Hoisting structure of precast concrete pipe pile
By designing the lifting base and adjustment components, the movable plate and clamping plate are driven close to the end of the precast concrete pipe pile and fixed with the limiting plug column, the problem of easy sliding of the hook is solved, the lifting safety is improved, and the elastic pad is reduced Rigid contact enhances operational safety.
Patent Information
- Application Number
- CN202420812689.7
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-04-18
- Publication Date
- 2025-01-03
- Estimated Expiration
- 2034-04-18
AI Technical Summary
During the lifting process of existing precast concrete pipe piles, the hooks are prone to slip and there are major safety hazards, and it is necessary to improve the lifting safety.
A lifting structure including a lifting base, a sliding cavity, a movable plate, a clamping plate and an adjustment assembly is designed. The movable plate and a clamping plate are driven close to the end of the precast concrete pipe pile by the adjustment assembly, and the limiting insertion column is used. Fixed and hoisting operations combined with lifting equipment to improve safety.
Effectively prevent the hook from slipping, improve the lifting safety of precast concrete pipe piles, and reduce the direct rigid contact between the clamping plate and the pipe piles through elastic pads, enhancing operational safety.
Smart Images

Figure CN222293343U_ABST
Abstract
Description
Technical Field
[0001] The present application relates to the technical field of building construction, and in particular to a hoisting structure of a precast concrete pipe pile. Background Art
[0002] Precast concrete pipe piles are a type of building component commonly used in infrastructure construction at this stage. They have the characteristics of high bearing capacity, quick and convenient construction, low environmental pollution, reliable pile quality, and good comprehensive technical and economic benefits, and have been widely promoted and used.
[0003] Precast concrete pipe piles are lifted by cranes during production, transportation and lifting. However, in the prior art, the existing method is to use a steel wire rope of a traveling crane to move the piles. A pair of hooks are provided on the steel wire rope of the traveling crane, and the hooks are fixed to the ports at both ends of the precast concrete pipe piles. The piles are then moved by the traveling crane. However, the hooks are easy to slip off the precast concrete pipe piles, which poses a great safety hazard and thus needs further improvement. Utility Model Content
[0004] In order to improve the safety of hoisting of precast concrete pipe piles, the present application provides a hoisting structure for precast concrete pipe piles.
[0005] The present application provides a prefabricated concrete pipe pile hoisting structure that adopts the following technical solution:
[0006] A lifting structure for precast concrete pipe piles, comprising a lifting base for placing the precast concrete pipe piles, the lifting base having a sliding cavity, two sliding cavities being arranged and distributed along the length direction of the lifting base, a movable plate being slidingly connected in each sliding cavity, the movable plate being fixedly connected to a guide rod slidingly penetrated by the lifting base, an end of the guide rod away from the movable plate being fixedly connected to a clamping plate externally arranged on the lifting base, the clamping plate being fixedly connected to a limiting plug correspondingly inserted into a port of the precast concrete pipe pile, and the lifting base being provided with an adjusting component for driving the two movable plates to slide toward or away from each other.
[0007] By adopting the above technical solution, after the precast concrete pipe pile is placed on the lifting base, the two movable plates are driven toward each other through the adjustment component, thereby driving the two clamping plates to slide toward the end of the precast concrete pipe pile and abut against the end face of the precast concrete pipe pile. In addition, the limit plug column is inserted into the port of the precast concrete pipe pile, so as to clamp and fix the two ends of the concrete pipe pile, and the lifting base is lifted by the lifting equipment to improve the lifting safety of the precast concrete pipe pile.
[0008] Preferably, the adjustment assembly includes an adjustment screw rotatably connected to the sliding cavity and a driving component for driving the adjustment screw to rotate, the axial direction of the adjustment screw is parallel to the axial direction of the guide rod, and the adjustment screw thread is penetrated through the movable plate.
[0009] By adopting the above technical solution, the adjusting screw is driven to rotate by the driving component, and the movable plate slides along the axial direction of the adjusting screw due to the thread restriction of the adjusting screw.
[0010] Preferably, the lifting base has a driving cavity located between the two sliding cavities, and one end of the adjusting screw extends into the driving cavity. The driving component includes a rotating shaft rotatably connected to the driving cavity, a first bevel gear built into the driving cavity and coaxially fixed on the rotating shaft, and a second bevel gear built into the driving cavity and coaxially fixed on the end of the adjusting screw, and the first bevel gear and the second bevel gear are meshed.
[0011] By adopting the above technical solution, the first bevel gear is driven to rotate by rotating the rotating shaft, so that the adjusting screw rod is synchronously rotated by the second bevel gear, thereby realizing the sliding movement of the two clamping plates.
[0012] Preferably, the lifting base is fixedly connected with a driving motor for driving the rotating shaft to rotate.
[0013] By adopting the above technical solution, the rotating shaft is driven to rotate by the driving motor, thereby realizing the electric operation of the clamping plate.
[0014] Preferably, the end of the rotating shaft away from the first bevel gear is fixedly connected to a handwheel externally disposed on the lifting base.
[0015] By adopting the above technical solution, the staff can rotate the shaft by turning the hand wheel, which is convenient for manual operation.
[0016] Preferably, the lifting base is provided with a limiter for limiting the rotation of the hand wheel.
[0017] By adopting the above technical solution, a limiting member is added to limit the rotation of the hand wheel, thereby improving operational safety.
[0018] Preferably, the limiting member is a limiting bolt threadedly connected to the handwheel, and the end face of the limiting bolt is pressed against the outer side wall of the lifting base.
[0019] By adopting the above technical solution, when the rotating shaft needs to be rotated, the limit bolt is loosened so that the end face of the limit bolt is separated from the outer wall of the lifting base, thereby releasing the rotation restriction of the hand wheel. After the clamping plate is adjusted, the limit bolt is tightened so that the end face of the limit bolt is pressed against the outer wall of the lifting base, thereby limiting the rotation of the hand wheel through damping.
[0020] Preferably, the clamping plate is provided with an elastic pad abutting against the end surface of the precast concrete pipe pile.
[0021] By adopting the above technical solution, the clamping plate is additionally provided with an elastic pad, thereby reducing the possibility of direct rigid contact between the clamping plate and the precast concrete pipe pile.
[0022] In summary, the utility model has the following beneficial effects:
[0023] 1. After placing the precast concrete pile on the hoisting base, the two movable plates are driven to approach each other through the adjustment component, thereby driving the two clamping plates to slide toward the end of the precast concrete pile and abut against the end surface of the precast concrete pile. In addition, the limit plug is inserted into the port of the precast concrete pile, so as to clamp and fix the two ends of the concrete pile. The hoisting base is hoisted by the hoisting equipment to improve the hoisting safety of the precast concrete pile.
[0024] 2. The clamping plate is equipped with an elastic pad to reduce the possibility of direct rigid contact between the clamping plate and the precast concrete pipe pile. BRIEF DESCRIPTION OF THE DRAWINGS
[0025] Figure 1 It is a schematic diagram of the overall structure of a hoisting structure of a precast concrete pipe pile;
[0026] Figure 2 It is a schematic diagram of the internal structure of the lifting base;
[0027] Figure 3 It is a schematic diagram of the structure of the lubricating bushing;
[0028] Figure 4 yes Figure 2 A local enlarged schematic diagram at point A.
[0029] In the figure, 1. lifting base; 11. limit bearing plate; 12. fixed plate; 13. mounting column; 14. pull ring; 15. sliding chamber; 16. driving chamber; 2. guide rod; 21. movable plate; 3. clamping plate; 31. elastic pad; 32. limit plug column; 4. lubricating bushing; 41. mounting ring plate; 42. liquid flow channel; 43. liquid flow hole; 44. lubricating sponge ring sleeve; 45. lubricating liquid injection pipe; 5. adjusting assembly; 51. adjusting screw; 52. driving component; 521. rotating shaft; 522. first bevel gear; 523. second bevel gear; 53. handwheel; 54. limit bolt. DETAILED DESCRIPTION
[0030] The following is combined with Figure 1-4 This application is described in further detail.
[0031] Embodiment 1:
[0032] The present application embodiment discloses a precast concrete pipe pile hoisting structure, referring to Figure 1, including a lifting base 1, the upper end surface of the lifting base 1 is fixedly connected with a limited receiving plate 11, the limited receiving plate 11 is an arc-shaped plate adapted to the lower peripheral wall of the precast concrete pipe pile for the precast concrete pipe pile to be placed, the axial direction of the limited receiving plate 11 is parallel to the length direction of the lifting base 1, and a plurality of limited receiving plates 11 are provided and spaced apart along the width direction of the lifting base 1. The outer side wall of the lifting base 1 in the length direction is fixedly connected with a fixing plate 12, and a mounting column 13 is fixedly connected to the fixing plate 12, and a pull ring 14 is fixedly connected to the upper end surface of the mounting column 13.
[0033] Reference Figure 2 , Figure 3 The hoisting base 1 has a sliding cavity 15 and a driving cavity 16. Two sliding cavities 15 are provided and distributed along the length direction of the hoisting base 1. One driving cavity 16 is provided and is located between the two sliding cavities 15. The outer wall of the hoisting base 1 in the width direction is provided with a sliding hole connected to the sliding cavity 15. The hoisting base 1 is provided with a lubricating bushing 4 fixedly inserted in the sliding hole. One end of the lubricating bushing 4 is coaxially fixedly connected to a mounting ring plate 41. The mounting ring plate 41 is fixedly connected to the outer wall of the hoisting base 1 by bolts. The peripheral wall of the lubricating bushing 4 has a liquid flow channel 42. The other end surface of the lubricating bushing 4 is provided with a liquid flow hole 43 connected to the liquid flow channel 42. The other end of the lubricating bushing 4 is fixedly connected to a lubricating sponge ring sleeve 44 built into the sliding cavity 15. The lubricating sponge ring sleeve 44 covers the liquid flow hole 43. The hanging base 1 is provided with a lubricating liquid injection pipe 45 connected to the liquid flow channel 42 , and lubricating oil is added to the liquid flow channel 42 through the lubricating liquid injection pipe 45 .
[0034] The lifting base 1 is provided with a guide rod 2 which is slidably inserted in the mounting ring plate 41, the lubricating bushing 4 and the lubricating sponge ring sleeve 44. In the present embodiment, two guide rods 2 are provided and distributed along the width direction of the lifting base 1. The axial direction of the guide rod 2 is parallel to the length direction of the lifting base 1. During the sliding of the guide rod 2, the lubricating liquid on the lubricating sponge ring sleeve 44 is smeared on the peripheral wall of the guide rod 2, thereby reducing the possibility of noise generated during the sliding process of the guide rod 2.
[0035] Reference Figure 1 One end of the guide rod 2 is fixedly connected to a movable plate 21 built into the sliding cavity 15, and the other end of the guide rod 2 is fixedly connected to a clamping plate 3 externally disposed on the hoisting base 1. The clamping plate 3 is fixedly connected to a limit plug 32 correspondingly inserted into the port of the precast concrete pipe pile, and the limit plug 32 is set in a conical shape at one end away from the clamping plate 3. The clamping plate 3 is fixedly connected to an elastic pad 31 abutting against the end surface of the precast concrete pipe pile, and the elastic pad 31 is a rubber pad.
[0036] Reference Figure 2 , Figure 4The hoisting base 1 is provided with an adjustment assembly 5 for driving the two movable plates 21 to slide toward or away from each other. The adjustment assembly 5 includes an adjustment screw 51 rotatably connected to the inner side wall of the sliding cavity 15 and a driving component 52 for driving the adjustment screw 51 to rotate. The axial direction of the adjustment screw 51 is parallel to the axial direction of the guide rod 2, and the adjustment screw 51 is threadedly arranged in the movable plate 21. One end of the adjustment screw 51 extends into the driving cavity 16, and the driving component 52 includes a rotating shaft 521, a first bevel gear 522 and a second bevel gear 523. The axial direction of the rotating shaft 521 is parallel to the width direction of the hoisting base 1, the rotating shaft 521 is built in the driving cavity 16 and is rotatably connected to the inner side wall of the driving cavity 16, the first bevel gear 522 is built in the driving cavity 16 and is coaxially fixedly sleeved on the end of the rotating shaft 521, and the other end of the rotating shaft 521 extends to the outside of the hoisting base 1. The second bevel gear 523 is built into the driving cavity 16 and is coaxially fixedly sleeved on the end of the adjusting screw rod 51 . The first bevel gear 522 and the second bevel gear 523 are meshed.
[0037] The hoisting base 1 is provided with a driving member for driving the rotating shaft 521 to rotate. In this embodiment, the driving member is a hand wheel 53 externally disposed on the hoisting base 1 and coaxially fixedly sleeved on one end of the rotating shaft 521. The hoisting base 1 is provided with a limiter for limiting the rotation of the hand wheel 53. The limiter is a limit bolt 54 threadedly connected to the hand wheel 53, and the end face of the limit bolt 54 is tightly pressed against the outer wall of the hoisting base 1. In other embodiments, the driving member can be a driving motor, which is a stepping motor. The driving motor is fixedly connected to the outer wall of the hoisting base 1, and the output shaft of the driving motor is coaxially fixedly connected to the rotating shaft 521.
[0038] The implementation principle of the lifting structure of a precast concrete pipe pile in the embodiment of the present application is as follows: after the precast concrete pipe pile is placed on the limit receiving plate 11, the limit bolt 54 is loosened, and the rotation restriction of the hand wheel 53 is released, the rotation of the rotating shaft 521 is realized by rotating the hand wheel 53, and the rotation of the rotating shaft 521 synchronously drives the first bevel gear 522 to rotate during the rotation of the rotating shaft 521, so that the rotation of the adjusting screw rod 51 is synchronously realized through the second bevel gear 523, and the movable plate 21 is restricted by the thread of the adjusting screw rod 51 and moves along the adjusting screw rod 51 The axial directions of the two clamping plates 3 slide toward each other, thereby driving the two clamping plates 3 to slide toward the end of the precast concrete pipe pile through the guide rod 2. The limiting plug column 32 is inserted into the port of the precast concrete pipe pile, and the elastic pad 31 abuts against the end face of the precast concrete pipe pile, thereby clamping and fixing the two ends of the concrete pipe pile. Then, tighten the limiting bolt 54, and finally hook the hook on the lifting equipment on the pull ring 14, and use the lifting equipment to lift the lifting base 1 to improve the lifting safety of the precast concrete pipe pile.
[0039] The above are all preferred embodiments of the present application, and the protection scope of the present application is not limited thereto. Therefore, any equivalent changes made according to the structure, shape, and principle of the present application should be included in the protection scope of the present application.
Claims
1. A hoisting structure for precast concrete pipe piles, characterized in that: The invention comprises a lifting base (1) for placing a precast concrete pipe pile, the lifting base (1) having a sliding cavity (15), two sliding cavities (15) being arranged and distributed along the length direction of the lifting base (1), a movable plate (21) being slidably connected in each sliding cavity (15), the movable plate (21) being fixedly connected to a guide rod (2) slidably penetrating the lifting base (1), the end of the guide rod (2) away from the movable plate (21) being fixedly connected to a clamping plate (3) externally arranged on the lifting base (1), the clamping plate (3) being fixedly connected to a limiting plug column (32) correspondingly inserted into a port of the precast concrete pipe pile, and the lifting base (1) being provided with an adjusting component (5) for driving the two movable plates (21) to slide in a direction of approaching or moving away from each other.
2. The hoisting structure of a precast concrete pipe pile according to claim 1, characterized in that: The adjustment assembly (5) comprises an adjustment screw (51) rotatably connected to the sliding chamber (15) and a driving component (52) for driving the adjustment screw (51) to rotate. The axial direction of the adjustment screw (51) is parallel to the axial direction of the guide rod (2). The adjustment screw (51) is threadedly inserted into the movable plate (21).
3. The hoisting structure of a precast concrete pipe pile according to claim 2, characterized in that: The hoisting base (1) has a driving chamber (16) located between the two sliding chambers (15), one end of the adjusting screw rod (51) extends into the driving chamber (16), and the driving component (52) comprises a rotating shaft (521) rotatably connected to the driving chamber (16), a first bevel gear (522) built into the driving chamber (16) and coaxially fixedly sleeved on the rotating shaft (521), and a second bevel gear (523) built into the driving chamber (16) and coaxially fixedly sleeved on the end of the adjusting screw rod (51), and the first bevel gear (522) and the second bevel gear (523) are meshed.
4. The hoisting structure of a precast concrete pipe pile according to claim 3 is characterized in that: The lifting base (1) is fixedly connected to a driving motor for driving the rotating shaft (521) to rotate.
5. The hoisting structure of a precast concrete pipe pile according to claim 3, characterized in that: The end of the rotating shaft (521) away from the first bevel gear (522) is fixedly connected to a hand wheel (53) externally disposed on the lifting base (1).
6. The hoisting structure of a precast concrete pipe pile according to claim 5, characterized in that: The lifting base (1) is provided with a limiting member for limiting the rotation of the hand wheel (53).
7. The hoisting structure of a precast concrete pipe pile according to claim 6, characterized in that: The limiting member is a limiting bolt (54) threadedly connected to the hand wheel (53), and the end surface of the limiting bolt (54) is pressed against the outer side wall of the lifting base (1).
8. The hoisting structure of a precast concrete pipe pile according to claim 1, characterized in that: The clamping plate (3) is provided with an elastic pad (31) abutting against the end surface of the precast concrete pipe pile.