Central air conditioner mounting and debugging equipment
By designing the debugging box, fixing mechanism, placement mechanism and auxiliary mechanism of the central air conditioning installation and debugging equipment, the problem of inconvenient carrying of tools and falling parts is solved, and the efficiency and stability of installation and debugging are improved.
Patent Information
- Application Number
- CN202421120770.5
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-05-22
- Publication Date
- 2025-01-14
- Estimated Expiration
- Not applicable · inactive patent
AI Technical Summary
The debugging tools for existing central air conditioners installation and debugging equipment are inconvenient to carry, and parts are prone to fall off during installation and debugging, which affects the progress of maintenance and debugging.
A central air conditioning installation and debugging equipment is designed, including a debugging box, a fixing mechanism, a placing mechanism and an auxiliary mechanism. The debugging box is equipped with a placement mechanism for carrying and adjusting tools, a fixing mechanism for auxiliary fixing of equipment, and an auxiliary mechanism for shielding parts and assisting in lifting installation.
Through this equipment, workers can carry and install debugging tools more conveniently, reduce the risk of parts falling, and improve the efficiency and stability of installation and debugging.
Smart Images

Figure CN222345516U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of central air-conditioning debugging equipment, in particular to a central air-conditioning installation and debugging equipment. Background Art
[0002] Large central air-conditioning installation and debugging equipment for buildings refers to equipment used to help installers debug and optimize when installing central air-conditioning systems. It is beneficial to improve the installation efficiency of large central air-conditioning for buildings, ensure installation quality, and simplify the maintenance process.
[0003] However, when central air-conditioning is installed and debugged, the debugging tools are heavy to carry, which makes it troublesome to carry. At the same time, when central air-conditioning is installed and debugged, the fallen parts cannot be covered, making it difficult to find the fallen parts, which affects the progress of maintenance and debugging. Utility Model Content
[0004] In view of the problems in the related technology, the utility model proposes a central air-conditioning installation and debugging device to overcome the above technical problems existing in the existing related technology.
[0005] To this end, the specific technical solutions adopted by the utility model are as follows:
[0006] A central air conditioner installation and debugging device comprises a debugging box, a fixing mechanism is arranged below the debugging box, and a placing mechanism is arranged on the inner wall of the debugging box;
[0007] An auxiliary mechanism one is arranged above the debugging box, and an auxiliary mechanism two is arranged above the auxiliary mechanism one.
[0008] Furthermore, the fixing mechanism includes a plurality of electric telescopic rods 1 fixedly arranged below the debugging box, a fixing seat is fixedly installed at the output end of the electric telescopic rod 1, and a plurality of fixed suction cups are installed below the fixing seat.
[0009] Furthermore, the placement mechanism includes a placement rack fixedly installed on both sides of the inner wall of the debugging box, the placement rack is provided with placement slots distributed at equal distances, three of which are placed on the inner walls of the placement slots, a shielding door is hinged on the inner wall of the debugging box, and the shielding door is fixedly connected to one side of the debugging box with a lock.
[0010] Furthermore, the auxiliary mechanism 1 includes an auxiliary slot opened above the debugging box, a lift is installed on the inner wall of the auxiliary slot, a debugging platform is fixedly installed above the lift, and an auxiliary frame is fixedly arranged above the debugging platform.
[0011] Furthermore, the auxiliary mechanism 2 includes auxiliary plates installed on the inner walls of both sides of the auxiliary frame, a protective pad is installed on the opposite side of the auxiliary plate, an electric telescopic rod 2 is installed on one side of the auxiliary plate, and installation grooves are opened on both sides of the debugging platform, and the inner walls of the installation grooves are fixedly connected to the electric telescopic rod 2.
[0012] Furthermore, push handles are fixedly connected to both sides of the debugging box, and anti-slip sleeves are installed on the push handles.
[0013] Furthermore, a plurality of support columns are fixedly installed below the debugging box, and moving wheels are fixedly arranged below the support columns.
[0014] The beneficial effects of the utility model are:
[0015] (1) Through the placement mechanism set in the debugging box, not only can the central air-conditioning installation and debugging tools be carried when the central air-conditioning installation and debugging equipment is moved, but the installation and debugging tools can also be adjusted and placed according to the sizes of different central air-conditioning installation and debugging tools, which is convenient for the staff to better install and debug the central air-conditioning. At the same time, the auxiliary mechanism 2 set in the auxiliary mechanism 1 can not only assist in shielding the parts from falling during the installation and debugging of the central air-conditioning, thereby reducing the situation where the progress of maintenance and debugging is affected by the falling parts, but also assist in fixing the central air-conditioning that needs to be installed.
[0016] (2) The fixing mechanism set in the debugging box facilitates auxiliary fixing of the central air-conditioning installation and debugging equipment when it is parked, thereby improving the stability of the central air-conditioning installation and debugging. At the same time, the auxiliary mechanism set in the debugging box facilitates the auxiliary lifting and installation of the central air-conditioning being installed and debugged, which facilitates better installation by the staff and improves work efficiency. BRIEF DESCRIPTION OF THE DRAWINGS
[0017] In order to more clearly illustrate the embodiments of the utility model or the technical solutions in the prior art, the drawings required for use in the embodiments will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the utility model. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative work.
[0018] Figure 1 It is a structural schematic diagram of a central air-conditioning installation and debugging device according to an embodiment of the utility model;
[0019] Figure 2 It is a structural schematic diagram of a fixing mechanism of a central air-conditioning installation and debugging device according to an embodiment of the utility model;
[0020] Figure 3 It is a schematic diagram of the placement mechanism structure of a central air-conditioning installation and debugging device according to an embodiment of the utility model;
[0021] Figure 4 It is a structural schematic diagram of an auxiliary mechanism of a central air-conditioning installation and debugging device according to an embodiment of the utility model;
[0022] Figure 5The utility model is a schematic diagram of the structure of the auxiliary mechanism 2 of the central air-conditioning installation and debugging equipment according to the embodiment of the utility model.
[0023] In the figure:
[0024] 1. Debug box; 2. Fixing mechanism; 201. Electric telescopic rod 1; 202. Fixing seat; 203. Fixed suction cup; 3. Placing mechanism; 301. Placing rack; 302. Placing slot; 303. Placing plate; 304. Shielding door; 305. Lock; 4. Auxiliary mechanism 1; 401. Auxiliary slot; 402. Lift; 403. Debugging table; 404. Auxiliary frame; 5. Auxiliary mechanism 2; 501. Auxiliary plate; 502. Protective pad; 503. Electric telescopic rod 2; 504. Mounting slot; 6. Push handle; 7. Anti-slip sleeve; 8. Support column; 9. Moving wheel. DETAILED DESCRIPTION
[0025] The technical solutions in the embodiments of the utility model will be clearly and completely described below in conjunction with the drawings in the embodiments of the utility model. Obviously, the described embodiments are only part of the embodiments of the utility model, rather than all of the embodiments. Based on the embodiments in the utility model, all other embodiments obtained by ordinary technicians in this field without making creative work are within the scope of protection of the utility model.
[0026] Embodiment 1:
[0027] See also Figure 1-Figure 5 A central air conditioning installation and debugging device comprises a debugging box 1, push handles 6 are fixedly connected on both sides of the debugging box 1, anti-slip sleeves 7 are installed on the push handles 6, a plurality of support columns 8 are fixedly installed below the debugging box 1, the number of the support columns 8 is four, and a moving wheel 9 is fixedly arranged below the support columns 8, a fixing mechanism 2 is arranged below the debugging box 1, the fixing mechanism 2 comprises a plurality of electric telescopic rods 201 fixedly arranged below the debugging box 1, the number of the electric telescopic rods 201 is two, a fixing seat 202 is fixedly installed on the output end of the electric telescopic rod 201, a plurality of fixed suction cups 203 are installed below the fixed seat 202, and the number of the fixed suction cups 203 is four;
[0028] A placing mechanism 3 is installed on the inner wall of the debugging box 1. The placing mechanism 3 includes a placing rack 301 fixedly installed on both sides of the inner wall of the debugging box 1. The placing rack 301 is provided with placing slots 302 distributed at equal distances. Three of the placing slots 302 are placed on the inner walls with placing plates 303. When actually used, the placing plates 303 are placed with central air-conditioning debugging tools and environmentally friendly refrigerants. The environmentally friendly refrigerant uses R410A, which can reduce the damage to the atmospheric ozone layer and reduce environmental pollution. A shielding door 304 is hinged on the inner wall of the debugging box 1. The shielding door 304 is fixedly connected to one side of the debugging box 1 with a lock 305;
[0029] The fixing mechanism 2 provided in the debugging box 1 can facilitate auxiliary fixation of the central air-conditioning installation and debugging equipment when it is parked. Meanwhile, the placing mechanism 3 provided in the debugging box 1 can not only carry the central air-conditioning installation and debugging tools when the central air-conditioning installation and debugging equipment is transported and moved, but also can be adjusted and placed according to the sizes of different central air-conditioning installation and debugging tools, so as to facilitate the staff to better install and debug the central air-conditioning. The push handle 6 and the moving wheel 9 provided in the debugging box 1 cooperate with each other, so as to facilitate the movement of the debugging box 1 and facilitate the staff to install and debug the central air-conditioning.
[0030] Embodiment 2:
[0031] See also Figure 1-Figure 5 A central air conditioner installation and debugging device, further comprising an auxiliary mechanism 4 provided above the debugging box 1, the auxiliary mechanism 4 comprising an auxiliary slot 401 opened above the debugging box 1, a lift 402 installed on the inner wall of the auxiliary slot 401, a debugging table 403 fixedly installed above the lift 402 for placing the indoor and outdoor units of the central air conditioner, and an auxiliary frame 404 fixedly provided above the debugging table 403;
[0032] An auxiliary mechanism 2 5 is provided above the auxiliary mechanism 1 4. The auxiliary mechanism 2 5 includes auxiliary plates 501 installed on the inner walls of both sides of the auxiliary frame 404. A protective pad 502 is installed on the opposite side of the auxiliary plate 501. An electric telescopic rod 2 503 is installed on one side of the auxiliary plate 501. Installation grooves 504 are opened on both sides of the debugging platform 403. The inner wall of the installation groove 504 is fixedly connected to the electric telescopic rod 2 503.
[0033] The electric telescopic rod 2 503, the lift 402, and the electric telescopic rod 1 201 are electrically connected to a controller during actual use. The controller has an intelligent energy-saving control function and can adjust energy consumption according to actual needs to minimize energy consumption. The controller, the electric telescopic rod 2 503, the lift 402, and the electric telescopic rod 1 201 are electrically connected to an external power supply or an energy-saving battery to reduce dependence on traditional energy and reduce carbon emissions.
[0034] By setting the auxiliary mechanism 1 4 in the debugging box 1, it is convenient to assist in the lifting and installation of the central air conditioner to be installed and debugged, so that the staff can better install it. At the same time, the auxiliary mechanism 2 5 set on the auxiliary mechanism 1 4 can not only assist in shielding the parts that fall during the installation and debugging of the central air conditioner, thereby reducing the situation where the progress of maintenance and debugging is affected by the falling parts, but also assist in fixing the central air conditioner that needs to be installed.
[0035] In summary, with the help of the above-mentioned technical scheme of the utility model, when the central air-conditioning installation and debugging equipment is moved, the push handle 6 and the moving wheel 9 provided in the debugging box 1 need to cooperate with each other, so as to facilitate the movement of the debugging box 1 and facilitate the staff to install and debug the central air-conditioning. When it is moved to the position where it needs to be parked, it passes through the fixing mechanism 2 provided in the debugging box 1, which is convenient for auxiliary fixation when the central air-conditioning installation and debugging equipment is parked. During debugging, the central air-conditioning that needs to be debugged and installed is placed on the placing mechanism 3 provided in the debugging box 1, which can not only carry the central air-conditioning installation and debugging tools when the central air-conditioning installation and debugging equipment is transported and moved, but also can be adjusted and placed according to the sizes of different central air-conditioning installation and debugging tools, so as to facilitate the staff to better install and debug the central air-conditioning. When debugging tools are needed, the auxiliary mechanism 2 5 provided by the auxiliary mechanism 1 4 can not only provide auxiliary shielding when parts fall during the installation and debugging of the central air-conditioning, and reduce the situation that the progress of maintenance and debugging is affected by the falling of parts, but also can assist in fixing the central air-conditioning that needs to be installed. When it needs to be installed after debugging, the auxiliary mechanism 1 4 provided in the debugging box 1 is convenient for auxiliary lifting and installation of the installed and debugged central air-conditioning, so as to facilitate better installation by the staff.
[0036] The above description is only a preferred embodiment of the present invention and is not intended to limit the present invention. Any modifications, equivalent substitutions, improvements, etc. made within the spirit and principles of the present invention should be included in the protection scope of the present invention.
Claims
1. A central air conditioning installation and debugging device, characterized in that: It comprises a debugging box (1), a fixing mechanism (2) is arranged at the bottom of the debugging box (1), and a placing mechanism (3) is installed on the inner wall of the debugging box (1); An auxiliary mechanism 1 (4) is provided above the debugging box (1), and an auxiliary mechanism 2 (5) is provided above the auxiliary mechanism 1 (4).
2. A central air conditioning installation and debugging device according to claim 1, characterized in that: The fixing mechanism (2) comprises a plurality of electric telescopic rods (201) fixedly arranged below the debugging box (1), a fixing seat (202) being fixedly mounted on the output end of the electric telescopic rod (201), and a plurality of fixing suction cups (203) being mounted below the fixing seat (202).
3. A central air conditioning installation and debugging device according to claim 1, characterized in that: The placement mechanism (3) comprises a placement rack (301) fixedly mounted on both sides of the inner wall of the debugging box (1), the placement rack (301) being provided with placement slots (302) distributed at equal distances, wherein three of the placement slots (302) are provided with placement plates (303) on the inner walls, the inner wall of the debugging box (1) being hinged with a shielding door (304), and the shielding door (304) being fixedly connected to one side of the debugging box (1) with a lock (305).
4. A central air conditioning installation and debugging device according to claim 1, characterized in that: The auxiliary mechanism 1 (4) comprises an auxiliary groove (401) opened above the debugging box (1), a lift (402) is installed on the inner wall of the auxiliary groove (401), a debugging platform (403) is fixedly installed above the lift (402), and an auxiliary frame (404) is fixedly arranged above the debugging platform (403).
5. A central air conditioning installation and debugging device according to claim 4, characterized in that: The auxiliary mechanism 2 (5) comprises auxiliary plates (501) mounted on the inner walls of both sides of the auxiliary frame (404), a protective pad (502) being mounted on the opposite side of the auxiliary plate (501), an electric telescopic rod 2 (503) being mounted on one side of the auxiliary plate (501), mounting grooves (504) being provided on both sides of the debugging platform (403), and the inner walls of the mounting grooves (504) being fixedly connected to the electric telescopic rod 2 (503).
6. A central air conditioning installation and debugging device according to claim 1, characterized in that: Push handles (6) are fixedly connected to both sides of the debugging box (1), and anti-slip sleeves (7) are installed on the push handles (6).
7. A central air conditioning installation and debugging device according to claim 1, characterized in that: A plurality of support columns (8) are fixedly installed below the debugging box (1), and moving wheels (9) are fixedly arranged below the support columns (8).