Civil engineering foundation pit drainage structure
By using filter mesh and climbing poles in the foundation pit drainage structure, the problem of silt blockage and sediment difficulty in cleaning up silt and sediment is solved, and efficient drainage and safe engineering operations are achieved.
Patent Information
- Application Number
- CN202421107359.4
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-05-21
- Publication Date
- 2025-01-10
- Estimated Expiration
- 2034-05-21
AI Technical Summary
In the existing foundation pit drainage structure, the pump is easily blocked by silt and sand, resulting in poor drainage, and the sediment deposited at the bottom of the collecting pit is difficult to clean, affecting the safety of the project.
A civil foundation pit drainage structure was designed, using a combination of a pump pump, a water collecting pit, a water collecting tank, a filter net, a floating plate and a climbing rod. The silt and sand are filtered through the filter net to prevent the silt and sand from entering the pumping pump and climbing through the climbing machine. The climbing pole makes it easier for staff to go down to the bottom of the collection pit to clean up sediment.
Effectively prevent silt and sand from entering the pump, improve drainage efficiency, and facilitate the cleaning of silt and sand at the bottom of the collecting pit, ensuring the safety and efficiency of foundation pit projects.
Smart Images

Figure CN222332741U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the field of civil construction foundation pit drainage, in particular to a civil construction foundation pit drainage structure. Background Art
[0002] Foundation pit drainage is an important part of foundation pit engineering protection and plays an important role in the safety of foundation pit engineering. The general foundation pit drainage structure is to set up drainage ditches on the top of the foundation pit or use a water pump for drainage.
[0003] However, when a water pump is used for drainage, the water pipe in front of the water pump will discharge the silt in the foundation pit while draining the water. A lot of silt will block the water pump, making it impossible to drain the water. Moreover, after a long period of water collection, a large amount of silt will settle at the bottom of the sump. Since the sump is deep, it is difficult for the staff to go down to the bottom for cleaning. Utility Model Content
[0004] The utility model aims to solve the shortcomings in the prior art and proposes a drainage structure for a civil construction foundation pit.
[0005] In order to solve the problems existing in the prior art, the utility model adopts the following technical solutions:
[0006] A civil engineering foundation pit drainage structure comprises a foundation pit body 1, a pair of water pumps 11 are fixedly arranged on the foundation pit body 1, a pair of water collection pits 12 are fixedly arranged at the bottom of the foundation pit body 1, water collection ports 13 are opened on both sides of the pair of water collection pits 12, a pair of water collection tanks 14 are fixedly arranged at the bottom of the foundation pit body 1, a plurality of water inlets 141 are opened on the water collection tanks 14, first filter screens 15 are fixed on both sides of the pair of water collection tanks 14, a plurality of cover plates 16 are arranged on the water collection tanks 14, the water collection tanks 14 are respectively fixedly connected to the water collection pits 12, and a pair of water collection tanks 14 are opened at both ends. There is a pair of slide grooves 17, and sliders 18 are slidably provided in the slide grooves 17. A second filter screen 19 is fixedly provided between each pair of sliders 18, and an arc-shaped hook ring 111 is fixedly provided on the second filter screen 19. A connecting pipe 112 is fixedly provided on the water pump 11, and a pair of limiting rods 113 are fixedly provided in the sump 12. A floating plate 114 is slidably provided on each pair of limiting rods 113, and a filter head 115 is fixedly provided at the bottom of the floating plate 114. A hose 116 is fixedly provided on the filter head 115, and the other end of the hose 116 is fixedly connected to the connecting pipe 112.
[0007] Preferably, a protective cover 2 is rotatably provided on the sump 12 , and a plurality of climbing poles 21 are fixedly provided on the inner wall of the sump 12 .
[0008] Preferably, the filter heads 115 all penetrate the floating plate 114 , the filter heads 115 are located at the center of the floating plate 114 , and the bottom center of the foundation pit body 1 is slightly inclined toward both sides.
[0009] Preferably, the sump 12 is located at the center of the short side of the foundation pit body 1 , and a plurality of cover plates 16 completely cover the top of the sump 14 .
[0010] Preferably, the connecting pipes 112 all pass through the sump 12 , and a pair of sump 12 are symmetrically arranged.
[0011] Preferably, the bottom of the water inlet 141 is parallel to the bottom of the foundation pit body 1 , and the water collection ports 13 correspond to the end positions of the water collection tank 14 .
[0012] Preferably, the second filter screens 19 are all located on one side of the water collection port 13 , and the first filter screens 15 are at the same height as the water inlet 141 .
[0013] Preferably, a plurality of climbing poles 21 are distributed in a linear upward vertical array, and a handle is fixedly provided on the protective cover 2 .
[0014] Compared with the prior art, the beneficial effects of the utility model are:
[0015] 1. In the utility model, by using a water pump, a sump, a sump, a first filter screen, a second filter screen, a connecting pipe, a floating plate, a filter head and a hose in coordination, when the water foundation pit body is drained, it can effectively prevent sediment from being pumped into the water pump, thereby reducing the influence of sediment on drainage.
[0016] 2. In the present invention, by using the protective cover and the climbing pole together, when a large amount of sediment has settled at the bottom of the sump for a long time, the staff can go down to the bottom of the sump through the climbing pole to clean up the settled sediment. BRIEF DESCRIPTION OF THE DRAWINGS
[0017] The drawings described herein are used to provide a further understanding of the present invention and constitute a part of the present application. The exemplary embodiments of the present invention and their descriptions are used to explain the present invention and do not constitute an improper limitation on the present invention. In the drawings:
[0018] Figure 1 This is a schematic diagram of the main structure of the utility model;
[0019] Figure 2 It is a schematic diagram of the cross-sectional structure of the foundation pit body of the utility model;
[0020] Figure 3 It is a diagram for the position relationship between the water collection port and the water collection pit of the utility model;
[0021] Figure 4 This is a schematic diagram of the cross-sectional structure of the sump of the utility model;
[0022] Figure 5 For the utility model Figure 2The enlarged schematic diagram at A in the middle;
[0023] Figure 6 For the utility model Figure 3 The enlarged schematic diagram of point B in the middle;
[0024] Serial numbers in the figure: 1. foundation pit body; 11. water pump; 12. sump; 13. water collection port; 14. sump; 15. first filter screen; 16. cover plate; 17. slide; 18. slider; 19. second filter screen; 111. arc hook; 112. connecting pipe; 113. limit rod; 114. floating plate; 115. filter head; 116. hose; 141. water inlet; 2. protective cover; 21. climbing rod. DETAILED DESCRIPTION
[0025] The technical solutions in the embodiments of the present invention will be described clearly and completely below in conjunction with the drawings in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, rather than all of the embodiments.
[0026] Embodiment 1: This embodiment provides a drainage structure for a civil foundation pit. Figure 1-6 Specifically, it includes a foundation pit body 1, a pair of pumps 11 are fixedly arranged on the foundation pit body 1, a pair of sumps 12 are fixedly arranged at the bottom of the foundation pit body 1, and a pair of sumps 12 are provided with water collection ports 13 on both sides of the pair of sumps 12, a pair of sump tanks 14 are fixedly arranged at the bottom of the foundation pit body 1, and a plurality of water inlets 141 are provided on the sump tanks 14, a first filter screen 15 is fixedly arranged on both sides of the pair of sump tanks 14, a plurality of cover plates 16 are provided on the sump tanks 14, and the sump tanks 14 are respectively fixedly connected to the sump pits 12, and a pair of sump tanks 14 are provided at both ends. A slide 17 is provided, and a slider 18 is slidably provided in the slide 17. A second filter 19 is fixedly provided between each pair of sliders 18. An arc-shaped hook ring 111 is fixedly provided on the second filter 19. A connecting pipe 112 is fixedly provided on the water pump 11. A pair of limit rods 113 is fixedly provided in the sump 12. A floating plate 114 is slidably provided on each pair of limit rods 113. A filter head 115 is fixedly provided at the bottom of the floating plate 114. A hose 116 is fixedly provided on the filter head 115. The other end of the hose 116 is fixedly connected to the connecting pipe 112.
[0027] The filter heads 115 all pass through the floating plate 114, the filter heads 115 are located at the center of the floating plate 114, the sump 12 is located at the center of the short side of the foundation pit body 1, the bottom center of the foundation pit body 1 is slightly inclined to both sides, and multiple cover plates 16 completely cover the top of the sump 14. The connecting pipes 112 all pass through the sump 12, and a pair of sump 12 are arranged symmetrically. The bottom of the water inlet 141 is parallel to the bottom of the foundation pit body 1, the water collection ports 13 correspond to the end positions of the water collection ports 14, the second filter screens 19 are all located on one side of the water collection port 13, and the first filter screens 15 are at the same height as the water inlet 141.
[0028] In the specific implementation process, Figure 1 and Figure 4 As shown, when it rains, rainwater falling into the foundation pit body 1 flows toward the sump 14 through the slope, flows into the sump 14 through the first filter screen 15 and the water inlet 141, the first filter screen 15 filters a large amount of sediment in the rainwater, and flows to the sump 12 through the sump 14. The water in the sump 14 flows into the sump 12 through the second filter screen 19 and the water inlet 13 for collection. The second filter screen 19 can filter the sediment remaining in the rainwater again. When the second filter screen 19 is blocked, the second filter screen 19 can be removed from the sump 14 through the arc-shaped hook ring 111 through the slide 17 and the slider 18 for cleaning, and then inserted back for use again. When there is too much water in the water, the water pump 11 draws water from the sump 12 through the filter head 115 and injects it into the hose 116, and then discharges it from the water pump 11 through the connecting pipe 112. The floating plate 114 can increase or decrease the water level in the sump 12, so that the filter head 115 will not contact the settled mud and sand at the bottom of the foundation pit body 1, thereby preventing the suction of a large amount of mud and sand from affecting the use of the filter head 115. Through the coordinated use of the water pump 11, the sump 12, the sump 14, the first filter screen 15, the second filter screen 19, the connecting pipe 112, the floating plate 114, the filter head 115 and the hose 116, when the foundation pit body 1 is drained, the mud and sand can be effectively prevented from entering the water pump 11.
[0029] Embodiment 2: In Embodiment 1, there is still the problem that it is difficult for the staff to go down to the bottom of the sump to clean up the silt. Therefore, based on Embodiment 1, this embodiment also includes:
[0030] A protective cover 2 is rotatably provided on the sump 12 , a plurality of climbing poles 21 are fixedly provided on the inner wall of the sump 12 , and the plurality of climbing poles 21 are distributed in a linear upward vertical array, and a handle is fixedly provided on the protective cover 2 .
[0031] In the specific implementation process, Figure 2 and Figure 4As shown, after long-term use in the sump 12, when a large amount of mud and sand are deposited at the bottom of the sump 12, the protective cover 2 is opened, and the staff slowly descends to the bottom of the sump 12 through the climbing rod 21 to facilitate the cleaning of the mud and sand at the bottom of the sump 12. The climbing rod 21 facilitates the staff to enter and exit the sump 12. Through the coordinated use of the protective cover 2 and the climbing rod 21, when a large amount of mud and sand are deposited at the bottom of the sump 12 for a long time, the staff can go down to the bottom of the sump 12 through the climbing rod 21 to clean the mud and sand.
[0032] Specifically, the working principle and operation method of the utility model are as follows:
[0033] Step 1: When it rains, rainwater falling into the foundation pit body 1 flows toward the water collection tank 14 through the slope, flows into the water collection tank 14 through the first filter screen 15 and the water inlet 141, and the first filter screen 15 filters a large amount of silt in the rainwater, and flows to the water collection pit 12 through the water collection tank 14. The water in the water collection tank 14 flows into the water collection pit 12 through the second filter screen 19 and the water collection port 13 for collection. The second filter screen 19 can filter the silt remaining in the rainwater again. When the second filter screen 19 is blocked, the arc-shaped hook ring 111 can be used to filter the silt that has passed through the second filter screen. 19, take it out from the water collection tank 14 through the chute 17 and the slider 18 for cleaning, and then insert it back for use again. When there is too much water in the water collection pit 12, start the water pump 11, and the water pump 11 pumps water from the water collection pit 12 through the filter head 115 and injects it into the hose 116, and then discharges it from the water pump 11 through the connecting pipe 112. The floating plate 114 can increase or decrease the water level in the water collection pit 12, so that the filter head 115 will not contact the sediment at the bottom of the foundation pit body 1, so as to prevent the suction of a large amount of sediment from affecting the use of the filter head 115;
[0034] Step 2: After a long period of use in the sump 12, when a large amount of silt is deposited at the bottom of the sump 12, the protective cover 2 is opened, and the staff slowly descends to the bottom of the sump 12 through the climbing rod 21 to clean the silt at the bottom of the sump 12. The climbing rod 21 facilitates the staff to enter and exit the sump 12, and the protective cover 2 can cover the top of the sump 12 for protection;
[0035] The above description is only a preferred specific implementation manner of the present invention, but the protection scope of the present invention is not limited thereto. Any technician familiar with the technical field can make equivalent replacements or changes within the technical scope disclosed by the present invention according to the technical scheme and the utility model concept of the present invention, which should be covered by the protection scope of the present invention.
Claims
1. A civil engineering foundation pit drainage structure, comprising a foundation pit body (1), characterized in that: A pair of water pumps (11) are fixedly provided on the foundation pit body (1), a pair of water collection pits (12) are fixedly provided at the bottom of the foundation pit body (1), water collection ports (13) are provided on both sides of the pair of water collection pits (12), a pair of water collection troughs (14) are fixedly provided at the bottom of the foundation pit body (1), a plurality of water inlets (141) are provided on the water collection troughs (14), a first filter screen (15) is fixedly provided on both sides of the pair of water collection troughs (14), a plurality of cover plates (16) are provided on the water collection troughs (14), the water collection troughs (14) are respectively fixedly connected to the water collection pits (12), a pair of slide grooves (17) are provided at both ends of the pair of water collection troughs (14), and the Slide blocks (18) are slidably provided in the slide grooves (17), a second filter screen (19) is fixedly provided between each pair of the slide blocks (18), an arc-shaped hook ring (111) is fixedly provided on the second filter screen (19), a connecting pipe (112) is fixedly provided on the water pump (11), a pair of limit rods (113) are fixedly provided in the sump (12), a floating plate (114) is slidably provided on each pair of the limit rods (113), a filter head (115) is fixedly provided at the bottom of the floating plate (114), a hose (116) is fixedly provided on the filter head (115), and the other end of the hose (116) is fixedly connected to the connecting pipe (112).
2. A civil construction foundation pit drainage structure according to claim 1, characterized in that: A protective cover (2) is rotatably provided on the water collection pit (12), and a plurality of climbing poles (21) are fixedly provided on the inner wall of the water collection pit (12).
3. A civil construction foundation pit drainage structure according to claim 1, characterized in that: The filter heads (115) all penetrate the floating plate (114), the filter heads (115) are located at the center of the floating plate (114), and the center of the bottom of the foundation pit body (1) is slightly inclined toward both sides.
4. A civil construction foundation pit drainage structure according to claim 1, characterized in that: The water collection pit (12) is located at the center of the short side of the foundation pit body (1), and the plurality of cover plates (16) completely cover the top of the water collection tank (14).
5. The civil construction foundation pit drainage structure according to claim 1, characterized in that: The connecting pipes (112) all penetrate the water collection pits (12), and a pair of the water collection pits (12) are symmetrically arranged.
6. A civil construction foundation pit drainage structure according to claim 1, characterized in that: The bottom of the water inlet (141) is parallel to the bottom of the foundation pit body (1), and the water collection ports (13) correspond to the end positions of the water collection tanks (14).
7. The civil construction foundation pit drainage structure according to claim 1, characterized in that: The second filter screens (19) are all located on one side of the water collection port (13), and the first filter screens (15) are at the same height as the water inlet (141).
8. The civil construction foundation pit drainage structure according to claim 2, characterized in that: The plurality of climbing poles (21) are distributed in a linear upward vertical array, and a handle is fixedly provided on the protective cover (2).