 pushes the movable arm 6, the atomizing nozzle 7 falls down. When the electric push rod 20 pulls the movable arm 6, the atomizing nozzle 7 rises upward. Of course, in addition to the electric push rod 20, other linear push mechanisms can also be used as substitutes, such as pneumatic push rods, hydraulic push rods, etc. Compared with manual adjustment, the control method using the electric push rod 20 saves manpower and is easy to operate, but correspondingly, the failure rate and maintenance cost are also increased.
[0048] The working principle of the present application: the guide pipe 8 is connected to the pipeline system deeply buried on the ground or underground, which is beneficial to the groundwater or water in the fire water pool to provide a water source for the atomizing nozzle 7. After the atomized droplets are sprayed out through the atomizing nozzle 7, they will cooperate with the enclosure 1 to increase the humidity in the air in the construction area and absorb dust particles and impurities in the air. The angle between the column 4 and the movable arm 6 is adjustable, and the spraying height of the atomizing nozzle 7 on the movable arm 6 can be adjusted according to the height of the enclosure 1. At the same time, the atomized droplets sprayed from the atomizing nozzle 7 will also be blown by the blowing assembly and blown toward the center of the construction area, further ensuring that the droplets will not overflow from the top of the enclosure 1 to the outside of the construction area.
[0049] In the description of the present application, it should be noted that the terms "upper", "lower", etc. indicate orientations or positional relationships based on the orientations or positional relationships shown in the accompanying drawings, and are only for the convenience of describing the present application and simplifying the description, rather than indicating or implying that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore cannot be understood as a limitation on the present application. Unless otherwise clearly specified and limited, the terms "installed", "connected", and "connected" should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection, or it can be an indirect connection through an intermediate medium, or it can be a connection between the two elements. For those of ordinary skill in the art, the specific meanings of the above terms in the present application can be understood according to the specific circumstances.
[0050] The above description is only a specific implementation of the present application, so that those skilled in the art can understand or implement the present application. Various modifications to these embodiments will be apparent to those skilled in the art, and the general principles defined herein can be implemented in other embodiments without departing from the spirit or scope of the present application. Therefore, the present application will not be limited to the embodiments shown herein, but will conform to the widest range consistent with the principles and novel features applied for herein.
Claims
1. A dust treatment device for construction engineering, comprising a plurality of enclosures (1) surrounding a construction area, a connecting plate (2) being provided between two adjacent enclosures (1), characterized in that: The connection plate (2) is provided with an atomizing spray mechanism; The atomizing spray mechanism comprises a column (4), the column (4) being detachably connected to the connecting plate (2), a movable arm (6) being provided at an upper half of a side of the column (4) away from the connecting plate (2), the lower end of the movable arm (6) being hinged to the column (4) via a hinge seat (9), and an adjustment mechanism for adjusting the angle between the column (4) and the movable arm (6) being provided on the column (4); The movable arm (6) is provided with an atomizing nozzle (7) and a guide pipe (8); the atomizing nozzle (7) is fixedly connected to the upper end of the movable arm (6); the guide pipe (8) is in communication with the atomizing nozzle (7); the upper end of the movable arm (6) is provided with an air blowing assembly; the air blowing assembly is placed between the atomizing nozzle (7) and the column (4).
2. A dust treatment device for construction engineering according to claim 1, characterized in that: The adjustment mechanism comprises a positioning plate (15), on which two second positioning bolts (17) are mounted, wherein one of the second positioning bolts (17) passes through a fourth positioning hole (16) provided on the positioning plate (15) and is threadedly connected to a second positioning hole (13) provided on the outside of the movable arm (6), and the other second positioning bolt (17) passes through the fourth positioning hole (16) and is threadedly connected to a third positioning hole (14) provided on the outside of the column (4). The positioning plate (15) has a plurality of fourth positioning holes (16) on the outside, the column (4) has a plurality of third positioning holes (14) on the outside, and the movable arm (6) has a plurality of second positioning holes (13) on the outside, and the second positioning holes (13) are evenly arranged along the length direction of the movable arm (6).
3. A dust treatment device for construction engineering according to claim 1, characterized in that: The air blowing assembly comprises a cover plate (10) arranged at the upper end of the movable arm (6); the cover plate (10) is detachably connected to a side of the movable arm (6) close to the column (4); a blower fan (11) is provided on the cover plate (10); and the cover plate (10) is arranged on one side of the atomizing nozzle (7).
4. A dust treatment device for construction engineering according to claim 1, characterized in that: A plurality of first positioning bolts (5) are mounted on the upright column (4), and the first positioning bolts (5) pass through the upright column (4) and are threadedly connected to first positioning holes (3) provided on the outside of the connecting plate (2).
5. A dust treatment device for construction engineering according to claim 3, characterized in that: A plurality of third positioning bolts (18) are mounted on the cover plate (10), and the third positioning bolts (18) pass through the cover plate (10) and are threadedly connected to fifth positioning holes (19) provided on the outside of the movable arm (6).
6. A dust treatment device for construction engineering according to claim 5, characterized in that: A groove seat (12) is provided on one side of the cover plate (10) close to the movable arm (6), and the groove seat (12) is sleeved on the outer side of the movable arm (6).
7. A dust treatment device for construction engineering according to claim 1, characterized in that: The adjustment mechanism comprises an electric push rod (20), the electric push rod (20) being disposed between the movable arm (6) and the column (4), the mounting end of the electric push rod (20) being rotatably connected to the column (4), and the output end of the electric push rod (20) being rotatably connected to the movable arm (6).